PMBOK 6th Ch07 3
PMBOK 6th Ch07 3
PMBOK 6th Ch07 3
SIXTH EDITION
Guide
CHAPTER 07
7.3 Determine Budget
DETERMINE BUDGET
aggregating costs of individual activities to generate cost baseline
1 Overview
Estimate Costs X
Determine Budget X
Control Costs X
@andieriawan
1 Overview
COST PROCESSES
Plan Cost Management Documenting how to manage
and control costs
Estimate Costs Approximating the finances
needed to complete project
activities
Determine Budget Aggregating costs of individual
activities to generate cost
baseline
Control Costs Monitoring project costs and
managing changes to the cost
baseline
@andieriawan
2 Outputs
COST BASELINE
Management
Reserve Cost Baseline
Overall
Contingency
Reserve
Contingency
Reserve
Project
Delivery Contingency
Cost
Reserve
Baseline Control Work
Accounts Package Activity
Estimates Cost
Estimates
@andieriawan
2 Outputs
• EXAMPLE:
Do you need $1M this month and $2M next
month?
• Cost Estimates
• Project Schedule
• Risk Register
@andieriawan
3 Tools & Techniques
Expert Judgment
Cost Aggregation
1. tallying the activity cost estimates at the work
package level; and then
2. totaling the work package levels to higher level WBS
component levels (such as the control accounts);
3. all the costs can be aggregated to obtain a total
project cost.
Data Analysis
• Reserve analysis → management reserve
• Cost of quality (COQ)
… the total cost to produce the product or service of
the project according to the quality standards
@andieriawan
3 Tools & Techniques
Financing
obtaining funding for the project and taking into
account how that funding will be tracked, reported,
and used throughout the project
@andieriawan
4 Inputs
Project DOCUMENTS
• Cost estimates
• Basis of estimates
… supporting detail regarding the estimates
• Risk register
… to aggregate the risk response costs.
• Project schedule
… helpful in developing the budget, such as start and end
dates for activities and milestones.
Business Documents
… includes the target benefits, such as net present value
calculations, timeframe for realizing benefits, and the metrics
associated with the benefits.
@andieriawan
4 Inputs
Agreements
… include cost information for purchased goods or services
EEF
• Exchange rates
OPA
… includes the target benefits, such as net present value
calculations, timeframe for realizing benefits, and the metrics
associated with the benefits.
@andieriawan
@andieriawan
5 Exam Spotlight
Cost Baseline
• Cost baselines are displayed as an S curve. The project
spending starts out slowly, gradually increases over the
project’s life until it reaches a peak, and then tapers off again
as the project wraps up.
@andieriawan
5 Exam Spotlight
Agile’s Budget
… when working on an agile project where cost or budget is the
primary constraint, you will need to adjust schedule and scope to
accommodate cost
@andieriawan
“ “
The budget was unlimited,
but I succeeded it.