A Lean Six Sigma Project To Reduce Waste and Variability in A Confectionery Manufacturing

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Proceedings of the International Conference on Industrial Engineering and Operations Management

Toronto, Canada, October 23-25, 2019

A Lean Six Sigma Project to Reduce Waste and


Variability in a Confectionery Manufacturing
José Daniel Ibarra, Andrés Robles, Alejandro Montemayor, Angel Iñiguez, Andrés Blanco,
and Alexis Torrecillas

Department of Engineering
Universidad de Monterrey
San Pedro Garza García, N.L., México

Abstract
Candy industry is facing challenges in production waste. Because of the strict regulations and specifications
that assure food safety, production needs to meet high standard requirements to deliver final product to the
customers. One of the principal problems industry has now a day is throwing to the rubbish food that can be
eaten, but that does not completely satisfy specifications. Candy manufacturers need to focus daily in these
requirements so waste can be reduced. This same problem is happening in the company where the authors
made this project. Specifications where not accomplished, and machinery malfunctions impacted directly in
the quality of the final product. Turning it out into waste. The purpose of this work was to reduce 10% of the
waste in a lollipop production line in a Confectionery Company in Mexico. Supporting the project in Lean Six
Sigma methodology, taking as support DMAIC tool. Throughout this work efforts realized in an international
to decrease variation in the cooking process of the candy will be described, to understand how 270 kilograms
of candy waste per day were reduced in a 36.51%. This investigation may be relevant for professionals
involved in food, confectionery and candy industry. But also for engineers looking for a classic Lean Six
Sigma Project and its development.

Keywords
Process improvement, Food Industry, Candy Industry, Waste Reduction, Confectionery Industry, Continuous
improvement, Lean Six Sigma, DMAIC.

1. Introduction

Satisfying world’s lollipop demand requires a 24/7 production, high standard, controlled operations, and hard
work. An actual problem candy industry is facing now a day is food wasted because of high standards non-
compliance. According to Tatum (2017) product that was checked and found to be slightly off spec but is still
good to eat is thrown to rubbish. Companies cannot assume contamination risks delivering final products, but
these strict specifications conclude in one of the biggest amount of waste in industry. Another challenge being
faced by the industry is machinery malfunctions. If a machine involved directly in food production has a
defect, it will impact directly on quality and food safety specifications. Machinery needs to be working
perfectly and aligned to FDA regulations.

An international confectionary manufacturing organization placed in the north part of México with more than
3,000 associates, it is having problem in the Lollipop Production Line since 2017 to middle 2018 (when this
continuous improvement project began), which contribute with the second most wasteful line from the 14

© IEOM Society International 631


Proceedings of the International Conference on Industrial Engineering and Operations Management
Toronto, Canada, October 23-25, 2019

production lines available in this organization. Therefore, the purpose of this paper isto reduce 10% of
lollipop waste.

There are several approaches of continuous improvement projects, such as Lean, Kaizen event, Lean Six
Sigma, and others. Considering that this improvement project was focused on reduction of waste and
variability, the research team decided to use the Lean Six Sigma approach with the DMAIC (define, measure,
analyze, improve, and control) methodology and document this project as a case study.

The remaining sections of this paper are structured as follow. First, research methodology includes
information about the confectionary company were the project was conducted and a description of the
activities or tools used to collect the data in each step of the DMAIC. Second, the section of results was split
in five subsections, one for each phase of the DMAIC. Lastly, in the conclusion section, the research team
included a summary of the findings, limitations of the research, and future work.

During the definition of the project a brief analysis in the Lollipop Production Line was needed in order to
define the problem since the actual waste indicators per shift were not valid. The results of the analysis are
that there are four critical areas that were waste is collected during production, but waste collected is
generated during different processes. In the next figure, lollipop production process is presented.

Figure 1. Lollipop production process

During the definition of the project measurements reflected the following areas:

1. Dropper Zone: Post-dosing process of the pallet, it consists of expelling the candy from the mold so
that it continues its way to the cooling tunnel. In this area, the injection of caramel process is the
cause of the waste in this zone

© IEOM Society International 632


Proceedings of the International Conference on Industrial Engineering and Operations Management
Toronto, Canada, October 23-25, 2019

2. Cooling tunnel: The Cooling Tunnel is responsible for the reduction of the temperature in the candy
so that it solidifies and get accepted in quality tests. In this zone, the caramel remains on the sides of
the cooling tunnel because the pallet is thrown off in the cooling process and falls out of the band
that leads the pallets to the inspection area.
3. Diverters: By means of two channels the candy that was to be fed to the caramel hopper is diverted
when a change of flavor is made or when the hopper candy has to be emptied because it does not
meet the quality standards.
4. Inspection zone: Area at the end of the cooling tunnel, where an operator, quality test, is responsible
for separating the pallets that do not meet quality requirements. In this area waste is not generated,
only the waste generated in the injection of caramel process and ring assembly process

With a measurement of 11 labor shifts (12 hours per shift), an average of 135 kg. of caramel waste per shift
was collected and 90% of the waste concentrates in the Inspection and Dropper Zones, with 69% and 21%
respectively. With the obtained measurements, the particular objectives were defined, as well as the general
objective. The next figure 2 shows sub processes involved in waste production.

Figure 2 Waste Sub processes generators

2. Description of methodology

This is a Lean Six Sigma project using the DMAIC methodology. This methodology aims to reduce waste or
variability and has 5 phases: Define, measure, analyze, implement, and control. It is an iterative method that
follows a structured and disciplined format based on a hypothesis, experimentation, and an evaluation to
confirm or reject the previous stated hypothesis according to McCarty et al. (2004). For each phase of the
methodology, the research team used different tools to collect dada and analyze these data:

© IEOM Society International 633


Proceedings of the International Conference on Industrial Engineering and Operations Management
Toronto, Canada, October 23-25, 2019

a. Define the necessity from which the project is going to take place, the scope, project goal, team
members, the areas involved to achieve the goal, and timeframe chart Bersbach (2009). It is also
important to define the process involved in candy production. According to Manene (2011), flow and
process diagrams are tools that helps to understand correctly the different phases of any process and
its operation, and, therefore, allows to understand and study it to try to improve its procedures.
b. Measure process performance and assess the measuring system if required (Brue, 2002). Tools used
in this phase were historic data given by the company, interviews with different workers involved
directly in the production process and a waste system established by the authors. This system
registered waste produced in each production turn.
c. Analyze data obtained from the current status of the process and determine the causes and
opportunities for improvement. With the historic data and the waste system established by the authors
Pareto diagrams were made. Also, to know variables involved in the process authors made design of
experiments and regressions.
d. Improve process performance through the implementation of actions defined by the LSS project team
(Orozco & Jaramillo, 2013). Several actions were proposed and using a decision matrix (criteria:
cost, time, training needed, complexity, and impact), the LSS project team selected 8 actions that
most contribute to the achievement of the general objective of this project.
e. Control is, focused on sustaining the improvements in order to obtain a long-term impact. During
this LSS project the following tools were used: by using statistical tools, non-statistical techniques,
establishing KPI (Key Process Indicators).

Descriptive information about the results obtained in each of the five phases of the DMAIC were documented
in the following section.

3. Application of Methodology

3.1 Define
In order to know what the real problem in the company was, the first thing to do, following DMAIC
methodology, was to define the problem. For that matter, the team analyzed historic records to establish of the
behavior of the production line and to see when the problem was originated. Analyzing the records, the
authors observed this production line was the second line generating more waste in the company since 2017;
with a total loss of $370,000 USD. Authors focused in solving problems in this line because the one that had
most of the waste already was interfered with an improvement project by the company. The authors also went
to the shop floor to work hand in hand with the production staff and learn how the cooking process worked.
Realizing Gemba Walks daily, the team could notice how the production and cooking of candy worked, and it
also gave symptoms to feed the Ishikawa Diagram to make a correct analysis of the problem.

The identification of independent and dependent variables that influence in the waste of sub processes is an
important step in any project related with Six Sigma, because controlling these variables will impact directly
in the reduction of the variance. To identify the relationship between the dependent and independent variables
the application of a XY matrix was necessary. According to Afza (2017) the matrix XY serves to compare
alternatives to a solution, demonstrate cause and effect, or reduce potential causes to a problem. The
independent variables, x, are the technical parameters of the process. The dependent variables, Y, are
requirements for the process and for the client; quality and packers.

The entitlement tool gives the best result obtained in a defined period of time according to Williams, B. &
Cygi, C (2014). Using the historical waste data of the lollipop production line from 2017 and the start of
2018, a goal of a maximum of 32% waste reduction was calculated. After discussing the results of the
entitlement with the authors, and based on the time given for the project, we established a goal of 10% waste
reduction. In order to achieve that 10% of average waste reduction, we used a Pareto’s diagram to identify

© IEOM Society International 634


Proceedings of the International Conference on Industrial Engineering and Operations Management
Toronto, Canada, October 23-25, 2019

which processes had the greatest impact on the production’s waste. The injection and the expulsion processes
were known to be the new intervention objectives to achieve the goal. In accordance with the authors, we
established the specific objectives that their sum would grant the achievement of the general objective. So
knowing the variables, how the process works and making initial pilot measurements, the three objectives
established were:
1. General objective: 10 % reduction of average waste in turn.
2. Specific objective: 12 % reduction of average waste in turn in injection process.
3. Specific objective: 10% reduction of average waste in turn in expulsion process.

3.2 Measure

Once the processes that generated waste were defined, the measure phase was crucial to develop the
improvement project. The team work established a waste measurement system, in which the operators
measured out the waste in kilograms in the sub-processes. In this way, a Pareto analysis could be made,
helping zooming in the crucial sub-processes that impacted the most in the production of waste.

This measurement system worked the whole project, and it functioned as a scoreboard to see how waste
increased or decreased daily. After analyzing eleven production shifts, the results showed that the two sub
processes that were generating more waste were the cooking and expulsion process. Graphs at control phase
will show results of this measurement system.

3.3 Analyze

Analyze stage in the project requires experience and data. A key task in this stage is the time spent during
production and maintenance. Living the process from A to Z clarifies and sustains the analysis of any
problem. The team spent hours in the three shifts measuring the amount of waste and analyzing maintenance
practices, which made up easy the symptoms collection. During DMAIC stages, authors recollected
symptoms, these symptoms were displayed in an Ishikawa diagram as shown in Figure 4.3, dividing it by
machines, personnel, materials, method, measurement and environment. According to Pérez, A. (2015)
Ishikawa diagram helps in the processing, organization and prioritization of new information. In this way,
information can be integrated in a simple way, making easier analysis of solutions, and obtaining a global
structured vision of the problem, so the real causes can be identified.

© IEOM Society International 635


Proceedings of the International Conference on Industrial Engineering and Operations Management
Toronto, Canada, October 23-25, 2019

Figure 3. Ishikawa diagram

After the categorization of 11,400 lollipops by defect, the team found that with the use of a Pareto Diagram
that 80% of the defects which caused waste came from the process of injections and a bad insertion of the
lollipop’s ring. Pareto´s Diagram is a useful tool which let visualize the majority of the problems and their
root causes- With the 20% of the defect types, you can obtain the 80% of its totality. It represents a major help
identifying the factors that impact on a determined situation. Making efforts to focus on better results
(Galgano, 1995).

Completing the two analysis with symptoms and defects,, the team made a 5 Whys analysis, to clarify
symptoms and, to finally, obtain the root causes of the problem. The success of the 5 Whys analysis was
because many leaders in the company participated on it, leaders who know the process perfectly.

Authors identified two main root causes:

1. There is not an operation standard established for the injection of caramel process.
2. Specifications and process for replacing critical components of machines were uncontrolled.

3.4 Improve

According to Turrent, A.L. (2015), improvement is not an easy stage, due to the fact that creative ideas are
not always viable for the practice. Another situation it needs to be controlled relates with the factors selected
to decide whether a solution is feasible in process conditions. At the moment of brainstorming ideas, the team
accepted all the ideas but did not implement any without the correct analysis and consulting the whole
shareholders. What Turrent recommends is to start a Pilot improvement and measure results of it, if it works,
replicate in a big scale with similar processes, if not, learn and create again a better solution.
During the stage of improvement, solutions where designed in collaboration with the most efficient and
experienced team leader of the process. The daily interviews with the Lollipop Production operators and team
leaders were the source of valid information to propose solutions.

© IEOM Society International 636


Proceedings of the International Conference on Industrial Engineering and Operations Management
Toronto, Canada, October 23-25, 2019

A prioritization exercise that consists of punctuating solutions against decision factors (Medina et al. 2010)
with 13 proposal solutions resulted with the selection of 7 solutions.

1. Implementation of cleaning inspection and lubrication standard (CIL):


2. Injector Standardization
3. Nozzles and injectors replacement system
4. Standardize candy levels in the injection hopper
5. Standardize temperature levels in the injection hopper
6. Detection system for damage molds
7. Revision and replacement system for molds

3.5 Control

The solutions implemented needed control in order to keep solutions for a long term. The team developed a
template and implemented as a key to control solutions. The template is called Control Document and since
implementations were in a short period of time and our project has a scalable focus, the Control Document
had as reference the structure as the Standard Operation Procedure Document, document that all operators
understand and use for its operations. The template includes the following sections:

In the first section, Objective, the goal of the implementation has to be define. In the second section, Scope, it
is established what will the solution reach, in this case all the solutions had the same scope. The third section,
Responsibilities, the personnel responsible for compliance with the procedure is establish. The fourth section,
Procedure, is the one that describes the process where the solution will be applied, for example, the standard
procedure of candy level in the process of injecting caramel into the mold. In the same section requirements
and specs to comply with the process are also establish, if they are not met, the Control Plan is consulted. The
procedure section has a Flow Chart and image to represent the process in graphically. The fifth section
includes the optimal operating parameters. The control section is to control modifications in the document
including the version, date, revision, responsible/role and comments.

In the following figures 5 to 7, the results of the implemented solutions are shown. In which the general
objective was accomplished, reducing 36.51% of the caramel waste, second objective, reducing the average
waste in injection process, had a reduction of 31.62%. And for the last objective, reduction of average waste
in expulsion process accomplished 53.93%.

© IEOM Society International 637


Proceedings of the International Conference on Industrial Engineering and Operations Management
Toronto, Canada, October 23-25, 2019

Waste
80

70

60

50
Kilograms

40

30

20

10

0
0 5 10 15 20 25 30 35
Turns

Fig. 5 Waste in expulsion process

This graph has two lines, the first one shows an intervention made in the beginning of the project and the
second one shows the last intervention with all the solutions explained before.

Waste
200
180
160
140
120
Kilograms

100
80
60
40
20
0
0 5 10 15 20 25 30 35
Turns

Fig 6. Waste in injection process

© IEOM Society International 638


Proceedings of the International Conference on Industrial Engineering and Operations Management
Toronto, Canada, October 23-25, 2019

Waste
250

200
Kilograms

150

100

50

0
0 5 10 15 20 25 30 35
Turns
|
Fig 7. General waste

4. Conclusions
Results of the project surpassed authors and the company expectancies. The general objective was
accomplished, reducing 36.51% of the caramel waste, 26.51% more than the general objective established in
the definition stage. For the second objective, reducing the average waste in injection process, the reduction
was a 31.62%, exceeding initial objective in 19.62%. For the last objective, reduction of average waste in
expulsion process, initial objective was surpassed with 43.93%, obtaining a final reduction of 53.93%.

It is important to mark that the success of the project was accomplished with the support of the production
line leaders, operators, and maintenance technicians due to the valuable information provided by their
experience in the field. The involvement of each person in the production plant was a key factor for decision
making in the different stages of the project.

Empowerment of the experts on the process is essential. The experts are the field operators and production
line leaders. Every point of view must be taken into consideration. Departments aspiring and contributing to
the same objective have to be involved.

One of the project limitations was time, authors only had 4 effective months to develop whole DMAIC phases
and improve the process. Measurements were made only in this period of time. A second limitations was
automatization tests in the production line. These tests stopped production, in this way authors could not work
in the project and waste incremented because of this tests. Despite these limitations, and as seen in the graphs
results showed the improvement.

And as a final learning, it is crucial that involved parties must have the same objective, so that the solution is
systematic. It will lead to better control in the future. A contingency plan must be devised to positively affect
all the people involved. Continuous improvement with the appropriate tools will guarantee foresight for the
evasion of all emerging restrictions and incidents.

© IEOM Society International 639


Proceedings of the International Conference on Industrial Engineering and Operations Management
Toronto, Canada, October 23-25, 2019

5. References
Afza, J. (2017). Lean Defined: The XY Project Selection Matrix. LeanCor.

Bersbach, P. (2009). The Roadmap to a Successful Six Sigma Project.Bersbach Consulting.

Brue, G. (2002). Six SIgma for Managers. McGraw Hill Professional.

Galgano, A. (1995). Los 7 instrumentos de la calidad total. Madrid: Díaz de Santos S.A.

Manene, L. M. (2011). Los diagramas de flujo: su definición, objetivo, ventajas, elaboración, fases, reglas y
ejemplos de aplicaciones.

McCarty, T., Bremer, M., Daniels, L. (2004). Six sigma black belt handbook. McGraw-Hill. Retrieved
08/13/2018.

Medina Vásquez, J., Ortiz, F., Franco, C. A., &Aranzazú, C. (2010). Matriz de Priorización para la Toma de
Decisiones. Recuperado el 18 de octubre de 2018, de Universidad del Valle

Orozco, V.D., Jaramillo, V.M. (2013). Reducción de desperdicios en el proceso de envasado del yogurt
purepak de 210 g en la máquina NIMCO en una empresa de lácteos, mediante la aplicación de la
metodología seis sigma. Universidad de la Costa. Barranquilla, Colombia.

Tatum, A. (2017) 10 ways food is wasted by manufacturers. The Grocer.

Turrent, A. L. (2015). Metodología SIX SIGMA. En A. L. Turrent, La aplicación de la metodología Six


Sigma DMAIC.Puebla: Publicia.Williams, B. &Cygi, C. (2014). Six sigma for Dummies. New Jersey: John
Wiley & Sons, Inc.

6. Biographies
Alejandro Montemayor actual student enrolled in the School of Engineering and Technologies at the
University of Monterrey, cursing Industrial and Systems Engineering. He has participated in different projects
in the industry. During his studies, he has been awarded with the distinguished student award and has
participated in a cultural exchange program at Disney World for 3 months.
Andres Robles, actual student enrolled in the School of Engineering and Technologies at the University of
Monterrey with a minor in International Entrepreneurship from Avans Hogeschool. He has been participating
in different projects related to banking, confectionary and urban transportation. During his studies, he has
been an exchange student for 1 year in Michigan, United States and 6 months in Breda, Netherlands. Andres
works as a Product Analyst for a Fintech company named ePesos, his goal is to work in any customer-centric
tech company.
Angel Iñiguez actual student enrolled in the School of Engineering and Technologies at the University of
Monterrey, cursing Industrial and Systems Engineering. He has been participating in different projects related
to continuous improvement in the confectionary industry, working actually as a logistics audit coordinator in
a Sigma Alimentos, Mexico.
Jose Daniel Ibarra actual student enrolled in the School of Engineering and Technologies at the University
of Monterrey, cursing Industrial and Systems Engineering. He has been involved in two improvement projects
in the industry, working actually as a data Analyst in Human Resources Strategic Planning in a firm in
Monterrey, Mexico.

© IEOM Society International 640


Proceedings of the International Conference on Industrial Engineering and Operations Management
Toronto, Canada, October 23-25, 2019

Andrés Blanco actual Quality Manager at a local freezer company in Monterrey, México, developing this roll
for more than 10 years. Transmitting his knowledge to students, he has participated in more than 20
consulting projects focused on variability reduction, waste reduction, Lean Six Sigma, logistics, quality
assurance and continuous improvement projects.
Alexis Torrecillas actual principal of Industrial and Systems Engineering at University of Monterrey. With
industrial experience in quality management, continuous improvement, logistics, and consulting solutions. In
the beginning of his career he managed custom formalities, then developed as a consultant in different
industries.