Ch5 Contract
Ch5 Contract
Ch5 Contract
CHAPTER 5
CONTRACT DOCUMENTS
2006 Edition
5.2 2006 Edition
SYNOPSIS
This Chapter provides a handy reference to the various standard documents, forms and
information that are regularly used in the preparation of contract documents for civil engineering
works. In some cases, standard forms and exact wording to be included in contract documents
are reproduced in the Chapter. However, where a printed version of a standard document is
available or where the information is contained in a well-known document, the Chapter makes
reference to such documents or source rather than reproducing them. Standard documents
referred to in this Chapter should be of the latest editions of the General Conditions of Contract
for Civil Engineering Works, Standard Method of Measurement for Civil Engineering Works,
General Specification for Civil Engineering Works, Sub-contract Articles of Agreement and
Conditions for Civil Engineering Works, Contractor Management Handbook and Construction
Site Safety Manual. The information in this Chapter would also be useful in the preparation of
documents for term contracts.
A contract for civil engineering construction is a very complex legal document containing
several inter-related documents each of which plays an important role in defining the obligations
and responsibilities of the parties concerned or in providing information on the works to be
constructed. It is therefore essential that the contract documents for each contract are prepared
with great care and by an experienced professional who has thorough knowledge of the works to
be constructed. The documents forming a contract must be scrutinized for comprehensive
coverage, accuracy and consistency with one another before tenders are invited.
5.3 2006 Edition
CONTENTS
Page No.
1. GENERAL 5.8
Page No.
6. SPECIFICATION 5.18
Page No.
8. DRAWINGS 5.28
Page No.
Page No.
APPENDICES
1. GENERAL
Contracts for construction may be broadly classified into the following types:
(e) a design and build contract involving both design and construction by the
Contractor. This type of contract is normally priced as a lump sum. (See WB
TC 31/99)
WB TCs 17/95 and 17/95A promulgate that lump sum contracts with firm Bills of
Quantities should be regarded as the preferred procurement approach for all civil engineering
works. The criteria set out in WB TC 17/95 should be followed in determining the type of
contract to be adopted. A measurement contract with a Schedule of Rates should normally be
used for term contracts involving maintenance works or works of a recurrent nature or works of
a minor nature.
Other types of contract may be used subject to the prior approval of the Head of
Office/Division who may seek higher authority as necessary.
For a typical civil engineering contract the tender documents generally include the
following:
(d) Form of Tender (see Clause 3.1, Appendix 5.1 & 5.2),
(e) Schedule of Proportions for calculating the Price Fluctuation Factor (see Clause
3.2, Appendix 5.3 & 5.4),
(n) Any relevant pre-contract correspondence with the Contractor (e.g. tender
addendum, circular letter to tenderers) (see WB TC 6/95).
Usually, only documents (d) to (n) listed above, the letter of acceptance of the tender and
the Articles of Agreement form the contract documents (see WB TC 6/95A).
The type or edition of document used shall be the current version as promulgated by
ETWB TCWs or other appropriate circular. Reference should also be made to the current
corrigenda issued to the GS and the SMM (see ETWB TCW 6/95B).
Care should be taken to avoid any ambiguities or discrepancies in the documents which
form a contract as contractual claims and disputes are often caused by inconsistencies in or
between the documents. If any ambiguities or discrepancies exist, it should be noted that the
provisions of the SCC prevail over those of the GCC, which in turn prevail over the PS and the
Drawings, which in turn prevail over the GS. GCC Clause 5(1) and GS Clause 1.01 are
relevant in this aspect.
The responsibility for ensuring that tender documents are properly prepared rests with
the professional officers handling the project. They may however seek advice from Contract
Advisers on tender documents when genuine doubts emerge. When seeking such advice the
officer concerned will inform the Contract Adviser of the doubts he has and the aspects of the
case on which he wants advice (see WB TC 15/2002).
5.10 2006 Edition
All tender documents for contracts estimated to exceed $300M in value must be
submitted through the appropriate Contract Adviser to the Legal Advisory Division of ETWB
(LAD/ETWB) for legal vetting prior to calling for tenders. Before submission to LAD/ETWB,
it is advisable to request the relevant Contract Adviser to comment on the documents.
Comments made by the relevant Contract Adviser on the draft should be attached for
LAD/ETWB’s information.
(b) Form of Tender and Appendix thereto (if these have been altered from the
standard version shown at Appendix 5.1),
(c) Articles of Agreement (if these have been altered from the standard printed
version),
A memo shall accompany the tender documents, drawing attention to the following:
(a) SCT clauses and SCC clauses together with reasons for their incorporation,
(b) alterations, if any, to the standard versions of the Articles of Agreement and the
Form of Tender and Appendix thereto, and
(c) any clause in the PS, any item in the BQ, or any other matter relating to the
tender documents or to the Contract which may have significant contractual or
financial implications.
LAD/ETWB will consider these documents (retaining a copy for future reference) and
may recommend amendments they consider advisable to the works division/regional office
concerned, who should incorporate such amendments as necessary into the documents before
calling for tenders. The vetting by LAD/ETWB will take at least three weeks and provision
should be made in the programme for tender preparation.
2. CONDITIONS OF TENDER
Commonly used GCT clauses to be included in the Conditions of Tender for works
contracts other than design and build contracts are given in ETWB TCW 26/2004. The project
officer may use the GCTs promulgated under ETWB TCW 26/2004 selectively since not every
item of the provisions is applicable to a particular contract. For the latest version, please refer
to the ETWB website:
http://www.etwb.gov.hk/press_releases_and_publications/publications/contract_doc/index.aspx
?langno=1&nodeid=852
Any alterations to a GCT shall be effected by a SCT. The SCT clauses to be included in
the Conditions of Tender for works contracts other than design and build contracts are provided
in ETWB TCW 26/2004. The project officer may use the SCTs promulgated under ETWB
TCW 26/2004 selectively since not every item of the provisions is applicable to a particular
contract.
The inclusion of the standard SCT clauses requires the approval of an officer of D1 rank
or above. When non-standard SCT clauses are needed, approval will have to be given by an
officer of at least D2 rank. When seeking such approval, the reasons for their inclusion and a
draft of them should be submitted.
For projects which funding has not been secured before tender invitation pursuant to FC
2/2003, an appropriate SCT shall be incorporated in the tender documents reflecting correctly
the funding status of the project and reminding the tenderers that the Government is not
responsible for their costs of preparing the bids.
The GCTs and SCTs promulgated under ETWB TCW 26/2004 have been uploaded to
the ETWB website under standard contract documents in the publications section and they will
be updated from time to time when new technical circulars are promulgated which may affect
the library content.
For capital works contracts, the standard Form of Tender as shown at Appendix 5.1
should be used. Guidelines on completing the form are given at Appendix 5.2. Regarding
Form of Tender for term contracts, reference should be made to PAH Chapter 8.
A Contract Price Fluctuation System (CPFS) is used in all civil engineering contracts
(except for contracts described in the third paragraph below) to cover changes in the cost of
labour and materials between the time of tender submission and the time payment is made for
Works completed. A description of the system and guidelines for the preparation and
administration of contracts using the CPFS are provided in ETWB TCW 21/2003.
The CPFS requires the inclusion of a Schedule of Proportions in the contract documents,
which will be used to calculate a Price Fluctuation Factor for adjusting payments to the
Contractor for items valued at tendered rates. The standard format for the Schedule of
Proportions and guidelines on its preparation are given at Appendix 5.3 and Appendix 5.4
respectively.
The CPFS should not be applied to contracts where the time for completion of the
Works (excluding Establishment Works period, if any) or Contract Period (for term contracts)
is 21 months or less.
The liquidated damages (LD’s) to be entered in the Appendix to the Form of Tender
should be a genuine pre-estimate of the likely loss to the Employer resulting from delay in
completion of the Works, or any Section of the Works, as the case may be. GCC Clause 52
has been drafted on the basis that if any part of the Works is designated as a Section, the
remainder of the Works must also be designated as a Section. If a contract contains
Sections, LD’s should be calculated for each Section of Works instead of the Works.
If it is possible to carry out a cost-benefit analysis, LD’s shall be calculated using the
daily rate of economic benefit likely to be generated by the project after completion and those
additional costs due to the delay in completion of the Works, if any. Where such analysis is
not possible, as is usually the case in public sector construction contracts, an amount being a
genuine pre-estimate of the likely loss to the Employer may be stipulated as the LD’s.
In estimating the likely loss to the Employer, there is a widely accepted formula
method which includes the following components:
(c) the additional sum payable to the Contractor in respect of fluctuations in the
cost of labour and materials; and
The empirical formulae and guidelines for calculating LD’s based on the above
components are given in ETWB TCW 4/2003.
It should be noted that the concept of minimum site staff establishment may not be
applicable to Sections, other than the last Section, as the supervision can be carried out by the
supervisory staff for the remaining Sections. However, there are exceptions, for instance, if
a Section of the Works is geographically or technically separated, entailing the need to
deploy staff purely for that Section of the Works. Another example is where some of the
staff could be released on completion of a major Section, leaving some minor works such as
landscaping works as the last Section to be completed.
Where the amount of LD’s is to a certain extent related to the contract value of the
Works or the Section, the rate of LD’s shall be stipulated as a function of the Contract Sum or
the contract value of the Section and an appropriate footnote should be added to deal with
possible anomalies which may arise as a result of negative pricing by the tenderers (see
paragraph 16 of ETWB TCW 4/2003).
It is important that those responsible for calculating LD’s should ensure that the
calculations are logical and free from error. In all cases, the full implications of the contract
must be considered in applying the formulae given in ETWB TCW 4/2003. In this respect,
LD’s calculations should always be subject to an independent check by a senior professional
officer. Calculations from which LD’s are derived must be set out clearly and kept on file
for future reference. Full record of any review of LD’s together with all related calculations
should also be kept on file.
As a provision for LD’s is enforceable only if the rate fixed is a genuine pre-estimate
of the Employer’s loss judged at the time of entering into the contract, there is a need to
review the formula immediately before a tender is accepted.
5.15 2006 Edition
4. ARTICLES OF AGREEMENT
Standard Articles of Agreement attached to the respective editions of the GCCs shall be
used, namely, GF 548 for Civil Engineering Works as modified by Appendix A of WB TC
20/2000 (GF 546 for term contracts), GF 549 for Design and Build Contracts, GF 541 for
Building Works, and GF 550 for Electrical & Mechanical Works. Appropriate modification to
the attestation clauses should be made in accordance with ETWB TCW 54/2002.
For Nominated Sub-contracts, the Articles of Agreement in the “The Government of the
Hong Kong Special Administrative Region, Sub-contract Articles of Agreement and Conditions
for Civil Engineering Works” (GF 543) shall be used for all Nominated Sub-contracts to capital
works contracts.
In accordance with Section 30 of the Hong Kong Reunification Ordinance (Ord. No. 110
of 1997) published in the Gazette on 1 July 1997, as from 1 July 1997 all pre-unification
contracts and agreements entered into with the Crown or the Government of Hong Kong are
required, subject to express provision to the contrary, to be construed as if references to the
Crown or the Government of Hong Kong were references to the Government of the Hong Kong
Special Administrative Region (HKSAR) and references to a public officer were references to
the corresponding officer of the Government of the HKSAR. The references to “the
Government of Hong Kong” shall be amended to “the Government of the Hong Kong Special
Administrative Region” in relation to the Articles of Agreement to be executed on or after the
transition on 1 July 1997.
5.16 2006 Edition
5. CONDITIONS OF CONTRACT
(a) The Government of the Hong Kong Special Administrative Region, General
Conditions of Contract for Civil Engineering Works, 1999 Edition (GF 548)
(This should be used for all capital works contracts);
(b) The Government of the Hong Kong Special Administrative Region, General
Conditions of Contract for Term Contracts for Civil Engineering Works, 2002
Edition (GF 546) (This should be used for term contracts);
(c) The Government of the Hong Kong Special Administrative Region, General
Conditions of Contract for Building Works, 1999 Edition (GF 541);
(e) The Government of the Hong Kong Special Administrative Region, General
Conditions of Contract for Term Contracts for Building Works, 2004 Edition
( ETWB 36);
(f) The Government of the Hong Kong Special Administrative Region, General
Conditions of Contract for Electrical and Mechanical Engineering Works, 1999
Edition (GF 550);
(g) The Government of the Hong Kong Special Administrative Region, General
Conditions of Contracts for Term Contracts for Electrical and Mechanical
Engineering Works, 1994 Edition (EMSD 292); and
(h) The Government of the Hong Kong Special Administrative Region, General
Conditions of Contract for Design and Build Contracts, 1999 Edition (GF 549).
Copies of the GCC are issued to all approved contractors on the ETWB Lists and it need
not be reproduced in tender documents.
The GCCs have been uploaded to the ETWB website (under standard contract
documents in the publications section and they will be updated from time to time when new
editions are promulgated which may affect the library content.
(http://www.etwb.gov.hk/press_releases_and_publications/publications/contract_doc/index.aspx
?langno=1&nodeid=852)
Any amendments, additions, deletions and amplifications to the GCC should be effected
by the inclusion of SCC clauses. However, SCC clauses should only be included when there is
a genuine need to alter or supplement the GCC.
5.17 2006 Edition
Standard SCC for use with the General Conditions of Contract for Civil Engineering
Works and Electrical & Mechanical Engineering Works are included in the Library of Standard
Special Conditions of Contract promulgated and updated regularly by ETWB in WB TCs
18/2000, 18/2000A and 18/2000B. Any SCC clauses promulgated by means of
memos/respective technical circulars after promulgation of the Library shall be deemed to have
been included in the Library. It shall also be used with the GCC for Building Works 1999
Edition and the GCC for Electrical & Mechanical Engineering Works 1999 Edition. All
additions and deletions from the Library of standard SCC will be vetted by the Conditions of
Contract Committee (CCC) and approved by the SETW. To maximize the usefulness of the
Library, any SCC developed for a particular contract that will have repeated use or could be of
use to others should be submitted to the CCC through the department’s representative with a
view to placing the clause in the Library of standard SCC.
In accordance with the technical circular promulgating the Library of Standard Special
Conditions of Contract, except for the clause deleting provision for extension of time due to
inclement weather, standard SCC clauses may be used as required with the approval of the chief
engineer (or a higher rank officer in cases of SCC for Sections subject to excision, care of the
Works insurance, third party insurance and designs or alternative designs by tenderers)
responsible for the administration of the particular contract. The use of the standard SCC
clause deleting the provisions for extension of time due to inclement weather must however be
approved by the Head of Department and endorsed by ETWB (attention PAS(W)3).
All non-standard SCC may be drafted and used as required on the approval of the Head
of Department/Office or those officers (not below the rank of D1) to whom this responsibility
has been delegated. When seeking such approval, the reasons for the inclusion of the SCC
clause and a draft of the clause should be submitted. Should the Head of Department/Office or
the delegated officer have any doubt as to the wording of a proposed SCC not contained in the
Library then the clause may be forwarded to LAD/ETWB for advice, through the relevant
Contract Adviser.
6. SPECIFICATION
The latest edition of the General Specification for Civil Engineering Works (GS) can be
found on the CEDD Homepage. The GS covers general requirements and may need varying
degrees of amplification and modification to suit individual contracts, e.g. on the general
description (major items only) of the Works, the list of drawings, works by other Contractors on
the Site running concurrently with the Works under the Contract. Amplifications and
modifications to the GS should be made in the PS, with the approval of an officer at or above the
rank of D1 administering the Contract.
Copies of the GS need not be reproduced in contract and tender documents. If any
amendments have been issued, the attention of the tenderers should be drawn to the specific
websites where the amendments are available or the amendments should be incorporated in full
in the tender documents.
Each contract will require a different set of PS clauses to suit its own circumstances (See
Clause 6.1). Standard clauses/guidelines may be available from ETWB TCW for the following
subjects:
(i) For capital works or maintenance works (including tree planting) within or
adjacent to the Kowloon-Canton Railway (Hong Kong) Section, Tsim Sha
Tsui Extension and Ma On Shan Rail, reference should be made to ETWB
TCW 2/2005;
(ii) For public works to be carried out within the Railway Protection Area for the
completed facilities of the West Rail, reference should be made to ETWB TCW
33/2003;
(iii) For public works to be carried out within the protection boundary for completed
facilities of the Mass Transit Railway Corporation, reference should be made to
WB TC 19/2002;
(iv) For contracts involving permanent prestressed ground anchors, reference should
be made to ETWB TCW 16/2004;
(v) For reclamation contracts involving public filling, reference should be made to
WB TCs 10/92, 2/93, 2/93B, 16/96, 4/98 & 4/98A and subsequent revisions;
(vii) For construction site safety, reference should be made to WB TC 30/2000 and
the updated Construction Site Safety Manual;
(ix) For the control of alkali-aggregate reaction (AAR) in concrete, reference should
be made to WB TC 5/94 and later amendments;
(x) For contracts involving importation of sand from PRC by barges, reference
should be made to WB TCs 10/95 & 10/95A;
(xi) For the Pay for Safety and Environment Scheme, reference should be made to
WB TC 30/2000, the updated Construction Site Safety Manual, ETWB TCW
19/2005, and the Interim Guidance Note on Administration of Environmental
Management and Pay for Safety and Environment Scheme for Public Works
Contracts promulgated under SETW’s memo ref. (014G7-01-1) in ETWB(W)
517/91/01 dated 19.6.2006;
(Amendment No. 6/2007)
(xii) For contracts including contract transport, reference should be made to LWB TC
11/84;
(xiii) For independent checking of the Design, Erection, Use and Removal of
Temporary Works, reference should be made to WB TC 3/97;
(xv) For the trip-ticket system for disposal of construction and demolition (C&D)
material at public facilities or landfills, reference should be made to ETWB
TCW 31/2004;
(xvii) For contracts involving vehicles for carrying dusty materials away from the Site,
reference should be made to SETW’s memo ref. ETWB (W) 211/32/01 dated
5.8.2002;
(xix) For contracts involving reinforced fill structures, references should be made to
ETWB TCW 24/2003 and the model specification in Appendix A to Geoguide 6,
“Guide to Reinforced Fill Structure and Slope Design” (ref.
http://www.cedd.gov.hk/eng/downloading/index.htm#11) [the project department
shall submit the specification to GEO for checking in accordance with ETWB
TCW Nos 29/2002 & 29/2002A];
(xxi) For contracts with concrete used in marine environment, reference should be
made to the ‘Recommended Specification for Reinforced Concrete in Marine
Environment’ issued by the Chairman of Standing Committee on Concrete
Technology (SCCT), which is available on the CEDD Homepage (ref.
5.20 2006 Edition
http://www.cedd.gov.hk/eng/downloading/index.htm#11);
(xxiii) For metallic site hoardings and signboards, reference should be made to WB TC
19/2001;
(xxvii) For enhanced control of site cleanliness and tidiness, reference should be made to
WB TC 6/2002 & ETWB TCW 6/2002A;
(xxix) For contracts involving the use of recycled aggregates in concrete production or
in road sub-base construction, reference should be made to WB TC 12/2002
and ETWB TCW 24/2004;
(xxx) For implementation of Site Safety Cycle and provision of welfare facilities for
workers at construction sites, reference should be made to ETWB TCW 30/2002;
(xxxi) For employment of technician apprentices and building & civil engineering
graduates by contractors of public works contracts, reference should be made to
ETWB TCW 12/2003 and 9/2005;
(xxxii) For preservation and protection of existing trees and, where required, the
registered Old and Valuable trees and shrubs, reference should be made to
ETWB TCW 29/2004 and 3/2006 and the Cyber Green Manual (ref.
http://etwbwb.host.ccgo.hksarg/) promulgated by ETWB TCW 11/2004;
(xxxiii) For contracts implementing Systematic Risk Management (SRM), the standard
particular specification in Annex I of ETWB TCW 6/2005 should be
incorporated;
(xxxiv) For contracts where an Environmental Permit has been obtained by the project
proponent for the works, the standard PS clause in Clause 1.6.5 in Appendix A to
ETWB TCW 13/2003 should be included;
(xxxv) For contracts involving excavation works on unleased land or streets maintained
5.21 2006 Edition
(xxxvi) For construction works and ground investigation works in the vicinity of the
Habour Area Treatment Scheme (HATS) Stage I sewerage tunnels, reference
should be made to ETWB TCW 28/2003; and
(xxxvii) For contracts involving tunnel works, reference should be made to ETWB TCW
15/2005.
In the drafting of any PS clause, it should be noted that according to Para. 9 of ETWB
TCW 33/2004, technical specifications shall, where appropriate, be in terms of performance
rather than design or descriptive characteristics and be based on international standards where
such exist. The same principle applies regardless of whether or not the tendering procedures
are governed by the Agreement on Government Procurement of the World Trade
Organization (WTO GPA). There shall be no requirement for or reference to a particular
trademark or trade name or patent or origin unless there is no sufficiently precise or
intelligible way of describing the procurement requirements and provided that “products
having equivalent functions or performance” shall always be permitted and indicated in the
tender documentation. (see S for W’s memo ref. WB(W) 272/31/02D dated 4.4.2002)
To accord with the green policy of the Government, used preliminaries can be
accepted if they are in good working and serviceable condition and if they can comply with
the requirements of the Contract. In the preparation of tender documents, project officers
are encouraged to specify, as far as reasonable and practicable and as much as possible, used
preliminaries which are to be supplied for use by Engineer during the contract period. In
warranted cases, works departments could specify clearly preliminary items as “used, but in a
condition acceptable to the Engineer” (or where appropriate, another more definitive
specification such as “not more than 2 years old” for land transport, etc) to save costs for the
government.
“All contract preliminaries items shall be provided to the office of the Engineer’s
Representative for central acceptance and distribution. The Engineer’s
Representative should inform the Contractor of the name of the officers responsible
for accepting these items. The Contractor shall not provide the items directly to an
individual member of the site supervisory staff.”
“Any equipment or facilities to be provided for the use of the Engineer’s staff are only
required to meet the minimum requirements stipulated in the Contract. Where this is
impracticable (e.g. when the model just satisfying the minimum requirements is
outdated or out of stock), the Contractor may provide at his own cost equipment or
facilities slightly exceeding the minimum requirements. Extravagant or out-of-the
norm over-provision is unnecessary and should be avoided. In the event that a much
higher quality than that stipulated shall be provided for legitimate reasons, the
Contractor shall give prior notification to the Employer of such an over-provision.”
The contract transport for the Engineer should be required to be painted with the
contract number/title and the Contractors’ name (or other suitable identifications, if such
names/titles are too lengthy) for easy identification.
In addition, it is necessary to include in the specification the provision, “Please note that
if the Contractor intends to use the intellectual property rights of another party in performing his
obligations under the Contract, appropriate licences should be obtained from the relevant
owners.” (see S for W’s memo ref. WB(W) 209/32/110 Pt. 12 dated 9.1.2001)
5.23 2006 Edition
7. BILLS OF QUANTITIES
7.1 GENERAL
(a) to allow a comparison of tender prices of tenders obtained from tenderers, and
(b) to provide a means of valuing the work executed when the Contract has been
entered into.
The BQ should be prepared in accordance with the SMM and the Standard Phraseology
of [Bill of Quantities] Item Descriptions. See also WB TCs 18/92, 21/93, 21/93A & 21/93B
and corrigenda to SMM promulgated from time to time (list of issued corrigenda can be found
on the Internet at CEDD Homepage).
Due attention is drawn to the amendments made to SMM pursuant to WB TCs 17/95
and 17/95A which promulgate the use of lump sum BQ contracts. The quantities in the lump
sum BQ contract must be measured accurately and regarded as firm, not subject to
remeasurement. Where quantities cannot be measured accurately, the respective items in the
BQ should be marked as “provisional”.
To remove site safety from the realm of competitive tendering and to enhance
environmental management on construction sites, all appropriate tenders as required under
ETWB TCW 19/2005 and the Interim Guidance Note on Administration of Environmental
Management and Pay for Safety and Environment Scheme for Public Works Contracts
promulgated under SETW’s memo ref. (014G7-01-1) in ETWB(W) 517/91/01 dated 19.6.2006
shall include a separate ‘Site Safety and Environmental Management’ section in the BQ.
(Amendment No. 6/2007)
The rules for preparing BQ are contained in Part III of the SMM and they should be
strictly followed. In accordance with the SMM, a BQ will comprise the following:
*(a) This Bill is to be provided for all appropriate tenders as required under ETWB
TCW 19/2005 and the Interim Guidance Note on Administration of
Environmental Management and Pay for Safety and Environment Scheme for
Public Works Contracts promulgated under SETW’s memo ref. (014G7-01-1)
5.24 2006 Edition
Separate bills should be prepared for works of a different nature, location, date of
commencement, time for completion or any other circumstance which may give rise to different
considerations of cost. Separate bills may also be considered, at the discretion of the project
engineer, for work items charged to different financial votes. When a lump sum form of
contract is used, the provisional quantities are included in the Bills wherever it is appropriate and
sensible to do so. Individual items to be remeasured can be mixed in with the “firm” items, or
a whole section can be shown separately and described as provisional. The items in each bill
should be grouped into the appropriate section of Part V of the SMM in the order shown. A
sample for the Grand Summary is given at Appendix 5.5.
Copies of the SMM are issued to all approved contractors on the ETWB Lists and it
needs not be reproduced in contract and tender documents.
Specimen BQ items provided in ETWB TCWs for various subjects such as site
cleanliness and tidiness, preservation and protection of preserved trees etc should be adopted
where applicable.
A set of standard clauses for the “General Preambles to the Bills of Quantities” is
contained in Part IV of the SMM. Any amendments or alterations to the SMM to be adopted in
the preparation of the BQ shall have the prior approval of an officer of D1 rank or above
administering the Contract and shall be included as Particular Preambles to the Bills of
Quantities.
The Preambles should also contain any other information which is considered to be
necessary for the pricing of the BQ but is not included elsewhere in the contract documents.
Standard Particular Preambles for various subjects set out in ETWB TCWs should be
adopted where applicable.
Provisional Item means an item describing work, the requirement for which is uncertain
at the time the tender documents are issued and which can only be carried out on the instruction
of the Engineer for the Contract. All works described by a Provisional Item should be clearly
specified and the provisional nature clearly explained in the PS and BQ.
The use of Provisional Items in the BQ should be avoided as far as possible. They
should not be included if it is impossible for the tenderer to provide a realistic tender price for
the work, taking into account its provisional nature and the manner in which the works may be
described. If the requirement for the work is very remote, issuing variations during the contract
is generally more advisable than trying to cover the work by inclusion of Provisional Items.
5.25 2006 Edition
Provisional Sum means a sum provided for work(s) or expenditure which has not been
quantified or detailed at the time the tender documents are issued. Contingency Sum means the
sum provided for work(s) or expenditure which cannot be foreseen at the time the tender
documents are issued. Prime Cost Sum means the sum provided for works to be executed or
for materials or services to be supplied by a Nominated Sub-contractor, after deducting any trade
or other discount. However, according to GCC Clause 1(1), both Provisional Sum and
Contingency Sum may include provision for works to be executed or for materials or services to
be supplied by a Nominated Sub-contractor.
Provisional Sums for specific purposes should be included in the relevant bills of the
BQ.
Under the GCC for Term Contracts 2002 Edition, Contingency Sum may also be
specified in a works order in term contracts for work or services or expenditure which cannot be
foreseen at the time such works order is issued.
However, if the work contained in the ‘Sections Subject to Excision’ is not ordered, any
preliminaries and overhead costs attributable to those Sections which may be covered elsewhere
in the Contract would still be payable to the Contractor. The effect of including ‘Sections
Subject to Excision’ and the probability of its incorporation in the Works should therefore be
carefully considered before it is included in the tender documents. Preliminary items in respect
of the ‘Sections Subject to Excision’, where these can be identified, should be included in a
separate bill of the BQ designated ‘Section Subject to Excision’.
Sample BQ, method of measurement and guidelines for preparing the section on site
cleanliness are given in WB TC 6/2002 & ETWB TCW 6/2002A.
With the promulgation of ETWB TCW 19/2005, all appropriate tenders included in the
Pay for Safety and Environment Scheme (PFSES) shall include a separate “Site Safety and
Environmental Management” section in the BQ. A number of sample BQ and guidelines for
preparing the “Site Safety and Environmental Management” Section of BQ are given in ETWB
TCW 19/2005 and the Interim Guidance Note on Administration of Environmental
Management and Pay for Safety and Environment Scheme for Public Works Contracts
promulgated under SETW’s memo ref. (014G7-01-1) in ETWB(W) 517/91/01 dated 19.6.2006.
Please also see Sub-section 9.15.
(Amendment No. 6/2007)
Payment for Site Safety Cycle (SSC) shall be made under the PFSES by including
appropriate sections in the Method of Measurement and appropriate items in the BQ. The main
item to be included for payment is collectively referred to as ‘Pre-work Activities’ which
comprise the following activities on one day:
Another payment item under the SSC is the provision of ‘Safety Bulletin Board’.
Guidelines for the SSC are given in ETWB TCW 30/2002. The updated sample BQ is
incorporated into Appendix E to ETWB TCW 19/2005 and the Interim Guidance Note on
Administration of Environmental Management and Pay for Safety and Environment Scheme
for Public Works Contracts promulgated under SETW’s memo ref. (014G7-01-1) in ETWB(W)
517/91/01 dated 19.6.2006.
(Amendment No. 6/2007)
To take care of the needs and welfare of workers and to promote site cleanliness and
5.27 2006 Edition
hygiene, the Contractor is required to provide storage compartments, drinking water facilities,
toilet facilities, hand-wash facilities and rubbish bins. Showering facilities may also be
required depending on the number of workers on site. These provisions shall be included in the
Preliminary Items ‘Temporary Accommodation for the Contractor’ or ‘Contractor’s Site
Accommodation in the Preliminaries’ as appropriate by incorporating the sample Particular
Preamble stipulated in ETWB TCW 30/2002.
Sample Particular Preamble is provided in ETWB TCW 31/2004 for the requirement of
Site Management Plan for Trip Ticket System.
Related sample Particular Preamble and sample BQ for preservation and protection of
preserved trees and old and valuable trees can be found in the Cyber Manual for Greening which
is posted on the government intranet, the ‘Central Cyber Government Office’ (CCGO) portal
(http://portal.ccgo.hksarg/index.jsp) under the heading ‘Other Useful Information
(http://etwbwb.host.ccgo.hksarg/). See also ETWB TCWs 11/2004, 29/2004 and 3/2006.
The project engineer should open a measurement file before any taking-off commences
and issue instructions to his staff regarding the method of measurement to be adopted and any
other guidance he considers necessary for the preparation of the BQ.
Standard forms for taking-off, abstracting and billing are included in Chapter 9
(Measurement Procedure), and should be used. All taking-off and abstract sheets should be
signed and dated by the officer preparing them and inserted into the measurement file.
The project engineer should arrange to have the taking-off sheets, abstract sheets and the
bills checked to ensure correctness in all respects. Checked documents should be dated and
signed by the officer who carries out the checks.
5.28 2006 Edition
8. DRAWINGS
These should be listed in the PS and should include sufficient drawings to enable the
tenderers to price the tender properly. Amongst these should be a general layout plan, general
arrangement drawings, typical structural details and any other drawings required for providing
tenderers with a good perspective of the extent and nature of the work.
It is not uncommon that drawings giving site investigation information, utilities drawings
and reinforcement details drawings are not included with the tender documents. In that case,
they should be listed in the PS and should be made available for inspection by tenderers during
the tender period. These drawings, when forming part of the Contract, should be issued to the
Contractor at the commencement of the Contract. Standard drawings, if applicable to the
Contract, should be listed (specifying the applicable version) in the PS but may be excluded
from the tender documents and the subsequent Contract documents if they are available in the
department’s website. Otherwise, they should be made available for inspection by tenderers
during the tender period, and, if necessary, be issued to the Contractor at the commencement of
the Contract.
Drawings giving information only, including site investigation plans and existing
utilities plans, do not form part of the Contract and should be stated as such so as to avoid
possible future claims. A note should also be added on the drawings to disclaim responsibility
for the accuracy or sufficiency of the information given. They should be made available for
inspection by the tenderers during the tender period.
9. SPECIAL TOPICS
Where the required financial and manpower resources are available, the contracts of a
multi-contract project are normally carried out in parallel to enable the completion of the project
in the shortest possible time.
Some of the issues that need to be considered and provided for in a multi-contract
project would include:
Suitable provisions should be made in the constituent contracts to cover these and other
relevant issues. Such provisions should be made in the SCC, PS and Drawings, where
appropriate.
For projects (i) involving sequential handling-over of the project site among contractors
of concurrent contracts and/or (ii) in which the work progress of one contractor is dependent on
that of another contractor in the same project, the compatibility of the multi-contract
arrangement with the preferred contract forms of the project should be carefully assessed. For
instance, before adopting the arrangement of implementing a conventional contract for civil
works and a design-and-build contract for E&M works at the same time, the pros and cons of
such arrangement should be thoroughly compared with that of combining the civil and the E&M
works into a single contract.
For projects involving substantial underground works, and hence with a relatively high
degree of uncertainty, consideration should be given to reducing risks by carrying out works at
different locations under separate contracts to be undertaken by different contractors. However,
before deciding on adopting this approach, its benefits would have to be balanced against
possible demerits such as the reduction in economy of scale and the need for greater
management effort to deal with contract interface problems.
It is important that all the merits and demerits of using multi-contract arrangement in a
project should be thoroughly assessed before deciding on the most appropriate number and form
of contracts in a project.
5.30 2006 Edition
For contracts to be completed in Sections, the tender documents, i.e. the Form of Tender,
SCC, PS and Drawings, where appropriate, should explicitly define the extent of the various
Sections and their respective time for completion. Separate amounts of liquidated damages and
minimum amounts of liquidated damages, if any, should be set for each Section of the Works in
the Appendix to the Form of Tender.
Each Section should preferably be a self-contained package of work. Great care should
be taken in defining the extent of each Section to avoid any possibility of ambiguity. There
should be no overlapping between Sections and all the Sections should add up to be the Works.
(b) Where such part of the Works includes materials and construction methods, the
design of which requires the specialist experience of contractors or suppliers;
(c) Exceptionally, where the detailed design of such part of the project is
insufficiently advanced and the completion of the project is urgent;
(d) For piling works where several solutions are available to implement the Works;
and
(e) For works of a limited lifespan, e.g. a temporary footbridge within a larger
project.
Where there is potential for better value for money, departments may, subject to the
approval of an officer of D2 level or above, invite tenderers to submit tenders incorporating their
own alternative designs for a certain part of the Works notwithstanding that a design for that part
of the Works has been provided by the Engineer. Departments shall specify in the tender
documents which part of the Works alternative designs are invited.
In requiring or inviting tenderers to submit tenders based on their own designs for part of
the Works, departments should take note of the following guidelines:
(a) The tender documents shall contain specific and complete instructions to
tenderers including a complete set of design criteria, outline drawings, survey
plans and any requirements pertaining to that part of the Works for which
tenderer’s design proposals are required or alternative design proposals are
invited (in a PS Clause);
5.31 2006 Edition
(c) A reasonable tender period and validity period shall be allowed, consideration
being given to the time required to formulate and prepare a design in sufficient
detail and for a reasonable assessment to be made during the tender assessment
period.
Where alternative designs for certain part of the Works are invited, tenderers may
elect to submit a tender conforming with the Engineer’s design and/or in accordance with the
invitation an alternative tender incorporating the tenderer’s alternative design for that part of
the Works (hereinafter refer to conforming tender and alternative tender respectively). It is
not necessary that an alternative tender must be accompanied by a conforming tender.
Where there is no invitation for alternative tender or design, alternative tenders or designs
shall not be considered. Departments are, however, encouraged to invite submission of
alternative tenders or designs from the tenderers where there is a potential for better value for
money.
The contractual provisions to be incorporated into the tender documents are given in
ETWB TCW 25/2004
(a) ETWB TCW 6/2005 sets out guidelines on the application of a systematic risk
management (SRM) process in public works projects. All public works
programme projects with cost estimates in excess of $200M will be required to
go through a SRM process promulgated under the subject circular. The risk
management process comprises a systematic approach to risk planning,
identification, assessment and treatment. One of the treatment options
available is to transfer certain risks to insurers through proper contract
documentation.
(b) For public works programme projects with cost estimates below $200M,
ETWB TCW 6/2005 does not apply. However, for the purpose of assessing
whether insurance is required for the respective contracts under that particular
public works programme project, departments should adopt a similar approach
to risk assessment and treatment set out under TCW 6/2005 to reach a decision
on the matter.
(d) If the result of the SRM process dictates that insurance procurement is the
proper treatment of the identified risks, two options exist on the procurement
of construction insurance viz: -
(1) Owner Controlled Insurance Programme (OCIP)
(2) Contractor Controlled Insurance Programme (CCIP)
5.32 2006 Edition
(e) Coverage for the contract works (Care of the Works) or for liability emanating
therefrom (Third Party Liability) should be procured in the joint-names of the
Owner (i.e. Government/Works Department), the Contractors (including co-
and sub-contractors) and their servants or agents in any tier and/or consultants
for their site activities only. The determination of the amount of insurance
coverage should follow the quantitative assessment methods outlined in the
SRM procedures. This can be procured by either OCIP or CCIP. If the
requirement for insurance is specified, the contract should state clearly by way
of inclusion of suitable special conditions, what insurance is required and who
is responsible to arrange the insurance. In cases where the nature and extent
of the risks identified in the SRM process which require insurance are routine
and are considered insignificant, the procurement of insurance should be left
with the Contractor on a self-arranged basis and the contract makes no mention
on the requirement for insurance. The Employer, in this event, relies on the
indemnity clauses under the contract for protection.
(f) For contract specified insurance, strategies have been developed on how
insurances are to be procured for the following categories of contracts: -
Category II – The insurance clauses within the contract conditions should state
that the contract works insurance should be procured by the contractor together
with a primary HK$10M limit of indemnity for third party liability insurance
i.e. a CCIP arrangement for the primary layer of liability. This limit should
be for any one occurrence.
Above the HK$10M limit of indemnity for third party liability, project
departments should arrange an excess liability policy for all minor works and
term contracts within the department for HK$XM (exact sum determined via
the SRM process) any one occurrence in excess of the contractor’s primary
HK$10M any one occurrence policy, providing a total limit of liability of
HK$(10 + X)M any one occurrence. The arrangement will effectively be a
multi-layer placement with a combination of a CCIP placement for the primary
layer and an OCIP placement for the secondary layer. Again, the engagement
of a specialist construction insurance advisor is recommended in the
structuring of the OCIP placement for the secondary layer. Multi-layer
insurance placement may also be suitable for Category I projects subject to the
result of the SRM taking into consideration the recommendation of the
insurance advisor and having regard to the prevailing market conditions.
Category III – The insurance clauses within the contract conditions should
state what insurance(s) the contractor is required to procure, i.e. the contract
works insurance, or the third party liability insurance, or both. This is a
traditional approach and the placement is solely on the basis of a CCIP
arrangement. Standard contract provisions for use in term contracts (primary
layer) and capital works contracts and a standard policy are available for a
CCIP placement and these are given in Appendix A and Appendix B of ETWB
TCW 7/2005. Risk assessment may show that additional coverage or
different policy wordings to those contained in the standard policy are required
and in such case, the department may look for the advice of an insurance
advisor, either employed independently or under the main consultancy as
suggested above.
For works within or adjacent to the Kowloon-Canton Railway (Hong Kong) Section,
Tsim Sha Tsui Extension and Ma On Shan Rail, consideration, in conjunction with the Senior
Director, Transport of the Kowloon-Canton Railway Corporation, shall be taken for providing
third party insurance in the Contract (See ETWB TCW 2/2005).
Where insurance against damage to the Works or third party risks is required under the
Contract, separate items should be provided in the BQ for the Contractor to price the cost of
such insurance.
The requirement for the Contractor to be represented at all times on the Site by a
competent and authorized English speaking agent is stipulated in GCC Clause 17. The
Engineer’s authority to withdraw his approval of the Contractor’s agent, thus causing this agent
to be removed from the Site, is also stated in GCC Clause 17. See also the GS and the
Guidance Notes on the GS.
The qualifications of the Contractor’s surveyor responsible for the setting out of the
Works are not particularly specified either in the GCC or the GS. However, it may be inferred
from GCC Clauses 18 & 19 that he should be skilled and experienced. It should be noted that
any person employed by the Contractor who is considered incompetent may be objected to by
the Engineer, and thus removed from the Works, in accordance with GCC Clause 18.
Contract transport refers to land or marine transport provided for use by the Engineer
(and his staff) and the Employer (and his employees) under the Contract. See LWB TC 11/84
and the GS for more details.
Contract transport should only be included under the Contract where it has been
established that such transportation is essential to the supervisory staff for the adequate and
proper supervision of the Works and for the discharge of other related duties. Critical
examination for justifications to provide contract transport shall be made with due regard to
meeting the operational need. The possibility of shared use of contract transport with other
relevant on-going contracts shall also be taken into account in the critical examination. In
particular, the adequacy of public transport for accessing the site direct shall be assessed in
determination of the quantity of contract transport. In making such determination, the project
office should not take into account the need to provide contract transport to serve the site staff to
and from the site if the site is adequately served by public transport. The prior approval of an
officer of D2 rank (D3 for HyD according to HyD’s internal procedures) or above is required for
the provision of contract transport.
The specification should be less restrictive so that there may be scope for savings.
Clause 7.1 of the LWB TC 11/84 states that a new motor vehicle will not always be required;
however, where a used motor vehicle will suffice, it is suggested that it should not be more than
2 years old when first brought to Site.
5.35 2006 Edition
All materials compliance testing required by the Contract or by the Engineer must be
done through Public Works Laboratories (PWL), except Chief Geotechnical Engineer/Standards
and Testing, GEO (CGE/S&T) advises that the required tests cannot be undertaken by PWL.
He would also advise on whether an additional Regional Laboratory should be established to
meet the testing demand. On such occasion, the project office should liaise with CGE/S&T
regarding the preparation of detailed layout plans, equipment lists and other contract
requirements for incorporation into suitable works contracts.
CGE/S&T should be consulted at an early stage in project planning regarding the testing
demand for testing services. In order to facilitate CGE/S&T to provide advice, the project
office should supply full details of the anticipated testing required, including information on
quantities and the programme. If CGE/S&T considers that certain tests cannot be undertaken
by PWL, then such tests have to be performed by an independent laboratory (i.e. with no
affiliation as a legal entity to the Contractor and its sub-contractors) subject to approval by the
Engineer. Test results obtained from a laboratory other than PWL should be checked by
periodic verification using another independent laboratory to conduct identical tests on items
selected from the same samples, or as advised by CGE/S&T.
(a) On loan from the Public Works Laboratories (or from the Employer), or
The list of equipment required for a particular contract should be forwarded at contract
design stage to CGE/S&T who will decide whether:
(a) All (or a part) of the testing equipment can be supplied on loan from the Public
Works Laboratories, or
(b) All (or a part) of the testing equipment should be supplied by the Contractor and
remain his property on completion of the works, or
(c) All (or a part) of the testing equipment should be supplied by the Contractor and
become the property of Government on completion of the works.
5.36 2006 Edition
Provision of testing equipment on loan from the Public Works Laboratories will be
recommended if stocks are available. Provision of testing equipment by the Contractor which
is to become the property of the Employer on completion of the Works will generally be
recommended if the testing equipment is likely to be useful to the Employer and is in good
condition at the end of the Contract. In each case CGE/S&T will seek approval from the
Director of Government Logistics for any testing equipment acquired in this way, and will
arrange for the testing equipment to be taken on charge at an appropriate time. The provision
in the Contract for the maintenance and taking over of the testing equipment should be agreed
with CGE/S&T.
The Contractor should normally obtain all materials necessary for use in the Works from
his own sources except for:
(a) General
Very often the Engineer may wish to retain control over which sub-contractor
will carry out certain specialized work under the main contract. This may be
achieved by writing into the main contract one of the following two alternatives:
(d) Sub-contracts with Contractors on the Approved List in the Waterworks category
If excavated materials are to be disposed of off Site, the specifying of particular disposal
areas in the Contract should be made. Reference should be made to WB TCs 2/93, 2/93B,
16/96, 4/98, 4/98A, ETWB TCWs 33/2002, 34/2002, 31/2004 and 19/2005, and the Interim
Guidance Note on Administration of Environmental Management and Pay for Safety and
Environment Scheme for Public Works Contracts promulgated under SETW’s memo ref.
(014G7-01-1) in ETWB(W) 517/91/01 dated 19.6.2006. The project engineer should estimate
the timing and the quantities of excavated materials (the secretary of the Marine Fill Committee
and the Public Fill Committee should be kept fully informed of anticipated volumes of excess
fill in accordance with WB TC 12/2000) and confirm with the managing office of the disposal
areas as to their availability. The PS should require the Contractor to dispose of excavated
materials at the specific locations and make provision for checking that he complies with this
requirement. The relevant BQ items should be worded accordingly. This procedure should
5.38 2006 Edition
also be followed when it is considered desirable for the Contractor to dispose of excavated
materials at a specific location irrespective of the quantities of excavated materials.
(Amendment No. 6/2007)
The Construction Waste Disposal Charging Scheme came into operation on 1 December
2005. A standard Note to Tenderers is given in SETW’s memo ref. (00W45-01-9) in ETWB
(W) 810/72/01 dated 21.11.2005.
For projects requiring excavation in rock or processing of hard inert Construction &
Demolition (C&D) material, consideration should be taken for setting up site crushers where it is
technically feasible. When it is proposed to include a site crusher in a contract, the Secretary of
the Public Fill Committee shall be advised and approval in principle from DCED shall be
obtained before tenders are invited. Approval from DEP is also required for installation and
operation of a site crusher in respect of the environmental requirements. Reference should be
made to WB TC 11/2002 for more details.
In every project where a site crusher is to be included, the following special conditions,
to be provided by DCED, shall be included in the tender documents:
(a) The permitted uses, and royalty rate if sales are permitted;
(b) If rock and hard inert C&D material may be imported to the site;
(c) The permitted duration for the operation of the site crusher and its regular
inspection by the Mines Division, CEDD;
5.39 2006 Edition
(d) The submission for approval of the details of the crushing plant and its dust
control systems; and
GCC Clause 86 stipulates that contractual disputes in all contracts can be resolved by
mediation in accordance with the Government of the Hong Kong Special Administrative Region
Construction Mediation Rules. Detailed guidelines are given in WB TC 4/99 and ETWB TCW
4/99A. Please also see S for W’s memo ref. WB (W) 250/32/72A dated 12.6.2002. If the
matter cannot be resolved by mediation, or if either the Employer or the Contractor does not
wish the matter to be referred to mediation, then either party may require the matter to be
referred to arbitration. A SCC as given in the Library of Standard Special Conditions of
Contract should be incorporated in the contract documents stating that place of arbitration shall
be in Hong Kong.
Environment, Transport and Works Bureau (ETWB) initiated a pilot scheme for
adopting Dispute Resolution Adviser (DRA) as an alternative dispute resolution for public
works in November 2004. Department should make enquiry to ETWB for adopting this
alternative dispute resolution. A full set of DRA documents is attached in SETW’s memo ref
(00E1C-0103) in ETWB(W) 506/00/01 dated 1.11.2004.
Contract provisions for specifying and paying for contract computer facilities are
given in ETWB TCW 12/2004. The cost of the contract computer facilities should not
exceed 1% of the estimated contract sum and should comply with the prevailing
Departmental Technical Specification (both Hardware Specification and Software
Specification). The proposal should be approved by an officer of D1 rank or above. The
Project Officer shall further seek the endorsement of the Departmental Computer Services
Unit if the proposal includes any one or all of the items described in paragraph 10 of the
ETWB TCW 12/2004.
However, owing to their small size and/or nature, some contracts may warrant changes to the
contractual provisions. Each works department will be the best judge of its own situation and
needs. Project engineers shall seek advice from their Departmental Safety and Environmental
Adviser and the agreement of the appropriate (D2 or above) officer for such changes.
(iii) Design and build contracts with estimated contract sums of $20M and above.
For works contracts and design and build contracts with estimated contract sums of
less than $20M and term contracts with total estimated expenditure of less than $50M, the
criterion to decide whether safety plans are required or not is whether dangerous situations are
anticipated by virtue of the site location or the operation involved in the construction work
within the scope of the contract. Departmental Safety and Environmental Advisers should be
consulted for advice on specific requirements.
All works contracts that are Bills of Quantities based and term contracts that are
Schedule of Rates based, and where safety plans are required, shall incorporate the Pay for
Safety and Environment Scheme (PFSES).
All capital works contracts including design and build contracts that are included in
PFSES, the contractual provisions on Site Safety Cycle given in ETWB TCW 30/2002 shall be
incorporated into the contract documents.
Departments shall observe the guidelines and procedures set out in ETWB TCW
13/2003 for obtaining any environmental permits (EPs) for Government projects and
proposals. Depending on the nature of project and the recommendations in the EIA reports,
project proponent may choose to apply for a single EP for a project or separate EPs for
5.41 2006 Edition
The standard clause in Clause 1.6.5, Appendix A of ETWB TCW 13/2003 shall be
included in the Particular Specification for works contracts where EP has been obtained by the
proponent for the works to safeguard against any unnecessary claims for extension of time and
additional costs from the Contractor due to application for a further EP or any subsequent
variation to the conditions of EP.
To ensure that the contractor has the full knowledge of the conditions of the EP, a copy
of the EP issued to the proponent shall be included in the Particular Specification to form part of
the tender documents and hence the contract. As part of the standard conditions of the EP, the
Contractor shall display the EP at the site throughout the construction period. The proponent
shall notify the Contractor any subsequent change or variation to the conditions of EP.
Where the requirements in ETWB TCW 13/2003 cannot be complied with, the
department responsible should:
(a) take action to critically review the results and assess the implications of the EIA
study (including the latest environment control conditions) as soon as it is
available; and
(b) if the tender documents have already been handed out, take action to immediately
inform all tenderers of the findings of the EIA study, so that they could take the
EIA findings into account before submitting their bids (SETW’s memo ref.
ETWB(B) 1552/662/CL SF(1) dated 3.12.2003 refers).
Circumstances may arise where it is desirable to fix the completion date (e.g. to tie in
with the opening of a school term) and hence the Contractor’s right to extensions of time for
inclement weather is deleted. Heads of departments may approve the deletion of GCC
Clause 50(1)(b)(i), (ii) and/or (iia), and submit details to the SETW for endorsement.
Tenders must not be invited until this endorsement has been received. The SCC in the
Library of SCC on ‘deletion of inclement weather’ shall be used as appropriate. Other than
for exceptional circumstances, a reasonable allowance for inclement weather shall be
included in the time for completion. What is reasonable will largely depend upon the nature
of the Works. In deciding whether or not to delete sub-clause (b)(ii) and/or (iia), the risk of
injury and/or damage to property must be considered. WB TC 26/98 promulgates the
procedures to be adopted where the Contractor’s right to extensions of time for inclement
weather is to be deleted.
Nevertheless, it should be noted that where the provision for extensions of time due to
inclement weather is deleted, Contractor’s entitlement to extensions of time in respect of
inclement weather which occurs after the expiry of the time originally prescribed in the
Contract for completion of the Works, but before the period of culpable delay, is not deleted.
5.42 2006 Edition
The time required for completion of time-critical projects should be critically assessed
prior to the invitation of tenders so as to ensure that sufficient time is allowed for completion of
the works. Furthermore, the implications and potential cost of including or deleting those
contract provisions (such as provisions for granting extension of time for inclement weather)
which could adversely affect the completion date of the works as stated in the contract
documents so as to avoid the need for negotiating a supplementary agreement with the
Contractor.
For time-critical projects with multiple works contracts, sufficient float time should be
allowed between the works contracts so as to minimize the risk of the knock-on effect of delay
in one contract on other contract(s).
If the projects require input from users on their design requirements, the departments
should:
(a) Always require users to finalise their design requirements before an agreed
cut-off date so as to avoid any design changes at a later stage; and
(b) Obtain the users’ explicit agreement to essential design requirements prior to the
letting of contracts so as to avoid delays and contractual claims arising from
changes in users’ requirements.
Issues relating to any conditions of a land grant, which could have an effect on the works
of the contracts, should be resolved with the Director of Lands before letting of the contracts.
Departments should take prompt action to assess the implications of such conditions before a
land grant is finalized.
For time critical contracts and/or large-scale contracts, and where the contract conditions
impose a substantially higher degree of risk than normal on the Contractor, implement measures
(such as the use of parent company guarantee and performance bond) should be considered to
minimize the risk of contract forfeiture. The contract conditions for the provision of parent
company guarantee and performance bond to ensure the required contract instruments are
submitted by the Contractor within the stipulated time limits should be strictly implemented (see
WB TCs 10/97 & 10/97A).
For large-scale works projects, the contract payment schedules should be critically
devised to ensure that progress payments are made, as far as possible, in line with the actual
progress of works.
5.43 2006 Edition
Some works under a works contract are to be carried out within the restricted hours.
Experience has shown that during the construction stage, additional locations of the site were
required for works to be carried out under restricted hours and have led to claims. Therefore,
the department concerned should, with a view to minimizing claims for EOT and prolongation
cost arising from works carried out within the restricted hours:
(a) Strengthen consultation with the Transport Department/Hong Kong Police Force
to ensure that all locations, which require works to be carried out within the
restricted hours, are identified before tendering; and
The project office which requests for works areas should note that any request for
additional works area after award of a contract will be subject to payment of rent by the
Contractor and any request for extension of works area should be provided with justifications, or
DLO may charge a rental or may refuse the request.
For contracts involving tunnel works, the project office shall include suitable clauses in
the PS and, in the case of design and build contracts, the Employer’s Requirements (ER) to
enable effective implementation of the ETWB TCW 15/2005. Where the GEO raises major
geotechnical concerns on the public safety aspects of the geotechnical design or the related PS or
the ER clauses, the project office must resolve such concerns before tenders are invited.
For future public-works projects, if the design requires large quantities of natural
boulders/cobbles/pebbles that are not readily available in the market, the project office should
consider stipulating in the contract documents clauses requiring the Contractor to submit
5.44 2006 Edition
documentary proof that extraction or production of these materials by the material suppliers
will not cause unacceptable environmental impacts (such as reports from independent
environmental consultants) and also proof of the legality of the source of materials. For
natural boulders/cobbles/pebbles that are to be obtained outside Hong Kong, the Contract
should require the Contractor to submit export permits from the relevant authorities. These
permits should have been verified by notary(ies) public of the originating place(s), where
applicable, in order to demonstrate that such materials are supplied legally and without
causing unacceptable environmental impacts to its source. The Engineer should be
empowered to seek further information from the Contractor in case he has any doubt.
Project offices and consultants please refer to the following ETWB group intranet portal
for the practice note which promulgates the guidelines and good practice for the implementation
of non-contractual partnering in public works contracts: -
http://portal.etwgi.etwb.hksarg/index.aspx?id=35
If the works under the Contract or any alternative design proposed by the Contractor
involve fabrication of construction components outside Hong Kong, the project office
should either arrange for the resident site staff of in-house projects or consultant-managed
projects to supervise and inspect the works in the fabrication area or require the Contractor
to employ an independent inspection agent (IIA)# to control the quality of the components
fabricated in the fabrication area. In this situation, the project office should determine the
most appropriate site supervision requirements, inspection arrangement and warranty from
the manufacturer, and should stipulate them in the contract documents. If an IIA is
employed by the Contractor to supervise and inspect the works in the fabrication area, the
project office should specify in the contract documents the qualification requirements of
the IIA and, where practicable, the IIA’s staff assigned for the supervision and inspection.
If an IIA is required under the Contract, apart from the qualification requirements of
the IIA and, where practicable, the IIA’s staff assigned for the supervision and inspection,
the project office shall also stipulate in the contract documents the following requirements:
(i) the qualifications of the IIA and the IIA’s staff shall be submitted to the
Engineer for approval;
#
Note: project officer is to decide the scope and extent of the IIA services
5.45 2006 Edition
(ii) the Contractor shall require the IIA and his staff to submit declaration of no
conflict of interest with the supplier/manufacturer/Contractor to the Employer
upon employment of the IIA. The Contractor shall also ensure that the IIA
and his staff declare any conflict of interest with the
supplier/manufacturer/Contractor to the Employer via the Engineer as soon as
such a conflict comes to the knowledge of the IIA, his staff or the Contractor.
In the event that such conflict or potential conflict between the
supplier/manufacturer/Contractor arises, the Contractor shall forthwith take
such reasonable measures as are necessary to mitigate as far as possible or
remove the conflict or potential conflict so disclosed;
(iii) the Contractor shall require the IIA to submit to the Engineer for approval a
site supervision and inspection plan for the fabrication works as well as any
subsequent changes, and to certify compliance with the site supervision and
inspection plan;
(iv) the Contractor shall caution the IIA and his staff not to accept lavish
entertainment during supervision and inspection;
(v) the Contractor shall not allow the IIA and his staff to accept any advantage
from suppliers, manufacturers and/or objects of supervision/inspection;
(vi) the Contractor shall require the IIA to submit to the Contractor and the
Engineer simultaneously site records and reports on any non-compliance with
the Contract’s requirements;
(vii) the Contractor shall require the IIA to submit periodic statistical returns (e.g.
returns on the number and periods of supervision and inspections conducted
by the IIA and his staff and the works covered in these supervision and
inspections) for management information; and
(viii) the Contractor shall require the IIA to certify to the Employer that the
fabrication works have been constructed in accordance with the Contract’s
requirements.
Notwithstanding the above requirements stipulated, the employment of the IIA shall not
relieve the Contractor of any duties or liabilities under the Contract. Guidelines to assist
project offices in controlling the quality of fabrication of construction components outside
Hong Kong are given in sub-section 21.21 of PAH Chapter 7.
WB TCs 17/95 and 17/95A promulgate that, wherever it is appropriate and feasible, civil
engineering works contracts shall be tendered lump sum, rather than the usual remeasurement
basis. As defined by the Circular, a lump sum contract means:
A contract where the quantities are substantially measured firm and the final price to be
paid is ascertained by adding to/deducting from the contractor’s accepted tender price the value
of variations and other specified items (e.g. provisional quantities and contingency items).
There are SCT, SCC and amendments to SMM to suit this type of lump sum contract
with firm BQ. For details, see WB TCs 17/95 and 17/95A.
5.47 2006 Edition
11. MISCELLANEOUS
Contract numbers will be allocated by the headquarters of the office managing the
Contract, notwithstanding that funds for the contract may be under the control of another
office. For CEDD, each development office allocates its own contract numbers.
Information that is relevant to the submission of tenders and contract award, but not
considered to be part of the tender documents, should be provided in the form of Notes to
Tenderers. There should be a remark on the Notes that they do not form part of the Contract.
The Notes should be bound separately from the tender documents and issued to tenderers at
the same time as tender documents.
Commonly used clauses to be included in the Notes to Tenderers for works contracts
other than design and build contracts are given in ETWB TCW 26/2004. The project officer
may use the clauses promulgated under ETWB TCW 26/2004 selectively since not every item
of the provisions is applicable to a particular contract.
The Notes to Tenderers promulgated under ETWB TCW 26/2004 has been uploaded to
the ETWB website under standard contract documents in the publications section and they will
be updated from time to time when new technical circulars are promulgated which may affect
the library content.
The tender documents should be bound together into booklets with a front cover sheet
showing the title and number of the contract and listing the documents contained therein. The
documents will be in accordance with the list in the Conditions of Tender except that the
Articles of Agreement, the GCC, Nominated Sub-contract Conditions, the GS, the SMM, the
Construction Site Safety Manual (Chapter 3), the Hong Kong International Arbitration Centre
Domestic Arbitration Rules need not be bound in where standard forms/documents are used.
All pages of the tender documents should be numbered.
Tender drawings may be bound together in a separate folder, in which case the folder
should have a cover sheet listing the tender drawings (see also Chapter 6).
The electronic version of tender documents for works contracts should be disseminated
in the form of “Electronic Dissemination Package” (EDP) in accordance with the manner and
format contained in Section 3 of the Dissemination Procedures under ETWB TCW 11/2005
(Appendix 1).
5.48 2006 Edition
12. REFERENCES
WB TC 17/95 & The Use of Lump Sum Bills of Quantities Contracts for Civil
WB TC 17/95A Engineering Works
WB TC 10/97 & Use of Performance Bonds Security and Retention Moneys and
WB TC 10/97A Standard Form of Bond
WB TC 4/98 & Use of Public Fill in Reclamation and Earth Filling Projects
WB TC 4/98A
ETWB TCW 29/2002 & Geotechnical Control for Slopes and Retaining Walls
ETWB TCW 29/2002A
ETWB TCW 30/2002 Implementation of Site Safety Cycle and Provision of Welfare
Facilities for Workers at Construction Sites
ETWB TCW 54/2002 Guidance on Execution of Public Works Contracts under Seal
ETWB TCW 2/2003, Regulating Action where a Serious Incident has or Site Safety or
ETWB TCW 2/2003A, Environmental Offences have occurred on a Construction Site
ETWB TCW 2/2003B &
ETWB TCW 2/2003C
ETWB TCW 13/2003 & Guidelines and Procedures for Environmental Impact
ETWB TCW 13/2003A Assessment of Government Projects and Proposals
ETWB TCW 21/2003 Contract Price Fluctuation System for Civil Engineering and
Building Contracts
ETWB TCW 22/2003 & Additional Measures to Improve Site Cleanliness and Control
ETWB TCW 22/2003A Mosquito Breeding on Construction Sites
ETWB TCW 28/2003 Protection of Harbour Area Treatment Scheme Stage I Sewerage
Tunnel
ETWB TCW 24/2004 Specification Facilitating the Use of Concrete Paving Units
Made of Recycled Aggregates
ETWB TCW 29/2004 Registration of Old and Valuable Trees, and Guidelines for their
Preservation
ETWB TCW 31/2004 Trip-ticket System for Disposal of Construction and Demolition
Materials
ETWB TCW 33/2004 Tender Procedures for Procurement governed by the Agreement
on Government Procurement of the World Trade Organization
ETWB TCW 2/2005 Capital Works or Maintenance Works (including Tree Planting)
within or Adjacent to the Kowloon-Canton Railway (Hong
Kong) Section, Tsim Sha Tsui Extension and Ma On Shan Rail
Chapters 3 and 12 of the Construction Site Safety Manual (version November 2000)
(Applicable to capital works contracts other than design and build contracts)
................................ DEPARTMENT
(Title of Contract)
FORM OF TENDER
NOTES:
(2) If the tenderer is a sole proprietorship or a partnership, the name(s) and residential
address(es) of the sole proprietor or all the partners shall be given in the spaces provided
below.
(3) In all cases, the tenderer must give the number and the expiry date of the business
registration certificate here:
Number :
Expiry Date :
1
To: The Chairman,
Central Tender Board,
Central Government Offices (East Wing),
Hong Kong.
Having inspected the Site, examined the Drawings, General Conditions of Contract and
Special Conditions of Contract (hereinafter referred to as “the said Conditions”), Specification
and 2Bills of Quantities for the execution of the Works as defined in the Contract, I/we offer to
construct, complete and maintain the whole of the said Works in conformity with the said
Conditions, Drawings, Specification 3and Bills of Quantities for the sum of
Dollars ............................................................... ($...............) or such sum as may be ascertained
in accordance with the said Conditions, Drawings, Specification and Bills of Quantities.
5.54 2006 Edition
FORM OF TENDER – P. 2
4
2. If my/our Tender is accepted I/we will when required,
#(a) deposit with the Director of Accounting Services, the Government of the Hong
Kong Special Administrative Region, as security for the due performance of the
Contract a sum of $........, such deposited sum to be returned to me/us in
accordance with the said Conditions.
#(b) with the approval of the Employer obtain the guarantee of a Bank or Insurance
Company [to be approved by the Employer] to be jointly and severally bound
with me/us in a sum of $.…... for the due performance of the Contract under the
terms of a Bond in accordance with the said Conditions.
3. I/We agree to abide by this Tender for the period of 590 days from the date of expiry
fixed for receiving the same and it shall remain binding upon me/us and may be accepted at any
time before the expiration of that period.
4. Unless and until the Articles of Agreement is prepared and executed this Tender together
with the written acceptance thereof by the Employer subject to the provisions of clause 3 hereof
shall constitute a binding Contract between us.
5. I/We understand that the Employer reserves the right to negotiate with any tenderer
about the term of the offer and is not bound to accept any tender irrespective of whether the
tender is the lowest offer or, where the assessment of the tenders is based on a marking scheme
or formula approach, the tender is with the highest overall mark.
NOTES:
1. Where the tenders are to be submitted to a tender board other than the Central Tender
Board, type in the name and the address of the tender board in lieu of that of the Central
Tender Board.
2. All references to Bills of Quantities may need to be suitably adjusted where some other
forms are used.
3. Replace “and Bills of Quantities” with “, Bills of Quantities and the technical
resources and technical proposals submitted in accordance with Clause 4(1)(d) of the
General Conditions of Tender” when the tender adopts a marking scheme for use in
tender evaluation.
5. Normally 90 days.
FORM OF TENDER – P. 3
Name ...........................................................................................................................................
Signature .....................................................................................................................................
......................................................................................................................................................
......................................................................................................................................................
......................................................................................................................................................
......................................................................................................................................................
......................................................................................................................................................
......................................................................................................................................................
......................................................................................................................................................
Date .............................................................................................................................................
Occupation .....................………………………………….......................................................
......................................................................................................................................................
......................................................................................................................................................
......................................................................................................................................................
......................................................................................................................................................
5.56 2006 Edition
FORM OF TENDER – P. 4
Amount .......................................................................................................................................
Date .............................................................................................................................................
5.57 2006 Edition
Clause No.
[For use where the Works are not divided into Section]
For the Works HK$[..............* (Y1 + …. Yn)+..............]3 per day
5.58 2006 Edition
*SCC __ Time, commencing from and including the date for commencement of
the Works notified by the Engineer in accordance with GCC Clause 47,
within which the Section Subject to Excision may be ordered .......... days
*SCC __ Minimum amount of liquidated damages for the *Works/Sections $ …. per day
*SCC __ Sum4 payable to the Employer in the event that Old and
Valuable Tree No. __ dies or becomes moribund $…………
*SCC __ Period for Aftercare to Old and Valuable Trees (*Tree/Trees No. __)5 ……months
Maintenance Period for Aftercare to Old and Valuable Trees5 ……months
NOTES:
2
Refer to ETWB TCW No. 4/2003 for guidance to include appropriate provisions in the
Appendix to the Form of Tender where there is no minimum LD’s and where there is
minimum LD’s
3
Choose from either (a) or (b) below an appropriate footnote depending on whether or not there
is minimum LD’s for the Works/Sections and, where the works involve excavation requiring
the application of excavation permits, add footnote (c):
“The value of the formula within the square brackets shall be taken as zero for the purpose of
computation of the daily rate of liquidated damages if and when the sum is worked out to be a
negative value by substituting Y1, …Yn with its corresponding value in the priced Bills of
Quantities.”
“The value of the formula within the square brackets shall be taken as HK$ [the minimum
amount of LD’s for the Works or, as the case may be, the relevant Section] per day for the
purpose of computation of the daily rate of liquidated damages if and when the sum is worked
out to be less than HK$ [the minimum amount of LD’s for the Works or, as the case may be,
the relevant Section] per day by substituting each of Y1, ....Yn with its corresponding value in
the priced Bills of Quantities.”
“In computing the above liquidated damages, the Employer has not taken into account the
Employer’s liability for fees including economic cost under the Land (Miscellaneous
Provisions) Ordinance, Cap. 28 (“the Ordinance”) for any extension in respect of a permit
referred to in Sections 10A(3) and 10D(4) of the Ordinance.”
4
Separate sum shall be applied to each tree if more than one Old and Valuable Tree is
involved. The sum for each Old and Valuable Tree shall be the genuine pre-tender
estimate of that particular tree.
5
The Period for Aftercare to Old and Valuable Trees together with its subsequent Maintenance
Period should preferably end on the same date as the Maintenance Period for the Works, or if
there is more than one Maintenance Period, on the same date as the last Maintenance Period.
5.60 2006 Edition
The maintenance periods for the Works and for Establishment Works are normally 12
months and 1 month respectively but may vary depending on the type of work. If
separate Sections of Works are provided for preservation and protection of existing trees,
and where required, the registered Old and Valuable Trees, the maintenance periods are
to be determined by the project office and would usually be 1 month.
(2) Actions of the Engineer subject to the Employer’s right of objection and direction
Clause 2 of the GCC 1999 Edition provides that the Employer may impose constraints
on the powers of the Engineer. According to existing policy, the Engineer shall
obtain the agreement of the Employer before ordering variation in excess of $300,000.
The Engineer may however commit expenditure other than in respect of claims if
such commitment is less than $300,000. This provision shall be set out in the
Appendix to the Form of Tender.
This provision is not usually required for typical works contracts but shall be included
where the circumstances as stated in Para. 2 of WB TC No. 10/97 warrant. If bond or
cash security is required, refer to Appendix A of WB TC No. 10/97 for such amount
(rounded off to the nearest $1000) with respect to the estimated contract value.
Appendix B of WB TC No. 10/97A gives the standard form of performance bond to be
incorporated in the tender documents if required.
(4) Time after acceptance of Tender within which the date for commencement of the Works
shall occur
Enter a specific number of days, generally between 7 and 42 days unless there are
reasons for specifying a different period.
This should be based on a realistic estimate of the normal period required for
construction of the Works or Section of the Works (including ‘Section subject to
Excision’), having regard to the date when completion of the project is required,
particularly with respect to the programme of other related projects.
See ETWB TCW 4/2003 for detailed guidelines on liquidated damages. The liquidated
damages for ‘Section subject to Excision’ shall also be included.
Refer to Appendix A of WB TC 10/97 for the rate of retention with respect to the
estimated contract value. Whenever practicable, the percentage used for the calculation
of Retention Money for Nominated Sub-contracts is to be the same as that used for the
main contract.
Refer to Appendix A of WB TC 10/97 for the limit of Retention Money (rounded off to
the nearest $1000) with respect to the estimated contract value.
According to LWB TC 7/87, the minimum amount of interim certificate for contracts
with an estimated contract sum of $2,000,000 or more is to be:
Minimum amount of
Estimated Contract Sum interim certificate
For contracts with an estimated contract sum of less than $2,000,000, the minimum
amount of interim certificate should be:
where F is a factor normally ranging between 0.6 and 0.8 and shall be decided by the
officer preparing the tender documents to suit the type and timing of the proposed work.
However, the minimum amount shall not exceed $50,000.
The minimum amount of third party insurance should normally be assessed following a
risk based approach given in ETWB TCW 7/2005. For works project with a cost
estimate in excess of $200M, a systematic risk management (SRM) promulgated in
5.62 2006 Edition
ETWB TCW 6/2005 shall be adopted. For works project at a cost less than $200M,
works departments should adopt an approach of risk assessment similar to the SRM.
(11) Works involving preservation and protection of existing tress and Old and Valuable
Trees
The guidelines regarding the preservation and protection of existing trees, and where
required, the protection and maintenance of registered Old and Valuable Trees can be
found in ETWB TCW No. 29/2004 and the Cyber Green Manual promulgated in
ETWB TCW No. 11/2004.
5.63 2006 Edition
........................ DEPARTMENT
(Title of Contract)
This Schedule must be completed in accordance with the Notes overleaf and submitted with the
Tender.
Signature: ___________________________
Company: ___________________________
Date: ___________________________
5.64 2006 Edition
Notes:
(*) Column (3) to be filled in by the tenderer in whole number within the limits set in
columns (1) and (2)
(†) Column (4) to be completed by the Engineer Designate prior to executing the Articles of
Agreement.
5.65 2006 Edition
The limits set in columns (1) and (2) of the Schedule of Proportions are to suit the type
of proposed contract, e.g. for a labour intensive contract the limits set for Labour will be
high. It is necessary to ensure that wide gaps between minimum and maximum levels
are not unintentionally provided. As a general check on the reasonableness of the range
of maximum and minimum percentages to be used it is suggested that, as a general rule,
the total of column (1) should not be less than 135 or more than 145 and that the total of
column (2) should not be less than 60 or more than 70.
The Director of Audit has recommended that in order to reduce the possibility of
speculation by contractors, the use of more than one Schedule of Proportions should be
considered, especially for contracts with two or more diverse elements where a single
Schedule of Proportions may not produce an equitable method of reimbursement of price
fluctuations. An example of the use of two Schedules of Proportions would be the case
of site formation works which would be followed by building works. In view of the
diverse nature of the two types of work, two schedules of proportions should be
considered. Another example would be a road construction contract with extensive
earthworks and bridgework but where bituminous pavement works would not be carried
out until the last few months of the contract period. In this case the bituminous
pavement works would be billed alone in one section of the BQ and a separate Schedule
of Proportions provided.
Where the use of more than one Schedule of Proportions is warranted, it will be
necessary to ensure that the schedules apply to specified bills of the BQ and that
appropriate Special Conditions of Contract and Special Conditions of Tender are
provided.
5.66 2006 Edition
................................ DEPARTMENT
(Title of Contract)
BILLS OF QUANTITIES
GRAND SUMMARY
1 Preliminaries
2 ..
.. ..
Contingency Sum
Grand Total
Adjustment Item
*Addition/*Deduction
Tender Sum
Date: ……………………………………………………………….
+ the Bill on Site Safety and Environmental Management is to be provided for all appropriate
tenders required under WB TC 32/99, 30/2000, ETWB TCW 19/2005 and the Interim
Guidance Note on Administration of Environmental Management and Pay for Safety and
Environment Scheme for Public Works Contracts promulgated under SETW’s memo ref.
(014G7-01-1) in ETWB(W) 517/91/01 dated 19.6.2006
(Amendment No. 6/2007)