Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
0% found this document useful (0 votes)
38 views3 pages

Cronograma Proyectos SSI AR CW 04

Download as pdf or txt
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 3

SSI Schaefer Argentina

Id Nombre de tarea Duración Comienzo Fin 2019 2024


2019 2020 2021 2022 2023 2024 2025
T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1
0 CRONOGRAMA DE PROYECTOS SSI ARG 1242 días mié 15/4/20 vie 14/2/25 CRONOGRAMA DE PROYECTOS SSI ARG
15/4/20 14/2/25
1 1 KELLERHOFF 697 días mié 14/10/20 vie 14/7/23 KELLERHOFF
14/10/20 14/7/23
2 1.1 Project start, system optimization  60 días mié 14/10/20 mar 5/1/21 Project start, system optimization and customer approval signed
and customer approval signed 14/10/20 5/1/21
3 1.2 Detailed engineering 180 días mié 6/1/21 mar 14/9/21 Detailed engineering
6/1/21 14/9/21
4 1.3 IT specifications book signed and  28 sem. mié 15/9/21 mar 29/3/22 IT specifications book signed and realization
realization 15/9/21 29/3/22
5 1.4 Production 52 días mié 15/9/21 jue 25/11/21 Production
15/9/21 25/11/21
6 1.5 Delivery of material and local  50 días vie 26/11/21 jue 3/2/22 Delivery of material and local import process
import process 26/11/21 3/2/22
7 1.6 Site Installation 11 sem. lun 18/7/22 vie 30/9/22 Site Installation
18/7/22 30/9/22
8 1.7 MHE PLC commisioning 6 sem. lun 27/3/23 vie 5/5/23 MHE PLC commisioning
27/3/23 5/5/23
9 1.8 IT commisioning 4 sem. lun 8/5/23 vie 2/6/23 IT commisioning
8/5/23 2/6/23
10 1.9 Tests and internal protocol  4 sem. lun 5/6/23 vie 30/6/23 Tests and internal protocol acceptance
acceptance 5/6/23 30/6/23
11 1.10 Ramp‐Up phase and final  2 sem. lun 3/7/23 vie 14/7/23 Ramp-Up phase and final acceptance signed
acceptance signed 3/7/23 14/7/23
12 2 20 DE JUNIO 782 días mié 15/4/20 vie 12/5/23 20 DE JUNIO
15/4/20 12/5/23
13 2.1 Project start, system optimization  60 días mié 15/4/20 mar 7/7/20 Project start, system optimization and customer approval signed
and customer approval signed 15/4/20 7/7/20
14 2.2 Detailed engineering 120 días mié 8/7/20 mar 22/12/20 Detailed engineering
8/7/20 22/12/20
15 2.3 IT specifications book signed and  90 días mié 8/7/20 mar 10/11/20 IT specifications book signed and realization
realization 8/7/20 10/11/20
16 2.4 Production 83 días mié 23/12/20 vie 16/4/21 Production
23/12/20 16/4/21
17 2.5 Delivery of material and local  35 días lun 19/4/21 vie 4/6/21 Delivery of material and local import process
import process 19/4/21 4/6/21
18 2.6 Site Installation 13,6 sem. lun 12/9/22 mié 14/12/22 Site Installation
12/9/22 14/12/22
19 2.7 MHE PLC commisioning 8 sem. lun 6/2/23 vie 31/3/23 MHE PLC commisioning
6/2/23 31/3/23
20 2.8 IT commisioning 4 sem. lun 3/4/23 vie 28/4/23 IT commisioning
3/4/23 28/4/23
21 2.9 Tests and internal protocol  2 sem. lun 17/4/23 vie 28/4/23 Tests and internal protocol acceptance
acceptance 17/4/23 28/4/23
22 2.10 Ramp‐Up phase and final  2 sem. lun 1/5/23 vie 12/5/23 Ramp-Up phase and final acceptance signed
acceptance signed 1/5/23 12/5/23
23 3 ASOPROFARMA  589 días lun 6/12/21 vie 5/4/24 ASOPROFARMA
6/12/21 5/4/24
24 3.1 Project start, system optimization  13 sem. lun 6/12/21 vie 4/3/22 Project start, system optimization and customer approval signed
and customer approval signed 6/12/21 4/3/22
25 3.2 Detailed engineering 50 sem. lun 7/3/22 lun 20/3/23 Detailed engineering
7/3/22 20/3/23

Fecha de última modificación: lun 23/1/23 Página 1


Autor de útlima mofificación: Federico García
SSI Schaefer Argentina

Id Nombre de tarea Duración Comienzo Fin 2019 2024


2019 2020 2021 2022 2023 2024 2025
T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1
26 3.3 IT specifications book signed and  48 sem. lun 2/5/22 lun 1/5/23 IT specifications book signed and realization
realization 2/5/22 1/5/23
27 3.4 Production 20 sem. lun 16/1/23 vie 2/6/23 Production
16/1/23 2/6/23
28 3.5 Delivery of material and local  5 sem. lun 5/6/23 vie 7/7/23 Delivery of material and local import process
import process 5/6/23 7/7/23
29 3.6 Site Installation 30 sem. lun 10/7/23 vie 2/2/24 Site Installation
10/7/23 2/2/24
30 3.7 MHE PLC commisioning 3 sem. lun 5/2/24 vie 23/2/24 MHE PLC commisioning
5/2/24 23/2/24
31 3.8 IT commisioning 2 sem. lun 26/2/24 vie 8/3/24 IT commisioning
26/2/24 8/3/24
32 3.9 Tests and internal protocol  2 sem. lun 11/3/24 vie 22/3/24 Tests and internal protocol acceptance
acceptance 11/3/24 22/3/24
33 3.10 Ramp‐Up phase and final  2 sem. lun 25/3/24 vie 5/4/24 Ramp-Up phase and final acceptance signed
acceptance signed 25/3/24 5/4/24
34 4 SUIZO TUCUMÁN 402 días mar 22/2/22 jue 5/10/23 SUIZO TUCUMÁN
22/2/22 5/10/23
35 4.1 Project start, system optimization  45 días mar 22/2/22 lun 25/4/22 Project start, system optimization and customer approval signed
and customer approval signed 22/2/22 25/4/22
36 4.2 Detailed engineering 60 días mar 26/4/22 lun 18/7/22 Detailed engineering
26/4/22 18/7/22
37 4.3 IT specifications book signed and  24 sem. mar 19/7/22 mar 31/1/23 IT specifications book signed and realization
realization 19/7/22 31/1/23
38 4.4 Production 24 sem. mar 19/7/22 mar 31/1/23 Production
19/7/22 31/1/23
39 4.5 Delivery of material and local  10 sem. vie 10/2/23 jue 20/4/23 Delivery of material and local import process
import process 10/2/23 20/4/23
40 4.6 Site Installation 8 sem. vie 21/4/23 jue 15/6/23 Site Installation
21/4/23 15/6/23
41 4.7 MHE PLC commisioning 6 sem. vie 16/6/23 jue 27/7/23 MHE PLC commisioning
16/6/23 27/7/23
42 4.8 IT commisioning 3 sem. vie 28/7/23 jue 17/8/23 IT commisioning
28/7/23 17/8/23
43 4.9 Tests and internal protocol  4 sem. vie 18/8/23 jue 14/9/23 Tests and internal protocol acceptance
acceptance 18/8/23 14/9/23
44 4.10 Ramp‐Up phase and final  3 sem. vie 15/9/23 jue 5/10/23 Ramp-Up phase and final acceptance signed
acceptance signed 15/9/23 5/10/23
45 5 DISVAL 535 días lun 30/1/23 vie 14/2/25 DISVAL
30/1/23 14/2/25
46 5.1 Project start, system optimization  10 sem. lun 30/1/23 vie 7/4/23 Project start, system optimization and customer approval signed
and customer approval signed 30/1/23 7/4/23
47 5.2 Detailed engineering 20 sem. lun 10/4/23 vie 25/8/23 Detailed engineering
10/4/23 25/8/23
48 5.3 IT specifications book signed and  48 sem. lun 10/4/23 vie 8/3/24 IT specifications book signed and realization
realization 10/4/23 8/3/24
49 5.4 Production 28 sem. lun 28/8/23 vie 8/3/24 Production
28/8/23 8/3/24
50 5.5 Delivery of material and local  6 sem. lun 11/3/24 vie 19/4/24 Delivery of material and local import process
import process 11/3/24 19/4/24
51 5.6 Site Installation 32 sem. lun 22/4/24 vie 29/11/24 Site Installation
22/4/24 29/11/24

Fecha de última modificación: lun 23/1/23 Página 2


Autor de útlima mofificación: Federico García
SSI Schaefer Argentina

Id Nombre de tarea Duración Comienzo Fin 2019 2024


2019 2020 2021 2022 2023 2024 2025
T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1 T2 T3 T4 T1
52 5.7 MHE PLC commisioning 3 sem. lun 2/12/24 vie 20/12/24 MHE PLC commisioning
2/12/24 20/12/24
53 5.8 IT commisioning 3 sem. lun 23/12/24 vie 10/1/25 IT commisioning
23/12/24 10/1/25
54 5.9 Tests and internal protocol  3 sem. lun 13/1/25 vie 31/1/25 Tests and internal protocol acceptance
acceptance 13/1/25 31/1/25
55 5.10 Ramp‐Up phase and final  2 sem. lun 3/2/25 vie 14/2/25 Ramp-Up phase and final acceptance signed
acceptance signed 3/2/25 14/2/25
56 6 DROGUERÍA SUR 510 días lun 5/9/22 lun 16/9/24 DROGUERÍA SUR
5/9/22 16/9/24
57 6.1 Project start, system optimization  60 días lun 5/9/22 vie 25/11/22 Project start, system optimization and customer approval signed
and customer approval signed 5/9/22 25/11/22
58 6.2 Detailed engineering 60 días lun 28/11/22 lun 20/3/23 Detailed engineering
28/11/22 20/3/23
59 6.3 IT specifications book signed and  24 sem. mar 21/3/23 lun 4/9/23 IT specifications book signed and realization
realization 21/3/23 4/9/23
60 6.4 Production 24 sem. mar 5/9/23 lun 19/2/24 Production
5/9/23 19/2/24
61 6.5 Delivery of material and local  10 sem. mar 20/2/24 lun 29/4/24 Delivery of material and local import process
import process 20/2/24 29/4/24
62 6.6 Site Installation 6 sem. mar 30/4/24 lun 10/6/24 Site Installation
30/4/24 10/6/24
63 6.7 MHE PLC commisioning 4 sem. mar 11/6/24 lun 8/7/24 MHE PLC commisioning
11/6/24 8/7/24
64 6.8 IT commisioning 4 sem. mar 9/7/24 lun 5/8/24 IT commisioning
9/7/24 5/8/24
65 6.9 Tests and internal protocol  4 sem. mar 6/8/24 lun 2/9/24 Tests and internal protocol acceptance
acceptance 6/8/24 2/9/24
66 6.10 Ramp‐Up phase and final  2 sem. mar 3/9/24 lun 16/9/24 Ramp-Up phase and final acceptance signed
acceptance signed 3/9/24 16/9/24
67 7 PUNTOFARMA 412 días lun 9/1/23 lun 12/8/24 PUNTOFARMA

68 7.1 Project start, system optimization  22 días lun 9/1/23 lun 13/2/23 Project start, system optimization and customer approval signed
and customer approval signed 9/1/23 13/2/23
69 7.2 Detailed engineering 60 días mar 14/2/23 lun 8/5/23 Detailed engineering
14/2/23 8/5/23
70 7.3 IT specifications book signed and  24 sem. mar 11/4/23 lun 25/9/23 IT specifications book signed and realization
realization 11/4/23 25/9/23
71 7.4 Production 20 sem. mar 9/5/23 lun 25/9/23 Production
9/5/23 25/9/23
72 7.5 Delivery of material and local  6 sem. mar 26/9/23 lun 6/11/23 Delivery of material and local import process
import process 26/9/23 6/11/23
73 7.6 Site Installation 8 sem. lun 26/2/24 vie 19/4/24 Site Installation
26/2/24 19/4/24
74 7.7 MHE PLC commisioning 6 sem. lun 22/4/24 vie 31/5/24 MHE PLC commisioning
22/4/24 31/5/24
75 7.8 IT commisioning 3 sem. lun 3/6/24 vie 21/6/24 IT commisioning
3/6/24 21/6/24
76 7.9 Tests and internal protocol  4 sem. lun 24/6/24 vie 19/7/24 Tests and internal protocol acceptance
acceptance 24/6/24 19/7/24
77 7.10 Ramp‐Up phase and final  3 sem. lun 22/7/24 vie 9/8/24 Ramp-Up phase and final acceptance signed
acceptance signed 22/7/24 9/8/24

Fecha de última modificación: lun 23/1/23 Página 3


Autor de útlima mofificación: Federico García

You might also like