Shanghai: Tower
Shanghai: Tower
Shanghai: Tower
Shanghai Tower
The Shanghai Tower, a 632 m high building, is the highest one in To control volume variations due to release of hydration heat,
China and the second highest in the world. The foundation raft of guidelines such as the Code for Construction of Mass Concrete
(GB50496-2009) [1] and others provisions (EC 2) [2] give limi-
high-rise buildings is usually a huge mat with cast-in-place mass tations on pouring of concrete, for example, a maximum volume
concrete. It is a structural member that transfers loads from the build- of poured concrete per unit time and a minimum interval
ing to the foundation base. To keep the integrity of a massive raft is a between pouring of each batch. Research interests are raised
worldwide to explore measures to avoid thermal cracks in mass
key issue both in design and construction phase. The key point to
concrete. Accordingly, many construction approaches aimed at
obtain a monolithic foundation raft is via continuous pouring of decreasing hydration heat and controling of heat accumulation
concrete without providing construction joints. This would definitely in a massive raft have been developed in practice. For example,
the pre-installed pipe system method was applied in the 13 500 m3
invoke a problem on how to mitigate hydration heat accumulated in
mat foundation of Jinmao Tower building [3] and layered
mass concrete during pouring of concrete. Preventing thermal cracks construction in the 9 m thick foundation raft of the World
is critical for large concrete members and this project presentation Financial Center [4]. This method increases project costs and
complicates the construction procedure. Some projects such as
shows how is dealt with this issue in the Shanghai Tower foundation.
Petronas Towers in Kuala Lumpur, Malaysia, were executed by
continuous pouring in 54 hours [5]. Excel Warehouse Project
[6] and Abu Dhabi’s Landmark Tower [7] also used this method. mega column
For the foundation of Shanghai Tower, more than 60,000 m3 of core tube
concrete had to be poured continuously, with no construction foundation slab
joints or post-cooling measures, for high-speed construction
and with high-quality impermeable concrete. To avoid early
age cracks, special measures such as mix design considering 1 1
hydration heat reduction and a pouring organization suitable
for continuous pouring were taken.
Location 3
Located in the central area of Lujiazui financial district in Shang- 123 000
6000
1600
1600
commercial and shopping mall, a conference hall and an exhibi-
tion hall, as well as leisure tourism and sightseeing platform. It 103 500
consists of a tower building and a surrounding podium building.
With the footprint of the complex covering an area of more than
30 000 m2, the total useful area of the complex is about 570 000 m2.
The tower building has 121 floors above the ground, and below Mix Proportions
ground is 5 storey basement. The main issue during the mix design is to minimize the
hydration heat of concrete. Therefore, raw materials which
Foundation raft of main building assure that the low-heat concrete is obtained, are used.
The foundation raft slab of the main building has a disk-like Locally produced cement with hydration heat of 220 kJ/kg
circular shape with a diameter of 123.0 m (fig. 3a). Along the and 289 kJ/kg at 3 and 7 days, respectively, is chosen. Beside
radial direction from the center to the perimeter, the thickness Ordinary Portland cement, fly ash and slag, as supplementary
of the slab changes from 6.0 m at the center to 1.60 m at the cementitious materials, are used as a binder. This leads to a
edge (fig. 3b). Special measures with respect to mix design and decreases of the hydration heat by 22.3% at 3 days and 13.5%
the organization of pouring were taken. The key challenge was at 7 days compared to the cement without addition of supple-
to ensure continuous pouring with the limited thermal issues. mentary cementitious materials. A polycarboxylic acid
3 2017 87
thema
4 Temperature comparisons (measured and simulated in the core of the element)
5 Strength developing curve
6 The concrete pouring plan, pouring area and pump arrangement: (a) from top
and (b) from side
80
70 measured
simulated
70
60
temperature(ºC)
50 60
strength(mpa)
No.1
No.2
40 50 No.3
No.4
30 No.5
40 No.6
20
30
7 14 21 28 35 42 49 56 63 70 77 84 91
0 200 400 600 800 1000
4 time(h) 5 age(d)
Table 1 Mix design of concrete C50 (kg/m3) figure 5. The strength all passes 50 Mpa at 28th day, so the
W/B water cement slag power fly ash sand gravel additional-agent concrete meets performance requirements.
P.O.42.5 S95 III middle 5~25 poly carboxylic acid
0.36 160 240 120 80 760 1030 4.4
Pouring Organization
Concrete supply and transportation is the basic issue of the
60 000 m3 pouring. The main principle was to fulfill the
superplasticizer is added to decrease the water - cement ratio. pouring work within 60 h. Careful calculation on concrete
The addition of superplasticizer resulted also in the reduction supply and transportation is combined with extensive project
of the hydration heat by 37.3% and 24.6% at 3 and 7 days, experience. Six pre-mixing plants are chosen with the total
respectively, in comparison to those without superplasticizer. supply capacity of 1250 m3/h. 355 mixing trucks with an
average size of 8 m3 were in charge of the transportation.
The final mix (see table 1) should also comply with the follow-
ing requirements: the 28 days strength is not below 50 MPa and Central flowering pouring
the slump is around 180 mm (based on pumping requirement). Pouring usually takes place from one side to another side in a
For the purpose of checking the thermal performance, a traditional pouring method. For this huge mass concrete
6.0 m × 8.0 m × 3.0 m test block is poured prior to casting of member the poring distance was too long. Therefore, a new
the foundation with the same mix proportions. Temperature concrete pouring method, called ‘central flowering pouring’, is
monitoring is carried out simultaneously. The temperatures used in this project. Unlike with the traditional pouring
reach the peak values within 48~72 h and the peak value does method, pouring of the concrete begins at the center and
not overpass 65°C. The designed mix proved to be suitable for concrete flows to the surrounding area.
the construction and it was further used in the actual project.
Mobile pumps have flexibility and high pouring capacity, but
Temperature monitoring is carried out on the spot during the its pouring range is limited by its arm. Fixed pumps can over-
project. Temperature development is also simulated, and come this disadvantage. Two kinds of mobile pumps were used
temperature comparisons are shown in figure 4. The tempera- i.e. a 56 m long arm concrete pump and a 48 m long arm one.
ture-time curves resemble except for peak values. The differ- As the maximum pouring distance is 61.5 m long (radius of
ence between simulated and measured temperature is 2°C. circular mat), the mobile pumps cannot reach the central area.
Strength tests were performed on concrete used for real Therefore, fixed pumps are in charge of that area. Based on
pouring. The average compressive strength of concrete, their maximum pouring length, the whole slab is divided into
obtained from each plant for foundation pouring is shown in three parts in the radial direction. The three areas in horizontal
ous soil digging platforms. Other pumps are arranged along the
edge of the foundation pit (fig. 6a). Based on experience and i : flowing slope
the actual situation, six fixed pumps are used for the pouring r: flowing radius
i =1:12
work of area 1. The theoretical pouring capacity of the three
h2
types of pumps is 40 m3/h (fixed pump), 80~100 m3/h (56 m
mobile pump) and 60~80 m3/h (48 m mobile pump) respec-
h1
tively. The average pouring speed should not be lower than
1000 m3/h. Therefore, eight 48 m-long arm pumps are chosen. r2 r1
Vs = Q1 ∙ N1 + Q2 ∙ N2 + Q3 ∙ N3 = 40 ∙ 6 + 80 ∙ 4 + 60 ∙ 8 = 1040 m3/h
In other words, the 60 000 m³ of concrete can be poured in
60 hours theoretically under such pump arrangement. ● REFERENCES