file TA send (file chị dùng giảng bài)
file TA send (file chị dùng giảng bài)
file TA send (file chị dùng giảng bài)
LAYOUT DECISION
Example 1: Tailwind, Inc., produces high-quality but expensive training shoes for
runners. The Tailwind shoe, which sells for $210, contains both gas- and liquid-filled
compartments to provide more stability and better protection against knee, foot, and
back injuries. Manufacturing the shoes requires 10 separate tasks. There are 400
minutes available for manufacturing the shoes in the plant each day. Daily demand is 60.
The information for the tasks is as follows the below table.
a) Draw the precedence diagram.
b) Assign tasks to the minimum feasible number of workstations
according to the “ranked positional weight” decision rule.
c) What is the efficiency of the process you completed in (b)?
d) What is the idle time per cycle?
Task Performance time (min) Task must follow task listed below
A 1 _
B 3 A
C 2 B
D 4 B
E 1 C, D
F 3 A
G 2 F
H 5 G
I 1 E, H
J 3 I
a)
Assign tasks to the minimum feasible number of workstations according to the “ranked
positional weight” decision rule
Workstation task time time left
(sec) (sec)
Workstation 1 A 1 5.67
Cycle time = 6.67 sec B 3 2.67
C 2 0.67
Workstation 2 F 3 3.67
Cycle time = 6.67 sec G 2 1.67
Workstation 3 D 4 2.67
Cycle time = 6.67 sec E 1 1.67
Workstation 4 H 5 1.67
Cycle time = 6.67 sec I 1 0.67
Workstation 5 J 3 3.67
Cycle time = 6.67 sec
Example 2: The Action Toy Company has decided to manufacture a new train set, the
production of which is broken into six steps. The demand for the train is 4,800 units per
40-hour work-week:
A 20 None
B 30 A
C 15 A
D 15 A
E 10 B, C
F 30 D, E
a)
b) The cycle time : (40x3600)/4800 = 30 seconds/unit
c) Total task time 20+30+15+15+10+30 = 120 seconds
Theoretical minimum number of workstations : 120/30 = 4 workstations
d) Assign tasks to workstations by using Most of following task rule
1. ABC ANALYSIS
Example:
Item stock Annual volume Unit
number units cost ($)
P1 1,000 90
P2 500 154
P3 1,550 17
P4 350 42.86
P5 1,000 12.5
P6 600 14.17
P7 2,000 .60
P8 100 8.5
P9 1,200 .42
D = 8000 units/year
H = $3 / order
S = $30 / order
❖ Reorder point:
● ROP = d x L = Demand per day x Lead time in days
● Reorder point with Safety stock: ROP = d x L + Safety stock
● Safety stock = Z x σ x Că n L - σ : standard deviation (Variance)
Example 1: Southeastern Bell stocks a certain switch connector at its central warehouse
for supplying field service offices. The yearly demand for these connectors is 15,000
units. Southeastern estimates its annual holding cost for this item to be $25 per unit. The
cost to place and process an order from the supplier is $75. The company operates 300
days per year, and the lead time to receive an order from the supplier is 2 working days.
a) Find the economic order quantity.
b) Find the annual holding costs.
c) Find the annual ordering costs.
d) What is the reorder point?
Example 2: The daily demand for 520 flat-screen TVs at Sarah’s Discount Emporium is
a standard deviation of 2 units. The lead time for receiving a shipment of new TVs is 10
days and is fairly constant. Determine the reorder point and safety stock for a 95%
service level.
a)
Unit price: P = $350/ unit
Holding cost: H $35/unit/year
Ordering cost: S= $120/order
Demand per month: 400 units per month => Annual demand: D = 400 x 12 -
4.800 unit/year
Optimal order quantity: EOQ = 181.42 units = 181 units / order
Total cost (per year) = Annual setup cost + Annual holding cost +
Purchase cost (Product cost) = SD/Q + HQ/2 + PxD
● With EOQ = 181 units per order, Price per unit is $325:
TC = SD/Q + HQ/2 + PxD = (120x4800)/181 + (35x181)/2 + 325x4800
- $ 1.566.350 per year
● If the company orders 200 units per an order, the unit price is $300/unit:
TC = … = (120x4800)/200 + (35x200)/2 + 300x4800 = $ 1.446.380 per year
● If the company orders 99 units per an order, the unit price is $350 unit:
TC = ... = (120x4800)/99 + (35x99)/2 + 350x4800 = $1.786.550 per year
Hence, the minimum annual cost is $ 1.446.380 per year with the optimal order
quantity is 200 units per order .
b) New holding cost : 10% x price per unit = 0.1P => H =0.1
Optimal order quantity: EOQ = 181.42 units = 181 units / order
● With EOQ = 181 units per order, Price per unit is $325:
TC = SD/Q + HQ/2 + PxD = (120x4800)/181 + (0.1x325x181)/2 + 325x4800
- $ 1.566.349.82 per year
● If the company orders 200 units per an order, the unit price is $300/unit:
TC = … = (120x4800)/200 + (0.1x300x200)/2 + 300x4800 = $ 1.445.880 per
year
● If the company orders 99 units per an order, the unit price is $350 unit:
TC = ... = (120x4800)/99 + (0.1x350x99)/2 + 350x4800 = $1.687.550 per year
Hence, the minimum annual cost is $ 1.445.880 per year with the optimal order
quantity is 200 units per order .
Example 2: David Rivera Optical has determined that its reorder point for eyeglass
frames is 50 (d * L) units. Its carrying cost per frame per year is $5, and stockout (or lost
sale) cost is $40 per frame. The store has experienced the following probability
distribution for inventory demand during the lead time (reorder period). The optimum
number of orders per year is six. How much safety stock should David Rivera keep on
hand?
30 .2
40 .2
50 .3
60 .2
70 .1
CHAP 14. MATERIAL REQUIREMENT PLANNING (MRP)
I. Product structure:
Example: Speaker Kit, Inc., packages high-fidelity components for mail order.
Components for the top-of-the-line speaker kit, “Awesome” (A), include 2 Bs and 3 Cs.
Each B consists of 2 Ds and 2 Es. Each C has 2 Fs and 2 Es. Each F includes 2 Ds and 1 G.
It is an awesome sound system. Identify the number of units of each item required to
satisfy demand for a new order of 50 Awesome speaker kits, draw product structure
and level.
Component A B C D E F G
Period 1 2 3 4 5 6 7 8 9 10 11 12
Gross 30 40 30 70 20 10 80 50
requirem
ent
Period 1 2 3 4 5 6 7 8 9 10 11 12
Gross
30 40 30 70 20 10 80 50
requirement
Schedule
0 0 0 0 0 0 0 0
receipts
Projected on
40 10 10 0 0 0 0 0 0 0
hand - 40
Net
0 30 30 70 20 10 80 50
requirements
Planned order
30 30 70 20 10 80 50
receipts
Planned order
30 30 70 20 10 80 50
releases
2. Lot for size (EOQ)
Period 1 2 3 4 5 6 7 8 9 10 11 12
Gross
30 40 30 70 20 10 80 50
requirement
Schedule
0 0 0 0 0 0 0 0 0
receipts
Projected on
40 10 10 27 27 54 41 21 21 11 45 45 52
hand - 40
Net
0 30 3 16 0 0 69 5
requirements
Planned order
57 57 57 114 57
receipts
Planned order
57 57 57 114 57
releases
POQ = EOQ / average (weekly) usage = 57/(330/12) = 2.1 weeks → POQ = 3 weeks
Period 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirement 30 40 30 70 20 10 80 50
Schedule receipts 0
Projected on hand | 40 40 10 10 30 30 0 20 0 0 80 0 0
Net requirements 0 30 0 70 0 10 0 50
Planned order receipts 60 90 90 50
Planned order releases 60 90 90 50
CHAP 15. SCHEDULING FOR THE SHORT-TERM
I. SEQUENCING JOBS
1. Priority rules:
- First come first serve
- Shortest processing time
- Earliest due date
- Longest processing time
● Average completion time =
● Utilization metric=
● Average number of jobs in the system =
● Average job lateness =
Example: Determine the sequence of processing according to FCFS, SPT, EDD, and LPT
rules.
A 6 8
B 2 6
C 8 18
D 3 25
E 9 23
1. FCFS:
D 3 5 25 0
A 6 11 8 3
C 8 19 18 1
E 9 28 23 5
3. EDD:
4. LPT:
5. Critical ratio:
Critical ratio = =
A 30 4
B 28 5
C 27 2
A (30-25)/4 = 1.25 3
B (28-25)/5 = 0.6 1
C (27-25)/2 = 1 2
Example: Five specialty jobs at a La Crosse, Wisconsin, tool and die shop must be
processed through two work centers (drill press and lathe). The time for processing
each job follows:
A 5 2
B 3 6
C 8 4
D 10 7
E 7 12
B E D C A
Work center 1 3 7 10 8 5
work center 2 6 12 7 4 2
Example 1: First Printing wants to find the minimum total cost assignment of 3 jobs to
3 typesetters.
Typesetters A B C
Jobs
R-34 $11 14 6
S-66 $8 10 11
T-50 $9 12 7
Typesetter A B C
s
Jobs
R-34 5 8 0
S-66 0 2 3
T-50 2 5 0
A chọ n S or T A chọ n T
C chọ n R or T C chọ n R
Hence, the company should choose typesetter A for job T-50, typesetter B for job S-66,
typesetter C for job R-34
Hiree
Hiree
Jones $800 1,100 1,200 1,000
Smith 500 1,600 1,300 800
Wilson 500 1,000 2,300 1,500
Dummy 0 0 0 0
Hiree
Jones 0 300 400 200
Smith 0 1,100 800 300
Wilson 0 500 1,800 1,000
Dummy 0 0 0 0
Hiree
Jones Smith 0 0 100 0
Wilson 0 800 500 100
Dummy 0 200 1,500 800
300 0 0 100
Office OMAHA MIAMI DALLAS NEW YORK
Hiree
Jones 100 0 100 0
Smith 0 700 400 0
Wilson 0 100 1,400 700
Dumm 400 0 0 100
y
Jone – Miami
Smith – New York
Wilson – Ohama
Dummy – Dallas
Hence, the company should choose Jone for Miami , Smith for NY, Wilson for Omaha,
Dummy for Dallas
The minimum total cost: $1,100 + $800 + $500 + 0 = $2,400