Contract Admin Manual 2 Works May 2018
Contract Admin Manual 2 Works May 2018
Contract Admin Manual 2 Works May 2018
PREPARED BY
FEBRUARY, 2018
Contract Administration Manual For Works – Manual 2
FOREWORD
On 31st December 2003, the Government of Ghana enacted the Public Procurement Act, 2003
(Act 663) which became operational in August, 2004. The Act provided a framework for the
conduct of procurement in the Public Sector to guarantee best value for money in the context
of poverty reduction, private sector development, good governance and anti-corruption. The
overriding aim of Act 663 is to ensure judicious, economic and efficient use of Public Funds
with procurement being carried out in a fair, transparent and non-discriminatory manner. The
Public Procurement Authority (PPA) considers sustainable training a critical component of its
efforts aimed at strengthening the public procurement systems and achieving value for
money.
The Public Procurement Authority, in 2007, developed twenty-five (25) Training Modules
and Manuals for training of various categories of Stakeholders on the provisions of the Public
Procurement Act, 2003 (Act 663). Over 20,000 Public and Private Operatives have since
benefitted from various training programmes on Public Procurement Act, 2003 (Act 663)
using these Modules. The Modules, however, were mainly on Procurement and did not cover
Contract Administration. To address this shortcoming, the PPA, in January 2015,
commissioned the Ghana Institute of Management and Public Administration (GIMPA) with
funding from the African Development Bank under the Ghana Institutional Support Project
(GISP)to develop detailed Contract Administration Modules and to review the existing
Manuals on Goods, Works and Services. These documents are to be used for the PPA’s
capacity development activities. The Contract Administration Modules and Manuals for
Goods, Works, Consulting Services and Technical Services have come at an opportune time,
given that in Ghana and other developing countries the procurement regime in the public
sector has not been able to address most of the challenges of managing contracts in line with
international best practices and standards.
It is in the light of this that the Public Procurement Authority (PPA) of Ghana, with funds
from supporting Development Partners, has developed these important Contract
Administration Training Modules and Manuals which will go a long way to assist
Procurement Entities in the Public Sector to manage contracts after contract award. These
Training Modules and Manuals will also be useful for the Oversight Institutions like the
Judiciary, Police, EOCO, Media and other Anti-Corruption Agencies to monitor and manage
Public Sector Contracts. It will also serve as reference literature for Lecturers and Students
teaching and pursuing courses in Public Procurement Management and related courses.
These Modules and Manuals touch essentially on the following areas: Contract Principles;
Basics of Contract Administration; Forms of Standard Goods/Works/Technical/Consultancy
Contract; Contract Administration Processes Especially Post Award Preliminary Tasks;
Monitoring of Contract Performance and Reporting and Contract Modification. The
remaining areas are Payment and Cost Control using GIFMIS System; Claims and Settlement
of Disputes; Contract Termination; Contract Records Management; Contract Performance
Evaluation and Post-Implementation Tasks of Contract Administration.
The Authority, therefore, anticipates that with the proper adherence to the principles espoused
in these Manuals, procurement stakeholders will achieve value for money through the
avoidance of time and cost over-runs.
ACKNOWLEDGEMENT
The Public Procurement Authority (PPA) extends profound gratitude and appreciation to the
Donors: Department for International Development (DFID), Deutsche Gesellschaft für
Internationale Zusammenarbeit (GIZ) who initially funded the preliminary development of
the Procurement Manuals and the Guidelines. Special appreciation goes to the African
Development Bank (AfDB) through its Ghana Institutional Support Project, which funded the
development of the current Contract Administration Training Modules and Manuals for
Goods, Works, Consulting Services and Technical Services together with the cost of
facilitation and logistics involved in the training of some Procurement Stakeholders across
the country.
Special acknowledgement goes to the PPA Technical Working Group (TWG) that reviewed
the initial Manuals and Guidelines which were prepared by Crown Agents, UK. Special
mention is made of A. B. Adjei Chief Executive of PPA, Eric V. Appiah, Director,
Benchmarking, Monitoring & Evaluation (BM & E) of PPA, Lesley Dodoo, Director Legal,
PPA, Carl Lokko, Director, Policy & Strategy (P&S), Emelia Nortey, Director, MIS, Vidal
Creppy, Director Capacity Development and the External Consultants namely Messrs.
Godfrey Ewool, Stephen Tackie, Nii Amasa Kotey and Jacqueline Angate.
Our special appreciation also goes to the PPA Team and the External Consultants that
reviewed the draft Contract Administration Manuals and Modules prepared by Ghana
Institute of Management and Public Administration (GIMPA), namely: Yvonne Quansah,
Minawara Adams, Andrew Baafi, Rhoda E. Appiah, Thomas K. Bondzi, Abraham Ablorh
Mensah, Joseph Kuruk, Faustina A. Okuadjo, Hilda A. Agyemang, Prince Agyemang-Badu,
Edwina Safee-Boafo and. Miriam Osei; and External Reviewer, John Benson. Additionally,
the Authority wishes to recognize the valuable contributions of participants of the Training of
Trainers/Validation Workshop which enhanced the final output of this document.
It is worthy to acknowledge the pioneering role of Hon. Samuel Sallas-Mensah, former Chief
Executive Officer of PPA and David Bennin, former Director, Capacity Development of PPA
in the development of these Manuals.
Finally, the Authority wishes to thank the GIMPA Consulting Team of Messrs. N.S.K.
Appiah, K .H Osei-Asante, Michael Kofi Quashie and Paul Nartey, who eventually
developed the final Contract Administration Manuals and the accompanying Training
Modules. Appreciation also goes to the following personnel of the GIMPA Consultancy
Services, who assisted in finalizing the Manuals: Dr. Kofi Fred Asiedu, former Managing
Consultant, Julius Hawkson-Aikins, Ag. Managing Consultant, Fred Appiah and Asafo
Adjei, both Consultants.
The Public Procurement Authority (PPA) wishes to record its appreciation for the time and
effort devoted by all the above-mentioned persons and organizations in the development of
these documents.
However, the ultimate responsibility for the form and content of the Manuals rest with PPA
TABLE OF CONTENTS
FOREWORD..............................................................................................................................i
ACKNOWLEDGEMENT.........................................................................................................iii
TABLE OF CONTENTS..........................................................................................................iv
LIST OF ABBREVIATIONS/ACRONYMS..........................................................................viii
GLOSSARY OF TERMS........................................................................................................xii
INTRODUCTION......................................................................................................................1
Background.............................................................................................................................1
Purpose of the Manuals..........................................................................................................1
Scope of Manual on Works-2................................................................................................1
Content/Structure of the Manual............................................................................................2
Exceptions to the Training Module........................................................................................2
Forms/Templates....................................................................................................................2
1.0 CONTRACT PRINCIPLES............................................................................................3
1.1 Contract –Definition....................................................................................................3
1.2 Essential Elements of a Valid Contract.......................................................................3
1.3 Formation of a Contract...............................................................................................3
1.4 The Law Applicable to a Contract...............................................................................4
1.5 The Nature of Works Contracts...................................................................................5
1.6 Challenges Posed by Works Contracts........................................................................5
1.7 End User involvement in the Management of Works Contracts.................................7
1.8 Types of Works Contracts...........................................................................................7
1.8.1 Basic Types of Works Contracts..........................................................................8
1.8.2 Characteristics, Merits and Demerits of Basic Types of Works Contracts........10
1.8.3 Factors Affecting the Choice of Contract Type.................................................11
1.8.4 Adaptations of the Basic Types of Works Contract...........................................12
1.8.5 Labour Intensive Contracts.................................................................................20
2.0 BASICS OF CONTRACT ADMINISTRATION.........................................................21
2.1 Introduction................................................................................................................21
2.2 Objectives of Contract Administration......................................................................22
2.3 The Role of Contract Administration.........................................................................22
2.4 The Benefits of Good Contract Administration.........................................................23
2.5 Poor and/or Fraudulent Contract Administration.......................................................23
2.6 Fraud and Corruption in Contract Implementation....................................................24
2.6.1 Possible Indicators of Corruption.......................................................................25
2.6.2 Remedial and Pro-Active Actions......................................................................25
2.6.3 Policy on Preventing, Detecting and Remediating Fraud and Corruption.........26
2.6.4 Conflicts of Interest.............................................................................................27
2.7 Summary of Main Tasks of Contract Administration.................................................27
2.8 Important Parties in a Works Contract......................................................................27
2.8.1 The Employer......................................................................................................28
2.8.2 The Engineer.......................................................................................................31
2.8.3 The Contractor....................................................................................................36
2.9 Organization for Contract Administration.................................................................38
2.9.1 Contract Administration Organization for Works..............................................41
2.10 Responsibilities of the Contract Administrator......................................................41
2.11 Contract Administrator Responsibilities................................................................46
2.12 Skills of the Contract Administrator......................................................................47
3.0 FORMS AND CONDITIONS OF STANDARD WORKS CONTRACTS.................48
3.1 Introduction................................................................................................................48
3.2 Basic Documentation for Works Contract.................................................................48
8.4.3 Payment..............................................................................................................88
8.4.4 Adequate contract documentation......................................................................89
v Public Procurement Authority (PPA),
Contract Administration Manual For Works –
8.4.5 Construction information....................................................................................90
8.4.6 Supervision.........................................................................................................90
8.5 Dispute Resolution.....................................................................................................91
9.0 TERMINATION OF CONTRACT................................................................................95
9.1 Introduction................................................................................................................95
9.2 Suspension of the works............................................................................................95
9.3 Termination by Employer/Contractor........................................................................95
9.4 Termination for Convenience.....................................................................................96
9.5 Payment upon Termination........................................................................................96
9.6 Termination Checklist................................................................................................97
9.7 Contingency Planning................................................................................................97
10.0 CONTRACT RECORDS MANAGEMENT..................................................................98
10.1 Introduction............................................................................................................98
10.1.1 What Is Records Management?...........................................................................98
10.1.2 Importance of Records.......................................................................................98
10.1.3 Procurement and Contract Records....................................................................98
10.1.4 Benefits of Good Records Management.............................................................99
10.1.5 Principles of Good Records Management..........................................................99
10.1.6 Consequences of Failure to Maintain Adequate Procurement Records...........100
10.1.7 The Records Life Cycle....................................................................................100
10.1.7 Opening a New File..........................................................................................101
10.1.8 Filing of Papers.................................................................................................101
10.1.9 File Movement Controls...................................................................................101
10.1.10 Closing a File................................................................................................102
10.1.11 Records Accommodation/Space....................................................................102
10.1.12 Equipment.....................................................................................................103
10.1.13 Records Personnel.........................................................................................103
10.2 Contract Administration File and Documentation...............................................103
10.2.1 Contracts Register.............................................................................................104
10.2.2 Separate Contract Files.....................................................................................104
10.2.3 Contract Sub-files.............................................................................................104
10.3 Automation of Records Management (Electronic Records Management)...........105
10.3.1 Benefits of Automation....................................................................................105
10.3.2 Records Management Functions That Can Be Automated..............................105
10.3.3 E-mail...............................................................................................................105
10.3.4 Digitization (Imaging/Scanning)......................................................................106
10.3.5 Challenges in the Management of Electronic Records.....................................106
11.0 EVALUATION OF CONTRACT PERFORMANCE..................................................108
11.1 Introduction..........................................................................................................108
11.2 Evaluation of Contractor Performance.................................................................108
11.3 Evaluation of Management/Supervision of Contract...........................................109
11.4 Evaluation Processes............................................................................................110
11.5 Evaluation checklist.............................................................................................111
11.6 Contract Review...................................................................................................111
12.0 POST IMPLEMENTATION TASKS.........................................................................113
12.1 Introduction..........................................................................................................113
12.2 Taking Over of the Works and Sections..............................................................113
12.3 Performance Certificate.........................................................................................114
12.4 Defects Notification Period..................................................................................114
12.5 Statement at Completion/Final Accounts.............................................................115
12.6 Discharge..............................................................................................................116
LIST OF FIGURES
LIST OF
AD Advance Payment
AGD Auditor-General’s Department
APS Advance Payment Security
AR Authorized representative
BOLF Build, Operate, Lease and Finance
BOQ Bills of Quantities
BOO Build, Operate and Own
BOOT Build, Operate, Own and Transfer
BOT Build Operate and Transfer
CA Contract Administrators
CC Commencement Certificate
CD Contract Data
CE Contracting Entity
CGGL Central Government General Ledger
CAGD Controller & Accountant –General’s Department
CM Contract Modification
CO Cost Over-runs
COI Conflicts of Interest
CAS Contract Agreement and Securities
CAM Contract Administration Manual
CAP Contract Administration Plan
CM Commencement Meetings
COPA Conditions of Particular Application
CP Cost Plus
CPM Critical Path Method
CRPF Cost Reimbursable Plus Fee
CT Contract Termination
DA Donor Agencies
DANIDA Danish International Development Agency
DBFO Design, Build, Finance, Operate
DBMF Design, Build, Maintain and Finance
DBOM Design, Build, Operate and Maintain
DBOMF Design, Build, Operate, Maintain and
Finance DB Design and Build
DC Design and Construct
DFID Department for International Development
DNP Defects Notification Period
DR Disputes Resolution
ECP Evaluation of Contract Performance
EMW Electrical and Mechanical Works
EOI Expression of Interest
GLOSSARY OF TERMS
TERM DEFINITION
Acceptance Refers to the acceptance of goods, works or services by the
Purchaser/Employer/Client.
Contract package The logical assembly of items within a contract that takes into
consideration timeliness, economies of scale, geographic
distribution, etc.
Economy Buying only what is needed for the project at the lowest
evaluated price.
Indefinite Delivery Framework Contract for on-call specialized services for which the
Contract extent and timing cannot be defined in advance.
Plant Any integral part of the works that have a mechanical, electrical,
chemical, or biological function.
Post review A review by the funding agency of awarded contracts and related
procurement documentation below a stated contract threshold.
Technical Services Services which are tendered and contracted on the basis of
performance of a measurable physical output such as drilling,
INTRODUCTIO
Background
Since the establishment of the Public Procurement Authority (PPA) as a result of the
promulgation of the Public Procurement Act, 2003 (Act 663) Amended, it has instituted a
number of pragmatic and far-reaching initiatives aimed at ensuring maximum returns for the tax-
payers’ money. Despite these laudable efforts, the annual procurement assessment conducted by
the PPA in the procurement entities reveal several challenges relating to the administration of
contracts awarded by most entities.
These challenges can be attributed to the absence of credible arrangements for contract
administration. The observation has been that contract administration in most public procurement
entities usually involve disjointed processes unfortunately resulting in poor supervision of
contracts and compliance as well as missed opportunities for achieving value for money.
As part of the means to address the above challenges, the PPA commissioned a firm to develop
separate contract administration manuals for Goods, Works, Consulting Services and Technical
Services.
There are four Manuals on contract administration. Manual 1 is on Goods, Manual 2 is on Works,
Manual 3 is on Consulting Services and Manual 4 is on Technical Services. To have full
knowledge of contract administration in Public Procurement, one will need to read all the four
Manuals. It is hoped that the manuals will prove to be useful as a handbook or resource material
for practitioners, facilitators and students.
Introduction
1.0: Contract Principles
2.0: Basics of Contract Administration
3.0: Forms and Conditions of Standard Works Contracts
4.0: Contract Administration Process: Post-Award Preliminary Tasks
5.0: Monitoring Contract Performance & Reporting
6.0: Contract Modification
7.0: Payment & Cost Controls
8.0: Claims and Disputes Resolution
9.0: Termination of Contract
10.0: Contract Records Management
11.0: Evaluation of Contract Performance
12.0: Post Implementation Tasks
Forms/Templates
In some of the chapters, templates/formats deemed useful have been presented in the
Appendices.
According to Public Procurement Act, 2003 (Act 663) as Amended, “a procurement contract
means a contract between the procurement entity and a supplier, contractor or consultant
resulting from procurement proceedings.”2
With certain exceptions, a contract need not be in writing. However, enforceability will
depend on being able to prove the existence and terms of a contract. It is therefore highly
recommended that all contracts be put into writing.
A Tenderer may withdraw, substitute or modify its Tender after it has been submitted by
giving notice in writing before the deadline for Tender submission as prescribed, duly signed
by an authorized representative and shall include a copy of the authorization in accordance
with the
1
Culled from Gosta Westring and George Jadoun (Rev.15th November 1996). Public Procurement Manual.
3 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
2
Refer to Section 98 of Public Procurement Act, 2003 (Act 663) as Amended.
Normally, a Procurement Entity should be able to rely on the validity of an offer which is
made in writing. However, many contracting agencies demand as an extra precaution that
security in the form of a Guarantee, a Bond or a Securing Declaration is submitted along with
the offer in order to reinforce the tenderers’ promise to keep the offer binding for a specific
period of time.
The importance of the applicable law, then, is first of all to regulate matters which the parties
have not addressed in their contract and, secondly, to hold the parties within limits drawn up
by the stringent provisions of the law. In addition, the applicable law is used by the judge or
arbitrator to interpret the contract and to fill in gaps in the contract where no contractual
provisions exist.
Under the various Standard Tender Documents of the Public Procurement Act, 2003, Act 663
as Amended, the Law Applicable to a Contract is that of Ghana.
The documents forming Works Contract are taken as mutually explanatory of one another
and for the purposes of interpretation, the composition and priority of the documents in many
conditions are to be in accordance with the following sequence:
Contract Agreement (if any),
Letter of Acceptance,
Letter of Tender
Particular Conditions,
Each project that has a works component deals with one general type of works – large
infrastructure projects (highways, bridges, roads, irrigation systems, dams etc.), smaller scale
municipal infrastructure projects (rehabilitation of buildings, roads, sewage, water or power
utilities), environmental rehabilitation projects (earthworks, planting, seeding, water
management etc.). Essentially, the Procurement Entities should have experience in those
types of works and possess the necessary in-house technical expertise.
Unfortunately, most Procurement Entities do not have the same level of experience or
expertise when it comes to the particular forms of contracts used in Standard Tender
Documents, particularly FIDIC Conditions of Contract and used for major works. While this
type of contract has been extensively used in the developed countries, its use in most of the
developing countries has been extremely limited. Experience and expertise in the use of these
Conditions of Contract are therefore not very easily available.
Technical expertise alone is rarely a success factor by itself and a thorough understanding of
the contract documents often proves more valuable than technical expertise.
Each and every one of these factors may and often have a direct impact on the successful
implementation of the works projects in terms of quality, timeliness, efficiency and
effectiveness of money spent etc.
All these are important reasons why the management of the works contracts is among the
most important challenges faced by the procurement entities, because proper management of
works contracts means not only an adequate contract administration, that is knowing and
enforcing contract conditions, clauses and remedies with supervisory roles over the contractor
and the consultant, with the assistance of the Engineer/Project Manager and more
importantly, managing the intricate relationships among all parties and stakeholders together
with a thorough understanding of risk management and their effect on project’s outcome and
In the form of an equation with a multitude of variables this would translate as:
Management of
Management of = + relationships with
Contract
Works contracts contract parties, third
administration
parties and stakeholders
Involving the community whenever this is possible and practical has many advantages:
a) Better control on the Contractor and on the outcome of the contract;
b) Reduces the possibility of fraud and corruption;
c) Increases community ownership and sustainability.
d) Micro works contracts – estimated to cost to GHS15,000, short contract duration (less
than 4 months), and where the magnitude of the potential risks involved is small for
both the Employer and the Contractor. The General Conditions of Contract are based on
the 1999 edition of the International Federation of Consulting Engineers’ (FIDIC)
“Conditions of Contract for Short Form of Contract”. These are normally used only for
Request for Quotations (RFQs)
The Unit Rate (UR) type of contract is the most common in general use internationally in the
public sector for the construction of infrastructure projects, both large and small, under
conditions of moderate perceivable risk in sectors such as transportation, power, irrigation,
water supply and sewerage, etc. Tenderers are invited to quote unit rates for carrying out the
Employer’s estimated quantities of different classes of work to be performed. The unit rates
are inclusive of all related inputs of labour, materials, equipment usage and a proportion of
overheads and profit. The Tender Price comprises the summation of estimated quantities
multiplied by the respective unit rate for all items of work. During contract execution,
quantities of work completed satisfactorily are measured periodically as a basis for payment.
The unit rates may be fixed for short duration contracts of 18 months or adjustments for
variations in the indexed price of inputs over longer duration contracts.
The tender documents and subsequent contract should emphasize a single responsibility for
the supply of plant/equipment/goods and the execution of related works in order to avoid
conflicts and delays in the event of non-compatibility. According to the relative
predominance of goods or works, the tender documents for minor/micro projects e.g. the
fabrication and erection of bus shelters, small grain silos, etc. For major projects with a
predominance of installed plant and equipment, the documents should incorporate the FIDIC
GCC for “Electrical and Mechanical Works including Erection on Site” 1999, the Yellow
Book or the World Bank’s trial STD, 1999 for the Supply and Installation of Plant and
Equipment.
A comprehensive site and subsoil survey is provided by the Employer as part of the tender
documentation which should also include the parameters of structural design and loading.
Competitive designs and lump sum tenders are called from qualified tenderers who provide
comprehensive design calculations, quantities and drawings. Tender evaluation includes:
Design checks and quantification of design errors,
Times of completions,
Payment schedules, and
Assessment of the aesthetics of the different proposals.
Tenderers and Applicants are sometimes compensated, on a sliding scale according to merit,
for the preparation of responsive proposals.
c) Turnkey
Turnkey contracting is used for the procurement of complex industrial process facilities and
plants such as steel mills, food processing, petroleum refineries, etc. when alternative systems
and processes could not provide satisfactory end product requirements, and it would therefore
be undesirable or impractical to prepare definitive designs and complete technical
specifications in advance. A two-step tender procedure is normally followed, first inviting
unpriced technical proposals and outline designs which are subject to clarification and
adjustment by the Employer, followed by the submission of detailed technical proposals and
priced tender in the second step.
The turnkey contractor undertakes to provide detailed designs, production process plant and
equipment, manufacturers’ authorization, related construction, procurement licenses,
guarantees, recruitment and training of operating staff, commissioning, start-up, initial
operation and maintenance and final handover of the “key” to the Employer for him to “turn”.
The contract price is normally quoted LS with periodic payments against specified stages of
partial completion. Price adjustment clauses may be provided for contracts of longer duration
than about two years and contractors may be encouraged to tender on a fixed price basis and
absorb the risk of future price fluctuation with payment in a hard foreign currency. FIDIC has
prepared GCCs (1999) for Design-Build and Turnkey Contracts.
d) Target Cost
This type of contract may be used in conditions of high uncertainty and unquantifiable risk
which make it difficult to define the value and scope of the works precisely before inviting
1 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
tenders. It is essentially a cost reimbursable plus incentive fee type of contract, where the
initial fee is adjusted with a bonus or penalty according to whether the final contract cost is
less or greater than an agreed Target Cost.
This form of contracting is more suited to single source procurement, where an Initial Target
Cost (ITC) can be the subject of competitive tender on a UR basis against provisionally
estimated quantities of work, with overheads and fee priced separately but competitively. As
the work progresses, the scope of the project and the target cost can be more precisely
defined. The ITC is updated periodically to include agreed variations, extra works, actual and
estimated quantities of work and price adjustment, if any, which becomes the Final Target
Cost (FTC) upon completion. Payment to the Contractor is made on a cost reimbursable basis
against actual inputs to the contract and upon completion, total payments are compared with
the FTC to determine the amount of final fee.
In effect, PPPs therefore have long term, contractual partnerships between the public and
private sector agencies, specially targeted towards financing, designing, implementing, and
operating infrastructure facilities and services that were traditionally provided by the
Government and/or its agencies.
These collaborative ventures are built around the expertise and capacity of the project
partners and are based on a contractual agreement, which ensures appropriate and mutually
agreed allocation of resources, risks, and returns. PPP is the approach of developing and
operating public utilities and infrastructure by the private sector under terms and conditions
agreeable to both the government and the private sector.
PPP Models
i. Service Contract
Government/public authority hires a private company or entity to carry out one or
more specified tasks or services for a period, typically 1–3 years,
Public authority remains the primary provider of the infrastructure service and only
contracts out portions of its operation to the private partner,
Private partner must perform the service at the agreed cost and must typically meet
performance standards set by the public sector, and
Private contractor is paid a predetermined rate for labour and other anticipated
operating costs, and
Duration of the leasing contract is typically for 10 years and may be renewed for up to
20 years.
Responsibility for service provision is transferred from the public sector to the private
sector and the financial risk for operation and maintenance is borne entirely by the
private sector operator.
The operator is particularly responsible for losses and for unpaid consumers' debts, and
A BOT type of contract may be considered when an Employer/Owner has limited budget
and/or borrowing capacity, or otherwise wishes to involve the private sector in financing a
typical public sector project. It is essentially a concessionary turnkey type of contract, which
includes financing in addition to the design, construction, operation and maintenance of
public and private revenue earning projects such as power generation and distribution, toll
roads and bridges, water supply, etc. Total costs and risks are borne by the private BOT
investors over the concession period, which may be some 20-30 years.
The BOT type of contract is one of a growing family of concessionary contracts involving
private sector financial participation, each of different features.
Types of Partnerships
The highest influence can be exerted with force-account (direct labor) procurement, where all
aspects of design, construction, supervision and financing are normally borne by the public
authority, which then has full exposure to all risks. The lowest influence/risk results from
High
Low
The higher the proportion of labour costs required, the more labour intensive the business.
Construction activities in Ghana are by their very nature labour intensive and support a large
reservoir of skilled and unskilled labour that produce to contribute to the gross domestic
product.
Labour intensive contracts are very common with the Road Sector in Ghana, where there are
clear Guidelines for the Implementation of Labour Intensive Projects. International and local
experiences have shown that with well-trained supervisory staff and an appropriate
employment framework, labour intensive methods can be used successfully for infrastructure
projects involving low-volume roads and sidewalks, storm water drains and trenches. On the
basis of this experience and in the context of high levels of unemployment, the government
has decided to require that these infrastructure projects must be carried out in a labor-
intensive manner.
It includes all dealings between parties to a contract from the time a contract is awarded until
the task has been completed and accepted or the contract terminated, payment has been made,
disputes have been resolved and the contract closed.
The stages of Contract Administration are intended to ensure that the parties work together to
achieve the objectives of the contract. Contract Administration is based on the idea that the
contract is an agreement, a partnership with rights and obligations that must be met by both
sides to achieve the goal. Contract Administration is aimed not at finding fault, but rather at
identifying problems and finding solutions together with all contracting parties involved.
Although the actual planning begins during the selection process, Contract Administration
actually starts upon the signing of the contract, which is the point at which the parties to the
contract are bound by its terms and conditions. As with contract management, contract
administration ensures that each party adheres to the contract and performs at or above the
levels specified in the contract.
If we compare the nature or characteristics of the activities associated with both contract
management and contract administration (see below) then we can see that the differences are
fundamental, yet without efficient contract administration, then effective contract
management becomes very difficult, if not impossible.
3
UN Handbook on Procurement, 2006
In the light of the above, most organizations/institutions use the two interchangeably.
However, in this Module, the Public Procurement Authority (PPA) has decided to use the
term ‘Contract Administration’.
a) Effective control, ensuring that both parties know their obligations and
implementing a contract controls system that reflects the performance requirements
of the contract and provides mechanisms of the coordination and dissemination of
information,
b) Performance to the required standard with the full use made of contractor’s own
management information and performance measurement systems and the contractor
reporting progress through agreed procedures.
c) Compliance with contract terms and conditions in managing them to help ensure
that they are met and when not provide remedies to be applied properly and
promptly,
d) Clear and documented records which are essential in the event of invoking default
procedures for seeking correction of failures to perform,
e) Management of change as it is the contract administrator’s responsibility to define
appropriate change control procedures which enable him/her to anticipate, manage
and control changes to requirements and/or costs, and
f) Value for Money as a balance of cost, risk, delivery and quality which should be
managed in a sustainable manner to:
i. Record costs;
ii. Ensure no change in the balance of risks;
iii. Ensure timely delivery; and
iv. Ensure quality.
g) Performance rating: the performance of the Contractor would be evaluated and
rated at the end of the contract by the Contract Administrator. The Contractor would
be informed of the result and this will help him/her to improve upon future
performance
a) Scope of contract is not achieved, where the end product is either not delivered or is
of a very poor quality,
b) Delays or time over-runs, or
c) Cost over-runs.
The worst case scenario is a situation where all these three situations described above are met
the contract does not achieve its objective and ends up with time and cost overruns.
The most frequent causes of badly managed contracts are often linked to:
i. The capacity of the contract administration team;
ii. Its willingness to act according to its mission and purpose, and/or
iii. delays in payment
The negative effect of lack of capacity can be successfully mitigated, especially if the issue of
capacity is addressed at an early stage during contract implementation.
Lack of willingness to act in the best interest of the contract can have two major causes,
different from an ethical perspective, but can be equally damaging to the success of contract
implementation:
lack of motivation of the staff, more benign and potentially less harmful due to
amongst others:
Dissatisfaction with the level of remuneration,
Lack of professional challenges,
Eroding routine,
Lack of recognition from the superiors, and
Sense of futility
These symptoms must be identified early in the implementation stage and properly addressed
through appropriate administrative and relationship decisions such as incentives, motivation,
correct allocation of tasks and responsibilities, correlation between responsibilities and
rewards, increased ownership of the process etc.
Staff inactivity has its roots in fraud and corruption and is the most dangerous risk
during contract implementation and connotes a high degree of certainty that the
proper execution of the contract is compromised.
Delays in payment most often can be attributed to lack of funds from central government or
improper cash flow planning by the Procurement Entity. It is only in rare instances that it
can be due to deliberate unwillingness of the contract administration team to act.
All these precautionary measures should not be interpreted as instigations to abuse the
contract mechanisms and remedies against the contractors. Overzealous and abusive
3 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
contract
Without limitation on the generality of the foregoing, a Contractor, including all parties
constituting the Contractor and any subcontractors and suppliers for any part of the Contract,
including related services, and their respective personnel and affiliates may be considered to
have a conflict of interest in terms Conflicting activities, Conflicting assignments and
Conflicting relationships and in the case of a Contractor, the Contract may be terminated.
A Contractor has an obligation to disclose any situation of actual or potential conflict that
impacts their capacity to serve the best interest of the Employer, or that may be reasonably
perceived as having this effect. Failure to disclose said situations may lead to the termination
of the Contract.
One of the biggest mistakes in the administration of works contracts is the belief that once
you hire a competent Engineer all your troubles are over. But this is only true in exceptionally
rare
3 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
cases because an effective contract administration requires a high degree of involvement from
the implementing agency/entity and there can never be a full and complete outsourcing of
contract administration, since the implementing agency/entity must retain critical key
functions within the process, at least final verification of documents and payment.
In large works contracts as well as in projects with many contracts with a wide geographical
spread the implementing agency/entity might also benefit from the expertise and experience
of third party technical auditors. These can be hired as an additional layer of supervision
responsible with checking how the contract parties, Contractor and Employer, including the
Engineer, are fulfilling their duties and responsibilities toward the successful completion of
the contract.
The Layers of supervision in the administration of works contracts below shows the different
layers of oversight responsibilities that should be interpreted as complementary to each other.
The presence of an additional layer of supervision represented by an outer circle should by no
means be interpreted as a superior hierarchical position of a subordination nature; it merely
indicates a greater scope of the supervision function.
Engineer’s
supervision
Employer’s
supervision
Third party
The involvement of so many layers of supervision in the case of major works contracts is by
no means an exaggeration or a whim. It must be fully understood that the administration of
these types of contracts is not a part time job and not a task to be entrusted to one single
party. Now the purpose, roles and responsibilities of each of these layers could suffice.
Some of these attributes derive from limitations to Engineer’s authority expressly mentioned
in the contract documents; others (most of them, in fact) are unwritten rules that must be
followed for successful contract implementation.
The Employer can put a limit on the authority of the Engineer (PCC 3.1):
a) By setting a maximum level of authority to approve variations, or
b) When approving any extensions of the Time for Completion, or
3 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
c) When approving of any subcontractor.
This is often done whenever the Employer wants to maintain a close control on the time and
costs.
In order to prevent the dilution of responsibility for the execution of the works, the
Employer can set maximum thresholds for subcontracting (PCC 4.4.) or limit the
possibility to subcontract only to specific, non-essential activities.
FIDIC Conditions of Contract allow the Engineer to approve payment of plant and
materials brought on site prior to their incorporation in the Works. This is advisable
whenever the Contractor should deliver expensive Plant, equipment or materials on
site, that are to be later incorporated in the Works and for which the Contractor could
normally seek reimbursement only in the first Interim Payment Certificate after their
incorporation in the works. PCC 14.5 can limit this practice by specifying the exact
nature of plant or materials for which the payment on delivery would be acceptable or
by denying this altogether.
The Employer may also set high thresholds for the minimum amount of Interim
Payment Certificates (PCC 14.6), with a double purpose:
a) To avoid situations when it would be flooded with Interim Payment
Certificates of small amounts, where and when the Employer need to manage
a large portfolio of contracts with limited payment processing capacity, and
b) To stimulate the Contractor to speed up the progress of works, so its monthly
statements would exceed the minimum threshold, noting that excessive
thresholds could backfire by forcing the Contractor to seek payment for
inexistent works.
Internal arrangements:
The Employer must first of all ensure that the proper internal arrangements are made in its
own organization. This mainly refers to people and processes:
Assigning detailed tasks to the individual or the team responsible with the specific
duties during the contract administration process. This would be equivalent to
creating job descriptions for everyone involved. The tasks assigned to each individual
should be precise and realistic, taking into account the specific experience, expertise
and workload of each staff, i.e. the procurement specialist should be responsible for
keeping track of the main contract milestones of commencement date, possession of
site, submission of securities, bank guarantees and insurance policies, advance
payment, time for completion etc., with the technical expert responsible for the
tracking of the conditions of contract and accurate recordkeeping of volumes of
work, main technical milestones etc.,
There are rather few, statistically FIDIC Contracts where all the responsibilities of the
Engineer are entrusted to one single individual. This should only happen in the case of
simpler contracts with straightforward bills of quantities where variations are very unlikely.
Usually the Engineer is a specialized consulting company that can mobilize various technical
expertise where there are many different skills that are required in the implementation of a
large works contract. Consequently, more than one single individual would be exercising
various supervision functions at any given time – quantity surveyors, land
surveyors/topographical engineers, structural engineers, roads/bridges engineers, electronic
and electro-mechanical engineers, hydrogeological and hydrological engineers,
environmental specialists, health & safety specialists, Quality Assurance/Control specialists
etc.
The Engineer may designate a number of staff some of them full time, others part time
experts, depending on the size, complexity or geographical spread of the works.
In the case of these supervising companies, the contractual term “Engineer” designates the
single individual person that has been delegated with the ultimate authority of supervision,
the team leader, leading engineer, site engineer, resident engineer, coordinating engineer or
whatever job title the respective person might have. All other personnel involved in the
While this may be true for most minor and micro works supervision, it is definitely counter-
productive in the case of major works supervision because of the reasons mentioned above:
Manpower and workload, where proper and adequate contract administration is not a
part- time job,
Expertise, where hard skills like technical or financial background, contractual
literacy, managerial skills, administrative skills, fluency in the language of the
contract or of the contractor are of particular importance,
Adequacy, where the right number of available and qualified people do possess the
requisite soft skills needed for a smooth and successful contract administration like
people skills, communication abilities, team spirit, cooperation, leadership,
facilitation, conflict mitigation, planning, coaching, motivation, innovative drive,
perseverance etc.,
Experience where many similar contracts of comparable scale have been successfully
managed or supervised.
In addressing these issues raised usually lead to the conclusion that the most effective and
efficient use of resources of money, time and people would be the selection and employment
of external persons to assist in the form of a Consultant/Consulting firm.
With all these arguments, the ultimate evidence is for the Employer to appoint a third party as
the Engineer to confirm the very spirit of the FIDIC Conditions of Contract, which is that the
Engineer should act impartially when exercising its duties and authority.
Since cases where these kinds of Engineers are employed instead of actual consulting firms
are and should be fairly rare, this manual focuses on the practice that represents the rule
rather than the exception, i.e. a consulting company being selected to act as Engineer.
These are two very powerful and valid arguments particularly in countries where professional
liability in works as well as professional prestige are very serious matters, as well as in
countries with very well-developed body of knowledge and experience in engineering.
In the real world of less-than-perfect engineering or weaker professional liability records, it
may prove damaging to have the same consulting engineer to do the designs and the
supervision of the works. There are many situations where the designer/engineer is more
preoccupied to hide or to mitigate the effects of its own potential design errors than to enforce
an adequate and cost-effective contract administration for its Employer, which happens for
two reasons, the:
(i) Engineer is not willing to admit any design errors, including grossly mistaken
quantities, unreasonable technological requirements etc. for fear of professional
liability/remedies from the Employer, or
(ii) Engineer is so dedicated to its own design that it rules out any alternative solutions
that would actually bring more value for money to the Employer.
Drawing a line and making a decision whether the Employer should consider an integrated
engineering/supervision solution or separate activities are not easy to decide.
Some countries have solved this dilemma by explicitly forbidding that the design and the
supervision be done by the same party, for fear of potential conflict of interest. Other
countries like Ghana has left this matter in a grey area by ruling that representatives of the
designer and the Engineer should sign off the works, but without specifically stipulating that
the two must actually be different parties. Most of the developed world does not impose
4 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
any restrictions,
For the selection of the Engineer, the issue then becomes which type of selection would be
the most appropriate, whether the focus should be only on price - least cost selection, only on
quality - quality-based selection, or should be a quality and cost-based selection. There is no
obvious or universal answer to this and it greatly depends on the scale and on the specific
nature of the assignment. Where large scale contracts that involve relatively simple activities
of the nature of earthworks with minimal highly specialized expertise, least cost selection
may be prudent. Whenever more specialized technical skills are required, the professional
quality of the Consultant should be the most important, if not the only factor for selection.
The tendency of the Employers to place a heavier weight on cost, as a premise for efficient
use of funds, is understandable. But it should borne in mind that any compromise in the
quality of the Engineer for the sake of savings may result in much higher costs for the
Employer, coming out of costly delays, unjustified variations, higher operation and
maintenance costs due to poor quality of materials or workmanship etc.
FIDIC always advocates the prevalence of quality over price in the selection of the Engineer
as a first premise of a successful implementation of a works project. It is recommended that
the Employer should be guided by the following principles when selecting the Engineer:
1. Professional competence,
2. Managerial ability,
3. Availability of resources,
4. Impartiality,
5. Fairness of fee structure,
6. Professional integrity, and
7. Quality assurance system.
Since all the above as well as other responsibilities of the Engineer can easily be inferred
from the actual contract clauses, we would focus on those contract administration
responsibilities
Consequently, the Employer’s own role in managing Micro/Minor Works contracts may
become more complicated than in the case of major works under FIDIC contracts.
The Project Manager should retain most, if not all roles and responsibilities assigned to the
Engineer in the FIDIC contract, while the Employer should continue to exercise its contract
supervision role exactly along the same lines as described above.
Responsibilities
A contractor is responsible for providing all of the material, labour, equipment and services
necessary for the construction of the project. The contractor may hire specialist contractors
and specialized subcontractors to perform all or portions of the construction work.
Responsibilities may include applying for permits, securing the property, providing
temporary utilities on site, managing personnel on site, providing site surveying and
engineering, disposing or recycling of construction waste, monitoring schedules and cash
flows, and maintaining accurate records.
Licensing Requirements and Qualifications
Licensing requirements to work legally on construction projects must be observed for all
businesses or individuals who work on any building, highway, road, parking facility, railroad,
excavation or other structure in Ghana and must be licensed by the Ministry of Water
Resources, Works and Housing and the Ministry of Roads and Highways with categories and
classifications thresholds set based on costs.
There are no set educational qualifications to become a contractor, though many employers
now prefer contractors who are educated. However, requisite technical qualifications are
needed for the personnel of the Contractor.
For Government of Ghana funding, where there is no foreign financing, it is only the right
side of the figure that is applicable. The institutions involved in public contract administration
include the following:
The Contracting Entity
The Line Ministry and other Sector Ministries
The Ministry of Finance (MoF)
The Auditor-General’s Department
The Controller & Accountant –General’s Department(CAGD)
The Ministry of Justice & Attorney-General’s Department
The Public Procurement Authority (PPA)
The Courts
Ministry of Justice/AGD
Public Procurement Authority
Funding Agency 1
Auditor-General
Controller &
Accountant General
Sources of Information
PROCUREMENT
ENTITY Sources of Information
The procurement structures for post contract activities are outlined below although the
involvement of the Entity Tender Committees and the Tender Review Committees is minimal.
Reports Submissions
Appoints
Request and queries
TRC & ETC to ensure compliance with the Public Procurement Act, 2003
Liaises Reports
(Act 663) Amended and Regulations on a transaction basis within their defined thresholds.
Originating Departments, Project or User Unit
Contract Administrator
The roles and responsibilities of the bodies that are involved in post contract activities are:
The Entity Tender Committees are responsible for the facilitation of Contract Administration.
Finance/Accounts Department
The Department within the Procurement Entity responsible for the financial affairs of the Entity
and the control of the Entity’s budget.
The number of participants or staff in the contract administration process will vary in number
from one to many depending on the size, level of risk and complexity of the contract. Early in
the procurement process, there is the need to identify the contract administrator and those who
are to assist him/her; this will allow for roles and responsibilities to be assigned.
It is worth noting that in most simple works contracts, the Engineer or Project Manager, acting
as the Contract Administrator can handle all responsibilities with the support of a few
Assistants. The full organizational structure for large works contracts is shown in Figure 5.
procurement in accordance with the legislation. These relationships and responsibilities are
summarized below:
Procurement Entity
Head of Procurement Entity
Project Manager
(Employer’s Representative)
Stores Dept
Project Consultants
Procurement Entity
Procurement Entity is the term used in this module to refer to a central, local and regional
government authority and other bodies governed by public law and delegated with the task of
discharging Contract Administration functions.
The overall size and structure of the Procurement Entity is governed by the mandate of its
establishment.
Preparation of tender documents Payment to contractors Monitoring actual progress Technical support to the operations unit
Tender opening and evaluation Controlling cost overruns Technical assessment of new procurement o
Budget control on contract by contract basis Design services for the implementation of cu
Purchasing and Logistics operations Measurement of periodic work accomplishment;
Personnel issues and trainingSupervision
and staff development
of compliance
plans
with quality standards
Supplier and price database Cost accounting for key operations
Operation of management information system (MIS)
The volume and repetitive nature of activities and the corresponding annual procurement
turnover determine the optimum size of the Procurement Entity’s operational staff levels and
skills.
The Contract Administration function is entrusted to the Contract Administrator (CA) who
assumes the ultimate responsibility for all Contract Administration tasks and is in charge of
mobilizing the Contract Administration team.
Depending on the mandate of the Procurement Entity, the CA may be in charge of one or more
contracts thus necessitating the presence of an efficient document control set-up.
The broad lines of responsibility for each of the disciplines of Contract Administration may be
summarized as follows:
I. Procurement
This discipline primarily deals with:
a) Preparation of the invitation to tender documents, inclusive of determining the contract
type and the general and particular conditions of contract in consultation with concerned
end-users, consultants and other disciplines within the Entity,
b) Tender opening and evaluation,
c) Purchasing and logistics operations for the requirements of the Procurement Entity on
assignments directly implemented by the Entity, and
d) Maintaining databases on market prices and sources of supply/vendors.
I. Administration
This discipline primarily deals with:
a) Payment to contractors,
b) Budget control on contract by contract basis,
c) Personnel issues and implementation of training and staff development plans, and
d) Cost accounting for key operations.
II. Operations
This discipline supervises the physical implementation of each contract:
a) Monitoring actual progress versus contract work plan/schedule,
b) Controlling cost overruns due to increased volume of operations or costs growth due to
variation orders,
c) Measurement of periodic work accomplishment,
d) Supervision of compliance with quality standards of inspection, testing, etc., and
e) Operation of management information system (MIS) for optimum coordination and
access to information amongst all disciplines.
The responsibilities of the document control office are developed within the internal operational
procedure of the Procurement Entity.
The number of participants in the contract administration process will vary in number from one
to many depending on the size, level of risk and complexity of the contract. Early in the
procurement process, identify staff to participate in contract administration. Identify a single
Contract Administrator and others to assist him/her. Assign roles and responsibilities which may
include:
Determining the sequence of activities, dependencies, required or desired outcomes, and
acceptable performance levels.
Developing a timetable and start and end date for each performance component. Include
milestones with accompanying timeframes, and monitoring and reporting requirements.
Monitoring contractor activity on a specified frequency to identify problem areas.
Meeting with the contractor on a regular basis to review progress, discuss problems and
consider necessary changes.
Providing access to state facilities, equipment, data, staff, materials and information.
Contacting other staff as necessary to provide equipment and data.
Establishing scope of authority, clear lines of communication and reporting and specific
individuals who will interact directly with the contractor.
Establishing control of correspondence, data and reports.
Identifying potential problems and solutions.
Defining terms or conditions of default.
3.1 Introduction
The FIDIC Conditions of Contract for Construction have become the prevailing international
standard for works contracts because they present a multitude of advantages over other forms
and conditions of contract to:
Cover in a clear and precise manner a lot of circumstances and events that may and
often occur during the implementation of a works contract, and
Provide a clear image on the roles and responsibilities of each party.
This is why Employers may favour the use of this type of contract even for Micro/Minor
works that would not normally qualify for this.
The LS turnkey contract is ranked second in importance for ICT projects, particularly in the
industry, power/energy/petroleum and telecommunications sectors where projects are usually
large although few in number. Supply and Install contracts are also frequently used in these
sectors for projects involving the installation of major items of permanent plant, machinery,
equipment or apparatus and the like with relatively minor amounts of works involved.
Micro/Minor LS works contracts are common for NCT procurement in sectors of rural
development, education, water supply, populations, health and nutrition, etc.
The Cost Plus and Target Cost types of contract are rarely used in Ghanaian projects,
primarily because the conditions for which they are most suited of poor initial project
definition and design and the lack of firm cost estimates do not provide a proper basis for
appraisal at that preliminary stage of the project cycle. Further design and cost estimation is
normally recommended with a view to adopting a more acceptable type of contract at a later
stage.
BOT contracting is a relatively new field for the public sector in Ghana and raises questions
regarding priorities in financing applications, acceptable prequalification and competitive
tendering procedures, tender and tariff evaluation, risk allocation and guarantees.
The conditions of contract spell out in detail the legally enforceable contractual obligations of
the parties, the law applicable to the contract, the mode and the forum for setting disputes,
alterations. In a competitive tender situation, all participants must tender on the basis of
identical terms in order to make their tender prices comparable. For this reason, conditions of
contract form part of the tender documents.
The contract documents usually comprise:
The Letter of Acceptance (and any minutes of final contract negotiations, if any
and/or clarifications),
The Tender,
The Agreement (Form of contract)
The Particular Conditions of Contract (Special conditions),
The General Conditions of contract,
The Drawings,
The Priced Bill of Quantities and the Day work schedule included therein,
The Schedule of Rates and process (if any), and
Other relevant documents or reference materials forming part of the Contract.
All the above-mentioned documents should be physically incorporated and bound into one
original contract version (or two originals, each party taking his own copy) in which the
parties have initialed each constituent page. The only exception might be that General
Conditions of Contract are incorporated by reference to a well-known and easily accessible
set of General Conditions of Contract.
The text of the Clauses in the GCC are not to be modified but are only subject to the
variations and additions set out under Conditions of Particular Application. The General
Conditions of Contract shall be provided to Pre-Qualified Tenderers as part of the Tender
Documents to be made available by the Employer.
There is usually an Annex to the Conditions of Particular Application which contain the
Contract Forms, which once completed, become part of the Contract. The forms for Letter of
Acceptance, Contract Agreement, Performance Security, Advance Payment Security and
Retention Money Guarantee, when required, shall be completed only by the successful
Tenderer after Contract award.
Anyone involved in a procurement project should sign a declaration of interest statement and
a non-disclosure agreement.
In dealing with Contract Administration Planning therefore, policies, systems and procedures
must concentrate on the following amongst others:
Assignment of individual/team responsibility for contract administration process.
Establishment of internal procedures (hierarchy, communication, level of authority,
flow of documents, verification and acceptance procedures, payment procedures,
internal audit etc.);
Evaluation of main risks and identification of mitigation measures.
Coordination of arrangements with third parties (other agencies, contractors, end
users, beneficiaries etc.).
Development of contract administration plan and milestones
Development of procedure for keeping track of the contract’s price adjustment
mechanism
It is also recommended to hold separate meetings with all other stakeholders – the parties
responsible with the design and engineering (if different from the Engineer); local authorities;
state agencies (works inspection, environmental, labor etc.); end users and beneficiaries etc.
The kick-off meeting between the Employer, Engineer and Contractor should normally take
place as soon as the Letter of Acceptance is issued and should also include a site visit, if
practicable.
Critical issues to be established during the kick-off meeting(s):
Introducing the parties, their roles and responsibilities - this applies equally to
Contractor’s representatives and key staff; Employer’s staff in charge with the
contract management; and the Engineer and the staff of the supervising consultant;
Establishing the communication procedures - (mechanisms, frequency etc.). The
parties should agree at the start of the project on the communication mechanisms
between the Contractor and the Engineer and the Employer (where applicable) as
well as on the frequency of the formal site meetings between the Contractor’s and
Engineer’s representatives (e.g. site representatives of the Engineer and the
Contractor should have at least weekly progress meetings and the minutes of these
meetings should be promptly shared with the Employer);
Review of contract documents - priority and inter-correlation of contract documents;
conditions of contract; technical specifications; payment schedules and covenants;
implementation milestones, etc.;
Review of applicable legislation and any obligations deriving in connection to the
execution of the contract in the Employer’s country (e.g. contract registration; fiscal
registration of Contractor in the Employer’s country; applicable tax regime, reporting
obligations to other Government agencies; permits and licenses etc.);
Establish a comprehensive reporting system between the parties (level, frequency,
templates for reports for each party involved);
Define escalation procedures to unblock critical situations or bottlenecks (delays in
performance or in obtaining permits and approvals; abuses of power from the
Engineer; non-performance of Contractor’s staff etc.);
Ensuring that all parties involved in the contract implementation share the same
understanding of their rights, roles and responsibilities derived from the contract
documents; of each other’s expectations; of the timeframe; of any particular
constraints in the implementation.
Setting the circumstances of the Employer giving the Contractor right of access to
and possession of the Site;
Establishing a tentative Commencement Date, by which all conditions required by
the Contract would be met (signing of Contract Agreement, submission of
performance security and advance payment guarantee, payment of advance etc.)
The guarantee contains a condition that the Employer should notify the Bank
whenever a variation is approved or whenever there is any modification to the
contract clauses and provisions – not acceptable as the guarantee should be
enforceable without the Employer having the burden of notifying any modifications
of the contract to the bank.
Terms and conditions that may render the policies invalid under certain circumstances
or events – the Employer should check any conditions attached to the insurance
policies such as prior notification requirements and any other clauses that may affect
its rights under the terms of the policy. Special attention should be paid in the case of
contract variations because most of the insurers would require to be notified whenever
changes to the scope of works occur. The same applies to extensions of time for
completion – the Employer should make sure that the policies are properly extended
to cover the new reality of the contract.
In effect, note should be taken of Coverage, Validity, Amounts, Text and Format, Jointly
insured parties (when applicable), Exclusions, Deductibles, Unacceptable Deviations and
Conditions, Notification Requirements and Insurance Premiums.
The Employer should supervise Contractor’s mobilization on site and use of the advance
payment, because usually this is a fairly good indication on Contractor’s later performance.
Any delays or deviations in site mobilization should be promptly notified to and remedied by
the Contractor.
Contractor’s mobilization should be seen as comprising at least the following key aspects:
Financial resources - if advance has been paid, than the Contractor should be able to
timely complete the appropriate mobilization arrangements; or if advance has not
been requested or paid, that means that the Contractor should have its own financing
arrangements in place that would allow an adequate mobilization;
Manpower - both in terms of Contractor’s key staff and sufficient labour to ensure
proper and timely execution of the works;
Plant, equipment, materials;
Site facilities – starting with proper fencing and securing the site; adequate site
accommodation facilities for the Contractor’s personnel and for Engineer’s staff (if
requested under the Contract); acceptable sanitary and hygienic conditions for all
personnel; proper storage facilities for the sensitive plant, equipment and materials
brought on site etc.
There may be cases where the Contractor receives the advance payment but fails to mobilize
up to the value of the advance payment or according to its own Mobilization Schedule, which
should have been part of its tender. If it is obvious that the Contractor does not have the
intention of making the adequate start up arrangements or uses the advance payment for other
purposes than the mobilization costs, then the Employer would be entitled and should not
hesitate to forfeit the advance payment guarantee, after due consultation with the Engineer,
who should be in the best position to determine Contractor’s capacity or intentions.
If everything goes according to the contract and the advance payment is properly used, the
next task of Employer’s staff, particularly financial specialists, is to ensure that repayment of
the advance is done correctly by the Engineer through the Interim Payment Certificates that
follow certification. It should be noted that Key Mobilization Considerations of Financial
resources, Manpower, Plant, equipment, materials, Site facilities and Mobilization Schedule
must be fully appreciated.
4.8 Development of Project Management Tools for Time and Cost Control
Day-to-day supervision and follow-up on the progress of works are essential attributes of the
Engineer, who should employ appropriate project management tools to ensure that critical
issues such as time, actual progress of works against planned and money, how much has been
paid versus how much has been done.
Many projects are badly managed simply because the supervisors are not familiar with basic
project management tools and techniques that would allow them to hold a firm grip on the
contract implementation. Employer’s technical staff should equally be conversant with these
tools. The following are the most widely used such instruments and have evolved in industry
standards throughout the years:
Work Breakdown Structure (WBS);
Program Evaluation and Review Technique (PERT);
Critical Path Method (CPM);
Gantt Chart;
Earned Value Management (EVM).
Engineer’s records should always be reflected in these monitoring instruments which if
correctly maintained would constitute a “mirror” of the project that can show at any given
time the actual progress achieved as compared with the planned schedule (both in terms of
physical output and money spent).
Another important aspect would be the desk control of Engineer’s documents. The Engineer
should maintain very accurate records of everything that happens on the Site.
The following documents should be the minimum required:
Measurement logs – the cornerstone of FIDIC Contract is that all quantities should be
re-measured by the Engineer and payment to the Contractor should be made only for
the quantities actually measured, that often differ from the quantities in the Contract,
Activity reports – daily, weekly, monthly; showing in tabular format quantities of
work done, number of staff and equipment involved, consumption of materials,
testing and samples etc. The reports should also mention any specific events,
incidents, weather conditions etc.
Issues Log – a record of all issues that occurred during the execution of works, with
appropriate description and indication of the date, cause, remedial measures to be
taken, responsible party, status of remediation etc.
Variation Orders – critical documents that justify changes in quantities, prices and
time for completion.
Requests to Contractor.
Correspondence with the Contractor and third parties (Government agencies, local
authorities, controlling bodies, end users, beneficiaries etc.)
Inspection and Control Logbook – a record of all inspections, audits and controls
performed by any party starting with the Employer, but also any third party
(environmental agency, financial control, local authorities etc.)
5.1 Introduction
The objective of monitoring contract performance is to ensure that the works are completed
in terms of cost, time and in accordance with the drawings and specifications under the
Contract. Where the Engineer exercises the desired supervision and control of the works, the
Employer’s investment is protected with a durable project obtained and prevents any resort to
claims by the Contractor.
An effective contract supervision and control can be achieved if all the parties involved aim
to work together. Co-operation, collaboration and coordination irrespective of any differences
of opinion and personality are essential. The supervision organization must be provided with
offices, laboratories, equipment and transport facilities to be operational. Supervision is the
responsibility of the Engineer and his/her primary duties are to direct the execution,
completion and maintenance of the Works and to test and examine materials and
workmanship.
The Contractor shall submit to the Engineer/Project Manager for approval an updated
Programme at intervals as shall be prescribed. If the Contractor does not submit an updated
Programme within this period, the Engineer/Project Manager may withhold the amount from
the next Payment Certificate and continue to withhold this amount until the next payment
after the date on which the overdue Program has been submitted and approved by the Project
Manager.
The Engineer/Project Manager’s approval of the Programme shall not alter the Contractor’s
obligations. The Contractor may revise the Programme and submit it to the Engineer/Project
Manager for approval again at any time. A revised Program shall show the effect of any
Variation and Compensation Events.
The Engineer/Project Manager shall extend the Intended Completion Date if a Compensation
Event occurs or a Variation is issued which makes it impossible for completion to be
achieved by the Intended Completion Date without the Contractor taking steps to accelerate
the remaining work in a manner that would cause the Contractor to incur additional cost.
The
6 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
Engineer/Project Manager shall also extend the Intended Completion Date if it determines an
event of Force Majeure has occurred.
The Engineer/Project Manager shall decide whether and by how much to extend the Intended
Completion Date within 21 days of (a) the Contractor asking him/her for a decision upon the
effect of a Compensation Event or Variation or (b) the Contractor or the Employer asking the
Engineer/Project Manager for a decision on the occurrence of an event of Force Majeure. In
each case, such request is to be in writing and shall be supplemented by full supporting
information. If the Contractor has failed to give early warning of a delay or has failed to
cooperate in dealing with a delay, the delay by this failure shall not be considered in
assessing the new Intended Completion Date.
When the Employer wants the Contractor to finish before the Intended Completion Date, the
Engineer/Project Manager shall obtain priced proposals for achieving the necessary
acceleration from the Contractor. If the Employer accepts these proposals, the Intended
Completion Date shall be adjusted accordingly and confirmed by both the Employer and the
Contractor. If the Contractor’s priced proposals for an acceleration are accepted by the
Employer, they are incorporated in the Contract Price and treated as a Variation.
The Engineer/Project Manager may instruct the Contractor to delay the start or progress of
any activity within the Works. Either the Engineer/Project Manager or the Contractor may
require the other to attend a management meeting. The business of a management meeting
shall be to review the plans for remaining work and to deal with matters raised in accordance
with the early warning procedure.
The Engineer/Project Manager shall record the business of management meetings and
provide copies of the record to those attending the meeting and to the Employer. The
responsibility of the parties for actions to be taken shall be decided by the Project Manager
either at the management meeting or after the management meeting and stated in writing to
all who attended the meeting.
The Contractor shall warn the Engineer/Project Manager at the earliest opportunity of
specific likely future events or circumstances that may adversely affect the quality of the
work, increase the Contract Price, or delay the execution of the Works. The Project Manager
may require the Contractor to provide an estimate of the expected effect of the future event or
circumstance on the Contract Price and Completion Date. The estimate shall be provided by
the Contractor as soon as reasonably possible.
The Contractor shall cooperate with the Engineer/Project Manager in making and considering
proposals for how the effect of such an event or circumstance can be avoided or reduced by
anyone involved in the work and in carrying out any resulting instruction of the
Engineer/Project Manager.
The Contractor shall request the Engineer/Project Manager to issue a Certificate of
Completion of the Works, and the Engineer/Project Manager shall do so upon deciding that
the work is completed. Engineer/Project Manager shall take over the Site and the Works
within seven days of the Engineer/Project Manager’s issuing a Certificate of Completion.
Variations are directed by the Engineer/Project Manager and the Employer. The
Engineer/Project Manager shall make any variation of the form, quality or quantity of the
Works. There may be variations arising out of measurement and those arising out
instructions. The Engineer/Project Manager shall have the authority to instruct the Contractor
in writing to carry out, and the Contractor shall do so for any of the following:
a) Increase or decrease the quantity of any work included in the Contract,
b) Omit any such work,
c) Change the character or quality or kind of any such work,
d) Change the levels, lines, position and dimensions of any part of the works.
e) Execute additional work of any kind necessary for the completion of the Works, and
f) Change any specified sequence or timing of construction of any part of the Works.
Therefore, the SO should instruct the Quantity Surveyor to ensure that he should monitor all
works executed by the Contractor and treat any variation instructed by the Engineer with all
seriousness.
The Engineer/Project Manager shall not adjust rates from changes in quantities if thereby the
Initial Contract Price is exceeded by more than 15 percent, except with the prior approval of
the Employer. If requested by the Engineer/Project Manager, the Contractor shall provide the
Project Manager with a detailed cost breakdown of any rate in the Bills of Quantities.
All Variations shall be included in updated Programmes produced by the Contractor. The
Contractor shall provide the Engineer/Project Manager with a quotation for carrying out the
Variation when requested to do so by the Engineer/Project Manager. The Engineer/Project
Manager shall assess the quotation, which shall be given within seven days of the request or
within any longer period stated by the Engineer/Project Manager and before the Variation is
ordered.
If the work in the Variation corresponds with an item description in the Bills of Quantities
and if, in the opinion of the Engineer/Project Manager, the quantity of work above the limit
stated or the timing of its execution do not cause the cost per unit of quantity to change, the
rate in the Bills of Quantities shall be used to calculate the value of the Variation. If the cost
per unit of quantity changes, or if the nature or timing of the work in the Variation does not
correspond with items in the Bills of Quantities, the quotation by the Contractor shall be in
the form of new rates for the relevant items of work.
If the Contractor’s quotation is unreasonable, the Engineer/Project Manager may order the
Variation and make a change to the Contract Price, which shall be based on the
Engineer/Project Manager’s own forecast of the effects of the Variation on the Contractor’s
costs.
Performance measurement must often be coupled with evaluation data to increase the
understanding of why results occur and what value a program adds. Performance
measurement cannot replace data on programme costs, political judgments about priorities,
creativity about solutions or common sense. A major purpose of performance measurement is
to raise fundamental questions; the measures seldom, by themselves, provide definitive
answers. Performance measurement keeps a focus on results.
Key Definitions and Concepts involve:
Strategic goals
Performance goals
Performance measures
Targets and timeframes
Characteristics of such goals/measures include:
Quality over quantity
Importance to budget decisions
Public clarity
Feasibility
Collaboration
In the management of insurance, the Employer should note the following tips for verifying
insurance policies out of some real life experiences concerning problems:
In some countries there is a practice among certain contractors and insurance
companies to have the insurance policy cancelled immediately after its signing. The
policy is obviously no longer valid and the Contractor gets back most of the money
paid as premium (the insurance company holds a percentage for agreeing to this
scheme). This way the Contractor still has a policy to show to the Employer, but there
is no real coverage, because the policy has been cancelled. The Employer should
check the existence of proofs of payment of insurance premiums and officially
request confirmation from time to time from the insurance company, at least twice a
year that the respective policies are still valid.
A variation of this scheme involves the insurer and the Contractor agreeing to an
amendment to the original policy, waiving most risks. The Employer is thus unaware
that the policy is worthless.
A similar mechanism applies to the payment of insurance premiums. The policy is
issued and requires payment in monthly or quarterly installments. The Contractor
Variations are therefore not only normal in a works contract, but also necessary to correct
shortcomings in the design, to improve the proposed technologies, to allow for the use of
newer or better materials etc. As long as they are carefully analyzed and duly justified from a
technical and economical perspective, variations should not be regarded as attempts of the
Contractor to get money in dubious ways.
The Engineer is again the most important player in this equation because it is the Engineer’s
duty to make sure that the variations requested by the Contractor are (i) necessary; and (ii)
make technical and economic sense. The next step would be to evaluate the financial impact
of the respective variations and duly inform the Employer about it. Depending on the limits
of Engineer’s authority established in the Particular Conditions, the Employer should approve
the variations that exceed the respective threshold.
Almost all construction projects vary from the original design, scope and definition. Whether
small or large, construction projects will have inevitably depart from the original tender
design, specifications and drawings prepared by the design team. This can be because of
technological advancement, statutory changes or enforcement, change in conditions,
geological anomalies, non-availability of specified materials, or simply because of the
continued development of the design after the contract has been awarded. In large
engineering projects variations can be very significant, whereas on small building contracts
they may be relatively minor.
Standard forms of contract generally make express provisions for the contract administrator,
generally the architect or engineer, to instruct variations. Such provisions enable the
continued, smooth administration of the works without the need for another contract.
Variation instructions must be clear as to what is and is not included, and may propose the
method of valuation.
All the above represent a minimum checklist for Employer’s technical and procurement staff.
7.1 Introduction
Payment of the Interim Payment Certificates issued by the Engineer based on Contractor’s
monthly statements is one of Employer’s key responsibilities and also the moment with the
maximum involvement of its technical, procurement and financial staff. This chapter analyses
the payment and cost control systems under contracts. Two modes of payment are discussed
in this Session. The first is the traditional method of reviewing invoices for payment and the
second is the new electronic system of payment in the public service called GIFMIS.
The Engineer/Project Manager shall check the Contractor’s monthly statement and certify the
amount to be paid to the Contractor which certified amount shall be set forth in a Payment
Certificate issued by the Engineer/Project Manager.
Payments shall be adjusted for deductions for advance payments and retention, if any. The
Employer shall pay, or cause to be paid to, the Contractor the amounts certified by the
Engineer/Project Manager within 28 days of the date of each Payment Certificate. If the
Employer makes a late payment, the Contractor shall be paid interest on the late payment in
the next payment. Interest shall be calculated from the date by which the payment should
have been made up to the date when the late payment is made at the rate of interest for each
of the relevant currencies of payment.
Unless otherwise stated, all payments and deductions shall be paid or charged in the
proportions of currencies comprising the Contract Price.
Items of the Works for which no rate or price has been entered in shall not be paid for by the
Employer and shall be deemed covered by other rates and prices in the Contract.
The Employer does not give access to a part of the Site by the Site Possession Date.
The Employer modifies the Schedule of Other Contractors in a way that affects
the work of the Contractor under this Contract.
The Engineer/Project Manager orders a delay or does not issue Drawings,
Specifications, or instructions required for execution of the Works on
time.
The Engineer/Project Manager instructs the Contractor to uncover or to carry
out additional tests upon work, which is then found to have no Defects.
The Engineer/Project Manager unreasonably does not approve a sub-contract to be let.
Ground conditions are substantially more adverse than could reasonably have been
assumed before issuance of the Letter of Acceptance from the information issued to
tenderers including the Site Investigation Reports, from information available publicly
and from a visual inspection of the Site.
The Engineer/Project Manager gives an instruction for dealing with an
unforeseen condition, caused by the Employer, or additional work required for
safety or other reasons.
Other contractors other than Subcontractors, public authorities, utilities, or the
Employer does not work within the dates and other constraints stated in this
Contract, and they cause delay or extra cost to the Contractor.
The advance payment, if any, is delayed.
8 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
The effects on the Contractor of any of the Employer’s Risks.
The Project Manager unreasonably delays issuing a Certificate of Completion.
If a Compensation Event would cause additional cost or would prevent the work being
completed before the Intended Completion Date, the Contract Price shall be increased and/or
the Intended Completion Date shall be extended. The Engineer/Project Manager shall decide
whether and by how much the Contract Price shall be increased and whether and by how
much the Intended Completion Date shall be extended.
As soon as information demonstrating the effect of each Compensation Event upon the
Contractor’s forecast cost has been provided by the Contractor, it shall be assessed by the
Engineer/Project Manager, and the Contract Price shall be adjusted accordingly. If the
Contractor’s forecast is deemed unreasonable, the Engineer/Project Manager shall adjust the
Contract Price based on the Project Manager’s own forecast. The Engineer/Project Manager
shall assume that the Contractor shall react competently and promptly to the event.
The Contractor shall not be entitled to compensation to the extent that the Employer’s
interests are adversely affected by the Contractor’s not having given early warning or not
having cooperated with the Engineer/Project Manager.
The Contractor, any Subcontractor and their respective personnel, and their eligible
dependents, shall follow the usual customs procedures of the Employer’s country
in importing property into the Employer’s country.
If the Contractor, any Subcontractor or any of their respective personnel, or any of their
eligible dependents, do not withdraw but dispose of any property in the Employer’s country
upon which customs duties or other Taxes have been exempted, the Contractor, the
Subcontractor or such personnel or eligible dependents, as the case may be, (a) shall bear
such customs duties and other Taxes in conformity with Applicable Law, or (b) shall
reimburse such customs duties and Taxes to the Employer if such customs duties and Taxes
were paid by the Employer at the time the property in question was brought into the
Employer’s country.
Without prejudice to the rights of the Contractor under the contract, the Contractor, any
Subcontractor and their respective Personnel will take reasonable steps as requested by the
Employer or the Government with respect to the determination of the Tax status described in
the contract.
If the Contractor, any Subcontractor, or any of their respective personnel, is required to pay
Taxes that are exempt under the contract or a related agreement, the Contractor shall
promptly notify the Employer (or such agent or representative designated by the Employer)
of any such Taxes paid, and the Contractor shall cooperate with, and take such actions as may
be requested by the Employer or their agents or representatives, in seeking the prompt and
proper reimbursement of such Taxes.
The Employer shall use reasonable efforts to ensure that the Government provides the
Contractor, any Subcontractor, and their respective personnel, the exemptions from taxation
applicable to such persons or entities, in accordance with the terms of the contract or related
agreement.
8 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
Where payments are made in currencies other than the currency of the Employer’s country,
the exchange rates used for calculating the amounts to be paid shall be the exchange rates
stated in the Contractor’s Tender.
Prices shall be adjusted for fluctuations in the cost of inputs only if provided for in the
COPA/SCC/Contract Data. If so provided, the amounts certified in each Payment Certificate,
before deducting for the advance payment, if any, shall be adjusted by applying the respective
price adjustment factor to the payment amounts due in each currency. A separate formula of
the type indicated below applies to each Contract currency:
Adjustment shall be made for the first time during the term of this Contract at the time
specified in the COPA/SCC/Contract Data.
If the value of the index is changed after it has been used in a calculation, the calculation
shall be corrected and an adjustment made in the next Payment Certificate. The index value
shall be deemed to take account of all changes in cost due to fluctuations in costs.
The Employer shall retain from each payment due to the Contractor the proportion stated in
the COPA/SCC/Contract Data until completion of the whole of the Works.
On completion of the whole of the Works, half the total amount retained shall be repaid to the
Contractor and half when the Defects notification period has passed and the Project Manager
has certified that all Defects notified by the Engineer/Project Manager to the Contractor
before the end of the Defects notification period have been corrected.
On completion of the whole Works, the Contractor may substitute retention money with an
“on demand” bank guarantee in a form and issued by a bank acceptable to the Employer.
The Contractor shall pay liquidated damages to the Employer at the rate per day stated in the
COPA/SCC/Contract Data for each day that the Completion Date is later than the Intended
Completion Date. The total amount of liquidated damages shall not exceed the amount
defined in the COPA/SCC/Contract Data. The Employer may deduct liquidated damages
from payments due to the Contractor. Payment of liquidated damages shall not affect the
Contractor’s liabilities.
If the Intended Completion Date is extended after liquidated damages have been paid, the
Engineer/Project Manager shall correct any overpayment of liquidated damages by the
Contractor by adjusting the next Payment Certificate. The Contractor shall be paid interest on
the overpayment, calculated from the date of payment to the date of repayment, at the rates
specified.
The Employer shall make an advance payment to the Contractor of the amounts stated in the
COPA/SCC/Contract Data by the date stated in the COPA/SCC/Contract Data, against
provision by the Contractor of an unconditional bank guarantee in a form and by a bank
acceptable to the Employer in amounts and currencies equal to the advance payment. Such
unconditional bank guarantee shall remain effective until the advance payment has been
repaid, but the amount of such guarantee shall be progressively reduced by the amounts
repaid by the Contractor. Interest shall not be charged on the advance payment.
The Performance Security shall be provided to the Employer no later than the date specified
in the Letter of Acceptance and shall be issued in the amount specified in the
COPA/SCC/Contract Data, in a form and by a bank acceptable to the Employer, and
denominated in the types and proportions of the currencies in which the Contract Price is
payable. The Performance Security shall be valid until a date 28 days from the date of issue
of the Certificate of Completion.
If applicable, the Day work rates in the Contractor’s Tender shall be used for small additional
amounts of work only when the Engineer/Project Manager has given written instructions in
advance for additional work to be paid for in that way.
All work to be paid for as Day work shall be recorded by the Contractor on forms approved
by the Engineer/Project Manager. Each completed form shall be verified and signed by the
Engineer/Project Manager within two days of the work being done.
The Contractor shall be paid for Day work subject to obtaining signed Day work forms.
Loss or damage to the Works or Materials to be incorporated in the Works between the Start
Date and the end of the Defects notification periods shall be remedied by the Contractor at
the Contractor’s cost if the loss or damage arises from the Contractor’s acts or omissions.
The Contractor shall supply the Engineer/Project Manager with a detailed account of the total
amount that the Contractor considers payable under this Contract before the end of the
Defects notification period. The Engineer/Project Manager shall issue a Defects Liability
Certificate and certify any final payment that is due to the Contractor within 56 days of
receiving the Contractor’s account if it is correct and complete. If it is not, the
Engineer/Project Manager shall issue within 56 days a schedule that states the scope of the
corrections or additions that are necessary. If the final account is still unsatisfactory after it
has been resubmitted, the Engineer/Project Manager shall decide on the amount payable to
the Contractor and issue a Payment Certificate.
7.4.1 Introduction
It is Government decision to deploy GIFMIS for the management of all public funds
(Consolidated Funds (CF), Internally-Generated Funds (IGF), Statutory Funds (SF) and
Donor Funds (DF)) across MDAs and MMDAs in the country, as part of the broader PFM
reforms programme. The use of GIFMIS for processing financial transactions at MDAs and
MMDAs started in 2012. It is a legal requirement to use GIFMIS for processing public
financial transactions under section 25(6) of the new PFM Act, 2016 (Act 921). The objective
is to improve efficiency, comprehensiveness and transparency in Public Financial
Management through the GIFMIS platform (Objective II of the PFM Strategy, 2015- 2018).
GIFMIS is jointly funded by four development partners- the (i). World Bank (ii). DFID of
UK (iii). European Commission-EU (iv). Danish International Development Agency-
DANIDA.
‘’The Ministry of Finance has observed with concern the indiscriminate award of contract
by Ministries, Departments and Agencies without due regard to their budgetary allocation.
With effect from 1st January, 2014, the Ministry is determined to safeguard the integrity of
the budget by ensuring that all contract awards are informed by the budgetary allocation
and cash ceiling.
Thus, beginning from January, 2014, the general public is being informed that this
Ministry will recognize contracts as valid if only they are duly authorized by PURCHASE
ORDER(PO)generated from the GIFMIS SYSTEM. (Please refer to paragraph 937 of
2014 Budget Statement and Economic Policy.)
By this announcement the general public especially contractors and suppliers should take
note and ensure their contracts follow the due process to be assured of prompt payment’’.
From the above announcement, it can be concluded that procurement planning, budget
approval, purchase order/contract award and contract administration (in terms of payments
and reporting) must all be linked to the GIFMIS platform.
It means that if the particulars of a Contractor, Supplier, Consultant or any other identified
procurement service provider are not linked to the GIFMIS Platform from the time of
contract award and subsequent approval on GIFMIS, the service provider will not be
recognized for payment during contract administration.
What Is GIFMIS?
The Ghana Integrated Financial Management Information System (GIFMIS) is an integrated
computerized financial management system used in:
Budget preparation
Budget Execution
Accounting and Financial Reporting
Cash Management.
Assets management
Human resource and payroll management
Among others
Aims of GIFMIS
To establish an INTEGRATED ICT-based PFM Information Systems in Ghana at the
MDAs located at National, Regional and District levels and MMDAs to improve efficiency
in public financial management including Consolidated Fund, IGF, Statutory Funds and
Donor Funds.
Why GIFMIS?
Lack of timely, accurate and current information on budgetary allocations,
commitments and actual revenue and expenditures
Publish Annual Financial Reporting and reduce delays in the payment processing
Poor feedback mechanism for assessing Budgetary Performance
Lack of uniform chart of accounts (COA) which make the comparison of the
performance of various budgets difficult.
Strengthen Internal Controls and Auditing Capabilities.
Modernize the Technical Infrastructure
Interface Data from Existing Data Stores
Budget Preparation
The budget preparation steps include:
1. Budget circular and instructions issued by MoF to all MDAs/MMDAs (FAR 152
& 153)
2. MDAs/MMDAs prepare and submit their budget proposals/estimates to MoF
(FAR 156)
3. MoF holds budget hearing with MDAs/MMDAs (FAR 161)
4. MoF consolidates MDAs/MMDAs budgets into a National Budget Estimates and
submits/presents it to Parliament for approval
5. Parliament debates the Budget and approves it for execution
Demand
Source
1. User Department Submit a Memo through their head to the Chief Director
(CD) for approval (Manual)
2. Upon approval of the Memo, Warrant is prepared and approved on the GIFMIS. For
Goods and Services warrants will now be done in bulk. No more specific warrants per
Memo. The release for May was done on GIFMIS successfully.
3. Once the Warrant is approved a Requisition is then booked on GIFMIS
by the User Department.
4. Route the Requisition through an approval hierarchy for approval by
the Spending Officer based on the limit for approval
5. Select Supplier (manual) – Tendering Process.
6. Once a Contractor is selected, the Procurement Department prepare PO
7. The PO is routed for Approval on GIFMIS once its approved budget
is encumbered.
8. Print PO on GIFMIS
1. Standard Purchase Orders: You generally create standard purchase orders for one-time purchase
of various items. You create standard purchase orders when you know the details of the goods
or services you require, estimated costs, quantities, delivery schedules, and accounting
distributions. If you use encumbrance accounting, the purchase order may be encumbered
since the required information is known.
2. Contract Purchase Orders: You create contract purchase agreements with your
suppliers to agree on specific terms and conditions without indicating the goods and
services that you will be purchasing. You can later issue standard purchase orders
referencing your contracts, and you can encumber these purchase orders if you use
encumbrance accounting.
b) You can issue scheduled releases against a planned purchase order to place the actual orders.
If you use encumbranceaccounting, you can use the planned purchase order to reserve
funds for long term agreements.
You can also change the accounting distributions on each release and the system will reverse
the encumbrance for the planned purchase order and create a new encumbrance for the
release.
Setting up of Contractors
Implementation Strategy
Categorization of Fixed Assets in 3 Categories
Main (Transport Equipment)
Major (Motor Vehicles)
Minor (Salon Cars)
Mapping of Fixed Assets Categories to Natural Accounts which are used to prepare
Appropriation Budget.
2. System Rollout
The Financial Accounting Modules (Oracle EBS) have been rolled-out as follows:
All MDAs subsisting on consolidated fund resources since 2012
250 national Spending Units (SUs) covered
350 Regional SUs covered
7 MMDAs out 216
49 IGF Institutions out of 59 are live as at end of April, 2016
Fixed Assets module at 5 headquarters MDAs
The Budget Modules was rolled-out to all MDAs since 2014
HRMIS Modules rolled-out to 3 MDAs (PSC, GSS, GFS) as at Feb. 2016.
Payroll module has been operational since the 1990s
3. System Maintenance
Business Continuity strategy was developed
Next Steps
1. Bringing on board other public funds
IGFs
Donor funds
Statutory funds
2. Extend financial modules to the remaining 209 MMDAs
3. Extend PBB and budget module to all MMDAs
4. Extend HRMIS module to all MDAs.
5. Complete interface with all key PFM Systems under the new PFM Strategy
6. Complete implementation of fixed assets module.
Some Challenges
Inadequate ICT infrastructure in the public sector of Ghana, especially Network
connectivity. NITA must be supported for this.
Relatively low computer literacy in the public sector
Change management- expectation by end-users that the system should support old ways
instead of current best practices.
People having the Mentality that the system has failed before and will still fail when
enough progress has been made.
8.1 Introduction
Disputes arise out of works contracts due to the complexity of operations on site with wide and
divergent views leading to claims that might lead to disputes. This chapter analyzes resolution of
claims, settlement of deputes and draws up their relationship.
(ii) The conditions of contract provide very little guidance on the exact situations and
mechanisms to enforce a claim on the security.
The FIDIC Conditions of Contract only state that “The Employer shall not make a claim under
the Performance Security, except for amounts to which the Employer is entitled under the
Contract”, which leaves the Employer to discern and make a judgment.
Since no other specific details are provided, we should look at other contract clauses to find clues
and information on the situations when the Employer is entitled to make a claim under
the performance security. These situations are:
Failure of the Contractor to pay an amount due to, claimed by, or determined in
the favour of the Employer, following Employer’s claims, arbitration etc.,
Failure of the Contractor to adequately extend the validity or increase the amount
of the security as may be requested under the Contract as in the case of
amendments,
It is important therefore to have a payment schedule that would allow this deduction of
penalties. Claim on the performance security or delay damages – which one to use?
Which one of these two contractual tools should the contract administration team use in the case
of delays in the contract implementation delays in the completion of the works?
Most contracts have an explicit or implied provision stating that you cannot impose two different
penalties for the same breach of Contractor’s obligations. Consequently, only one of these
penalties should apply. But which one?
Normally the employer prefers quite correctly to use the delay damages because they are the
obvious and most straightforward choice particularly when it comes to justifying and calculating
the actual damage/loss.
However, situations may occur when we should also apply for remedies under the performance
security. One of these situations is described supra, when most of the contract price has already
been paid and the outstanding payments are less than the amount of the delay damages, the delay
damages have reached the 10% limit, but we only have 5% left to pay to the Contractor. In this
situation, we are entitled to claim the difference of 5% from the proceeds of the performance
security without breaching in any way the contract provisions.
Another situation is when the delay is linked or has been caused by some other breach of
contract on the part of the Contractor, as listed above. In such cases, the employer is entitled to
apply both types of remedies, delay damages and claim under the performance security, if it can
adequately prove and justify the respective damages.
Even if the Government agrees to an extension of the contract, it may still recommend the
Procurement Entity to impose delay damages or forfeiture of the performance security, if the said
extension was not 100% caused by the Employer of Force Majeure. Consequently, agreeing to an
extension of time for various reasons on the extension does not prejudice Employer’s rights to
impose remedies.
The key issue is to understand and establish the nature of Claims because it determines:
Where to look for grounds
Whether the Project Manager has powers to deal with it
Basis of evaluation
There are three (3) Categories of Claims:
Contractual, where there is a provision in the Contract within the Project Manager’s
powers.
Extra-Contractual, where the Contract does not make express provision – resort to
Common Law - Project Manager has no powers except authority is given by the
Employer to examine and make recommendations.
Ex-gratia, basically an award since such claims have no grounds and either party cannot
successfully sue; an “act of grace” and acknowledgement of moral obligation.
Disputes on the other hand arise when negotiation fails, over variations in scope of works,
unforeseen physical conditions and delay and disruption of the works. There is a Breach of
Contract when one party fails to fulfill his part or one party states that he will not perform the
Contract or alternately puts himself in such a position that he will be unable to perform.
Breach by Employer when he/she fails to pay appropriate consideration, delays payment beyond
the stipulated period and fails and/or delays in executing work he is bound.
Breach by Contractor when he/she fails to perform and delays beyond agreed period
Disputes Caused by Employer include:
Failure to give early possession of Site,
Delays in payment,
Failure to execute work to supplement completion
Disagreement over payment and compensation for direct loss and/or expense -
To prevent conflict under this heading, construction information, instructions and variations should
be adequate and made available in good time. Extension of time, when necessary, should be
granted equitably to enable Contractors to completion the works.
The above conflicts may be avoided if the design and detailing facilitate buildability, reflect the
skill of readily available operatives, and ensure good selection of materials and components,
standard of quality required clearly shown in contract documentation, work inspected constantly
for quality and communication on quality issues improved on site.
Generally, a contractor, who operates a systematic planning and cost control, is able to compare
at any point in time, what is happening in relation to what was budgeted to happen and can
reconcile cost and value. Moreover, a contractor’s own internal valuation enables him/her to
determine interim valuation levels – an important data for planning cash flow requirements.
While it is recognized that maintenance of good cash flow is the life-blood of a contractors’
business, a contractor may experience the following process of payment which disrupts his/her
efforts to maintain good cash flow:-
a) Interim certificates which do not reflect the true value of work properly executed,
b) Interim certificates issue at irregular periods,
c) Failure of Employer to honour interim certificates on time, and
d) Late settlements of final account and contractual claims for loss and/or expense.
Factors contributing to the foregoing domain of conflict are many and may include the following:
a) Interim valuation prepared by over-cautious Quantity Surveyor or Engineer who is in fear
of over payment a contractor,
b) Extent of works under-measured by the Quantity Surveyor or Engineer in the contract
bills of quantities,
c) Quantity Surveyor or Engineer failing to prepare an interim valuation statement in good
time to enable the architect to issue an interim certificate,
d) Architect’s failure to process the interim certificate in good time,
e) Failure of Quantity Surveyor and the contractor to value and agree on variation s
executed for inclusion in the current interim valuation,
f) Quantity Surveyor failure to prepare and settle final account in good time,
g) Delays by the contractor in submitting contractual claims for loss and /or expense,
h) Delays by the contractor in submitting details of claim for fluctuations of wages and
materials,
i) Poor performances by contractor employing an unplanned or unspecified method,
untrained or incompetent operatives or planning with inaccurate data, and
j) Under-priced items in bills of quantities by the contractor – estimating error.
The foregoing shows that care and attention are required if conflicts under this heading are to be
avoided. Employer’s professional advisers should ensure that accuracy of the bills of quantities,
reasonably accurate interim valuation s and prompt payment of interim certificates, prompt
settlement of final accounts and contractual claims. Also, adequate time should be given to
contractors for tender action to effect preparation of reasonable accurate estimates and/or tenders.
To prevent such disputes from arising, contract documentation should be carefully, adequately
and accurately prepared and be consistent throughout. This is important as post-contract project
information should not impose any additional obligations beyond those contained within the
contract conditions, rather, it should clarify or supplement existing project information.
Conflicts, however, arise from the issue of this information caused by the following:
a) Architect’s/Engineer’s instruction lacking preciseness in wording,
b) Architect’s/Engineer’s instructions do not indicate its purpose (i.e., whether new work is
being ordered, alteration is required to work already executed or clearance of
discrepancy),
c) Architect’s/Engineer’s instruction effected merely by issue of revised drawings without
any explaining of the nature and extent of variations on the drawings, and
d) Architect’s /Engineer’s instruction sand/or information issued late (e.g., after an item of
work for which the variation is intended has been executed).
The above practices do not promote smooth running of projects. Rather, they create difficult
working conditions, complicate purchasing and administration and upset financial arrangements.
Timely, clear add adequately worded instruction or information have a positive effect on site
operations and productively.
8.4.6 Supervision
Close supervision on site is essential to achieve the specified standard relating to quality of work.
Those in charge of day-to-day supervision on site are the contractor’s site supervision team (i.e.,
site agent and trade foremen). The clerk of works, who acts for the Employer, is responsible for
inspecting the quality of materials and workmanship and ensuring that a good working practice is
adopted.
On construction projects, conflicts arise where contractors fail to supervise the works properly.
A bad working practice, if not corrected, may create the following complications:
Conflicts may be reduced, if quality levels are clearly specified, contractors are made aware of
them and works are supervised properly and regularly inspected for quality.
Arbitration
Arbitration is a proceeding in which a dispute is resolved by an impartial arbitrator or panel
whose decision the parties to the dispute have agreed, or legislation has decreed, will be final and
binding with limited rights of review and appeal of arbitration awards.
Mediation
Mediation refers to any instance in which a third party helps others reach agreement. More
specifically, mediation has a structure, timetable and dynamics that ordinary negotiation lacks.
The process is private and confidential, enforced by law in Ghana with participation typically
voluntary. The mediator acts as a neutral third party and facilitates rather than directs the process.
Mini trial
The mini trial is an alternative dispute resolution (ADR) procedure that is used by businesses to
resolve legal issues without incurring the expense and delay associated with court litigation. The
mini-trial does not result in a formal adjudication but is a vehicle for the parties to arrive at a
solution through a structured settlement process. It is used most effectively when complex issues
are at stake and the parties need or wish to maintain an amicable relationship.
Negotiation
Negotiation is a method by which people settle differences and a process by which compromise
or agreement is reached while avoiding argument and dispute. In any disagreement, individuals
or organisations understandably aim to achieve the best possible outcome for their position with
principles of fairness, seeking mutual benefit and maintaining a relationship as keys to a
successful outcome.
Litigation
A lawsuit may involve dispute resolution of private law issues between individuals, business
entities or non-profit organizations. A lawsuit may also enable the state to be treated as if it were
Conciliation
Conciliation is an ADR process whereby the parties to a dispute use a conciliator, who meets
with the parties both separately and together in an attempt to resolve their differences. They do
this by lowering tensions, improving communications, interpreting issues, encouraging parties to
explore potential solutions and assisting parties in finding a mutually acceptable outcome.
Expert resolution
Expert resolution is a flexible alternative procedure for the resolution of disputes based upon the
decision of an independent third party, the expert. The participants agree beforehand to be bound
by the decisions of an independent expert. It is often the quickest and most effective way of
resolving disputes which are relatively simple in content or are essentially technical in nature.
Med/Arb
This is a combination of mediation and arbitration. A form of arbitration in which the arbitrators
starts as a mediator but in the event of a failure of mediation, the arbitrator imposes a binding
decision.
Ombudsman
An ombudsman, or public advocate is an official who is charged with representing the interests
of the public by investigating and addressing complaints of maladministration or a violation of
rights. The ombudsman is usually appointed by the government or by parliament but with a
significant degree of independence.
Diwan Al-Madhalim
Diwan al-Madhalim as the Ombudsman's Office set up in keeping with the cultural values of
solidarity of some Moslem societies with the administrative courts and institutions which receive
and resolve complaints from individuals and groups about violations of any kind in principle and
assists many poor families and a number of vulnerable groups.
Executive tribunal
Executive Tribunals operate formal processes to adjudicate disputes in a similar way to courts of
law, but have different rules and procedures; and only operate in a specialized area. In theory,
their procedures may be better suited for particular types of disputes, cheaper to administer and
require less-qualified officials.
Shadow Mediation
In this type of ADR, the parties have a negotiation or arbitration or even litigation and a mediator
is present but does not participate. At some juncture, the mediator then works with the parties to
attempt to move toward settlement. It operates similar to Arb-Med in that the parties get to move
well into the case and then have a neutral, who has also seen and heard everything step in.
In mediation that occurs as a part of the litigation process the attorneys for the parties and the
parties themselves must appear. At times, however, resolution may be hard to reach if there is
someone else upon whom an individual relies for support or decision making. These individuals
are referred to as “shadow parties.”
Rent-a-judge/Private judge
Rent-a-judge blossomed early in Los Angeles where a sitting judge, for example, would assign
lengthy debates over accounting to a retired judge and then incorporate his report into the final
decision. The broader application spread rapidly when the law enabled a retired judge to handle
an entire case. They got the approval of the court's presiding judge and created the modern rent-
a- judge system. The descriptive term "rent-a-judge," which caught on with lawyers and litigants,
was originally disdained by the retired judges. But the tag has now won even the judges'
grudging acceptance.
Limitation of the Public Procurement Law, Act 663 as amended in the Procurement Cycle of
Ghana
A legal framework to govern the commencement and conduct of ADR proceedings in Ghana and
enforcement of both domestic and foreign awards and decisions has been born.
9.1 Introduction
This chapter seeks to draw readers’ attention to those matters that could lead to termination of
contract by the parties to a contract. When either party to the Contract gives notice of a breach of
Contract to the Project Manager for a cause other than those listed under the contract, the Project
Manager shall decide whether the breach is fundamental or not, which upon his/her
determination could lead to termination on either way.
b) The Contracting Officer’s failure to act within the time specified in the contract, or
within a reasonable time if not specified, then an adjustment shall be made for any
increase in the cost of performance of the contract, excluding profit necessarily caused by
the unreasonable suspension, delay, or interruption and the contract modified in writing
accordingly. However, no adjustment shall be made under this clause for any suspension,
delay, or interruption to the extent that performance would have been so suspended,
delayed, or interrupted by any other cause, including the fault or negligence of the
Contractor or for which an equitable adjustment is provided for or excluded under any
other term or condition of the contract.
a) The Contractor stops work for 28 days when no stoppage of work is shown on the
current Programme and the stoppage has not been authorized by the Project Manager,
b) The Project Manager instructs the Contractor to delay the progress of the Works, and
the instruction is not withdrawn within 28 days,
c) The Employer or the Contractor is made bankrupt or goes into liquidation other than
for a reconstruction or amalgamation,
d) A payment certified by the Project Manager is not paid by the Employer to the
Contractor within 84 days of the date of the Project Manager’s certificate,
e) The Project Manager gives Notice that failure to correct a particular Defect is a
fundamental breach of Contract and the Contractor fails to correct it within a
reasonable period of time determined by the Project Manager,
9 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
f) The Contractor does not maintain a Security, which is required, and
g) The Contractor has delayed the completion of the Works by the number of days for
which the maximum amount of liquidated damages can be paid, as defined in the
Special Conditions of Contract,
h) If the Contractor, in the judgment of the Employer has engaged in corrupt or
fraudulent practices in competing for or in executing the Contract, for which it is
understood as:
When either party to the Contract gives notice of a breach of Contract to the Project Manager
for a cause other than those listed as above, the Project Manager shall decide whether the breach
is fundamental or not.
If the Contract is terminated for the Employer’s convenience or because of a fundamental breach
of Contract by the Employer, the Project Manager shall issue a certificate for the value of the
work done, Materials ordered, the reasonable cost of removal of Equipment, repatriation of the
Contractor’s personnel employed solely on the Works and the Contractor’s costs of protecting
and securing the Works and less advance payments received up to the date of the certificate.
All Materials on the Site, Plant, Equipment, Temporary Works, and Works shall be deemed to be
9 Public Procurement Authority (PPA),
Contract Administration Manual For Works –
the property of the Employer if the Contract is terminated because of the Contractor’s default.
a) Containment of damage or injury to, or loss of, personnel and property, and
b) Continuity of the key operations of the organization.
10.1 Introduction
The Public Procurement Act, 2003(Act 663) as amended in Section 28, statutorily requires all
procurement entities to keep records of procurement proceedings in a structured and systematic
manner and in accordance with national and international standards. The annual procurement
assessment conducted in the Procurement entities by the Public Procurement Authority (PPA)
reveal challenges relating to the management of procurement and contract management
documentation by most entities thus contravening the Public Procurement Act, 2003(Act 663) as
amended. The observation has been that procurement and contract records management in most
procurement entities usually involve disjointed processes which result in loss of vital
procurement and contract information, thus undermining accountability, transparency and good
corporate governance. Good records management is therefore essential for any corporate body to
function effectively.
A Procurement and Contract Records system promotes the efficient and systematic control of the
creation, receipt, maintenance, use and disposal of public procurement records.
Authentic
It must be possible to prove that records are what they purport to be and who created
them, by keeping a record of their management through time. Where information is later
added to an existing document within a record, the added information must be signed and
dated. With electronic records, changes and additions must be identifiable through audit
trail.
Accurate
Records must accurately reflect the transactions that they document.
Accessible
Records must be readily available when needed.
Complete
Records must be sufficient in content, context and structure to reconstruct the relevant
activities and transactions that they document.
Comprehensive
Records must document the complete range of an organization’s business.
Effective
Records must be maintained for specific purposes and the information contained in them
must meet those purposes. Records will be identified and linked to the business process
to which they are related.
Secure
Records must be securely maintained to prevent unauthorized access, alteration, damage
or removal. They must be stored in a secure environment, the degree of security
reflecting the sensitivity and importance of the contents. Where records are migrated
across changes in technology, the evidence preserved must remain authentic and
accurate.
Current or active records are the open files that are in use for conducting the current business
of the organization. Current records and documents are constantly in use and should therefore be
maintained close to the users. They should be maintained and managed within a logical filing
system that facilitates their access. Current records are usually maintained in records offices (or
registries)
Semi-current records consist of the recently closed files. They are only infrequently used. They
should be entered in a closed record register and systematically transferred and organized in a
departmental records centre. The register acts as a retrieval tool.
The disposal information indicates what is to be done with the file when it is closed. On the
“related files” space are indicted the titles and reference numbers of other files that are closely
related with the file.
A file is opened when an existing one matures for closing and the next volume is opened, when a
new subject or activity arises which cannot be accommodated in the existing files, or when an
existing file subdivides into new subjects. A file should be opened after adequate consultation
with the unit or officer responsible for records management. Consultation and care in file
opening is necessary to avoid opening files when similar or the same files are in existence, and
which leads to needless duplication of files.
This leads to uncertainty in filing of papers. The papers in the file should be neatly arranged in
chronological order, and on a specific subject.
The principal file movement control tool is the file movement register, where the file name,
reference number, name of the officer to whom the file is issued, and date of issue and return are
recorded.
A file movement register should have the following format:
Date out;
File title;
File reference number;
To whom issued and signature;
Date in; and
Signature of officer receiving file in registry.
The file’s return to the records office will be marked on the “date in” column. By regularly
checking the column the registry officers will be able to tell cases where files are overdue for
return and therefore to take necessary steps to have the files returned.
There should be an administrative guideline stipulating how long an officer should hold a file -
usually no officer should possess a file for more than four days. Borrowed files should be
promptly returned to the records office once an officer has completed consulting it.
The records staff must ensure that a requested file is promptly provided. Speedy provision of
requested documents and files is one way of cultivating and maintaining confidence in the users
of the registry services.
Closed files should be reviewed after every six (6) years to determine whether they warrant
further retention.
A contract file or folder should be opened by the Contract Administrator and the contract should
be carefully analyzed, taking note of the rights and obligations of each party. Any issues
requiring clarification or change of the contract should be fully documented in this file.
Although practice may vary among organizations, the following documents normally are part of
the contract administration file/folder:
10.3.3 E-mail
E-mails that are evidence of business transactions are official records and should be managed
and kept for as long as is required for functional purposes.
E-mails that approve or authorize an action, contain guidance, advice or direction, relate to
project activities or contain policy decisions should be managed as records and should be filed in
a file plan.
The documents to be digitized must be analyzed to determine their suitability for scanning. The
documents must be well organized and indexed. Priority for digitization should be accorded to
documents or files that are heavily consulted and whose digitization will facilitate multiple and
simultaneous access. Important documents and files in poor physical form and whose frequent
use may lead to their further physical deterioration can also be a priority for digitization.
It is important to select the right scanner, and this will depend on the volume of materials to be
scanned and the compatibility of the scanner with the existing hardware and software. The
digitized images should be stored in an appropriate and secure media such as hard drives, optical
disks and magnetic tapes.
A functional network will be necessary for staff to access the digitized images. The software
used should be able to handle multiple simultaneous access and permit only authorized staff to
access the digital images.
In spite of the challenges highlighted here automated records management and information has
immense benefits as observed elsewhere in this document. What is recommended is a hybrid or
dual system, meaning maintenance of paper records system parallel to the automated system.
11.1 Introduction
Contract evaluation should encompass the overall performance of the contract and of the
Contracting Entity’s administration of the contract. The evaluation of the operation of the
contract and of contract outcomes can be very useful in understanding and improving overall
contract administration, improving contractor performance and can assist in future stakeholder
decision- making.
An evaluation should be undertaken at the end of all contracts and should be planned for in
advance. When a transition from one contract to another is to occur, it is better practice for an
evaluation to be undertaken before the contract ends so that any problems that have occurred
with aspects of the contractual arrangement are identified and, where appropriate, improvements
made in the future contractual arrangements.
Time management
In assessing the contractor’s time management performance the following should be considered:
Ability to meet programmed milestones;
Timely allocation of appropriate resources to critical activities;
Updating of the work program to account for delays;
Overall progress of the work;
Timely submission of progress reports; and
Delays by the contracting entity or other parties, outside the contractor’s control.
Standard of service
Standard of service will generally be measured against the technical, financial and reporting
requirements set out in the conditions of engagement. In particular:
Compliance with brief/scope of work;
Quality of work including conformance with specified performance criteria, if applicable;
Adherence to budget;
Achievement of expected value for money;
Reviews and reports delivered in accordance with the brief;
Amount of rework required from the contractor;
Need to engage another contractor to undertake additional or remedial work; and
Extent of involvement required from the contracting entity to achieve the desired
standard of work.
Co-operative relationships
Assessment items include:
Commitment and implementation of management approach that fosters continuous
improvement, self-assessment and general industry monitoring;
Adoption and commitment to a cooperative contracting approach with Employers, ; and
Commitment to resolving issues through open and effective communication with a non-
adversarial approach.
For big contracts, the evaluation should be a thorough and independent review that is informed
by those involved in establishing and managing the contract.
The evaluation will need to be tailored to the particular circumstances but should consider both
the effectiveness and efficiency of the arrangement. To get the best out of the evaluation, entities
should:
Review all aspects of contract performance and its management;
Provide feedback to the contractor; this should not be done as part of another
procurement process;
Report to stakeholders; and
Identify lessons learned.
Potential sources of information that can be used to inform the evaluation include: notes from
meetings; performance data; interviews with management and the contractor; Employer and end-
user feedback; quality assurance reports; complaints data; and reports of any disputes.
Lessons learned
It is better practice that the findings of any evaluation be analyzed to provide lessons learned to
underpin both continuing and future contracting activity. Lessons learned should be documented
and provided to the appropriate parties. Any manuals, plans or policies should be reviewed and
updated as necessary.
Report to stakeholders.
An evaluation report should be provided to relevant stakeholders, for example, senior
management of the contracting entity. The approach used to inform stakeholders about the
evaluation findings should be tailored to suit their particular role in the contract and may include
both written and oral briefings. This enables particular attention to be given to significant matters
that need to be considered by decision-makers.
Examine how the relationship was managed and whether the level of resources and/or skills was
sufficient to achieve the contract outcomes.
After the review a report should be prepared and distributed as necessary. The report shall
provide good lessons for management of future contracts. Where there is need for action
resulting from the report the management of the contracting entity shall decide. Where the team
has performed well it should be commended and where it has not done very well it shall note for
future improvement.
12.1 Introduction
This chapter describes post implementation tasks and provide requisite contractual procedures
towards contract close-out.
The Contractor may apply by notice to the Engineer for a Taking-over Certificate not earlier than
14 days before the Works will, in the Contractor’s opinion, be complete and ready for taking
over. If the Works are divided into Sections, the Contractor may similarly apply for Taking-Over
Certificate for each Section. The Engineer shall, within 28 days after receiving the Contractor’s
application:
a) Issue the Taking-Over Certificate to the Contractor, stating the date on which the Works
or Section were completed in accordance with the Contract, except for any minor
outstanding work and defects which will not substantially affect the use of the Works or
Section for their intended purpose (either until or whilst this work is completed and these
defects are remedied); or
b) Reject the application, giving reasons and specifying the work required to be done by the
Contractor to enable the Taking-Over Certificate to be issued. The Contractor shall then
complete this work before issuing a further notice.
If the Engineer fails either to issue the Taking-Over Certificate or to reject the Contractor’s
application within the period of 28 days, and if the Works or Section, as the case may be, are
substantially in accordance with the Contract, the Taking-Over Certificate shall be deemed to
have been issued on the last day of that period.
The Engineer may, at the sole discretion of the Employer, issue a Taking-Over Certificate for
any part of the Permanent Works.
The Employer shall not use any part of the Works, other than as a temporary measure which is
either specified in the Contract or agreed by both Parties unless and until the Engineer has issued
A Taking–Over Certificate for this part. However, if the Employer does use any part of the
Works before the Taking-Over Certificate is issued:
a) The part which is used shall be deemed to have been taken over as from the date on
which it is used,
b) The Contractor shall cease to be liable for the care of such part as from this date, when
responsibility shall pass to the Employer, and
After the Engineer has issued a Taking-Over Certificate for a part of the Works, the Contractor
shall be given the earlier opportunity to take such steps as may be necessary to carry out any
outstanding Tests on Completion. The Contractor shall carry out these Tests on Completion
as soon as practicable before the expiry date of the relevant Defects Notification Period.
If the Contractor incurs Cost as a result of the Employer taking over and/or using a part of the
Works, other than such use as is specified in the Contract or agreed by the Contractor, the
Contractor shall (i) give notice to the Engineer and (ii) been titled subject to Contractor’s Claims
to payment of any such Cost plus reasonable profit, which shall be included in the Contract
Price. After receiving this notice, the Engineer shall proceed in accordance with Determinations
to agree or determine this Cost and profit.
If a Taking-Over Certificate has been issued for a part of the Works other than a Section, the
delay damages thereafter for completion of the remainder of the Works shall be reduced.
Similarly, the delay damages for the remainder of the Section if any in which this part is included
shall also be reduced. For any period of delay after the date stated in this Taking-Over
Certificate, the proportional reduction in these delay damages shall be calculated as the
proportion which the value of the part so certified bears to the value of the Works or Section as
the case may be as a whole. The Engineer shall proceed in accordance with Determinations agree
to or determine these proportions. These provisions shall only apply to the daily rate of delay
damages under Delay Damaged, and shall not affect the maximum amount of these damages.
The Engineer shall issue the Performance Certificate within 28 days after the latest of the expiry
dates of the Defects Notification Periods, or as soon thereafter as the Contractor has supplied all
the Contractor’s Documents and completed and tested all the Works, including remedying any
defects. A copy of the Performance Certificate shall be issued to the Employer.
Only the Performance Certificate shall be deemed to constitute acceptance of the Works.
The notice shall be given as soon as practicable after the Employer became aware of the event or
circumstances giving rise to the claim. A notice relating to any extension of the Defects
Notification Period shall be given before the expiry of such period.
The particulars shall specify the Clause or other basis of the claim, and shall include
substantiation of the amount and/or extension to which the Employer considers himself to be
entitled in connection with the Contract. The Engineer shall then proceed in accordance with
Determinations to agree or determine (i) the amount, if any, which the Employer is entitled to be
paid by the Contractor, and/or (ii) the extension, if any, of the Defects Notification Period in
accordance Extension of Defects Notification Period.
a) The value of all work done in accordance with the Contract up to the date stated in
the Taking-Over Certificate for the Works,
b) Any further sums which the Contractor considers to be due, and
c) An estimate of any other amounts which the Contractor considers will become due to
him under the Contract, Estimated amounts shall be shown separately in this
Statement at completion. The Engineer shall then certify in accordance with Issue of
Interim Payment Certificates.
Application for Final Payment Certificate must be done within 56 days after receiving the
Performance Certificate, the Contractor shall submit, to the Engineer, six copies of a draft final
statement with supporting documents showing in detail in a form approved by the Engineer.
a) The value of all work done in accordance with the Contract, and
b) Any further sums which the Contractor considers to be due to him under the Contract
or otherwise.
If the Engineer disagrees with or cannot verify any part of the draft final statement, the
Contractor shall submit such further information as the Engineer may reasonably require and
shall make such changes in the draft as may be agreed between them. The Contractor shall then
prepare and submit to the Engineer the final statement as agreed. This agreed statement is
referred to in these Conditions as the “Final Statement”.
12.6 Discharge
When submitting the Final Statement, the Contractor shall submit a written discharge which
confirms that the total of the Final Statement represents full and final settlement of all moneys
due to the Contractor under or in connection with the Contract. This discharge may state that it
becomes effective when the Contractor has received the Performance Security and the
outstanding balance of this total, in which event the discharge shall be effective on such date.
These tests shall be carried out in accordance with the terms applicable to the previous tests,
except that they shall be carried out at the risk and cost of the Party liable, under Sub-Clause 11.2
[Cost of Remedying Defects], for the cost of the remedial work.
19. International Training Centre (ILO) and World Bank, (April 2000). Works
Procurement Management – Contract Implementation and Management: WPM Module.
20. Public Procurement Authority Accra, Ghana (Rev, January, 2015)
Standard and Sample Contract for Consultant’s Services -Small
Assignments, Time-Based Payments.
21. Public Procurement Authority Accra, Ghana (Rev, January, 2015)
22. Standard Tender Document for Selection of Technical Service Providers.
23. Public Procurement Authority Accra, Ghana (Rev, January, 2015)
Standard and Sample Contract for Consultant’s Services -Small
Assignments, Lump-Sum Payments.
24. Public Procurement Act (Act 663 as amended).
25. Public Procurement Authority Accra, Ghana (Rev, January, 2015)
26. Standard Document for Request of Expression of Interest.
27. UN Handbook on Procurement, 2006
APPENDIX 1
1. Contract Summary
History
Objectives
Key deliverables
2. Contacts
Name Role
Name Role
3. Communication
Detail how parties are to communicate about the contract both internally, across PE and
publicly. If contractor and/or PE is to promote the contract within PE what are the
protocols for doing this.
4. Disclosure
5. Payment processes
6. Performance
7. Consequences
What will happen if KPIs are not met, e.g. Contractor must explain issue and actions in place to
remedy, actions to be monitored. What are the penalties for under performance?
8. Reporting
What reports are required, when are they required and who are they sent to?
Insert meeting and review requirements (based on whether this is an operational, tactical or
strategic arrangement). Indicate meeting type, timing, required attendees and expected protocols
10. Disputes
11. Variations
Develop a risk management plan and establish a process for raising, recording and monitoring.
PE sign off
Name Position
Signature Date / /
Name Position
Signature Date / /
Version Date / /
1. CONTRACT PERIOD - 12
MONTHS
6. Ordering materials by
Check Contractor action Mon 23.05.15
Contractor
8. Milestone I - Mobilization
Check Contractor action Wed 01.06.15
completed
9. Milestone II – Preparation.
Rights of way granted and
Mon 23.05.15 Thurs 02.06.15
all affected residents
informed
12. Milestone V – All pipes laid Check Contractor action Fri 16.09.15
PROGRAMME
APPENDIX 2
Highlights of the Elements of Work, the Human Resources and Plant and Equipment to
be employed on the Works as required have been assessed and reflected in the attached
Proposed Programme for ease of reference and evaluation.
Materials as specified in the Preambles and Bills of Quantities will be followed unless
otherwise varied.
Materials Requisition/Orders and Stock Levels will be done with due diligence to ensure
scheduled deliveries for early completion of works as programmed.
Generally, the project will be under the overall supervision of a Project Engineer with three
(3) Supervisors as Assistants heading the three (3) Teams to carry out the Works
concurrently – for the Executive Wing, Main Office and the Greenfield/3rd Floor
Remedial. Trades Supervisors for the various sections will enhance direct artisanry and
labourer/helper supervision. Tasks will be allotted and workmen will be organized into
trade gangs to facilitate and quicken operations.
The Project will commence from the Executive Wing with the dismantling/demolition
and re-fixing/alteration.
Due to the urgency of the Works, we shall work on day and night basis up to 8pm and on
Saturdays and Sundays.
From details as provided, the volume of works have been assessed and we propose to
engage upon the works the best of specialist artisans for a standard finish as expected by
the Drawings and Specifications to ensure a good blend with existing
structures/infrastructure.
We have examined the Drawings and visited the site and are fully aware of the extent of
Plant and Equipment, including the use of Generating set, needed for the works.
We shall bring our cherished experience on other and similar Projects to bear on this
particular Project.
1. Summary
1.1 Introduction [≈3 short paragraphs - Source of Funds, Location, Scope of Works
e.g. Spot Improvement]
1.2 Contract Details [Tabular Format update monthly]
- Contract Title
- Reporting Period
- Employer
- Contractor
- Supervising Consultants
- Contract Start Date
- Initial Contract Period
- Initial Time for Completion
- Extensions of Time Granted
- Extended Time for Completion
- Percentage Time Elapsed
- Estimated Completion Date
1.3 Financial Summary [Tabular Format update monthly]
- Original Contract Price
- Agreed Adjustments to Contract Price (Breakdown and
Summary)
- Summary of Claims and Valuations Outstanding
- Estimated Final Value
1.4 Summary of Physical Progress [Bar Chart Format]
- Current Programme
- Estimate of Overall Progress Against Current Programme
- Summary of Progress of Major Work Items
4. Administration
[SHORT narratives ≈ 1-2 paragraphs for each section]
4.1 Site Safety and Accidents
4.2 The Contractor’s Site Staff
4.3 The Project Manager’s Representative’s Site Staff
4.4 Visitors to Site
5. Appendices
5.1 Progress Photographs
5.2 Minutes of Progress Meetings
Letterhead)
(Reference)
(Date)
(Contract Title)
ORDER №SR/ [enter sequential №]
Extension of Time
Dear Sirs,
We refer to your application dated [insert date] reference [insert reference] made for an extension to
the period of performance of the contract to which you consider yourself entitled pursuant to
Clause xxx of the Conditions of Contract.
In consultation with the Employer, we have carefully considered your application for an
extension to the period of performance and all the circumstances affecting the works outlined
therein. I now confirm at the behest of the employer that we are able/unable to grant any
extension to the period of performance.
Any delays [beyond those for which an extension of the period of completion was previously
granted] are considered wholly attributable to circumstances or default for which you as
Contractor are held solely responsible under the terms of the contract.
Yours faithfully,
C.C.
(Reference)
(Date)
(Contract Title)
Dear Sirs,
We refer to your application dated [insert date] reference [insert reference] made for an extension of
the Intended Completion Date to which you consider yourself entitled pursuant to Sub-Clause
28.2 of the Conditions of Contract.
In consultation with the employer, we have carefully considered your application for an
extension of the Intended Completion Date and all the circumstances affecting the Works
outlined therein. I now confirm at the behest of employer that at this time it is considered that
you are entitled to an [interim/overall] extension of the Intended Completion Date amounting to
[insert number] days.
The said [interim/overall] extension is awarded pursuant to the Sub-Clauses of the Conditions of
Contract and the grounds tabled below: [delete lines and complete table as appropriate]
Yours faithfully,
C.C.
(Letterhead)
(Reference)
(Date)
(Contract Title)
Dear Sirs,
Pursuant to Clause xxx of the Conditions of Contract we hereby certify that the works were
substantially completed in accordance with the contract and ready for acceptance on [insert date]
and, in accordance with the provisions of Clause xxx, the maintenance period commenced on
that date.
Yours faithfully,
C.C.