Perform Quantitative Risk Analysis
Perform Quantitative Risk Analysis
Perform Quantitative Risk Analysis
Introduction
Quantitative Risk Analysis refers to the thorough and complete numeric analysis of the overall
effect of the total quantifiable amount of risks involved in the project objectives.
Results evaluate the likelihood of success and estimate contingency reserves for time and cost
that are appropriate to both risks and project stakeholders.
It is inappropriate if the qualitative risk analysis provides enough information especially in the
case of smaller projects.
The Plan Risk Management process should ensure the application of quantitative risk analysis in
projects.
Calculating estimates of overall project risk is the focus of the Perform Quantitative Risk Analysis
process.
An overall risk analysis, such as one that uses quantitative technique, estimates the implication
of all quantified risks on project objectives.
Results of the quantitative risk analysis compared to the project plan gives the overall
estimate of the project risk and answers the following questions:
Estimation of overall project risk using quantitative methods helps to distinguish projects
where quantified risks threaten objectives beyond the tolerance of the stakeholders.
Critical Success Factors for the Perform Quantitative Risk Analysis Process
The critical success factors for the Perform Quantitative Risk Analysis process are:
Perform Quantitative Risk Analysis Process happens after the Identify Risks and Perform
Qualitative Risk Analysis Processes.
Reference to a prioritized list of identified risks ensures that Perform Quantitative Risk Analysis
Process will consider all the significant risks while analyzing.
Frequently used project models include the project schedule, line-item cost estimates, decision
tree and other total-project models.
Sensitive to the completeness and correctness of the model of the project that is used.
3. Unbiased Data
Successful gathering of data about risks should be done by interviews, workshops, and expert
judgment.
The Perform Quantitative Risk Analysis process is based on a methodology that correctly derives the
overall project risk from the individual risks. E.g., Monte Carlo simulation for risk analysis of cost and
schedule, decision tree for making decisions when the future is uncertain.
Common root cause risks likely to occur together are addressed by correlating the risks that are
related.
Using a risk register to list risks or root cause risks and attaching it to several project elements.
Tools and Techniques for the Perform Quantitative Risk Analysis Process
The characteristics of tools and techniques used for quantitative risk analysis are as follows:
Risk models permit representation of any, if not all, of the risks, opportunities, and threats that
have impact on an objective simultaneously.
Facilitates the correct calculation of the effect of many risks and are described at the level of
total project.
The methods should be able to handle the way uncertainty is represented, be it the probability
of occurrence or probability of distributions for a range of outcomes. E.g. Monte Carlo
simulation permitting the combination of probability distributions of line-item costs or schedule
activity durations.
They include:
Results from quantitative tools are not available in standard project management methods such
as project scheduling or cost estimating. E.g. Probability distribution of project completion dates
or cost estimation.
The elements of the quantitative risk analysis are illustrated in Figure 7.1.
Periodical analysis of individual risks of project enhances the success of quantitative risk analysis.
The frequency of analysis is planned in the Plan Risk Management process, and events within the
project also influence it.
Overall project contingency reserve in time and cost should be reflecting in the project schedule and
budget.
If the contingency reserves required exceeds the time or resources, changes in the project scope
and plan may result.
The results of the quantitative risk analysis are recorded and passed on to the personnel/ group
for any further action required to make full use of the results.
TECHNIQUES
The Perform Quantitative Risk Analysis seeks to determine the overall risks to project objectives
when all risks potentially operate simultaneously on the project.
It provides answers to several questions regarding the project. They are as follows:
Causes the organization to structure the costs and benefits of decisions when the results are
determined in part by uncertainty and risk.
Solution of the decision tree helps select the decision that provides the highest Expected
Monetary Value or expected utility to the organization.
o Careful structuring of the decision tree; all alternative decisions that are materially different
should be considered; decision trees should be specified completely
o Access to high-quality data about probability, cost, and reward for the decisions and events
specified using historical information or judgment of experts.
o Use of a utility function that has been validated with the organization’s decision makers.
o Availability and understanding of the specialized software needed to structure and solve the
decision tree.
Weaknesses:
Specialized and widely available software used specifies the structure of the decision with
decision nodes, chance nodes, costs, benefits, and probabilities
User can evaluate the different decisions using functions based on Expected Monetary Value or
non-linear utility functions of various shapes.
Figure 7.2: Example of Decision Tree for Choosing between an Experimental Technology vs. Commercial Off the
Sheet (COTS) Technology.
Source: Precision Tree from Palisade Corporation
Allows the user to calculate the weighted average (expected) value of an event that includes
uncertain outcomes.
o Identification of all possible events that need to be included in the EMV calculation.
o Access to historical data or expert opinions on the values of probability and impact that are
needed for the calculation of EMV.
o Understanding of the difference between EMV and the output of simulation tools such as
Monte Carlo analysis.
Weaknesses are:
o Assessment of probability of risky events’ occurring and of their impact can be difficult to
make.
o EMV provides only the expected value of uncertain events; risk decisions often require more
information than EMV can provide.
o Sometimes used in situations where Monte Carlo simulation would be more appropriate and
provide additional information about risk.
The EMV calculation for an event by weighting the individual possible outcomes by their
probabilities of occurring is shown in Figure 7.3 below.
Example of an Expected Monetary Value (EMV) Calculation for a Business Strategy that Depends on
Uncertain Market Demand
A Fault Tree Analysis is the analysis of a structured diagram which identifies elements
that can cause system failure.
This technique is based on deductive logic and can be adapted to risk identification to
analyze how risk impacts arise. The effective application of this technique requires a
detailed description of the area being discussed.
The undesired outcome is first identified and then all possible conditions/failures which
lead to that event are identified. This reveals potentially dangerous elements at each
phase of the project.
Disadvantage:
Figure 7.4 Fault Tree Analysis of the Possible Causes of a Crash at the Main Road Junction
Used primarily for project schedule and cost risk analysis in strategic decisions.
Calculates quantitative estimates of overall project risk; reflects the reality that several risks may
occur together on the project.
o Creation of a good project model and typical models include the cost estimate and the
schedule.
o Use summary-level models such as project schedules and cost estimates.
o Access to high-quality data on risks including the risks impact on project elements, uncertain
activity durations and uncertain cost elements; the credibility depends on the quality of the
data collected
o Use of correct simulation tools.
Weaknesses include:
o Schedules are not simple and often cannot be used in simulation without significant de-
bugging by an expert scheduler.
o The quality of the input data depends heavily on the expert judgment and the effort and
expertise of the risk analyst.
o Simulation is sometimes resisted by management as being unnecessary or too sophisticated
compared to traditional project management tools.
o Requires specialized software which must be acquired and learned, causing a barrier to its
use.
o Produces unrealistic results unless input data include both threats and opportunities.
Examples of the output of schedule and cost risk results are shown in Figures 7.5 and 7.6.
Figure 7.5: Example Histogram from Monte Carlo Simulation of a Project Schedule
Source: Pertmaster v 8.0 Primavera Pertmaster
Figure 7.6: Example Histogram from Monte Carlo Simulation of a Project Estimate.
Source: Crystal Ball v. 7.3.8 from Oracle Hyperion (Decisioneering)
The review of risk databases of previous projects, such as those that arise from post-
project reviews or lessons learned exercises or historical information within an
organization or industry can reveal information relevant for a current project.
This technique leverages previous experience, and prevents the occurrence of the same
mistakes or missing the same opportunities again.
Disadvantages: Only those risks that have occurred previously can be identified. The
information available may also be incomplete with no details on ineffective strategies,
lack of details of successful resolution etc.
6. System Dynamics:
Successful application of this technique depends upon the quality of the model, accuracy
of input data collected for the project, understanding of feedback, and competence in
applying the tools and understanding their output.
Figure 7.7 Example of a Simple System Dynamics Model with Feedback Loops
2. Cause: Events or circumstances which currently exist and which might give rise to risks.
3. Decision Tree Analysis: A diagram that describes a decision under consideration and the
implications of choosing one or another of the available alternatives. It is used when some
future scenarios or outcomes of actions are uncertain.
4. Monte Carlo Analysis: A technique that computers or iterates the project cost or project
schedule many times using input values, selected at random from probability distribution of
possible costs or durations, to calculate a distribution of possible total project cost or
completion of project dates.
5. Overall Project Risk: It represents the effects of uncertainty on the project as a whole.
6. Perform Quantitative Risk Analysis: The process of numerically analyzing the effect of
identified risks on overall project objectives.
7. Project Management Process Group: The project management process group refers to
specifically the area of logic oriented grouping or arrangement of the numerous projects.
8. Risk Model: A representation of the project including data about project elements and risks
that can be analyzed by quantitative risk analysis.