04 Week VII - S. 10 To 15
04 Week VII - S. 10 To 15
04 Week VII - S. 10 To 15
Week 7 – COMPOSITION OF
ARBITRAL TRIBUNAL
- U./S. 34(2)(a)(v) the parties can challenge the award when the
composition of the arbitral tribunal is not in accordance with the
agreement of the parties.
+ MMTC Ltd. v. Sterlite Industries Ltd. (1996) 6 SCC
716
The parties entered into a contract, containing the arbitration
clause, before the commencement of the A&C Act, 1996 but the
proceedings commenced after the coming into force of the 1996
Act. Hence provisions of the A&C Act, 1996 apply here.
The arbitration clause provided: Both the parties shall nominate one
Arbitrator each and the arbitrators shall appoint an umpire before
proceeding with the reference…The provisions of the Indian
Arbitration Act and Rules made thereunder shall apply for
proceedings.
2) The contract (if any) between the parties and the arbitrators;
and
Ω Whether the CJ u/S. 11(6) can look into the validity of the arbitration
agreement?
iv. The existence of the condition for the exercise of his power
and on the qualifications of the arbitrator(s).
d) The CJ or the designated Judge would be entitled to seek the
+ opinion of an institution in the matter of nominating an arbitrator
qualified in terms of S. 11(8) if the need arises but the order
appointing the arbitrator could only be that of the CJ or the
designated Judge.
g) Once the matter reaches the Arbitral Tribunal, the HC would not
interfere with the order passed by the arbitrator during the course of
the arbitration proceedings and the parties could approach the
Court only in terms of S. 37 or S. 34.
Later, Boghara sent Nat’l a legal notice seeking the balance amount
within 15 days, otherwise the notice be considered as notice
invoking arbitration. Nat’l in its reply rejected the claim and stated
the claim has been fully and finally accepted by Boghara and no
question of invoking arbitration arise.
Held:
c) A contract may be non est in the sense that it never came legally into
existence or it was void ab initio. In that event, as the original
contract has no legal existence, the arbitration clause also cannot
operate, for along with the original contract, it is also void.
d) Though the contract was validly executed, the parties may put an end
to it as if it had never existed and substitute a new contract for it,
solely governing their rights and liabilities. In such an event, as the
original contract is extinguished by the substituted one, the
arbitration clause of the original contract perishes with it.
e) Between the two extremes referred to in paras (c) and (d), are the cases
where the contract may come to an end, on account of repudiation,
frustration, breach etc. In these cases, it is the performance of the
contract that has come to an end, but the contract is still in existence
for certain limited purposes, in respect of disputes arising under it or
in connection with it. When the contracts subsist for certain purposes,
the arbitration clauses in those contracts operate in respect of those
purposes.
+
Arbitration Agreement cannot be invoked to seek reference of any
dispute to arbitration, in the following circumstance, when the
contract is discharged on account of performance, or accord and
satisfaction, or mutual agreement, and the same is reduced to
writing and signed by both the parties or by the party seeking
arbitration:
Held:
b) U/S.11(6) no time limit has been prescribed. Therefore, if the party does
not make an appointment of the arbitrator within 30 days the right to
appointment does not get automatically forfeited after expiry of 30 days.
If the opposite party makes an appointment even after 30 days of the
demand, but before the first party has moved to the court u/S.11 that
would be sufficient.
c) The court did not decided if 30 days period is mandatory for sub-
sections (4) and (5).
+ Indian Oil Corpn. Vs. Raja Transport Pvt. Ltd.
(2009) (pre-amendment case)
Facts: On 28/2/2005 IOC appointed Raja Transport as its dealer for retail
sale of petroleum products but terminated the dealership on the
recommendation of the Vigilance dept. on 6/8/2005.
The agreement between the parties had an arbitration clause whereby the
parties had decided that Director, Marketing of the Corp. or some officer of
the Corp. nominated by the Director shall be the sole arbitrator.
Both parties challenged the order which was dismissed by District Court.
While the appeals were pending, RT issued notice to IOC referring that
appointment of Director cannot lead to fair treatment or justice and therefore
such an appointment was prejudicial to its interest. IOC protested that RT’s
request is contrary to the arbitration agreement and there cannot be an
outside arbitrator.
GPL invited tenders for the expansion its facilities and Duro Felguera and its
Indian subsidiary (FGI) were considered by GPL and Duro Felguera and FGI
were selected as "the Contractors" for the work. After discussion between
the parties, Original Package No. 4 TD was divided into five different and
separate Packages dated 10.05.2012, namely, New Package No. 4-F.O.B.
Supply of Bulk Material Handling Equipments (awarded to foreign
company-M/s. Duro Felguera), Package No. 6-design, manufacture, supply,
installation, erection, testing, commissioning of Bulk Material Handling
Equipments and all other activities related therewith; Package No. 7-Civil
Works and all other activities related therewith; Package No. 8-International
Transportation of Bulk Material Handling Equipments and parts through sea
including insurance and all related activities; Package No. 9-Installation,
Testing and Commissioning of Ship Unloaders and all other activities
related therewith (Packages No. 6 to 9 awarded to Indian subsidiary- FG I).
Separate Letters of Award (dated 17.03.2012) for five different Packages
were issued to Duro Felguera and FGI for the above said work respectively.
When the disputes arose in 2016, GPL contends that reference of disputes to
be made to a composite tribunal whereas Duro and FGI claim that separate
tribunal to be constituted under each contract.
+
Issues:
Where the contract provides that the standard form of terms and
conditions of an independent trade or professional institution will
bind them or apply to the contract, such standard form of terms and
conditions including any provision for arbitration in such standard
terms and conditions, shall be deemed to be incorporated by
reference.
Where the contract between the parties stipulates that the conditions
of contract of one of the parties to the contract shall form a part of
their contract (as for example the general conditions of contract of
the Government where the Government is a party), the arbitration
Clause forming part of such general conditions of contract will apply
to the contract between the parties.
+
In the MoU, Original Package No. 4 Tender Document is merely referred
only to have more clarity on technical and execution related matters and
the parties agreed that the works shall be carried out as per the priority
of the documents indicated thereon. Mere reference to Original Package
No. 4 Tender Document in the sequence of priority of documents (as
serial No. 4) indicates that the documents Original Package No. 4 TD
containing arbitration Clause was not intended to be incorporated in its
entirety but only to have clarity in priority of the documents in execution
of the work. It is pertinent to note that MoU dated 11.08.2012 itself does
not contain an arbitration clause.
As per the amended provision of S.11(6A), the power of the court is only
to examine the existence of arbitration agreement. When there are five
separate contracts each having independent existence with separate
arbitration clauses there cannot be a single arbitral tribunal for ICA. All
preliminary issues are left to be decided by the arbitral tribunal.
+ Malaysian Airlines System Bhd (II) vs. Stic
Travels (P) Ltd. (2000)
pre-amendment and pre-SBP
Malaysian Airlines made an application under S.11(5) seeking reference of
dispute to arbitration.
In several countries where the UNCITRAL model is adopted which in Article 6(4)
only speaks of "taking into account" the nationality as one of factors, it has been
held that it is not impermissible to appoint an arbitrator of a nationality of one of
the parties to arbitration. Therefore the word 'may' in Section 11(9) is not intended
to be read as 'must' or 'shall'. The provision is not mandatory.
While nationality of the Arbitration is a matter to be kept in view, it does not follow
from Section 11(9) that the proposed arbitrator is necessarily disqualified because
he belongs to the nationality of one of the parties. In case the party who belongs
to a nationality other than that of the proposed arbitrator, has no objection, the
Chief Justice of India (or his nominee) can appoint an arbitrator belonging to a
nationality of one of the parties. In case, there is objection by one party to the
appointment of an arbitrator belonging to the nationality of the opposite party, the
Chief Justice of India (or his nominee) can certainly consider the objection and
see if an arbitrator not belonging to the nationality of either parties can be
appointed. While taking that decision, the Chief Justice of India (or his nominee)
can also keep in mind, in cases where the parties have agreed that the law
applicable to the case is the law of a country to which one of the parties belongs,
whether there will be an overriding advantage
+ Section 11A: Power of the CG to amend Fourth
Schedule
Fourth Schedule provides a model feel structure that can be
followed by the court, as stated in S.11(14).
Consequences of Non-disclosure:
i. At the first stage: Will vitiate the appointment, and invalidate the entire
proceedings and the resulting award.
ii. At the second stage: Will vitiate the proceedings subsequent to the
coming into existence of the circumstances likely to give rise to
justifiable doubts as to the independence or impartiality of the
arbitrator. The award will be invalid and liable to be set aside.
+
Grounds to determine Independence or Impartiality:
Fifth Schedule [S.12(1)]:
Other circumstances
+
Prior Knowledge: A party who appointed an arbitrator, or
participated in the appointment, whose lack of qualifications
or impartiality the party was aware of, prior to the
appointment, is later precluded from challenging the
appointment of the arbitrator on these grounds. Otherwise, he
can challenge the appointment. [S.11(4)]
Waiver: Where the arbitrator has made the disclosure as
required of him, and a party does not take objection as to the
independence or impartiality of the arbitrator after such
disclosure, he would be deemed to have waived his right to
raise such an objection. [S.4]
Grounds for Absolute Ineligibility of the arbitrator
[S.12(5)]:
Categories specified in the Seventh Schedule; Exception:
Explanation 3.
Grounds apply notwithstanding any prior agreement to the
contrary unless subsequent to dispute having arisen, the parties
waive the applicability of this sub-section by an express
agreement in writing.
Voestalpine Schienen GmbH vs. Delhi Metro
+ Rail Corporation Ltd. (2017)
As per the contract entered into between the parties on August 12, 2013, following
procedure was agreed to be followed: Three arbitrators are to constitute the arbitral
tribunal. DMRC would make out a panel of engineers with the requisite qualifications
and professional experience, which panel will be of serving or retired engineers of
government departments or public sector undertakings. From this panel, the DMRC has
to give a list of five engineers to VSG and both the parties are required to choose one
arbitrator each from the said list. The two arbitrators so chosen have to choose the third
arbitrator from that very list, who shall act as the presiding arbitrator.
VSG stated that appointment of the arbitral tribunal as per the aforesaid Clause, if
followed, would lead to appointment of 'ineligible persons' being appointed as
arbitrators, in view of Section 12(5) of the Act read with Clause 1 of Seventh Schedule.
Thus, it nominated a retired judge of the Court as a sole arbitrator and requested DMRC
for its consent.
DMRC stuck to the procedure as prescribed for the arbitration Clause and asked VSG
to nominate an arbitrator from the panel of five persons which it forwarded to them.
On August 17, 2016 application U/S.11 was filed by VSG for constitution of the arbitral
tribunal by this Court with the prayer that the arbitrator nominated by VSG (i.e. a
former Judge of this Court) should be appointed as the sole arbitrator if DMRC
consents to it or any impartial and independent sole arbitrator if appointment of VSG’s
nominee is objected to by DMRC. Alternate prayer is made for appointment of an
independent and impartial arbitral tribunal comprising of three members u/S.11(6)
read with S.11(8) for adjudication of the disputes between the parties.
+Issue: Whether panel of arbitrators prepared by the DMRC violates the
amended provisions of Section 12?
In fact, when the party appointing an adjudicator is the State, the duty to
appoint an impartial and independent adjudicator is that much more onerous
and the right to natural justice cannot be said to have been waived only on
the basis of a "prior" agreement between the parties at the time of the
contract and before arising of the disputes.
Therefore, the Court dismissed the application u/S.11 but asked DMRC to
prepare a broad list of panel, including persons from other fields.
+ Section 13: Challenge Procedure
Party Autonomy: Parties are free to agree on a procedure to be
adopted for challenging an arbitrator [S.13(1)];
Fee: If
the challenge is successful, and the arbitrator is
removed from his office, or the award of the arbitral
tribunal rejecting the challenge is set aside by the
court under S. 34, then the court under S. 13(6) has the
discretion to decide as to whether the such arbitrator
is entitled to any fees on the principle of quantum
meruit or otherwise.
Section 14: Failure or Impossibility to Act
+
Section 15: Termination of Mandate and Substitution of
Arbitrator
Following are the grounds for the Termination of the Mandate of the
Arbitrator: