Data Sheet +tender Document For Contractors - Mali
Data Sheet +tender Document For Contractors - Mali
Data Sheet +tender Document For Contractors - Mali
Republic of Mali
Invitation to Tender
Construction
of
0
PROJECT DATA SHEET
Project Name:
The Saudi Program for Drilling of Wells and Rural Development in Africa, Phase V - Mali
Financer:
Saudi Fund for Development
The Consultant
Projects House for Engineering Consulting/ EDS INTERNATIONAL
Duration
24 months
The Project works include the Construction of about (110) drilled wells (water
Boreholes) equipped with solar pumping system, elevated water tanks, 30 water
distribution Network System (with a various piping diameters), concrete posts each
with two taps and one meter of the Saudi Program for Drilling of Wells and Rural
Development in Africa, phase V in Mali.
Construction of about (110) drilled-wells (water Boreholes) equipped with solar pumping
system
Supply and installation of a 110 galvanized steel tank 10m³ and tower of 6m height with all
necessary parts
Supply and installation of PVC pipes in 30 water distribution Network System (77km with a
various piping diameters), concrete posts each Two taps and one meter
Animation/sensitization, which means beneficiaries contact with management and
maintenance of the water system for awareness, during and after construction
1
Submission of Offers:
All contractors who are interested in participating to implement the project should
submit their offers to the Saudi Fund for Development before 23rd of Mars 2023 at
14:00 in sealed envelopes including the technical and financial offers (hard and soft
copies), to the following:
We hope that you send an email to confirm if you wish to compete and submit your technical
and financial offers to be able to respond to any inquiries or observations for the companies
which are willing to apply, to the following emails:
- Saeed_zz@sfd.gov.sa
- projectshouseeds@gmail.com
- eds.eds.ingenierie@gmail.com
Very important
The aforementioned sticker must be placed on the outer package and
any package without the sticker will not be opened
2
Technical and Financial العرض الفين والمايل
offer for لتنفيذ أعمال مرشوع
Hands over to the General Directorate of Africa يسلم لإلدارة العامة لعمليات أفريقيا
Operations الصندوق السعودي للتنمية
Saudi Fund for Development الدور الرابع
4th Floor
3
Table of contents
SECTION 1................................................................................................................................ 8
INVITATION TO BIDDERS .................................................................................................... 8
SECTION 2............................................................................................................................. 10
GENERAL INFORMATION .................................................................................................. 10
Section -2: General Information – The Republic of Mali ........................................................ 11
SECTION 3.............................................................................................................................. 13
INSTRUCTIONS TO BIDDERS ............................................................................................ 13
Section 3: Instructions to Bidders ............................................................................................ 14
A. General ............................................................................................................................ 14
1. Scope of Bid............................................................................................................... 14
2. Source of Funds ......................................................................................................... 14
3. Eligible Bidders ....................................................................................................... 14
4. Qualification of the Bidder ......................................................................................... 14
5. One Bid per Bidder ..................................................................................................... 17
6. Cost of Bidding ........................................................................................................... 17
7. Site Visit .................................................................................................................... 17
B. Bidding Document .......................................................................................................... 18
8. Content of Bidding Documents .................................................................................. 18
9. Clarification of Bidding Documents ............................................................................ 18
10. Amendment of Bidding Documents .......................................................................... 18
C. Preparation of Bids .......................................................................................................... 19
11. Language of Bid......................................................................................................... 19
12. Documents Comprising the Bid ................................................................................. 19
13. Bid Prices ................................................................................................................... 19
14. Currencies of Bid and Payment ............................................................................... 19
15. Bid Validity................................................................................................................ 19
16. Bid Security ............................................................................................................... 20
17. Alternative Proposals by Bidders ............................................................................. 20
18. Format and Signing of Bid......................................................................................... 20
D. Submission of Bids ......................................................................................................... 22
19. Sealing marking and presentation of Bids ................................................................. 23
20. Deadline for Sub-mission of Bids .............................................................................. 25
21. Late Bids ................................................................................................................... 25
22. Modification And Withdrawal of Bids ..................................................................... 25
E. Bid Opening and Evaluation .......................................................................................... 26
23. Bid Opening ............................................................................................................... 27
4
24. Process to Be Confidential ......................................................................................... 27
25. Clarification of Bids and Contacting the Employer................................................... 27
26. Examination of Bids and Determination Of Responsiveness .................................... 28
27. Correction of Errors ................................................................................................... 28
28. Currency for Bid Evaluation ...................................................................................... 28
29. Evaluation and Comparison of Bids .......................................................................... 29
F. Award of Contract .......................................................................................................... 30
30. Award Criteria ........................................................................................................... 30
31. Employer's Right to Accept any Bid and to Reject any or all Bids ........................... 30
32. Notification of Award and Signing of Agreement..................................................... 30
33. Performance Security ................................................................................................. 31
34. Advance Payment ...................................................................................................... 31
35. Corrupt or Fraudulent Practices ................................................................................. 31
G. Bidding Data ................................................................................................................... 32
2.1 - (Instruction to Bidders)............................................................................................ 32
SECTION 4.............................................................................................................................. 34
A. General ......................................................................................................................... 35
1. Definitions ................................................................................................................... 36
2. Interpretation ................................................................................................................ 37
3. Language and law ........................................................................................................ 38
4. Consulting Engineer’s Decisions ................................................................................. 38
5. Delegation .................................................................................................................... 38
6.Communications ........................................................................................................... 38
7. Subcontracting ............................................................................................................. 38
8. Personnel ...................................................................................................................... 38
9. Employer’s and Contractor’s Risks ............................................................................. 39
10. Employer’s Risks ....................................................................................................... 39
11. Contractor’s Risks...................................................................................................... 39
12. Insurance .................................................................................................................... 39
13 Queries about the Contract Data ................................................................................. 40
14. Contractor to Construct the Works ............................................................................ 40
15. The Works to Be Completed by the Intended Completion Date ............................... 40
16. Approval by the Consulting Engineer (CE) ............................................................... 40
17. Safety ......................................................................................................................... 40
18. Discoveries................................................................................................................. 40
19. Possession of the Site ................................................................................................. 41
20. Access to the Site ....................................................................................................... 41
21. Instructions, Inspections and Audits .......................................................................... 41
22. Disputes ..................................................................................................................... 41
5
B. Time Control ................................................................................................................... 42
23. Program ...................................................................................................................... 43
24. Extension of the Intended Completion Date .............................................................. 43
25. Acceleration ............................................................................................................... 43
26. Delays Ordered by the Consulting Engineer ............................................................ 44
27. Management Meetings ............................................................................................... 44
28. Early Warning ............................................................................................................ 44
C. Quality Control................................................................................................................ 45
29. Identifying Defects .................................................................................................... 45
30. Tests ........................................................................................................................... 45
31. Correction of Defects ................................................................................................. 45
32. Uncorrected Defects .................................................................................................. 45
D. Cost Control .................................................................................................................... 46
33. Bill of Quantities ........................................................................................................ 47
34. Changes in the Quantities .......................................................................................... 47
35. Variations ................................................................................................................... 47
36. Payments for Variations............................................................................................. 47
37. Cash Flow Forecasts .................................................................................................. 48
38. Payment Certificates .................................................................................................. 48
39. Payments .................................................................................................................... 48
40. Compensation Events ................................................................................................ 48
41. Tax ............................................................................................................................. 50
42. Retention .................................................................................................................... 50
43. Liquidated Damages .................................................................................................. 50
44. Advance Payment ...................................................................................................... 51
45. Securities .................................................................................................................... 51
46. Day Works ................................................................................................................. 52
47. Cost of Repair ............................................................................................................ 52
E. Finishing the Contract ..................................................................................................... 53
48. Completion................................................................................................................. 54
49. Taking Over ............................................................................................................... 54
50. Final Account ............................................................................................................. 54
51. Operating and Maintenance Manuals ........................................................................ 54
52. Termination ................................................................................................................ 54
53. Payment upon Termination ........................................................................................ 55
54. Property ...................................................................................................................... 56
55. Release from Performance ......................................................................................... 56
56. Suspension of Project Financing................................................................................ 56
57. FIDIC ......................................................................................................................... 56
6
SECTION 5.............................................................................................................................. 57
CONTRACT DATA ................................................................................................................ 57
Bidding and Contract Data .................................................................................................. 58
SECTION 6.............................................................................................................................. 61
LETTER OF ACCEPTANCE ......................................................................................... 70
FORMAT OF TENDER SECURITY [Option 2–Insurance Guarantee]......................... 72
FORM OF TENDER-SECURING DECLARATION .................................................... 73
AGREEMENT ................................................................................................................. 74
Advance Payment Guarantee ......................................................................................... 75
Defects Liability Guarantee ............................................................................................. 78
Taking-Over Certificate ................................................................................................... 81
Defects Liability Certificate............................................................................................. 82
SECTION 7.............................................................................................................................. 83
TECHNICAL SPECIFICATIONS .......................................................................................... 83
3-2 WORKS OF WATER SUPPLY SYSTEMS ................................................................. 92
SUPPLY AND INSTALLATION OF WATER TANKS ................................................... 92
Regulation of the water level in the water tower ..................................................................... 95
CONSTRUCTION OF TAP POST ....................................................................................... 100
SECTION 8............................................................................................................................ 101
BILL OF QUANTITIES ........................................................................................................ 101
TABLE OF CONTENTS....................................................................................................... 102
APPENDIX A: LIST OF LOCALITES ................................................................................ 110
APPENDIX B: DRAWINGS ................................................................................................ 114
7
SECTION 1
INVITATION TO BIDDERS
8
Date: 22/01/2023
The Saudi Program for Drilling of Wells and Rural Development in Africa - Phase V
Dear Sir,
We are pleased to herewith forward to you the Tender Documents for Construction of
about (110) drilled-wells (water Boreholes) equipped with solar pumping system,
elevated water tanks, 30 water distribution Network System (with a various piping
diameters), concrete posts each Two taps and one meter. Of the Saudi Program for
Drilling of Wells and Rural Development in Africa, phase V in the Mali.
Please be aware that the evaluation of your offer will follow the selection criteria laid
out in Section 6, (Forms of Bids and Contract). Each tenderer must submit a separate
offer.
For details on the actual situation in the different project region as access, location and
hydrogeological situation of the well sites as well as for the standard design of the wells
and water supply systems each tenderer has to visit the project area and to contact the
local authorities (Water department) in the Mali.
Yours sincerely
9
SECTION 2
GENERAL INFORMATION
10
Section -2: General Information – The Republic of Mali
Mali lies mostly between latitudes 9° and 15°N (a small area is north of 15°), and longitudes
6°W and 3°E.
It is made up of two major types of countryside. The larger part of the country is covered by a
peneplain, which forms a gently undulating landscape with, in some areas, a few isolated hills,
the last vestiges of a Precambrian massif. The southwest of the country, on the other hand,
forms a sandstone massif, where the highest peak, Ténakourou, is found at an elevation of 749
meters (2,457 ft). The massif is bordered by sheer cliffs up to 150 m (492 ft) high. The average
altitude of Mali is 400 m (1,312 ft) and the difference between the highest and lowest terrain
is no greater than 600 m (1,969 ft). Mali is therefore a relatively flat country.
The country owes its former name of Upper Volta to three rivers which cross it: the Black
Volta (or Mouhoun), the White Volta (Nakambé) and the Red Volta (Nazinon). The Black
Volta is one of the country's only two rivers which flow year-round, the other being the Komoé,
which flows to the southwest. The basin of the Niger River also drains 27% of the country's
surface.
The Niger's tributaries – the Béli, Gorouol, Goudébo, and Dargol – are seasonal streams and
flow for only four to six months a year. They still can flood and overflow, however. The
country also contains numerous lakes – the principal ones are Tingrela, Bam, and Dem. The
country contains large ponds, as well, such as Oursi, Béli, Yomboli, and Markoye. Water
shortages are often a problem, especially in the north of the country.
Savannah near the Gbomblora Department, on the road from Gaoua to Batié
Administrative divisions
Main articles: Regions of Mali, Provinces of Mali, and Departments of Mali
The country is divided into 13 administrative regions. These regions encompass 45 provinces
and 301 departments. Each region is administered by a governor.
Water
The Grand marché in Koudougou, Mali
While services remain underdeveloped, the National Office for Water and Sanitation (ONEA),
a state-owned utility company run along commercial lines, is emerging as one of the best-
performing utility companies in Africa.[110] High levels of autonomy and a skilled and
dedicated management have driven ONEA's ability to improve production of and access to
clean water.
Since 2000, nearly 2 million more people have access to water in the four principal urban
centres in the country; the company has kept the quality of infrastructure high (less than 18%
of the water is lost through leaks one of the lowest in sub-Saharan Africa), improved financial
reporting, and increased its annual revenue by an average of 12% (well above inflation).
Challenges remain, including difficulties among some customers in paying for services, with
the need to rely on international aid to expand its infrastructure. The state-owned,
commercially run venture has helped the nation reach its Millennium Development Goal
(MDG) targets in water-related areas, and has grown as a viable company.
However, access to drinking water has improved over the last 28 years. According to UNICEF,
access to drinking water has increased from 39 to 76% in rural areas between 1990 and 2015.
In this same time span, access to drinking water increased from 75 to 97% in urban areas
Climate
Mali has a primarily tropical climate with two very distinct seasons. In the rainy season, the
country receives between 60 and 90 cm (23.6 and 35.4 in) of rainfall; in the dry season, the
harmattan – a hot dry wind from the Sahara – blows. The rainy season lasts approximately four
months, May/June through September, and is shorter in the north of the country. Three climatic
11
zones can be defined: the Sahel, the Sudan-Sahel, and the Sudan-Guinea. The Sahel in the
north typically receives less than 60 cm (23.6 in)[74] of rainfall per year and has high
temperatures, 5–47 °C (41–117 °F).
A relatively dry tropical savanna, the Sahel extends beyond the borders of Mali, from the Horn
of Africa to the Atlantic Ocean, and borders the Sahara to its north and the fertile region of the
Sudan to the south. Situated between 11°3' and 13°5' north latitude, the Sudan-Sahel region is
a transitional zone with regards to rainfall and temperature. Further to the south, the Sudan-
Guinea zone receives more than 90 cm (35.4 in)[74] of rain each year and has cooler average
temperatures.
Natural resources
Mali's natural resources include gold, manganese, limestone, marble, phosphates, pumice, and
salt.
Wildlife and the environment
Mali has a larger number of elephants than many countries in West Africa. Lions, leopards
and buffalo can also be found here, including the dwarf or red buffalo, a smaller reddish-brown
animal which looks like a fierce kind of short-legged cow. Other large predators live in Mali,
such as the cheetah, the caracal or African lynx, the spotted hyena and the African wild dog,
one of the continent's most endangered species.[75]
Mali's fauna and flora are protected in four national parks:
• The W National Park in the east which passes Mali, Benin, and Niger
• The Arly Wildlife Reserve (Arly National Park in the east)
• The Léraba-Comoé Classified Forest and Partial Reserve of Wildlife in the west
• The Mare aux Hippopotames in the west
12
SECTION 3
INSTRUCTIONS TO BIDDERS
13
Section 3: Instructions to Bidders
A. General
1. Scope of Bid 1.1 The Employer as defined in the Contract Data, invites bids for the
construction of Works, as described in the Contract Data. The name and
identification number of the Contract is provided in the Bidding Data and
Contract Data.
1.2 The successful Bidder will be expected to complete the Works by the
Intended Completion Date specified in the Contract Data.
2. Source of 2.1 The Beneficiary, as defined in the Contract Data, intends to apply the funds
Funds of the Employer financing, as defined in the Bidding Data, towards the cost
of the Project, as defined in the Bidding Data, to cover eligible payments
under the Contract for the Works. Payments by the Employer will be
made only at the request of the Consulting Engineer as defined in the
Bidding Data and Contract Data and upon approval by the Employer in
accordance with the Financing Agreement, and will be subject in all
respects to the terms and conditions of that Agreement. Except as the
Employer may specifically otherwise agree, no party other than the
Beneficiary shall derive any rights from the Financing agreement or
have any rights to the financing proceeds.
3.2 All bidders shall provide their bid in the form in section 6.
14
If the Employer has not undertaken prequalification of potential bidders,
4.3
all bidders shall include the following information and documents with
their bids in Section 6, unless otherwise stated in the Bidding Data:
(c) experience in works of a similar nature and size for each of the
last five years, and details of work under way or contractually
committed and clients who may be contacted for further
information on those contracts;
(a) the Bid shall include all the information listed in Sub-
Clause 4.3 above for each joint venture partner:
15
(c) all partners shall be jointly and severally liable for the
execution of the Contract in accordance with the Contract
terms.
To qualify for award of the Contract, bidders shall meet the following
4.5 minimum qualifying criteria:
16
5. One Bid per 5.1 Each Bidder shall submit only one Bid, either individually or as a
Bidder partner in a joint venture. A Bidder who submits or participates in more
than one Bid (other than as a subcontractor or in cases of alternatives that
have been permitted or requested) will cause all the proposals with the
Bidder's participation to be disqualified.
6. Cost of 6.1 The Bidder shall bear all costs associated with the preparation and
Bidding submission of his Bid, and the Employer will in no case be responsible or
liable for those costs.
7. Site Visit 7.1 Considering the COVID 19 pandemics, the site visit is not compulsory and
left to the discretion of the bidders.
However If the bidder still would like to visit the sites in order to obtain
complementary information for preparing the bid, it is recommended to
liaise with the coordinator of the program
Mr. Damassa Bouare, Head of programming and project monitoring
section on email: bouaredamassa@yahoo.fr , phone: 76 16 25 46
17
B. Bidding Document
8. Content of 8.1 The set of bidding documents comprises the documents listed in the
Bidding table below and addenda issued in accordance with Clause 10:
Documents
Section 3 Instructions to Bidders
Section 4 Conditions of Contract
Section 5 Contract Data
Section 6 Forms of Bid and Contract
Section 7 Specifications
Section 8 Drawings, Technical Data sheet and Sketches
Section 9 Bill of Quantities
18
C. Preparation of Bids
11. Language of 11.1 All documents relating to the Bid shall be in the English language.
Bid
12. Documents 12.1 The Bid submitted by the Bidder shall comprise the following:
Comprising the
(a) The Bid (in the form in Section 6)
Bid
(b) Bid Security in the forms in Section 6
(c) Priced Bill of Quantities (Section 9)
(d) Qualification Information Form and Documents
(form in Section 6)
(e) Alternative offers if any
13. Bid Prices 13.1 The Contract shall be for the whole Works as described in Sub- Clause
1.1, based on the priced Bill of Quantities submitted by the Bidder.
13.2 The Bidder shall fill in rates and prices for all items of the Works described
in the Bill of Quantities. Items for which no rate or price entered by the
Bidder will not be paid for by the Employer when executed and shall
be deemed covered by the other rates and prices in the Bill of Quantities.
14. Currencies 14.1 The unit rates and prices shall be quoted by the Bidder entirely in
of Bid and American dollars. Payment will be in American dollars.
Payment
15. Bid Validity 15.1 Bids shall remain valid for a period of 180 days after the dead line for
the Bid submission specified in the tender document.
15.2 In exceptional circumstances, the Employer may request that the bidders
extend the period of validity for a specified additional period. The
request and the bidders' responses shall be made in writing or by cable.
A Bidder agreeing to the request will not be required or permitted to
otherwise modify the Bid, but will be required to extend the validity
of Bid Security for the period of the extension, and in compliance with
Clause 16 in all respects.
19
16. Bid Security 16.1 The Bidder shall furnish, as part of the Bid, a Bid Security in American
dollars, at height between 2% to 5% of the bid price.
16.2 The Bid Security shall, at the Bidder's option, be in the form of a certified
check, letter of credit, bank guarantee from a banking institution, or a
bond issued by an insurance or bonding institution from a reputable
institution selected by the Bidder and located in any eligible country.
The format of the Bid Security should be in accordance with one of the
forms of Bid Security included in Section 6 or another form acceptable
to the Employer. Bid Security shall be valid for 28 days beyond the
validity of the Bid.
16.3 Any bid not accompanied by an acceptable Bid Security shall be rejected
by the Employer. The Bid Security of a joint venture must define as
"bidder" all joint venture partners and list them in the following manner:
a joint venture consisting of "-----------"
And "-----------"
16.4 The Bid Security of unsuccessful bidders will be returned within 30 days
of the end of the Bid validity period specified in Sub- Clause 15.1 above.
16.5 The Bid Security of the successful Bidder will be discharged when the
Bidder has signed the Agreement and furnished the required Performance
Security.
(a) if the Bidder withdraws the Bid after Bid opening during the period
of Bid validity;
(b) if the Bidder does not accept the correction of the Bid price, pursuant
to Clause 27: or
(c) in the case of a successful Bidder, if the Bidder fails within the
specified time limit to
20
"ORIGINAL." in addition, the Bidder shall submit copies of the Bid and
clearly marked as ''COPIES." in the event of discrepancy between them,
the original shall prevail.
18.2 The original and all copies of the Bid shall be typed or written in indelible
ink and shall be signed by a person or persons duly authorized to sign on
behalf of the Bidder, pursuant to Sub- Clauses 4.3(a) or 4.4(b), as the case
may be. All pages of the Bid where entries or amendments have been
made shall be initiated by the person or persons signing the Bid.
21
D. Submission of Bids
22
19. Sealing 19.1 The Bidder shall seal the original and all copies of the Bid in two inner
marking and envelopes and one outer envelope, duly marking the inner envelopes as
"ORIGINAL" and "COPIES'".
presentation of
Bids 19.2 The inner and outer envelopes shall:
(b) bear the name and identification number of the Contract as defined in
the Contract Data; and
(c) Provide a warning not to open before the specified time and date for
Bid opening as defined in the Bidding Data.
19.4 If the outer envelope is not sealed and marked as above, the Employer
will assume no responsibility for the misplacement or
premature opening of the Bid.
19.5 Each Original and Copy Envelop will contain the followings:
Technical file:
(1) Power of Attorney to sign the Proposal
(2) Letter of Bid
(3) The Bid Security (please refer to form in section 6)
(4) TECH-1:
• The Technical Submission Form (please refer to section 6),
• If the Proposal is submitted by a joint venture, attach a
letter of intent or a copy of an existing agreement.
• No pre-set format/form. In the case of a Joint Venture,
several are required: a power of attorney for the authorized
representative of each JV member, and a power of attorney
for the representative of the lead member to represent all
JV members
(5) TECH-2 :
• Contractor Statutory Documents
• Contractor’s Organization
• Contractor’s relevant experience:
1. Water supply (number and Km) and well
construction (number of wells and depth)
2. Surface Construction,
3. Experience in Sub-Saharan Africa
4. Experience with the SFD.
(6) TECH-3 :
• Contractor’s Organization for implementing the works
(Please include the organization Chart showing the
relationship between the Project Management Staff (senior
23
staff and support staff from the HQ), the Key Field Staff
and the subcontractors.
• The CVs of the Key Field Staff in English and highlighting
the relevant experience (please refer to section 6
Qualification information):
1. Project Manager (Engineer),
2. Civil Engineer,
3. Hydrogeologist/Geophysicist Engineer,
4. Hydraulic Engineer,
5. Surveyor Engineer,
6. Solar system expert (Engineer)
7. Animation Expert (Social Expert speaking local
languages and French).
• The list of the non key staff :name, position and year of
relevant experience (Survey team (at least 3 persons), one
Auto CAD operator, two Drillers, two Assistant drillers,
five Skilled labourers (masons, electricians and
mechanics), five car drivers, one crane driver).
AND
Sealed Envelope with the Financial Proposal:
(1) Priced Bill of Quantity,
The cost breakdown of each unit price (Material, Labour, Equipment,
Overhead, Profit)
24
20. Deadline for 20.1 Bids shall be delivered to the Employer at the address specified in the
Sub-mission of Bidding Data later than the time and date specified in the Bidding Data.
Bids
20.2 The Employer may extend the deadline for submission of bids by issuing
an amendment in accordance with Clause 10, in which case all rights
and obligations of the Employer and the bidders previously subject to the
original deadline will then be subject to the new deadline.
21. Late Bids 21.1 Any Bid received by the Employer after the deadline prescribed in
Clause 20 will be returned unopened to the Bidder.
22. 22.1 Bidders may modify or withdraw their bids by giving notice in writing
Modification before the deadline prescribed in Clause 20.
And
22.2 Each Bidder's modification or withdrawal notice shall be prepared,
Withdrawal of sealed, marked, and delivered in accordance with Clauses 18 and
Bids 19, with the outer and inner envelopes additionally marked
"MODIFICATION" or "WITHDRAWAL," as appropriate.
22.3 No Bid may be modified after the deadline for submission of Bids.
22.4 Withdrawal of a Bid between the deadline for submission of bids and the
expiration of the period of Bid validity specified in clause 15.1 above or
as extended pursuant to Sub-Clause 15.2 may result in the forfeiture of
the Bid Security pursuant to Clause 16.
22.5 Bidders may only offer discounts to, or otherwise modify the prices
of their bids by submitting Bid modifications in accordance with this
clause, or included in the original Bid submission.
25
E. Bid Opening and Evaluation
26
23. Bid 23.1 The Employer will open the bids, including modifications made pursuant
Opening to Clause 22, in the presence of the bidders' representatives who choose
to attend at the time and in the place specified in the Bidding Data.
23.2 Bids for which an acceptable notice of withdrawal has been submitted
pursuant to Clause 22 shall not be opened.
23.3 The bidders' names, the Bid prices, the total amount of each Bid and of
any alternative Bid (if alternatives have been requested or permitted),
any discounts, Bid modifications and withdrawals, the presence or
absence of Bid Security, and such other details as the Employer may
consider appropriate, will be announced by the Employer at the opening.
The Employer will prepare minutes of the Bid opening, including the
23.4 information disclosed to those present in accordance with Sub-Clause
23.3
24. Process to 24.1 Information relating to the examination, clarification, evaluation, and
Be Confidential comparison of bids and recommendations for the award of a contract shall
not be disclosed to bidders or any other persons not officially concerned
with such process until the award to the successful Bidder has been
announced. Any effort by a Bidder to influence the Employer's
processing of bids or award decisions may result in the rejection of
his Bid.
25. 25.1 From the time of bid opening to the time of contract award, if any
Clarification of bidder wishes to contact the Employer on any matter related to the bid,
it should do so in writing.
Bids and
Contacting the 25.2 To assist in the examination, evaluation, and comparison of bids, the
Employer Employer may, at the Employer's discretion, ask any Bidder for
clarification of the Bidder's Bid, including breakdowns of unit rates
The request for clarification and the response shall be in writing or by
cable but no change in the price or substance of the Bid shall be sought,
offered, or permitted except as required to confirm the correction of
arithmetic errors discovered by the Employer in the evaluation of the bids
in accordance with Clause 27.
25.3 Any effort by the Bidder to influence the Employer in the Employer's bid
evaluation, bid comparison or contract award decisions may result in the
rejection of the Bidders' bid.
27
26. 26.1 Prior to the detailed evaluation of bids, the Employer will determine
Examination of whether each Bid (a) meets the eligibility criteria defined in Clause
3; (b) has been properly signed; (c) is accompanied by the required
Bids and
securities; and (d) is substantially responsive to the requirements of the
Determination bidding documents.
Of 26.2 A substantially responsive Bid is one which conforms to all the terms,
Responsiveness conditions, and specifications of the bidding documents, without
material deviation or reservation. A material deviation or reservation is
one (a) which affects in any substantial way the scope, quality, or
performance of the Works; (b) which limits in any substantial way,
inconsistent with the bidding documents, the Employer's rights or the
Bidder's obligations under the Contract; or (c) whose rectification would
affect unfairly the competitive position of other bidders presenting
substantially responsive bids.
27.2 The amount stated in the Bid will be adjusted by the Employer in
accordance with the above procedure for the correction of errors and, with
the concurrence of the Bidder, shall be considered as binding upon the
Bidder. If the Bidder does not accept the corrected amount, the Bid
will be rejected, and the Bid Security may be forfeited in accordance with
Sub-Clause I 6.6(b).
28. Currency 28.1 Bids will be evaluated as specified in clause 14.1
for Bid
Evaluation
28
29. Evaluation 29.1 The Employer will evaluate and compare only the bids determined
and to be substantially responsive in accordance with Clause 26.
Comparison of
29.2 In evaluating the bids, the Employer will determine for each Bid the
Bids evaluated Bid price by adjusting the Bid price as follows:
29.3 The Employer reserves the right to accept or reject any variation,
deviation, or alternative offer. Variations, deviations, and alternative
offers and other factors which are in excess of the requirements of the
bidding documents or otherwise result in unsolicited benefits for the
Employer will not be taken into account in Bid evaluation.
29.4 The estimated effect of any price adjustment conditions under Clause 47
of the Conditions of Contract, during the period of implementation of the
Contract, will not be taken into account in Bid evaluation.
29
F. Award of Contract
30. Award 30.1 Subject to Clause 31, the Employer will award the Contract to the Bidder
Criteria whose Bid has been determined to be substantially responsive to the
bidding documents and who has offered the lowest evaluated Bid price,
provided that such Bidder has been determined to be:
(a) eligible in accordance with the provisions of Clause 3, and
(b) qualified in accordance with the provisions of Clause 4.
31. Employer's 31.1 Notwithstanding Clause 30, the Employer reserves the right to accept or
Right to Accept reject any Bid, and to cancel the bidding process and reject all bids, at any
time prior to the award of Contract, without thereby incurring any liability
any Bid and to
to the affected Bidder or bidders or any obligation to inform the affected
Reject any or Bidder or bidders of the grounds for the Employer's action.
all Bids Furthermore, rejection of all bids may be following two cases:
1- the bids are not compliant with the tender documents
2- reception of less than 3 bids
32. Notification 32.1 The contract shall be awarded to the bidder whose bid has been determined
of Award and to have given clear proof of the required technical and financial ability,
and the best economic financial evaluation
Signing of
The Bidder whose Bid has been accepted will be notified of the award by
Agreement the Employer prior to expiration of the Bid validity period by cable
confirmed by registered letter. This letter (hereinafter and in the
Conditions of Contract called the "Letter of Acceptance") form shown in
Section 6 will state the sum that the Employer will pay to the Contractor
in consideration of the execution, completion, and maintenance of the
Works by the Contractor as prescribed by the Contract (hereinafter and in
the Contract called the "Contract Price").
32.2 The notification of award will constitute the formation of the Contract,
subject to the Bidder furnishing the Performance Security in accordance
with Clause 33 and signing the Agreement in accordance with Sub-
Clause 32.3.
32.4 Upon the furnishing by the successful Bidder of the Performance Security,
the Employer will promptly notify the other bidders that their bids have
been unsuccessful.
30
33. 33.1 Within 21 days after reception of the Letter of Acceptance, the successful
Performance Bidder shall deliver to the Employer a Performance Security in the amount
stipulated in the Contract Data and in the form (Bank Guarantee and/or
Security
Bond) stipulated in the Bidding Data, denominated in the type and
proportions of currencies in the Letter of Acceptance and in Accordance
with the Conditions of Contract.
The mount of the Performance Security shall not be less than 10% of the
contract price
33.4 Failure of the successful Bidder to comply with the requirements of Sub-
Clause 33.1 shall constitute sufficient grounds for cancellation of the
award and forfeiture of the Bid Security.
34. Advance 34.1 The Employer will provide an Advance Payment on the Contract Price as
Payment stipulated in the Conditions of Contract, subject to a maximum amount of
20% of the contract price against a valid Advance Payment Guarantee.
(a) defines, for the purposes of this provision, the terms set forth
below as follows:
31
G. Bidding Data
Construction of about (110) drilled-wells (water Boreholes) equipped with solar pumping system,
elevated water tanks, 30 water distribution Network System (with a various piping diameters),
concrete posts each Two taps and one meter.
Instructions to Bidders Reference
Clause
2.1 - - The Project Name is The Saudi Program for Drilling of Wells and Rural
Development in Africa, Phase V – Republic of Mali - The Project
Identification Number is P5/2021/Mali - The Employer is The Saudi Fund
2.1 - (Instruction to For Development SFD P.O. Box 50483, Riyadh, 11523, Kingdom of Saudi
Bidders) Arabia. - The Beneficiary is Ministry of Water and Sanitation – Mali.
33
SECTION 4
Conditions of Contract
34
A. General
35
1. Definitions 1.1 Boldface type is used to identify defined terms.
The Start Date is given in the Contract Data. It is the latest date
when the Contractor shall commence execution of the Works.
It does not necessarily coincide with any of the Site Possession
Dates.
(1) Agreement,
(2) Letter of Acceptance,
(3) Contractor’s Bid.
(4) Contract Data,
(5) Conditions of Contract,
(6) Specifications,
(7) Drawings,
(8) Bill of Quantities and
(9) any other document listed in the Contract Data as forming
part of the Contract.
The language of the Contract and the law governing the Contract
3. Language and 3.1 are stated in the Contract Data.
law
Except where otherwise specifically stated, the Consulting
4.1 Engineer (CE) will decide contractual matters between the
4. Consulting
Employer and the Contractor in the role representing the
Engineer’s Employer.
Decisions
The Consulting Engineer (CE) may delegate any of his
5. Delegation 5.1 duties and responsibilities to other people after notifying the
Contractor, and may cancel any delegation after notifying the
Contractor.
38
stating the reasons, the Contractor shall ensure that the person
leaves the Site within seven days and has no further connection
with the work in the Contract.
9. Employer’s and The Employer carries the risks which this Contract states are
Contractor’s 9.1 Employer’s risks, and the Contractor carries the risks which this
Contract states are Contractor’s risks.
Risks
10. Employer’s By this contract the employer does not carry any risk. The contractor
Risks 10.1 shall notify the consultant engineer and/or the employer to any
probable risk to be agreed on the consequence.
11. Contractor’s From the Starting Date until the Defects Correction
Risks 11.1 Certificate has been issued, the risks of personal injury, death,
and loss of or damage to property (including, without
limitation, the Works, Plant, materials, and Equipment).
12. Insurance The Contractor shall provide, in the joint names of the
12.1 Employer and the Contractor, insurance cover from the Start
Date to the end of the Defects Liability Period, in the
amounts and deductibles stated in the Contract Data for the
following events which are due to the Contractor’s risks:
(a) loss of or damage to the Works, Equipment, Plant, and
Materials;
(b) Professional Liability Insurance;
(c) loss of or damage to property (except the Works,
Plant, Materials, and Equipment) in connection with the
Contract = Third Party Insurance;
(d) Personal injury or death.
39
13 Queries about The Consulting Engineer (CE) will clarify queries on the Contract
13.1 Data.
the Contract Data
The Contractor shall construct and install the Works in accordance
14. Contractor to with the Specifications and Drawings, beside he shall:
Construct the
Works 14.1 (a) Provide an office at his base camp for the Consultant
Engineer (EC) with all facilities; furniture, laptops, printing,
facsimile, digital cameras, refrigerator, etc…
(b) Two four wheel drive vehicles for the sole use of the
Supervisor and the Animation Expert
15. The Works to All the operation costs of the Consultant premises as well as the
three 4WD (including driver cost) are to be provided by the
Be Completed by
Contractor.
the Intended 15.1
Completion Date
40
19. Possession of The Employer shall give possession of all parts of the Site to
the Site the Contractor. If possession of a part is not given by the date
19.1 stated in the Contract Data, the Employer will be deemed
to have delayed the start of the relevant activities, and this will
be a Compensation Event.
20. Access to the
The Contractor shall allow the Consulting Engineer (CE) and
Site any person authorized by the Consulting Engineer (CE) access
20.1 to the Site and to any place where work in connection with
the Contract is being carried out or is intended to be carried
out.
21. Instructions,
Inspections and The Contractor shall carry out all instruction of the Consulting
Audits Engineer (CE) which comply with the applicable laws where
21.1 the Site is located.
41
B. Time Control
42
23. Program 23.1 Within the time stated in the Contract Data, the Contractor shall
submit to the Consulting Engineer (CE) for approval a Program
showing the general methods, arrangements, order, and timing for
all the activities in the Works..
23.3 The Contractor shall submit to the Consulting Engineer (CE) for
approval an updated Program at intervals no longer than the period
stated in the Contract Data. If the Contractor does not submit
an updated Program within this period, the Consulting Engineer
(CE) may withhold the amount stated in the Contract Data from
the next payment certificate and continue to withhold this
amount until the next payment after the date on which the
overdue Program has been submitted.
23.4 The Consulting Engineer’s (CE) approval of the Program shall not
alter the Contractor’s obligations. The Contractor may revise
the Program and submit it to the Consulting Engineer (CE) again at
any time. A revised Program shall show the effect of
Variations and Compensation Events.
24. Extension 24.1 The Consulting Engineer (CE) shall extend with the approval of the
employer the Intended Completion Date if a Compensation Event
of the occurs or a Variation is issued which makes it impossible for
Intended Completion to be achieved by the Intended Completion Date
Completion without the Contractor taking steps to accelerate the remaining
Date work, which would cause the Contractor to incur additional cost.
24.2 The Consulting Engineer (CE) shall decide whether and by how
much to extend the Intended Completion Date within 21 days
of the Contractor asking the Consulting Engineer (CE) for a
decision upon the effect of a Compensation Event or Variation
and submitting full supporting information. If the Contractor has
failed to give early warning of a delay or has failed to cooperate
in dealing with a delay, the delay by this failure shall not
be considered in assessing the new Intended Completion Date.
25. 25.1 When the Employer wants the Contractor to finish before the
Intended Completion Date, the Consulting Engineer (CE) will
Acceleration
obtain priced proposals for achieving the necessary acceleration
from the Contractor. If the Employer accepts these proposals, the
Intended Completion Date will be adjusted accordingly and
confirmed by both the Employer and the Contractor.
25.2 If the Contractor’s priced proposals for an acceleration are
accepted by the Employer, they are incorporated in the Contract
Price and treated as a Variation.
43
The Consulting Engineer (CE) may instruct the Contractor to delay the
26.1 start or progress of any activity within the Works.
26. Delays
Ordered by
the
Consulting
Engineer
Either the Consulting Engineer (CE) or the Contractor may require
27.1 the other to attend a management meeting. The business of a
27. management meeting shall be to review the plans for remaining
Management work and to deal with matters raised in accordance with the early
Meetings warning procedure.
The Consulting Engineer (CE) shall record the business of
27.2 management meetings and provide copies of the record to those
attending the meeting and to the Employer. The responsibility
of the parties for actions to be taken shall be decided by the
Consulting Engineer (CE) either at the management meeting or
after the management meeting and stated in writing to all who
attended the meeting.
The Contractor shall warn the Consulting Engineer (CE) at the earliest
28.1 opportunity of specific likely future events or circumstances that may
28. Early
adversely affect the quality of the work, increase the Contract Price
Warning or delay the execution of the Works. The Consulting Engineer (CE)
may require the Contractor to provide an estimate of the expected
effect of the future event or circumstance on the Contract Price and
Completion Date.. The estimate shall be provided by the
Contractor as soon as reasonably possible.
The Contractor shall cooperate with the Consulting Engineer
28.2 (CE) in making and considering proposals for how the effect of
such an event or circumstance can be avoided or reduced by
anyone involved in the work and in carrying out any resulting
instruction of the Consulting Engineer (CE).
44
C. Quality Control
29. 29.1 The Consulting Engineer (CE) shall check the Contractor’s work
and notify the Contractor of any Defects that are found. Such
Identifying
checking shall not affect the Contractor’s responsibilities. The
Defects Consulting Engineer (CE) may instruct the Contractor to s e a r c h for
a Defect and to uncover and test any work that the
Consulting Engineer (CE) considers may have a Defect.
30. Tests 30.1 If the Consulting Engineer (CE) instructs t h e Contractor to carry out
a test not specified i n the Specification to check whether any work
has a Defect and the test shows that it does, the Contractor shall
pay for the test and any samples. If there is no Defect, the test
shall he a Compensation Event.
31. 31.1 The Consulting Engineer (CE) shall give notice to the Contractor
of any Defects before the end of the Defects Liability Period,
Correction of
which begins at Completion, and is defined in the Contract Data.
Defects The Defects Liability Period shall b e extended f o r as long as
Defects remain to be corrected.
31.2 Every time notice of Defect is given, the Contractor shall correct the
notified Defect within the length of time specified by the Consulting
Engineer’s (CE) notice.
32. 32.1 If the Contractor has not corrected a Defect within the time specified in
Uncorrected the Consulting Engineer’s (CE) notice, the Consulting Engineer will
Defects assess the cost of having the Defect corrected, and the Contractor will
pay this amount.
45
D. Cost Control
46
33. Bill of 33.1 The Bill of Quantities shall contain items for the construction,
installation, testing, and commissioning work to be done by the
Quantities
Contractor.
34. Changes 34.1 If the final quantity of the work done differs from the quantity in
in the the Bill of Quantities for the particular item by more than 25
percent, provided the change exceeds 1 percent of the Initial
Quantities Contract Price, the Consulting Engineer (CE) shall adjust the
rate to allow for the change.
34.2 The Consulting Engineer (CE) shall not adjust rates from changes
in quantities if thereby the Initial Contract Price is exceeded by more
than 15 percent, except with the prior approval of the Employer.
35. Variations 35.1 All Variations shall be included in updated Programs produced by the
Contractor.
36.4 If the Consulting Engineer (CE) decides that the urgency of varying
the work would prevent a quotation being given and
47
considered without delaying the work, no quotation shall be given
and the Variation shall be treated as a Compensation Event.
36.5
The Contractor shall not be entitled to additional payment for cost that
37. Cash Flow 37.1 could have been avoided by giving early warning.
Forecasts
When the Program is updated, the Contractor shall provide Consulting
38. Payment 38.1 Engineer (CE) with an updated cash flow forecast.
Certificates
The Contractor shall submit to the Consulting Engineer (CE) 3 months
statements of the estimated value of the work executed less than the
38.2 cumulative amount certified previously.
The value of work executed shall comprise the value of the quantities
of the items in the Bill of Quantities completed.
38.5
The value of work executed shall include the valuation of Variations
38.6 and Compensation Events.
Items of the Works for which no rate or price has been entered in will
not be paid for by the Employer and shall be deemed covered by
40. 40.1 other rates and prices in the Contract.
Compensation
The following shall be Compensation Events:
Events
(a) The Employer does not give access to a part of the Site by
the Site Possession Date stated in the Contract Data.
48
(c) The Consulting Engineer (CE) orders a delay or does not
issue Drawings, Specifications, or instructions required or
execution of the Works on time.
49
40.4 will assume that the Contractor will react competently and promptly to
the event.
50
• Liquidated damages are limited at a maximum of 10% of the contract
price
The Employer may, without prejudice to any other method of recovery,
deduct the amount of such penalty from any monies due to or to become
due to the Contractor, the Payment or deduction of such penalty shall
not relieve the Contractor from his obligations to complete the works,
or from any other of his obligations and liabilities under this Contract,
43.3 namely for damages caused by delay.
51
46. Day If applicable, the Day works rates in the Contractor’s Bid shall
Works be used for small additional amounts of work only when the
Consulting Engineer (CE) has given written instructions in advance
46.2 for additional work to be paid for in that way.
47.1
Loss or damage to the Works or Materials to be incorporated in
47. Cost of the Works between the Start Date and the end of the Defects Correction
Repair periods shall be remedied by the Contractor at the Contractor’s
cost if the loss or damage arises from the Contractor ‘s acts or
omissions.
52
E. Finishing the Contract
53
48. 48.1 The Contractor shall request the Consulting Engineer (CE) to issue
a certificate of Completion of the Works, and the Consulting Engineer
Completion
(CE) will do so upon deciding that the work is completed.
49. Taking 49.1 The Employer shall take over the Site and the Works with in seven
Over days of the Consulting Engineer’s (CE) issuing a certificate of
Completion.
50. Final 50.1 The Contractor shall supply the Consulting Engineer (CE) with a
Account detailed account of the total amount that the Contractor considers payable
under the Contract before the end of the Defects Liability Period. The
Consulting Engineer’s (CE) shall issue a Defects Liability Certificate
and certify any final payment that is due to the Contractor within 56 days
of receiving the Contractor’s account if it is correct and complete. If
not, the Consulting Engineer (CE) shall issue within 56 days a schedule
that states the scope of the corrections or additions that are necessary.
If the Final Account is still unsatisfactory after it has been resubmitted,
the Consulting Engineer’s (CE) shall decide on the amount payable to
the Contractor and issue a payment certificate.
51. Operating 51.1 If “as built” Drawings and/or operating and maintenance manuals are
required, the Contractor shall supply them by the dates stated in the
and
Contract Data.
Maintenance
Manuals If the Contractor does not supply the Drawings and/or manuals by the
51.2
dates stated in the Contract Data, or they do not receive the Consulting
Engineer’s (CE) approval, the Consulting Engineer (CE) shall withhold
the amount stated in the Contract Data from payments due to the
Contractor.
52.2 Fundamental breaches of Contract shall include, but shall not be limited to,
the following.
(a) The Contractor stops work for 28 days when no stoppage of work is
shown on the current Program and the stoppage has not been authorized
by the Consulting Engineer (CE).
(b) The Consulting Engineer (CE) instructs the Contractor to delay the
progress of the Works, and the instruction is not withdrawn within 28
days.
54
(c) The Employer or the Contractor is made bankrupt or goes into
liquidation other than for a reconstruction or amalgamation;
(e) The Consulting Engineer (CE) gives Notice that failure to correct a
particular Defect is a fundamental breach of Contract and the
Contractor fails to correct it within a reasonable period of time
determined by the Consulting Engineer (CE);
(f) The Contractor does not maintain a Security, which is required; and
(g) The Contractor has delayed the completion of the Works by the
number of days for which the maximum amount of liquidated damages
can be paid, as defined in the Contract Data.
52.3 When either party of the Contract gives notice of a breach of Contract
to the Consulting Engineer (CE) for a cause other than those listed
under Sub-Clause 52.2 above, the Consulting Engineer (CE) shall decide
whether the breach is fundamental or not.
52.5 If the Contract is terminated, the Contractor shall stop work immediately,
make the Site safe and secure, and leave the Site as soon as reasonably
possible.
53. Payment 53.1 If the Contract is terminated because of a fundamental breach of Contract
upon by the Contract or, the Consulting Engineer shall issue a certificate for
Termination the value of the work done and Materials ordered less advance payments
received up to the date of the issue of the certificate and less the
percentage to apply to the value of the work not completed, as indicated
55
in the Contract Data. Additional Liquidated Damages shall not apply. If
the total amount due to the Employer exceeds any payment due to the
Contractor, the difference shall be a debt payable to the Employer.
All Materials on the Site, Temporary Works’, and Works shall be deemed
54. Property to be the property of the Employer if the Contract is terminated because of
54.1 the Contractor’s default.
If the Contract is frustrated by the outbreak of war or by any other event
55. Release entirely outside the control of either the Employer or the Contractor, the
from 55.1 Consulting Engineer shall certify that the Contract has been frustrated.
The Contractor shall make the Site safe and stop work as quickly as
Performance
possible after receiving this certificate and shall be paid for all work
carried out before receiving it and for any work carried out afterwards
to which a commitment was made.
56
SECTION 5
CONTRACT DATA
57
Bidding and Contract Data
Reference
1.1 • Project Name: The Saudi Program for Drilling of Wells and Rural
(Instruction to Bidders) Development in Africa, Phase V - Mali
1.1 • The Donor is: The Saudi Fund for Development SFD
(Instruction to Bidders) P.O. Box: 50483
Riyadh, 11523
Kingdom of Saudi Arabia
2.1 • The Beneficiary is: The ministry of Water and Sanitation Mali.
(Instruction to Bidders)
2.1 • The Consultant Engineer is: Projects House For Engineering Consultin
(Instruction to Bidders) EDS DS INTERNATIONAL
• Project Country: Mali
• The Sites of Work:
110 villages in the four regions (KOULIKORO, SIKASSO, SEGOU and MOPTI).
• The Works Include:
• 110 Drilled Wells equipped with simplified solar system steel tanks and water pipe
1.1 • Work also includes animation/sensitization which means beneficiaries contact
(Condition of the Contract) with management and maintenance of the water system for awareness, during and
after construction.
• The work shall be completed with a maximum period of 18 months from start of
works. The period includes the rainy season. This is the intended completion date;
18 month after date of star of works.
19.1 The Contractor shall submit a revised Program for the works within 7 days of
(Condition of the Contract) the delivery of the letter of Acceptance.
23.1 The period between program update is one month. The amount to be withhold
(Condition of the Contract) for late submission of an update program is 10,000 USD.
53.1 The percentage to apply to the value of the work not completed is 100 %.
(Condition of the Contract)
59
60
SECTION 6
61
Project No.: P5/2021/ Mali
Tender No.: P5/2021/ Mali /Contractor
Project Title: The Saudi Program for Drilling of Wells and Rural Development in
Africa; Phase V in the Mali.
Contractor: …………………………………….
To: The Saudi Fund for Development SFD
P.O. Box: 50483
Riyadh, 11523
Kingdom of Saudi Arabia
Dear Sir,
1. Having examined the Conditions of Contract, Sketches, Technical Specifications, Bill
of Quantities and all other documents received with the Invitation to Tender for the
execution of the Works in connection with the above name Project and having
acquainted ourselves with all the local conditions and Sites, we, the undersigned, offer
to execute and complete such Works and remedy any faults and defects therein in
conformity with the conditions spelt out in aforementioned documents.
It is understood, that the Contract Price is an absolutely fixed upper limit of the remuneration
and payments due by the Employer and we agree to waive any rights which would have the
effect that this Contract Price is exceeded.
2. We undertake, if our Tender is accepted, to commence the Works within the time
required in the Contract Conditions, and to complete the whole of Works comprised in
the contract within the time stated in the Contract Conditions.
3. We agree to be bound by this Tender for the period of 180 days from the submission
date stated in the Invitation to Tender and it shall remain binding upon us and may be
accepted at any time before the expiration of that period.
4. Unless and until a Contract Agreement is signed, this Tender , together with your written
acceptance thereof, shall constitute a binding contract between us.
5. We understand that you are not bound to accept the lowest or any tender you may
receive.
62
Encl.: APPENDIX TO TENDER
Project name and Name of client and Type of work Value of contract
country Contact person performed and year of
completion
1.4 Major items of Contractor’s Equipment proposed for carrying out the
Works. List all information requested below. Refer also to Sub-Clause
4. 3(d ) of the Instructions to Bidders.
Item of Description, make, Condition (new, good, poor Owned, leased (from
equipment and age (years) and number available) whom?), or to be
purchased (from whom?)
63
1.5 Qualifications and experience of key personnel proposed for
administration and execution of the Contract. Attach biographical
data Refer also to Sub-Clause 4.3 c & e of the instructions to bidders
and Sub-Clause 9.1 of the Instruction to Bidders.
1.7 Financial reports for the last five years: balance sheets, profit and
loss statements, auditors’ reports, etc. List below and attach copies.
1.9 Name, address, and telephone, telex, and facsimile numbers of banks
that may provide references if contacted by the Employer.
64
1.12 Proposed Program (work method and schedule). Descriptions, drawings.
And charts, as necessary, to comply with the requirements of the bidding
documents.
2. Joint Ventures 2.1 The information listed in 1.1 - 1.11 above shall be provided for each
partner of the joint venture.
2.2 The information in 1.12 above shall be provided for the joint
venture.
2.3 Attach the power of attorney of the signatory of the Bid authorizing
signature of the Bid on behalf of the joint venture.
2.4 Attach the .Agreement among all partners of the joint venture (and
which is legally binding on all partners), which shows that
(a) all partners shall be jointly and severally liable for the
execution of the Contract in accordance with the Contract terms;
(a) Provide a Two new 4 - wheel drive car of reputable mark for the
sole use of Consultant Engineer and his crew.
(b) Provide an office in his base camp fully furnished and equipped
for the use of Consultant Engineer and his staff.
(c) Provide accommodation and transportation at all sites camp for
the Consultant Engineer and technicians.
65
Tender Evaluation
Criteria for the technical evaluation
The Technical criteria are stated in the Technical Evaluation Sheet:
1. Experience of the Company will be rated according to the number of similar projects
(more than 20 wells projects). The bidder with maximum experience will have a full
mark while the rest of bidders marks will be rated as a percentage:
(Number of References of the bidder / Number of references of the bidder having max
of references) X max score.
This will apply from items a to e in the Technical Evaluation Sheet below.
2. Technical Proposal will be evaluated by the Consultant as per his expertise. The
Evaluation report will detail the strength and weakness in each item of the technical
proposal (please refer to item 2 in the Technical Evaluation Sheet below).
3. Equipment for Execution of Works: The equipment will be evaluated as per the
Capacity, age and number. As stated in the Technical specification two method will
be used Rotary Drilling Technique or Down the Hole Hammer. The bidders who will
provide the two types of drilling rig will have full grade.
4. Drawings will be evaluated by the Consultant as per his expertise. The Evaluation
report will detail the strength and weakness of the suggested drawings by each bidder.
5. Timing will be evaluated by the Consultant as per his expertise. The Evaluation report
will detail the strength and weakness of the suggested time schedule by each bidder.
6. Staffing: will be evaluated by the Consultant as per his expertise.
a) Project Management Staff (senior staff and support staff from the HQ: Project
Director, Procurement team, logistic team, quality controller, support staff),
b) Field Management Staff: please refer to the marks in folio minimum staff,
c) Field Team, Qualification, number: please refer to the marks in folio
minimum staff.
Only bids attaining ≥ 70% will be accepted to qualify for further financial evaluation and
will be considered to be substantially responsive.
66
Bid without the bid guaranty will be considered as non-responsive bid and the financial offer
will not be evaluated.
SFD will grant the Saudi Contractors a privilege of 10% in the financial offer to
International firms from other Nationalities
Identification of anomalous pricing: Eventual anomalous unit prices will be discussed with the
prospective winner at the contract negotiation.
1. Identification of front loaded financial proposal: The Consultant will signal to the
SFD if the lowest evaluated bid is front loaded (cost that are applied
disproportionately to the works that take place early in the project to improve the cash
flow of the Contractor. The SFD will decide how to proceed:
a. Require the Bidder to produce detailed price analyses for any or all items of
the Schedules, to demonstrate the internal consistency of the prices with the
methods and schedule proposed.
b. Require that the amount of the performance security be increased at the
expense of the Bidder to a level sufficient to protect the SFD against financial
loss in the event of default of the successful Bidder under the Contract,
c. Consider the tender non responsive and negotiate with the next lowest bidder.
2. Identification of seriously unbalanced financial proposal: The Consultant will signal
to the SFD if the lowest evaluated bid is unbalanced. In that case the SFD will:
a. Require the Bidder to produce detailed price analyses for any or all items of
the Schedules, to demonstrate the internal consistency of the prices with the
methods and schedule proposed.
b. Consider the tender non responsive and negotiate with the next lowest bidder.
Technical Evaluation
Section 6 -Technical evaluation sheet
Contractor 1 Contractor n
Valuation Valuation
1. Experience of the Company Max Points critria Points critria
Note: Points estimated from prequalification Number of Number of
document projects projects
a) Water supply and well construction 5
b) Surface Construction 5
c) Sub-Saharan Africa 2
d) In the country 2
e) Experience in SFD funded programs 4
Total 1. 18
Consultant Consultant
2. Technical Proposal Max Points Points
evaluation evaluation
a) Overall Concept (organization structure of
the Contractor for the project and staff tasks), 5
Standards (compliance)
67
b) Drilling Concept, Digging methods 6
c) Water Supply network, tanks, solar pump
4
etc. (methodology)
d) Surface Constructions (methodology) 5
e) Construction Materials (quality) 3
f) Pumping and Testing Equipment 4
g) Animation concept and staffing 3
h) Maintenance, Spare Parts supply 4
i) Organization of Works 4
Total 2. 38
Compliance to Compliance to
Minimum Minimum
3. Equipment for Execution of Works Max Points Points
Equipment , Equipment ,
Capacity, age Capacity, age
The Contractor has to submit the minimum
required equipment listed in 4.5c in the
Instruction to Bidders.
a) Drilling/Digging Equipment
a.1) Mud Drilling rig (more than 300 m) 3
a.2) Down hole Hammer (more than 300 m) 3
b) Equipment for surface installations 3
c) Camps and supply installation 2
Total 3. 11
Consultant Consultant
4. Drawings Max Points Points
evaluation evaluation
a) Completeness of construction drawings 5
b) Quality of drawings, dimensions etc. 3
Total 4. 8
Consultant Consultant
5. Timing Max Points Points
evaluation evaluation
a) Specification of Time Schedule 5
b) Appropriateness 5
Total 5. 10
Minimum Minimum
5. Staffing Max Points Key staff and Points Key staff and
Experience Experience
a) Project Management Staff (senior staff
3
and support staff from the HQ)
b) Key Field Staff 8
b1. Project Manager (Engineer), 2
b2. Civil Engineer, 1
b3. Hydrogeologist/Geophysicist Engineer, 1
b4. Hydraulic Engineer, 1
b5. Surveyor Engineer, 1
b6. Solar system expert (Engineer) 1
b7. Animation Expert (Social Expert speaking
1
Swahili and English).
c) Field Team, Qualification, Number
(please refer to the minimum required staff 4
listed in 4.5c in the Instruction to Bidders).
Total 6. 15
Total 1 – 6* 100
68
* Minimum Percentage: 70% of Technical
Offer
Final Ranking: Offer with lowest price
knowing that the SFD will grant the Saudi
Contractors a privilege of 10% in the financial
offers compared to International firms from
other Nationalities
69
LETTER OF ACCEPTANCE
[date……………]
This is to notify you that your Bid dated [date] for execution of the [name of 1he Contract and
identification number, as given in the Contract Data] for the contract Price [amount in numbers and
words] [name of currency] is hereby accepted by our Agency.
You are hereby instructed to proceed with the execution of the said Works in accordance with
the Contract documents.
Attachment: Agreement
70
FORM OF TENDER SECURITY (BANK GUARANTEE)
(b) fails or refuses to furnish the Performance Security in accordance with the Instructions
to Tenderers,
We undertake to pay to the Purchaser the above-mentioned amount upon receipt of its first
written demand, without the Purchaser having to substantiate its demand, provided that the
Purchaser states in its demand that the amount claimed therein is due to the Purchaser owing to
the occurrence of one or both of the above conditions and specifies the condition or conditions
which have occurred.
This Guarantee shall remain in force up to and including the date falling
thirty (30) days after the period of validity of the Tender, as such period may be extended with
the agreement of the Tenderer, notice of which extension(s) is hereby waived by the Bank. Any
demand in respect of this Guarantee shall be
presented to the Bank not later than the date specified above.
Done in [name of city] on the ..................day of [month] of [year].
[Signature(s) on behalf of the Bank]
[Name(s) of Authorized Representative(s)]
[Designation(s)]
[Seal of the Bank]
71
FORMAT OF TENDER SECURITY [Option 2–Insurance Guarantee]
TENDER GUARANTEE No.:
1. Whereas ………… [Name of the tenderer] (hereinafter called “the tenderer”) has
submitted its tender dated ……… [Date of submission of tender] for the ……………
[Name and/or description of the tender] (hereinafter called “the Tender”) for the
execution of under Request for Tenders No. .
Sealed with the Common Seal of the said Guarantor this ___day of ______ 20 __.
3. NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if
the Applicant:
a) has withdrawn its Tender during the period of Tender validity set forth in the
Principal's Letter of Bid (“the Tender Validity Period”), or any extension thereto
provided by the Principal; or
b) having been notified of the acceptance of its Tender by the Beneficiary during
the Tender Validity Period or any extension thereto provided by the Principal; (i)
failed to execute the Contract agreement; or (ii) has failed to furnish the
Performance Security, in accordance with the Instructions to bidders (“ITB”) of
the Beneficiary 's Tendering document.
4. This guarantee will expire: (a) if the Applicant is the successful Tenderer, upon
our receipt of copies of the contract agreement signed by the Applicant and the
Performance Security and, or (b) if the Applicant is not the successful Tenderer,
upon the earlier of (i) our receipt of a copy of the Beneficiary's notification to
the Applicant of the results of the Tendering process; or (ii)twenty-eight days after
the end of the Tender Validity Period.
5. Consequently, any demand for payment under this guarantee must be received by
us at the office indicated above on or before that date.
_________________________ ______________________________
[Date ] [Signature of the Guarantor]
_________________________ ______________________________
[Witness] [Seal]
Note: All italicized text is for use in preparing this form and shall be deleted from the final product.
72
FORM OF TENDER-SECURING DECLARATION
[The Bidder shall complete this Form in accordance with the instructions indicated]
Date:................................................ [Insert date (as day, month and year) of Tender
Submission]
Tender No.:............................................... . [Insert number of tendering process]
To: ................................................ [Insert complete name of Purchaser]
Signed:…………………………………………………………………..……….. Capacity /
Name:…………………………………………………………………………….. Duly
authorized to sign the bid for and on behalf of: [insert complete name of Tenderer] Dated
This Agreement, made the [day] day of [month, [year] between [name of the Client or
Beneficiary] (hereinafter called “the Client” or “the Beneficiary”) and [name and address of
Contractor] (hereinafter called “the Contractor’”) of the other part.
Whereas the Employer is desirous that the Contractor executes / name and identification
number of Contract (hereinafter called the Works) and the Employer has accepted the Bid by
the Contractor for the execution and completion of such Works and the remedying of any
defects therein.
1. In this Agreement, words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred to, and they
shall be deemed to form and be read and construed as part of this Agreement.
In Witness whereof the parties thereto have caused this Agreement to be executed the day
and year first before written.
74
The Saudi Program for Drilling of Wells and
Rural Development in Africa; Phase V - Mali
SPECIMEN
Advance Payment Guarantee
Contractor: …………………………………………
…………………………………………
Object of Works: Construction of about (110) drilled-wells (water Boreholes) equipped with
solar pumping system, elevated water tanks, 30 water distribution Network System (with a
various piping diameters), concrete posts each Two taps and one meter.)
………………………………………………………
US$................................
(in words:.....................................................................)
Explicitly waiving all objections and defenses, we undertake to render said payment
upon receipt of the Employer first written demand, provided that the latter states that
the Contractor has failed to observe all or part of his contractual obligations.
In case of any claim under this guarantee payments by the Guarantor shall be made to the
account of the Saudi Fund for Development.
75
This guarantee shall become effective with the first advance payment made by the Employer
and shall expire when the advance payment has been set off in full.
The Employer shall return this guarantee to us as soon as its validity expires.
.........................................................
76
The Saudi Program for Drilling of Wells and
Rural Development in Africa; Phase V - Mali
Date: ..................................
To: ............................................................ [name and address of Employer]
Whereas, with a view to signature of a formal contract with .......................................
[name of Contractor] , whose principal place of business is at ............................................
.........................................[address of Contractor] , (hereinafter called the Contractor), you
have accepted a tender by the Contractor for the construction and completion of ..............
..............................................[state designation or short description of Works] (hereinafter called
the Works) and the remedying of any defects therein;
Whereas, by virtue of the acceptance of his tender, the Contractor is obligated to provide a
guarantee by a bank acceptable to you of the good performance of his obligations under the
contract made or to be made hereafter for the execution of the Works, (said contract hereinafter
referred to as the Contract); and
Whereas, we have agreed to furnish such bank guarantee.
NOW, THEREFORE, in consideration of your acceptance of this bank guarantee
in fulfillment of the Contractor's obligation to provide such guarantee, we, .......................
...........................[bank], waiving all objections and defences on the basis of the Contract,
hereby irrevocably and unconditionally undertake to pay to you up to the maximum
amount of ................................................................................................................[amount of
Guarantee in figures and words], without any demur to such payment, argument or delay, upon
your first written demand stating that the Contractor failed to perform any of his obligations under
the Contract, such statement by you being deemed as conclusive for the purpose of this bank
guarantee. In case of any claim by you under this bank guarantee, payment shall be made by us in
the types and proportions of the currencies in which, as stated by you in your demand, the Contract
Price is payable.
We hereby specifically waive any right we may have to require that you demand payment
by the Contractor before demanding payment under this bank guarantee.
We further agree that any forbearance or extension of time granted by you to the Contractor
or any change, addition to or modification of the Contract or of the Works to be executed
thereunder shall not in any way release us form our liability under this bank guarantee, and we
hereby waive any right to consent to or receive notice of such forbearance, extension of time,
change, addition or modification.
This guarantee shall be governed by the laws of ................................[state country of the
Employer] and the courts of that country shall have exclusive jurisdiction to
adjudicate on any dispute relating to the interpretation or application of this guarantee.
This guarantee shall be valid from the date hereof until 28 days after the issue of the Defect
Liability Certificate provided for in the Contract.
Signed .................................................
[Signature(s), as appropriate, on behalf of the
Guaranteeing Bank] [Seal of the Bank]
77
The Saudi Program for Drilling of Wells and
Rural Development in Africa; Phase V - Mali
SPECIMEN
Defects Liability Guarantee
Contractor: …………………………………………
Object of Works: Construction of about (110) drilled-wells (water Boreholes) equipped with
solar pumping system, elevated water tanks, 30 water distribution Network System (with a
various piping diameters), concrete posts each Two taps and one meter.
Contract Price: US$.....................................
We hereby undertake to grant the Employer an independent guarantee for the warranty claims
to which he is entitled vis-à-vis the Contractor pursuant to the aforementioned Contract,
including any incidental claims, up to the amount of
US$................................
(in words:.....................................................................)
Explicitly waiving all objections and defenses, we undertake to render said payment
upon receipt of the Employer first written demand, provided that the latter states that
the Contractor has failed to observe all or part of his contractual obligations.
In case of any claim under this guarantee payments by the Guarantor shall be made to the
Account of the Saudi Fund for Development.
This guarantee shall become effective upon the date of payment of the retention money on
the Contractor’s account and shall expire upon the end o the Defects Liability Period, but only
after receipt of the Defects Liability Certificate.
The Employer shall return this guarantee to us as soon as its validity expires.
.........................................................
(Signature of the Guarantor, stamp)
78
The Saudi Program for Drilling of Wells and
Rural Development in Africa; Phase V - Mali
Date: ..................................
To: ............................................................ [name and address of Employer]
Whereas, a contract dated ..........................................................(hereinafter referred to
as the Contract) was entered into by you with ........................................................................
[insert name of the Contractor] (hereinafter called the Contractor), whereby the
Contractor undertook to execute and complete .......................................................................
[state designation or short description of Works] ;
Whereas, the Contract provides for an advance payment to be made by you to the Contractor
in the amount(s) of .....................................................................[state currency / currencies and
amount /amounts] (hereinafter referred to as the Advance Payment) for the purpose of
mobilization, provided the repayment of such advance is guaranteed by a bank acceptable to you;
Whereas, we are willing to provide the required guarantee in accordance with the request of
the Contractor.
NOW, THEREFORE, in consideration of your making the Advance Payment to the
Contractor against the security of this guarantee, we ............................................................. [bank],
hereby unconditionally and irrevocably guarantee, as primary obligor and not merely as surety,
the payment to you, upon your first written demand, of an amount not
exceeding .......................................................................................................[state currency /
currencies and amount / amounts in figures and words] , without any objection on our part, on
whatever grounds, and without requiring that you demand payment by, or proceed against the
Contractor before demanding payment by us.
The amount of this guarantee shall be reduced by the amounts, if any, recovered by you by
deductions from payments due to the Contractor under the Contract, and your statement of the
total of such amounts, if any, shall be deemed as conclusive for the purpose of this guarantee.
We agree that any forbearance granted by you to the Contractor or any change, addition to
or modification of the Contract or of the Works to be executed thereunder shall not in any way
release us from our liability under this guarantee, and we hereby waive any right to consent to or
receive notice of such forbearance, change, addition or modification.
No drawing may be made by you against this guarantee until we have received notice from
you that the Advance Payment has been made to the Contractor. Such notice shall be deemed as
conclusive for the purpose of this guarantee.
79
This guarantee shall be governed by the laws of ..................................[state country of the
Employer] and the courts of that country shall have exclusive jurisdiction to adjudicate on any
dispute relating to the interpretation or application of this guarantee.
This guarantee shall remain valid and in full force and effect from the date of making the
Advance Payment to the Contractor by you, as such date is notified by you, until the Advance
Payment is repaid in full to you by the Contractor.
Signed ...................................................................
[Signature(s) , as appropriate, on behalf of the
Guaranteeing Bank]
[Seal of the Bank]
80
The Saudi Program for Drilling of Wells and
Rural Development in Africa; Phase V - Mali
SPECIMEN
Taking-Over Certificate
No …………………………………………………………………………
Region …………………………………………………………………….
District …………………………………………………………………….
Village ……………………………………………………………………..
on_________
2. The following minor defects and/or minor remaining works were found:
a) Minor defects
b) Minor remaining works
c) Deadline for correction of defects and, if applicable, for completion of remaining
works.
………………...……...….....
3. Remarks
81
The Saudi Program for Drilling of Wells and
Rural Development in Africa; Phase V- Mali
SPECIMEN
Defects Liability Certificate
Contractor:
1. The permanent Works have been completed according to the above mentioned Contract
without defects.
2. The Contractor has fulfilled his obligations according to the Contract documents.
Place:
Date:
82
SECTION 7
TECHNICAL SPECIFICATIONS
83
1. Introduction:
The contractor is required to closely observe this technical specification to execute the works
in this project and instruction of the Consultant Engineer during the course of the project.
However the contractor is required to put to the work equipment and tools in good working
condition and in sufficient number so as to guarantee conditions work without stoppage beside
providing qualified and experience staff to perform the work to the state-of-the art and to the
highest standard. The tenderer is supposed to have aquinted himself with the situation in Mali
and the sites of the work. He shall always put the goals of the Saudi Fund for Development of
sponsoring the project. The execution of the work, the materials and procedure shall depend
on the known International Regulation and standard. Drawing and measurements are to be in
SI - units.
2. Organization of works:
Immediately following the signing of the contract and for a period not more than 2 months,
the contractor has to mobilize his equipment, materials and personnel to his base camp. He has
to prepare all construction methods, drawings and final schedule of the work.
The contractor has to collect all relevant information about the hydrogeology of sites to be
executed. This will include:
- Interpretation of aerial photos
- Geophysical data
The hydro-geological study shall be conducted for every site in an area bounded by a circle of
5 km. The concerned villages being the centre of the circle.
The study shall consist of:
1. Desk study
1.1 Collection of existing data from relevant department.
1.2 Collection of available maps i.e. topographic, geological and meteorological.
2. Field survey
2.1 Field reconnaissance survey to locate vegetation, depression, houses, farms etc.
2.2 Well inventory within and around the village.
4. Conducting (4) geophysical survey and setting priority of drilling according to the result of
the survey.
All these works shall be under the direct Supervision of the Consultant Engineer and the
reports of the study to be handed to him.
Meetings shall follow this between the Contractor, the Consultant Engineer and the
representative of Water Department.
84
The list of villages proposed are shown in Annexes.
Based on the results of the geophysical survey, the consultation of the local beneficiaries and
the water department, the exact location of each well will be marked on the ground in the
presence of the Engineer.
In case the first hole does not produce the required quantity of water, 5 m3/hr, the contractor
will drill other location in the site up to 3 trails.
The cost of the negative drilling shall be included in the unit rates of the individual items of
work in the Bill of Quantities and will not be paid to the Contractor.
The contractor shall furnish his base camp, workshops, parking area, office building, stores,
laboratories, etc. which needed for the proper execution of the works. This will include but not
limited to preparation of the space including grading, removal of shrumps, garbish, access
roads, etc. the contractor can use a government owned land close to the centre of the area but
if use private land he has to arrange with the owner on his own expense.
The base camp shall be in a location center to the project with consultation and agreement of
the Consultant Engineer. Site camps shall be at drilling site locations. The main camp has to
include a furniture office for the sole use of the Consultant Engineer staff. The office shall be
provided by electricity, printing and faxing machines and desktops.
The contractor shall provide the Consultant Engineer technician with accommodation at the
base camp and transport and accommodation at the sites.
The contractor has to provide the Consultant Engineer with a two new four wheel drive car
with reputable mark.
A signpost with Project symbol shall be erected at the commencement of the work at each site
and also a well identification plate shall be put in the site at completion of the working giving
details of the well characteristics.
The contractor has to select people from the village to be a committee for looking after the
well management, maintenance and operation. The committee is to be selected by the villagers
under supervision of the Consultant Engineer.
3. Description of Work:
This is the works under the Saudi Program of Drilling of Wells and Rural Development in
Africa, Phase V in the Mali. The intention of the programs multiple goals of which:
• To raise the standard of living of the rural population by long-term provision of a safe
drinking water supply.
• To improve the water supply situation in rural areas to benefit as many people as
possible and provide a basis for gradual development.
85
• To provide hygienically safe drinking water.
• To train local communities to operate and maintain the water points for a long term
benefit.
• To spread the goodwill of the Kingdom of Saudi Arabia towards the poor communities
in Africa.
The geological framework is generally known with regard to the different intervention regions
(KOULIKORO, SIKASSO, SEGOU and MOPTI).
For all boreholes (F1 and high flow), the layout will give indications of the drilling depths.
The weathering thickness is generally between 34 and 45 meters and can often reach 60m. The
estimated average depth of the boreholes will be about 80 meters and will exceptionally exceed
100 meters for type F1 boreholes and 150m for high flow rate boreholes.
The consulting engineer in charge of works control will ensure that the required minimum flow
is reached while seeking the best flow and will ensure that the drilling is properly equipped.
Decisions on stopping drilling rest with the consulting engineer although the company has set
up the drilling.
In any case and whatever the geological conditions, the Contractor undertakes to carry out the
drilling leading to obtaining clear water with the required flow rate (0.7 m3 / h at least for the
boreholes of type F1 and at least 5 m3 / h for high flow boreholes).
86
a casing device in advance. or allowing the use of temporary PVC or steel working casing.
Unless an exemption has been granted by the control, the drilling of the base with a down-hole
hammer cannot be done before the installation of a temporary working casing in line with the
alteration formations, and correctly anchored in the base.
Crossing unconsolidated levels may require foam injection or the use of mud. The products
used in these cases will be of a composition suitable for not clogging the productive layers and
must be self-biodegradable.
1. The choice of methods and materials to be used as well as of the exact drilling diameters
will be at the initiative of the Contractor and under his sole responsibility. However, it is
specified that the following instructions must be observed: Obtaining at least 5 m3 / h,
and at least 8" for the diameter of the borehole.
Operating mode
The operating mode will generally look like this :
2. Drilling of clay or clay-sand formations up to the roof of the hard rock.
3. Installation of a PVC or steel work column.
4. Continue drilling in the consolidated rock using the down-the-hole hammer until the
required flow is obtained from aquifers accepted by the control. In the event of insufficient
flow when stopping drilling, the drilling is declared negative.
The conductivity of the water will be measured during the development phase of the
borehole. In the event that it is outside WHO standards, further operations are
suspended and the borehole will be considered unfit for consumption and closed. The
company is then paid for the service performed. If the test meets the standards, the
company will perform flow testing and water analysis. Whatever the result of the water
analysis, the company is paid but the borehole can be closed and not taken in acceptance
if the water is unfit for consumption.
5. Installation, in line with the water inlets, of a PVC collection column provided that the
borehole flow rate is greater than or equal to 5 m3 / h.
6. Installation of the filter bed.
7. Installation of a waterproof plug of expanding clay above the filter bed.
8. Fill the annular space above the plug with expanding clay.
9. Development of drilling.
10. Cementing at the top of the borehole.
11. Closing of the borehole using a padlocked metal cover.
12. Flow test and water analyzes on boreholes deemed to be exploitable.
Sampling
Whatever the drilling method used, the Contractor will take samples from all the formations
crossed. In particular, he will take a sample:
- at each meter;
- at each change of rock type;
87
- at each fracture zone;
- at each water inlet.
Samples (200-300 g) will be stored in plastic bags. On each bag will be indicated the name
and serial number of the quarter, the number of the borehole, the depth of sampling. The
samples will be stored in compartmentalized wooden boxes, numbered and provided with a
card allowing proper identification. The crates will be made according to the instructions of
the Technical Project Manager. The crates will be transported and stored by the Contractor at
his expense at the headquarters of the Client or his representative.
The Contractor, with the support of the controller responsible for monitoring, will provide a
written and detailed geological description of the samples that make up the borehole section.
Measures during construction
The Contractor must communicate to the Technical Project Manager all the information
requested, in particular:
- the precise geological description of the layers crossed;
- the depths of the base, of the fractured zones, of the various water inlets;
- the water flow rates, at each change of rod, at each new significant water inlet and at the
end of drilling, before fitting;
- the conductivity of the water during drilling in order to abandon the drilling at this stage
if the conductivity is out of specification.
- the forward speeds for each rod..
At the end of the drilling, the Contractor will communicate to the Technical Project Manager
in written form in the workbook the total depth of the drilling, the depth of water inflows, as
well as the flow rate at the end of the drilling.
Measuring instruments
The Contractor will permanently maintain the appropriate measuring instruments on his sites
and will make them available to the Contracting Authority's agents so that they can carry out
the necessary checks at any time. Failure to do so, the Client will buy them at the expense of
the Contractor and the corresponding amount will be deducted from the sums due to him. The
Contractor must have all the tools necessary for the execution of the work in accordance with
the professional rules in accordance with the required equipment.The precision required for
the measurements will be:
- 10% for flow rates;
- 2 cm for the water levels;
- 5 cm for the depths.
88
between the works controller and the Contractor's site manager, but the realization of the
catchment according to the rules of the art will be the responsibility of the Contractor.
- All collection equipment will be made of new materials and must be approved by the
control before its installation. The positive boreholes will be equipped over their entire
height with 150/165 mm full and strainer PVC tubes.
The base of the casing column will have a PVC settling tube and will be plugged with a foot
plug factory made of screwed PVC and cement. The height of the cap will not exceed 10 cm.
The collection column must be equipped with stainless steel centering devices installed around
the strainers every three meters to allow a good distribution of the filtering mass around the
strainers. To allow a good adaptation of the casing plan to the geological profile encountered,
the Contractor must have on the site elements of solid tubes and strained tubes of 1 m and 3
m. The quantities that are expected on average per drilling on the site are as follows :
- 3 elements of 1 m of solid tubes;
- 2 elements of 1 m of strainers;
- 2 elements of 3 m of solid tubes;
- 2 elements of 3 m of strainer tubes;
- and other solid or screened elements 3 m to 6 m in length.
PVC tubing stored on site must be properly protected from direct sunlight.
The annular space will be filled with rolled quartz gravel, up to 5 meters above the upper side
of the strainers. The use of lateritic gravel or crushed granite is prohibited. The granulometry
of the gravel will be adapted to the aquifer formations.
In crystalline fissured rocks, a 2-4 mm gravel filter bed will be used. In coarse arena weathering
formations and loose layers, 1-2 mm gravel will be used. The gravel of these two grain sizes
must be available in sufficient quantity on the site in order to avoid delays when equipping the
boreholes.
Directly above the filter bed, a dam made of expansive clay will be put in place to isolate the
captured part. The dam will be made of expanding clay pellets (dry montmorillonitic clay or
equivalent) to a height of 2 meters. The filling of the annular space located above the plug with
expansive clay will be carried out after the development of the borehole using raw coal sand-
clay materials.
The tolerance on the verticality of the tubes will be 0.5%. The PVC casing will exceed the
ground surface by one (01) meter and will be closed by a padlocked metal cover.
The lower part of a borehole could possibly be filled up to a certain depth indicated by the
control, before proceeding with the equipment. The filling will be done with the gravel of the
filter bed. A wait of at least thirty (30) minutes is mandatory before continuing the equipment.
Under these conditions, the entire drilled depth will be taken into account in the billing but the
filling will not be remunerated. As a general rule, the infill will not exceed 10 m.
Development of boreholes
The development of boreholes deemed positive will be carried out with an air lift by an
independent development unit or by the drilling workshop using an air injection column made
of galvanized or flexible pipes of diameter 1 "1 / 2. The water pipe will be formed by the PVC
of the borehole. Development by the drilling shop is not allowed.
89
Development will continue until clear water is obtained, free from sandy or clay particles. The
Contractor must control the sand content by the so-called "sand spot" method observed in a
10-liter bucket. The diameter of the sand spot should not exceed 1 cm. The minimum
development time is four (4) hours. In rare cases where the basis of the alterations has been
captured, the development time will be six (6) hours minimum. If after 6 hours of development,
the water does not manage to be clear, the development will be continued at the expense of the
Contractor until clear water is obtained.
The flow rate obtained at the start of development must not be less than 10% less than the flow
rate obtained at the end of drilling and must remain greater than or equal to 5 m3 / h. Flow
rates will be measured every 15 minutes for the duration of development. The water level and
the depth of the borehole must be measured before and after development. Only the controller
will decide whether to stop or continue development.
If execution faults appear during drilling or during its development, the continuation of
development operations beyond four (4) hours will be the responsibility of the Contractor. In
the event that this development does not result in obtaining clear water or if the flow rate is
more than 10% lower than that obtained at the end of drilling, all the work relating to this
structure will not be taken into account in the works cost statement. The Contractor shall be
required to take back the drilling equipment at its own expense, failing which a new drilling
will be carried out near the first.
The annular space of the borehole after development will be filled with raw coal, to a depth of
6 meters below the ground surface.
The first six (6) meters of the annular surface space will be cemented after the drilling has
developed in order to seal the annular space, prevent pollution by surface water and anchor the
column in the ground. The implementation of the cementation is left to the choice of the
Contractor. He could for example use a tube type "gas" descended into the annular space. The
slag for the cementation will consist of 50 l of water per 100 kg of cement.
Pumping tests
On these boreholes, it will be carried out after development, stage tests and long-term tests.
These pumping tests will be carried out by means of submerged electric pumps of diameter
adapted to the diameter of the equipment casing, able to give a flow rate of 12 m3 / h for a
total manometric head (HMT) of 80 meters.
90
Pumping at a constant rate (this rate will be calculated according to the interpretation of the
pumping data in stages) for 72 hours. The long-term pumping will be followed by an ascent
which will be observed for 24 hours.
During pumping, no stoppage must take place, otherwise the Contractor will restart the test
after reestablishing the initial static level. The resumption of such pumping is the responsibility
of the Contractor and the irregularity of the pumping test must be noted in the site book and
communicated to the Client.
The flow rate will be measured from a water meter, and a 100-liter gauged tank. The water
levels will be measured by means of an electric probe. The depth of the borehole will be
measured before and after each pumping test. The Contractor will have an emergency electrical
probe in reserve on the site.
The flow rate and dynamic level measurement intervals will be given to the Contractor in good
time by the delegated Project Manager.
The rhythm of the pumping or ascent measurements will be as follows :
Water analysis
At the end of the test, the Contractor will take at least two water samples, of 1 liter each. The
type of sample bottle will be approved by the Technical Project Manager. On each of the two
samples will be written the name of the village with its number (Provided by the Client), the
borehole number, the time and date of sampling and the name of the person responsible for
sampling. The bottles will be hermetically sealed.
Samples from each borehole will be handed over for physico-chemical and bacteriological
analysis to an approved laboratory. The samples will be transported by the Contractor's care
and at his expense and the bottles placed in suitable crates for transport. The taking of the
samples, the storage of the samples and the determination of the maximum delay before their
91
reception at the laboratory will be described by the laboratory. The samples will be analyzed
in the laboratory to determine the concentration of the following parameters:
Sodium Na Chlorides Cl pH
The arsenic content will be the subject of a specific analysis in accordance with the
quantities of the estimate and the unit price schedule.
The entrepreneur must take into account the indications described above when drawing up his
financial offer.
The company will also do the bacteriological analysis in an approved laboratory.
To avoid any risk of deterioration, the structures will be closed immediately after the pumping
test operations by a padlocked metal cover. The Contractor will be solely responsible for any
damage to structures due to a lack of protection during the period from the end of the pumping
test.
Characteristics
a) General
92
The towers will be metallic (steel type E24 / 1 or equivalent, or galvanized, or stainless
steel), cylindrical in shape and based on three (03) feet. For the capacities and height under
raft of the water towers, refer to the framework of the estimate.
− A water level indicator will be placed at the level of the tank and readable from the
ground;
− The metal profiles used in the construction of works, will be offered for the approval of
the contracting authority;
93
d) Soudures et Welds and sealing
− If the water tower tank is made of welded steel, the welding will be done in accordance
with all the standards in force and with the greatest care. The weld of the tank must
ensure that it is watertight
− The welded surfaces must be thoroughly cleaned before starting the welding work. In the
case of multi-layer welding, the surfaces should be cleaned well after each coat before
continuing with the next coat.
− All welded joints must show a uniform cross-section, a smooth, non-priority surface and
an absence of wrapping. Visual inspection should show good fusion with the base
metals.
− The tank will be perfectly sealed and its interior wall or the lining thereof will be food
grade. The materials, products and coatings used must not be a source of toxicity to the
stored water.
− All bolts and nuts used for assembling the tanks and structures will be galvanized steel
or stainless steel.
− In the case of a bolted tank, the seal will be ensured by a waterproof film of the liner type
or equivalent.
− The piping will be in galvanized steel with threaded parts. The water tower will be
equipped:
✓ delivery pipe inside or outside the tank and allowing the water to fall
(oxygenation) when filling the tank;
✓ distribution pipe comprising at the upper part inside the tank, a strainer
whose opening will be at most 20 cm from the raft, and along the down pipe;
✓ a by-pass that will connect the discharge line and the distribution line,
equipped with a gate valve and a non-return valve;
✓ overflow and drain pipes connected to each other below the raft and draining
excess water through a horizontal part onto a concrete area located at least
20 m from the tower;
✓ ventilation chimney with anti-mosquito net;
✓ a water level indicator in the tank, readable from the ground.
For all supply, distribution, emptying and overflow pipes, a stabilization device must be
provided, taking into account the height under the raft of at least 10 meters.
94
− Access to the manhole can be made using a metal ladder fitted with a crinoline-type
guardrail. An access system inside the tank will be provided by a stainless steel
ladder without a crinoline. Any other form of access will be offered at the discretion
of the Project Manager.
The water tower will be equipped with a float valve which will close when the high water level
in the castle is reached. This will cause an overpressure on the network, which will be detected
by a pressure switch placed in the well collection manhole which will then transmit the
information to the control box which will stop the pump in operation.
The pipes of the drilling head will be either cast iron or galvanized steel, of suitable diameter,
taking into account the drilling equipment of the borehole and the discharge pipe.
These works include:
95
- Supply and installation of a steel tube with a minimum diameter of 200 mm and fully
protected against corrosion;
- Installation of a reinforced concrete block dosed at 350 kg of cement / m3;
- Installation of a closing cover and mounting system for the riser;
- Supply and installation of elbow, fitting and pipe;
- Supply and installation of a cast iron check valve including mounting accessories adapted
to the diameter;
- Supply and installation of a suction cup;
- Supply and installation of a DN 50 meter including mounting accessories adapted to the
diameter. The installation will be done in accordance with the straight lengths upstream
and downstream meter, indicated by the manufacturer;
- Supply and installation of a pressure switch;
- Installation of supports with collar;
- Construction of the drill head manhole, including the metal cover;
- etc. (refer to the drawing of the catchment structure)
NB: The plate at the head of the borehole must be equipped with an opening and a ¾ " pipe
with a plug allowing the passage of an electric probe for measurements of the water level in
the borehole.
- Supply and installation of pipes
For the length of the discharge line pipes, comply with the validated execution file.
Pipes storage
96
PVC pipes will be stored on a level area, free of any hard objects and must be protected from
direct sunlight. The Administration reserves the right to refuse the use of any pipe it deems
defective.
Pipe laying
The excavations will be carried out preferably by hand or by mechanical means. The explosive
will only be used in case of absolute necessity and after authorization from the Client.
Excavations will be carried out at each point in accordance with the project dimensions
indicated on the longitudinal profiles. Unless otherwise indicated in this document, the normal
excavation depth is such that the thickness of the backfill is not less than 0.80 m above the
upper generatrix of the pipe.
In the case of crossings of important tracks and roads the indicated depths could increase. The
trenches will have to deepen regularly as they approach these crossings.
The minimum width will be equal to 0.40 m. The bottom of the excavation will be carefully
leveled and purged of any hard material, and niches will be dug at the junctions to allow the
pipes to rest along their entire length. The over-depths will be carried out according to the
plans without giving rise to the right to a gain.
The Contractor must make himself aware of the nature of the land. Price increases caused by
hard terrain will not be granted. Only increases due to the use of jackhammers will be granted.
The minimum slopes and the minimum overlap depending on specific cases will be subject to
the approval of the Consulting Engineer.
The Consulting Engineer will take delivery of the completed trench. This reception will mainly
focus on the longitudinal profile of the bottom of the trench. The Contractor must therefore
always notify the Consulting Engineer after the completion of the trench and before any
commencement of the laying of the pipes.
The Contractor will take all necessary measures to ensure that the transport and handling of
the pipes and their accessories do not cause deformation, destruction of the protective coating,
or cracks. The Consulting Engineer may prescribe measures in the event of failure on the part
of the Contractor. Damaged areas will be repaired according to the advice of the Consulting
Engineer.
97
c) Laying of buried pipes
The pipes will be laid in the excavations on a layer of 0.10 m of fine sand. The flexibility of
the pipes makes it possible, under certain conditions, to make curves with large radii without
the use of fittings.
The curve must be made between the joints, therefore no deviation to the right of the joints
inside the sockets is allowed.
The pipes will be laid in accordance with any specific instructions given by the manufacturer,
in addition to concerns about exposure to sunlight and expansion.
The pipes will be held in place by sand jumpers leaving the joints visible.
After the pressure test, a sand backfill is placed up to 0.15 m above the upper generator and
carefully tamped, after laying an identification screen, the rest of the trench is backfilled with
raw coal material, coming from the excavation itself, well compacted. The various parts or
fittings giving rise to changes of direction are wedged by lean concrete stops dosed at 250 kg
/ m3.
Elbows, tubing pieces, gate valves and all the devices inserted in the pipes and likely to give
rise to forces on the ground will be counterbrained, without giving rise to the right to an added
value, by concrete blocks whose calculation will be subject to the approval of the Consulting
Engineer.
The Contractor will keep the pipes on the site protected from the sun. At each work stoppage,
the ends of the pipes being laid will be blocked with a buffer to prevent the introduction of
foreign bodies or animals.
The Contractor cannot start the backfill without the permission of the Engineer.
The installation of pipes, fittings and valves in elevation along masonry or concrete walls is
carried out by means of clamps fitted with tabs which will be sealed in the wall.
98
The collars must allow the removal of the part they are holding without having to loosen it.
When the pipes are placed on a floor or above the ground, they rest on small masonry cleats
which keep them elevated from the ground.
b) Backfilling
In principle, the materials extracted from the trenches are reused for backfilling. The top face
of the backfill must be leveled with great care to avoid water stagnation. After completion of
backfilling, excess material will be promptly removed to landfill at the Contractor's expense.
If the pavement of a roadway must be cut to cross the road, the top face of the backfill should
be paved with the same material as the original pavement. The Contractor will be responsible
in the event of an accident caused by poor maintenance of the backfill of the trenches during
the execution of the works.
The pipe being placed on the laying bed, its sides will be lined up to the level of the horizontal
axial plane. The coating of the lower part of the pipes and fittings will be carried out by pushing
the backfill under the pipe and its sides with a shovel.
The coating material must contain less than 12% of elements smaller than 0.1mm and must
not include elements with a diameter greater than 30mm. A warning screen must be installed
above the pipe.
Backfilling is done in successive layers of 0.10 m up to 0.20 m above the pipeline and then in
layers of 0.20 m, compacted one after the other using the excavation of the trench under
conditions that it be redacted from stones (element <100mm). Compaction should be better
than 95% of normal proctor.
After backfilling, the contractor will have concrete bollards along the entire route of the pipes
as a benchmark. These will be arranged especially to the right of changes of direction and
doubled to the right of the gate valves.
a)Tap – Valves
The gate valves will be quarter (1/4) turn in chrome-plated brass or cast iron, with a diameter
corresponding to the pipe on which they will be placed.
All buried gate valves will be placed in keyed mouths including a keyed mouth head, an
extension PVC tube, a tabernacle. The assembly will be operated by a crutch wrench.
b) Suction cups
99
The suction cups will be placed in a manhole.
The suction cups will be made of cast iron and their float will have an elastomeric overmolded
steel core
c) Drains
The pipes will be equipped with a gate valve placed at the low point of the network and placed
in a manhole as shown in the diagram. These changes will purge the network.
They constitute the main service points of the network. The public drinking fountains consist
of a rectangular paving in the center of which there is a construction serving as a seat
supporting 3 draw-off taps. A sump located about 6 m away will collect the water lost by a
gutter inside which rubble stones will have been placed.
The rubble must be hard, insensitive to water, sound, non-scalable, non-freezing and non-
friable, having the highest possible density (minimum 2.20 t / m3).
This material must be clean, have a homogeneous shape in its three (3) dimensions and be
made of quality stones.
The particle size will be between 100 mm and 250 mm, excessively large elements being to
be avoided.
The public drinking fountain equipment will include galvanized steel pipes DN 1'', 1''3/4 with
elbows, reduction pieces and T-pieces, 1'' valve connections, 1'' 1/2 meter, 1'' 1/4 taps, full
support valve and all constraints.
The manholes
All buried gate valves will be placed in keyed mouths comprising a keyed valve head, an
extension PVC tube. The whole will be operated by a crutch wrench.
All emptying and suction cups will be placed in the manholes, carried out according to the
plans provided. The manholes will be closed by prefabricated reinforced concrete slabs.
The various parts or fittings giving rise to changes of direction and tees will be wedged by lean
concrete stops dosed at 250 kg / m3. The stops must leave the joints accessible.
The contractor must build watertight reinforced concrete (or masonry) manholes on the drain,
air purge and valve devices.
He must first submit standard plans to the Consulting Engineer before they are made.
100
SECTION 8
BILL OF QUANTITIES
101
TABLE OF CONTENTS
Lot No.
1. Mobilisation, demobilisation
2. Drilled Wells
3. Surface Installation
4. Well Equipment
5. Traiining of Service Personnel and Maintenance
6. Animation/Sensitisation
7. Summary of Prices
102
Item Description Unit Qty. price in US$
No.
Unit Total
1 Lot 1: Mobilisation, Demobilisation
103
2.1.9 Supply and filling in of 4 m cement grout. m 440
2.1.10 Development of Drilled Well. pcs 110
2.1.11 Test pumping of Drilled Well. Step test CIEH pcs
110
6 hrs.
2.1.12 Test pumping of Drilled Well. Long dur. CIEH pcs
110
24hrs.
2.1.13 Recovery test; include for measurements and pcs
110
records CIEH 6h.
2.1.14 Recovery test; include for measurements and pcs
110
records CIEH 24h.
2.1.15 Disinfection of Drilled Well. pcs 110
2.1.16 Bacteriological and chemical analyses. pcs 110
2.1.17 Verticality and alignment tests. pcs 110
2.1.18 Geo-physical logging for borehole, 100m pcs
110
deep.
Sub-Total Lot 2.1 0,00
3 Surface Installations for Solar Water
Systems
3.1 Construction of a concrete well head, pcs 110
galvanized steel well head and furnishing all
necessary parts.
3.2 Supply and inst. of a galvanized steel tank pcs 110
10m³ and tower of 6m height with all necessary
parts.
3.3 Supply and inst. of a galvanized steel tank pcs PM
30m³ and tower of 12m height with all
necessary parts.
3.4 Tap posts. pcs 400
3.5 Supply and construction of a wire mesh fence. pcs 110
3.6 Supply and installation of water pipe from well m 2200,00
head to the reservoir.
3.7 Supply and installation of PVC pipes m 8000,00
(NOD125 PN10)
3.8 Supply and installation of PVC pipes (NOD m 13000,00
110 PN10)
3.9 Supply and installation of PVC pipes (NOD 90 m 21000,00
PN10)
3.10 Supply and installation of PVC pipes (NOD 75 m 15000,00
PN10)
3.11 Supply and installation of PVC pipes (NOD 63 m 36000,00
PN10)
3.12 Provide for road crossing for distribution pipes PM
including excavation, laying of pipes,
backfilling & compaction and making bypass
for traffic
104
Sub-Total Lot 3.2
4 Well equipment
Submersible pumps for solar system
4.1 Supply and install. of submersible pumps pcs 110
(Grundfos type SQ flex HMT 70m), Qmin
30m³/day including all accessories.
4.2 Supply and install. of submersible pumps pcs PM
(Grundfos type SQ flex HMT 40m), Qmin
30m³/day including all accessories.
4.3 Supply and install. of submersible pumps pcs PM
(Grundfos type SQ flex HMT 50m), Qmin
40m³/day including all accessories.
4.4 Supply and install. of submersible pumps pcs PM
(Grundfos type SQ flex HMT 60m), Qmin
30m³/day including all accessories.
4.5 Solar generator of international standard
4.5.1 Supply and install. of a complete solar pcs 110
generator Qmin 30m³day, HMT 70m.
4.5.2 Supply and install. of a complete solar pcs PM
generator Qmin 30m³day, HMT 40m.
4.5.3 Supply and install. of a complete solar pcs PM
generator Qmin 40m³day, HMT 50m.
4.5.4 Supply and install. of a complete solar pcs PM
generator Qmin 30m³day, HMT 60m.
Total Lot 4 0,00
5 Lot 5: Training of Service Personnel and
Maintenance
5.1 Training of mechanics for the maintenance of pcs 110
Solar Water Supply Systems.
5,2 Supply of tool boxes suitable for maintenance pcs 110
of Solar Systems.
Total Lot 5 0,00
6 Lot 6: Animation/Sensitisation
Animation and sensitisation services included l.s 1
mobilisation, transportation (4x4 vehicles,
motorbikes) of the animation teams and all
necessary equipment from one site to another
for all well sites for a period of 25 months,
starting from one month prior to the drilling
activities. Seminars in the villages (hygiene,
formation, accounting, etc.), services including
staff and transportation means proposed, to be
described by the bidder.
105
7. Summary of Prices Total Price per
Lot
Summary Lot 1 0,00
Summary Lot 2 0,00
Summary Lot 3 0,00
Summary Lot 4 0,00
Summary Lot 5 0,00
Summary Lot 6 0,00
TOTAL GENERAL 0,00
PS: The VAT is not applicable in this contract. The VAT will be given for information only.
The VAT amount will enable the Mali Authorities to have an estimate of the tax exception
amount.
The contractor shall be exempted from the added income tax in the country of the employer
unless if he is a resident or a citizen
106
Item No Equipment Unit Unit Price US-Dollar
1 Drilling rig Month
2 Drilling compressor Month
3 Development compressor Month
4 Excavation compressor Month
5 General sets Month
6 Truck Month
7 Pick-up cars Month
8 Concrete mixer Month
9 Crane truck Month
10 5 doors 4*4 car Month
11 Submersible pump Month
12 Solar panel Month
107
Materials
108
Personnel
109
APPENDIX A: LIST OF LOCALITES
110
111
112
113
APPENDIX B: DRAWINGS
114
115
116
117
118
119
120
APPENDIX C: UNIT PRICE
BREAKDOWN SPECIMEN
121
122
123