Professional Documents
Culture Documents
PP-16-Project Board Terms of Reference
PP-16-Project Board Terms of Reference
PP-15-PPTR
Project Board Terms of Reference
3. Ensure timely decisions are made and that the brief and design are signed off and frozen at the
defined work stages.
4. Review and manage all change control requests; the project board able to approve change that
remains in-line with the approved project budget allocation, however considers risk
apportionment.
5. Ensure work streams (e.g. IT, Communications, Finance, HR, and Operations etc.) are resourced
adequately and review work stream reports by exception.
6. Escalating issues to the Physical Estate Programme Implementation Board when required.
Note: Where change requests (individual or cumulative) exceed acceptable pre-construction levels
e.g. 10% contingency (design and construction), this would require escalation. Once in post-contract
(construction) stage, a risk/contingency drawdown schedule should be produced by the project
team for approval by the project board to encourage effective allocation/apportionment of risk
contingency as risk reduces throughout the project lifecycle.
The Project Board will be convened monthly and chaired by a member of the Estates Directorate.
The ‘Project Owner’ will attend as defined in the Project Charter. The Chair will be responsible for
ensuring the Board adheres to the Terms of Reference. The Chair will also be responsible for:-
1. Establishing the project Board and setting out the necessary communication processes.
2. Where appropriate, identify and obtain all necessary resources (financial and people) to ensure
that the Project Board completes its work effectively.
3. Ensure that a Project Charter and Project Manager Dashboard are in place before proceeding
with the Project.
4. Ensure that any changes in circumstances affecting the project are evaluated and that
appropriate action is taken.
5. Ensure that a post occupancy evaluation is carried out and considered by all users and key
stakeholders on the project.
6. Balance the needs of the University and the user’s requirements.
Secretariat
Normally to be provided by Estates and Campus Services.
Reports to
Physical Estate Programme Implementation Board
To enable the project board to fulfil its responsibilities, an update on project status will be issued 3
days in advance (minimum) of the meeting and presented by the University Project Manager. This
will be presented in the form of the Dashboard Report and contain the following;
• An illustration of project programme including assessment of performance against key
tasks/milestones/gateways,
• A short review of progress, by reference to key dates and project milestones.
• A review of principal actions undertaken during the period.
• Elemental summary of financial performance; Anticipated Final Cost of the project, compared
with the approved budget.
• ‘Headline’ review of contract administration.
• Project approval status.
• An explanation of departures from, and updated forecasts for, project performance, programme
and budget objectives.
• Resolution of key decisions required.
• Establish problems requiring resolution.
• A forecast of principal actions for the forthcoming period.
• A list of key issues including potential changes in scope of the Works.
• A list of outstanding information or decisions required to maintain project progress in accordance
with the programme.
• Change control status.
• Risk status, including factorised cost.
• Forthcoming key meetings.
Duration of Appointment
For the duration of the project.
Frequency of Meetings
To be agreed at the first meeting.
Quorum
All who are required to attend a project board meeting must make a concerted effort to ensure
continuity of personnel is maintained for the full duration of the project to encourage proper
discharge of their responsibilities. If deputies are to be nominated, they must be fully briefed prior to
attending and hold delegated powers to facilitate decision making.
Note: When required, a ‘Quorum’ project board may need to be convened to facilitate key decisions
preventing delay to programme. As a minimum, the following must be represented at such a
meeting;
Project Chair
Project Sponsor or Senior End-User Representative (Delegate)
Project Owner
Project Manager