Petronas Technical Standards: PETRONAS Risk-Based Inspection (PRBI)
Petronas Technical Standards: PETRONAS Risk-Based Inspection (PRBI)
Petronas Technical Standards: PETRONAS Risk-Based Inspection (PRBI)
PTS 15.40.01
December 2016
FOREWORD
PETRONAS Technical Standards (PTS) has been developed based on the accumulated knowledge,
experience and best practices of the PETRONAS group supplementing National and International
standards where appropriate. The key objective of PTS is to ensure standard technical practice across
the PETRONAS group.
Compliance to PTS is compulsory for PETRONAS-operated facilities and Joint Ventures (JVs) where
PETRONAS has more than fifty percent (50%) shareholding and/or operational control, and includes
all phases of work activities.
Contractors/manufacturers/suppliers who use PTS are solely responsible in ensuring the quality of
work, goods and services meet the required design and engineering standards. In the case where
specific requirements are not covered in the PTS, it is the responsibility of the
Contractors/manufacturers/suppliers to propose other proven or internationally established
standards or practices of the same level of quality and integrity as reflected in the PTS.
In issuing and making the PTS available, PETRONAS is not making any warranty on the accuracy or
completeness of the information contained in PTS. The Contractors/manufacturers/suppliers shall
ensure accuracy and completeness of the PTS used for the intended design and engineering
requirement and shall inform the Owner for any conflicting requirement with other international
codes and technical standards before start of any work.
PETRONAS is the sole copyright holder of PTS. No part of this document may be reproduced, stored
in a retrieval system or transmitted in any form or by any means (electronic, mechanical, recording or
otherwise) or be disclosed by users to any company or person whomsoever, without the prior written
consent of PETRONAS.
The PTS shall be used exclusively for the authorised purpose. The users shall arrange for PTS to be
kept in safe custody and shall ensure its secrecy is maintained and provide satisfactory information to
PETRONAS that this requirement is met.
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 3 of 23
ANNOUNCEMENT
Please be informed that the entire PTS inventory is currently undergoing transformation exercise from
2013 - 2015 which includes revision to numbering system, format and content. As part of this change,
the PTS numbering system has been revised to 6-digit numbers and drawings, forms and requisition
to 7-digit numbers. All newly revised PTS will adopt this new numbering system, and where required
make reference to other PTS in its revised numbering to ensure consistency. Users are requested to
refer to PTS 00.01.01 (Index to PTS) for mapping between old and revised PTS numbers for clarity. For
further inquiries, contact PTS administrator at ptshelpdesk@petronas.com.my
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 4 of 23
Table of Contents
1.0 INTRODUCTION ..................................................................................................... 5
1.1 SCOPE .............................................................................................................................. 5
1.2 GLOSSARY OF TERM ........................................................................................................ 5
1.3 SUMMARY OF CHANGES ................................................................................................. 7
2.0 REQUIREMENTS..................................................................................................... 8
2.1 SPECIAL REQUIREMENT FOR FACILITIES OPERATING IN MALAYSIA ............................... 8
2.2 STAGES OF PRBI IMPLEMENTATION ............................................................................... 8
3.0 PRBI APPROACH .................................................................................................... 9
4.0 PRBI TEAM .......................................................................................................... 10
5.0 PRBI STUDY IMPLEMENTATION ........................................................................... 12
5.1 CORROSION ASSESSMENT ............................................................................................ 12
5.2 RISK ANALYSIS ............................................................................................................... 15
5.3 INSPECTION EVALUATION ............................................................................................. 16
6.0 PRBI MONITORING .............................................................................................. 18
7.0 PRBI REVIEW ....................................................................................................... 19
7.1 PRBI Reassessment ....................................................................................................... 19
7.2 PERIODIC REVIEW ......................................................................................................... 19
8.0 PRBI MANAGEMENT REVIEW ............................................................................... 20
9.0 BIBLIOGRAPHY .................................................................................................... 21
APPENDIX 1: REQUIRED DATA/INFORMATION FOR PRBI STUDY ...................................... 22
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 5 of 23
1.0 INTRODUCTION
This PETRONAS Technical Standards (PTS) provides the minimum technical requirements for
PRBI system which is applicable for PETRONAS new projects or in-service inclusive of Special
Scheme of Inspection (SSI) program.
This PTS incorporates Factories and Machinery (Special Scheme of Inspection) (Risk-Based
Inspection) Regulation 2014 [P.U. (A) 96/2014] requirements gazetted in June 2014 to ensure
successful implementation of Special Scheme of Inspection (SSI) across PETRONAS. It also
incorporates related RBI best practices and lesson learnt from other OPUs.
1.1 SCOPE
1.1.1 PRBI methodology covers RBI analysis for metallic static equipment and piping which is
governed by applicable code and standard i.e. pressure vessel, column, boiler, furnace, heat
exchanger, launcher/receiver and storage tank.
1.1.2 Items such as civil structures, electrical equipment, electronic devices, rotating equipment,
pipeline, risers and non-metallic equipment/piping are excluded from this PTS.
Refer to PTS 00.01.03 for PTS Requirements, General Definition Of Terms, Abbreviations &
Reading Guide.
No Term Definition
No Term Definition
recommendation of Inspection Planning based
on associated risk of equipment or piping.
No Abbreviation Description
2 CF Certificate of Fitness
9 GA General Arrangement
16 MC Management Committee
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 7 of 23
No Abbreviation Description
27 SA Situational Assessment
2.0 REQUIREMENTS
2.1.1 For onshore facilities, it shall be governed by Department of Occupational Safety and Health
(DOSH) Regulations:
i. Factories & Machinery (SSI) (RBI) Regulation 2014 (June 2014) shall be applied for
OPUs that embark on SSI whereby PRBI has been recognized as one of the RBI
methodologies. For standardization of SSI implementation, DOSH requirement
shall be complied
ii. Factories And Machinery (Notification, Certificate of Fitness and Inspection)
Regulations, 1970 shall be applied to a time-based DOSH equipment which
require renewal and extension of certificate of fitness i.e. CF70 at specific interval.
iii. It is a DOSH requirement for OPUs to submit PRBI assessment result during CF70
(Postponement and Extension) and SSI application. These application shall be
submitted through Online PRBI DOSH Module to expedite the DOSH approval
process and support government paperless initiative.
2.1.2 For offshore facilities, it shall be governed through the exemption order, P.U.A 106, Factories
& Machinery (Exemption to Petroliam Nasional Berhad) Order 2013, whereby RBI is
recognised as a tool to manage the Asset Integrity under Offshore Self-Regulation
Management System (OSRMS).
2.2.1 The PRBI study for PETRONAS Group wide shall be applied for the following scenarios:
i. Project Stage: PRBI study to be conducted at this stage (i.e. Brownfield and
Greenfield) to provide basis for baseline database for equipment and piping
during in-service stage.
ii. Operation Stage: PRBI study to be utilized to optimize the inspection activities
based on updated risk rating and/or as a pre-requisite document for OPUs to
embark on SSI scheme and supporting document for postponement and
extensions of CF70 application.
PRBI is a semi quantitative methodology that uses relative risk as a basis for prioritizing and
managing the inspection programs. It shall focus on inspection activities to specifically address
threats to the integrity of the equipment/piping’s capacity to operate as designed.
The Probability of Failure (PoF) and Consequence of Failure (CoF) are assessed separately and
then combine to determine the risk ranking. Risk ranking is analysed and prioritised for
inspection planning and risk mitigation (if any). The risk mitigation plan may include options
in addition to inspection program such as changes of material of construction, the use of
corrosion inhibitors, changes in operating condition, and/or installation of liners and coatings.
PRBI study shall be reviewed and updated periodically through suitable PRBI reassessment
cycle to ensure the results are reliable and reflecting the relevant operating conditions. The
details of PRBI reassessment is discussed in the section 7.0. The overall PRBI approach can be
depicted as in Figure 3.1.
OPU shall establish PRBI team that consist of competent (i.e. skilled and knowledge) personnel
for the execution of the PRBI implementation which is involved s multidisciplinary activity as
shown in Table 4.1:
Management of OPU shall issue an appointment letter to all respective team members with
specific role and responsibilities. Any changes of team members, new appointment letter shall
be issued and RBI team organization chart shall be updated accordingly.
PRBI methodology and software training shall be provided to all RBI team member to ensure
they are knowledgeable to conduct PRBI study.
Team Leader shall conduct a regular PRBI meeting for at least quarterly with the presence of
all team member to update and discuss on current PRBI implementation. Minute of meeting
shall be prepared after the meeting and kept for future reference.
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 12 of 23
Adequate dossiers containing essential data shall be made available and maintain to ensure
PRBI assessments are reliable. All assumptions made as an input to the study shall be properly
documented and maintained as per list in the Appendix 1.
All the data used in PRBI shall be up-to-date and reliable. Data entry can be performed by
Inspector with the supervision from Inspection Engineer. However, Team Leader shall ensure
proper validation shall be done on the data to be input into PRBI database by relevant team
members as follows:
i. Inspection data by Inspection Engineer.
ii. Degradation mechanism (if any) by Corrosion Engineer.
iii. Process data by Process/Operation Representative.
iv. Production data by Financial/Business Representative.
v. Repair cost and maintenance data including MOC by Maintenance/Mechanical
Representative.
Corrosion assessment is one of the important steps in PRBI implementation whereby all active
and credible damage mechanism shall be identified based on latest information regarding
process parameter and material used for the equipment/piping. The corrosion assessment
activities shall be led by the qualified Corrosion Engineer with the participation from RBI team
members which at least consist of Team Leader, Inspection Engineer and Process/Operation
Representative. The assessment consist of the following activities:
A Corrosion Group (CG) is defined as an assembly of static equipment and its interconnected
piping operated within similar operating parameters, having similar process stream, damage
mechanism and material of construction.
The CG shall be identified and marked-up on latest PFD and UFD. The development of CG for
in-service plant or facilities shall consider information obtained from inspection and/or repair
history and actual condition at site.
Any changes on current CG, it shall be reviewed at least by Corrosion Engineer, Inspection
Engineer and Process/Operation Representative prior to approval by Team Leader for
implementation. The changes shall be recorded for future reference.
The CG will be broken down further to smaller manageable segments of continuous piping
exposed to similar damage mechanism which are termed as Piping Circuit. A representative
line shall be selected for each piping circuit based on team member’s agreed criteria prior to
PRBI analysis. The piping circuit shall be identified and marked-up on latest P&ID.
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 13 of 23
Any changes on current piping circuit, it shall be reviewed at least by Corrosion Engineer and
Inspection Engineer prior to approval by Team Leader for implementation. The changes shall
be recorded for future reference.
Corrosion Engineer shall ensure each equipment’s component has been assigned with correct
damage mechanism with verification from latest inspection findings and operation parameter
trending.
Any deletion or addition from current identified damage mechanism, it shall be reviewed at
least by Corrosion Engineer, Inspection Engineer and Process/Operation Representative prior
to approval by Team Leader for implementation. The changes shall be recorded for future
reference.
In PRBI, Corrosion Rate (CR) can be obtained from the following sources:
i. Expected CR as per Subject Matter Expert (SME) advise, corrosion prediction
model or based reference standard e.g. API RP 581
ii. Measured CR is consists of Long Term CR or Short Term CR which calculated
based on thickness measurement trending records. Inspection Engineer shall
ensure all the thickness measurement has been carried out based on established
procedure.
iii. Monitored CR obtained from NDE, coupon and probe reading for specific
monitoring location
iv. Calculated CR for Corrosion Under Insulation (CUI) using PRBI calculator
From the above available CR information, Corrosion Engineer shall determine the most
appropriate corrosion rate to represent the anticipated damage mechanism to be used for
precise PRBI analysis.
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 14 of 23
In the event of “Measured CR” and “Expected CR” are available, Corrosion Engineer may refer
the below approach to determine final CR:
Any deviation from the above mentioned approaches, Corrosion Engineer shall consult and
obtain approval from Team Leader. The deviation shall be recorded for future reference.
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 15 of 23
Risk is a product of the probability of failure (PoF) and the consequence of failure (CoF) and
defined by the below expression:
Risk = Probability of Failure x Consequence of Failure
As a result of PRBI analysis, each equipment component and piping circuit is classified into
one of the risk rating categories; High, Medium, Low and Very Low.
The results of the PRBI analysis are presented by 6x5 risk matrix with the PoF categories of A
to E and the CoF categories of 0 to 5. The lowest risk category will be 0-A, and the highest risk
category will be 5-E. The PRBI risk matrix is shown in Figure 5.2.
PRBI analysis is performed using PRBI web-based software. Team Leader shall ensure the
following tasks to be completed prior to PRBI risk analysis:
i. Verification of equipment/piping data
ii. Finalization of corrosion study and assignment of corrosion group to the
components of the equipment/piping circuit as well as ensure the right damage
mechanism and CR have been assigned
iii. Finalization of economic data
iv. Assignment of inspection confidence, if any
v. Updating of latest inspection data into the inspection database
Prior to risk finalizing, PRBI team members shall review with the risk results to ensure the
credibility and accuracy of the result. If there is any dispute on the risk result, all the tasks as
described in para 5.2.1 shall be re-verified.
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 16 of 23
During this stage, the CoF rating for Environment and Reputation shall be assigned and
finalised in the PRBI software by Inspection Engineer/Corrosion Engineer with input from
SHO/HSE Representative.
Risk result only can be saved as final in the PRBI system after PRBI team members have
reviewed and agreed on the risk rating. Team Leader shall approve the final risk result for
future reference.
Any dispute on the final risk result, team member to re-verify all tasks as described in para
5.2.1. Team Leader to approve the changes (if any) and to update management on the final
risk results.
Inspection evaluation is important process in PRBI analysis. It is crucial to ensure all the
inspection data input into PRBI software shall be verified and evaluated by Inspection
Engineer. The following are the activities for inspection evaluation in PRBI software:
Each inspection location shall be properly specified and marked on the relevant drawing e.g.
isometric drawing, GA drawing etc. based on established Thickness Measurement Location
(TML) Procedure. For in-service equipment and piping, the TML shall be based on credible
location identified during internal visual inspection or failure history record. Inspection
Engineer shall ensure the following has been verified:
i. all the active TMLs being registered in PRBI database
ii. all TMLs ID in PRBI database are similar with TML ID at site and drawing
iii. all “inactive” TMLs status in PRBI shall be justified e.g. due to insignificant CR,
inaccessible location etc. and to notify Team Leader
iv. Tmin calculation used is correct for respective TMLs
Corrosion Engineer shall evaluate thickness reading trending based on verified thickness data
recorded in PRBI database and decide on final CR to be used for PoF analysis of equipment/
piping circuit components. Any abnormality of CR i.e. growing of thickness or significant metal
loss detected, Corrosion Engineer shall inform Team Leader for his/her decision for any further
verification or assessment.
Inspection Engineer shall ensure all inspection report for dedicated equipment/piping circuit
be recorded to the respective NDT method in PRBI database. After all inspection report have
been recorded, Inspection Engineer shall determine the inspection confidence rating in PRBI
software based on the following information:
i. Type of damage mechanism
ii. Inspection method
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 17 of 23
Inspection confidence rating may be assigned based on PRBI Inspection Confidence Criteria or
using API RP 581 as guidance.
The final inspection confidence shall also consider other factors that contribute to the
accuracy of the result such as NDT operator competency, compliance to procedure and report
quality.
Any significant inspection findings, Inspection Engineer to notify Corrosion Engineer for
further evaluation.
Inspection Reference Plan (IRP) is the final product of PRBI analysis. IRP shall be developed for
each equipment/piping circuit based on the PRBI risk analysis results. For each degradation
mechanism, the PRBI software will recommend the inspection method(s), extent and
frequency of inspection based on the Inspection Priority for respective equipment/piping
circuit.
Inspection Engineer and Corrosion Engineer (if required) shall review the recommended
inspection plan and may accept or modify the IRP as necessary. The Inspection Engineer shall
also review the recommended inspection interval to comply with statutory requirements and
company business strategy. Team Leader shall approve of the final IRP and accountable for its
execution. Any deviation from approved IRP, Inspection Engineer shall obtain approval from
Team Leader and all deviation/changes shall be recorded.
It is recommended that PSOE shall be developed based on latest risk and IRP. SME shall be
consulted for the development of PSOE as it require involvement from multi discipline e.g.
maintenance, mechanical, turnaround team etc.
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 18 of 23
6.1.1 For identified non-age related degradation mechanisms, Corrosion Engineer shall monitor the
critical parameters such as moisture content, chloride content, temperature and etc.,
accordingly. Monitoring of other critical parameters is also applicable to age-related
degradation mechanism (e.g. pH of acid corrosion, temperature for creep) in addition to the
thickness measurement.
6.1.2 Any deviation from Integrity Operating Windows (IOWs) value, Corrosion Engineer shall
evaluate the effect to the current identified damage mechanisms and to be recorded in PRBI
database (Corrosion Study). Corrosion Engineer shall inform PRBI team members on the
deviation for further discussion or decision.
6.1.3 For corrosion control, monitoring and testing purposes, the risk of degradation mechanism
analysed in PRBI may be used as an input for development of Corrosion Management Plan
(CMP) as part of risk mitigation plan. Any changes in CMP, Corrosion Engineer shall update the
information in PRBI database (Corrosion Study) to ensure its consistency and updated
information.
6.1.4 PRBI team members shall analyse all risk rating for equipment and piping to determine its
driven factors. Priority monitoring and inspection shall be given to the High risk rating that
driven by high PoF. Team Leader shall decide a suitable risk mitigation plan, if necessary.
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 19 of 23
PRBI is a dynamic tool that can provide current and projected future risk assessment based on
data and knowledge during the assessment. PRBI assessment results shall be updated in the
system based on latest review findings (if any). The review process includes the following but
not limited to:
7.1.1 PRBI Reassessment is an important review process to ensure recent inspection, process, and
maintenance information are incorporated and analysed which may have significant effects
on risks and subsequently, inspection plan. There are several events that might change the
risk rating whereby the PRBI Reassessment shall be conducted as below:
i. After significant changes in process parameter
ii. After a set of period; although significant changes may not have occurred, over
time many small changes may occur and cumulatively cause significant changes
in the RBI assessment. Users should set default maximum time periods for
reassessments.
iii. Upon completion of any inspection activities where inspection data and
verification has been performed.
iv. Major modifications have been made or new equipment is being introduced
7.1.2 PRBI Reassessment shall be conducted at specified interval of not more than 3 years by RBI
team members.
PRBI Situational Assessment (SA) shall be conducted once to provide a baseline assessment
from an independent third party review to assess the adequacy and comprehensiveness of
PRBI program. PRBI SA shall be followed by Periodic Peer Review to assess the effectiveness
and sustainability of PRBI program at interval frequency of 3-5 years. The results from this
review can be used to benchmark PRBI programs amongst the OPUs to ensure consistency,
effectiveness and sustainability across the PETRONAS Group wide as well as to ensure
compliance with local and national authority.
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 20 of 23
8.1.1 The Plant Manager/Plant Head shall responsible for PRBI management review which to be
conducted yearly. The Plant Management Committee or designated committee, as
representatives of the Plant Manager/Plant Head, shall review the effectiveness of PRBI
implementation of their facilities for the past 1 year.
8.1.2 The PRBI management review shall discuss, but not limited to:
i. Sharing of PRBI risk results and the effect to the asset integrity
ii. Adequacy of resources (i.e. financial, staff, etc.) to sustain PRBI implementation
iii. SSI Audit Readiness and Compliance (applicable for OPU that embark on SSI)
iv. RBI team member competency and qualification
v. PRBI identified gaps and gap closure plans
vi. PRBI IRP and monitoring implementation status and effectiveness
vii. Changes in legislation requirement, if any
viii. Opportunities for risk reduction and mitigation
ix. Related MOC which will effect on PRBI assessment, etc.
8.1.3 During the review, the Management shall set suitable Key Performance Indicators (KPI) for all
RBI team members and its related department to ensure the effectiveness of PRBI
implementation.
8.1.4 Minutes of the meeting shall be taken and proposed actions shall be assigned to individuals
for implementation and tracking purposes.
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 21 of 23
9.0 BIBLIOGRAPHY
INTERNATIONAL STANDARDS
Risk-Based Inspection Technology API RP 581: April
2016
PTS 15.40.01
PETRONAS RISK-BASED INSPECTION (PRBI) December 2016
Page 22 of 23
The following are the minimum essential data/information required for the PRBI assessment:
(k) Layout
Management of
Change (MOC)
(a) Process changes
records
4 (applicable for in-
(b) Equipment modifications/ change of material of
service
construction
equipment/piping
only)