TL 9000 Quality Management System Measurements Handbook FRT Examples
TL 9000 Quality Management System Measurements Handbook FRT Examples
TL 9000 Quality Management System Measurements Handbook FRT Examples
5.2
FRT Examples
Problem reports from customers are expected to produce an action by the supplier to fix or alleviate the problem (see definition of Problem Report in the Glossary). The problem fix is to be delivered in a time frame determined the rules in 5.2.4 d) 1). Since FRT deals only with reported problems from customers and the responsiveness of the supplier to fixing the problem, the FRT measurement is not normalized but reported as a percentage of problems fixed on time. It may be that an organization has no problems to fix in a particular month. In that case 0 is reported for the number of problems fixed and also for the number of problems due to be fixed, which results in an FRT of 100%.
Table 5.2.1-1 FRT Data Table Report for Product Categories 1, 2, 3, 4, 5, 6, and 9
Identifier MeasurementID Fr2c Fr2d Fr3c Fr3d Value FRT 5 5 20 25
Table 5.2.1-2 FRT Source Data and Measurement Calculation for Product Categories 1, 2, 3, 4, 5, 6, and 9
Fixes Available On Time Fr2c = 5 Fr3c = 20 Severity Fixes Due FRT Measurement Results Problem Reports Closed On Time FRT2 = 100% FRT3 = 80%
Major Minor
Fr2d = 5 Fr3d = 25
The calculation of FRT2 is 100 * 5 / 5 = 100%. The calculation of FRT3 is 100 * 20 / 25 = 80%.
Table 5.2.2-1 FRT Data Table Report for Product Categories 7 and 8
Identifier Product Category MeasurementID Fr4c Fr4d Value 7.1 FRT 16 20
Table 5.2.2-2 FRT Source Data and Measurement Calculation for Product Categories 7 and 8
Fixes Available On Time Fr4c = 16 Fixes Due Fr4d = 20 FRT Measurement Results Problem Reports Closed On Time FRT4 = 80%
They may exclude the interval that access to the site was denied (March 12 through 31), which has the effect of moving the due date of the problem report from March 31 to April 18. If they fix the problem on or before April 18, then the problem was fixed on time. The problem report is therefore reported with the April data per counting rule 5.2.4 b) 4).
The problem is due to be fixed in December and reported with in the December FRT data submission. It is not considered due nor reported in the preceding months of July through November. If Release R3.1 contains the fix to the problem report and the fix works, then the problem report is counted on time. If Release R3.1 does not fix the problem, then the problem report must be reported as due but not fixed in July. This will require a resubmission of the July data. Furthermore, it is now overdue and according to counting rule 5.3.4 b) 3) must be reported as overdue in all months from July through December and continuing until it is fixed. This also will require resubmission of the August through November data.
The problem is due to be fixed in June and reported in the June FRT data submission. On August 15 Customer finds that the problem is not completely fixed and rejects the fix, then the problem report must be reported as due but not fixed in June. This will require a resubmission of the June data. Furthermore, it is now overdue and according to counting rule 5.3.4 b) 2) must be reported as overdue in all months from June through August and continuing until it is fixed. This also will require OFR data resubmission of the June through August data.