SUMMARY REPORT INSTALLATION COMPRESSOR MUSI BARAT SKG 19 - 1 Maret - 20 Maret

Download as pdf or txt
Download as pdf or txt
You are on page 1of 39

PT.

Indoturbine SITE DAILY ACTIVITY REPORT Prepared by Report Dates


Distributor Of Solar Turbines
YUSUF SAIFUL ANWAR 01 - Mart - 2020
Country Customer Name Site Name CSA Numbers
INDONESIA PERTAMINA EP SKG 19 MUSI BARAT -
Project Name
ISNTALLATION COMPRESSOR LP C505
Package Compressor LP Compressor HP Package Engine Service
Job ref Customer Tag
S/N S/N S/N Hours Hours Order No.
GTC 214-A TC14N02 G930050 (New) G2600037 (Old)
GTC 224-B TC14N03 G930051 (New) G2600038 (Old)
29-20004 - - -
GTC 234-C TC14N04 G930052 (New) G2600039 (Old)
GTC 244-D TC14N05 G930053 (New) G2600040 (Old)

UPGARDING SKG 19 PERTAMINA EP MUSI BARAT


ISNTALLATION COMPRESSOR LP C505

PT. Indoturbine 1/39


PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

CREW

1. YUSUF SAIFUL ANWAR


2. AYI SOPANDI
3. HELPER 5 PERSON

CONTENTS

SECTION 1 _ INTRODUCTION………………………………………………………………………………. 3
Purpose of Visit……………………………………………………………………………………………. 3
SECTION 2 _ DAILY REPORT……………………………………………………………………………….. 3
Day to day work…………………………………………………………………………………………… 3
SECTION 3 _ ATTACHMENT, PICTURE NAME PLATE …………………………………………………. 38
Name Plate Compressor…………………………………………………………………………………… 38

PT.Indoturbine 2/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

SECTION 1_ INTRODUCTION

Purpose of Visit,

The purpose of INSTALL COMPRESSOR LP at SKG 19 MUSI BARAT


SECTION 2 _ DAILY REPORT

Day to Day Work

01, Mart, 2020

• Daily today activities:


- Travel from JKT to SILAMPARI Linggau.
- Travel from SILAMPARI to Mess PTI.

02, Mart, 2020

• Daily morning meeting.


• Issued Permit to Work.
• Daily today activities.
- Induction.
- Issued permit to work.
- Moving tools and monorail from workshop to GOC area.
- Check the location of the work.

PT.Indoturbine 3/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

03, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Waiting permit to work (SIKA).
- Waiting fabrication lifting compressor (Gantry Mono rail).
- Check material.
- Waiting PM Unit B.

04, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Dismantle grating unit A.
- Dismantle grating Unit C.
- Waiting fabrication lifting compressor (Gantry Mono rail).

PT.Indoturbine 4/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

05, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Dismantle wooden box compressor for unit A.
- Prepare track trolly.
- Waiting fabrication lifting compressor (Gantry Mono rail).

PT.Indoturbine 5/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

06, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Install support gantry mono rail.
- Prepare track trolly.
- Waiting fabrication trolly Gantry Mono rail.

PT.Indoturbine 6/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

07, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Dismantle wooden box compressor unit A
- Prepare track trolly.
- Install trolly Gantry Mono rail.
- Trial gantry mono rail.
- Change compressor for unit A to unit B.
- Moving compressor from laydown area to building unit C.

PT.Indoturbine 7/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

08, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Waiting fabrication table temporary.
- Dismantle and check wooden box compressor, G930051, G930052, G930053.
- Continue moving compressor unit B for area OHC unit C.
- Moving compressor for unit A from area unit C to area unit A.
- Prepare track trolly.

PT.Indoturbine 8/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

09, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Moving compressor from laydown area unit A to insert building unit A
- Waiting fabrication table temporary.
- Install hub coupling compressor LP.
- Troubleshooting OHC.

PT.Indoturbine 9/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

10, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Dismantle enclosure unit A
- Install table temporary.
- Moving compressor from area OHC to On skid unit A.

PT.Indoturbine 10/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

11, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Unloading compressor from Table temporary to base skid unit A.
- Install enclosure unit A.

PT.Indoturbine 11/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

12, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Continue install enclosure unit A
- Pre alignment unit A.
- Install super bolt unit A.
- Moving compressor unit C to unit D.

PT.Indoturbine 12/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

13, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Prepare moving compressor unit D.
- Waiting switch over Unit D, (stand by)
- Install enclosure main hole pipe from unit D to unit A.

PT.Indoturbine 13/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

14, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Install hub interconnect shaft coupling unit D.
- Dismantle enclosure unit D.
- Install temporary table.
- Moving compressor from OHC to on skid unit D.

PT.Indoturbine 14/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

15, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Unloading compressor from table temporary to base skid unit D.
- Dismantle table temporary.

PT.Indoturbine 15/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

16, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Install enclosure unit D.
- Pre alignment.

PT.Indoturbine 16/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

17, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Dismantle enclosure unit C and install at unit D.
- Waiting switch over Unit C, (stand by)
- Troubleshooting OHC.
- Dismantle grating unit B.

18, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Dismantle wood box compressor for unit C.
- Moving compressor unit C from laydown area to insert building (under OHC area).
- Moving compressor unit B from OHC unit C to OHC unit B.
- Install temporary table temporary at Unit C.
- Troubleshooting OHC.
- Moving compressor from under OHC to insert On skid.

PT.Indoturbine 17/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 18/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

19, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Stop work to HOT TAP.
- Unloading compressor from table temporary to base compressor unit C.

PT.Indoturbine 19/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

20, Mart, 2020

• Daily morning meeting.


• Daily today activities:
- Continue unloading compressor from table temporary to base compressor unit C.
- Install enclosure unit C.
- Dismantle enclosure unit B.
- Install table temporary at unit B.

PT.Indoturbine 20/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 21/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 22/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 23/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 24/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 25/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 26/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 27/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 28/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 29/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 30/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 31/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 32/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 33/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 34/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 35/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 36/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 37/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 38/39
PT. Indoturbine SITE DAILY ACTIVITY REPORT Prepared by
Distributor of Solar Turbines
YUSUF SAIFUL ANWAR

PT.Indoturbine 39/39