Programme

The document outlines a project schedule with 43 tasks over 608 days from February 2020 to March 2022. It provides details on task names, durations, start and finish dates for each phase of the project broken down by year, quarter and month.

Uploaded by

Bharat Maddula
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

ID ID Task Task Name Duration Start Finish 2020 2021 2022

Mode H2 H1 H2 H1 H2 H1
1 1 Contract PT327 608 days Thu 2/1/20 Tue 3/5/22
2 2 Letter of Award 1 day Thu 2/1/20 Fri 3/1/20
3 3 Preliminaries 60 days Thu 2/1/20 Thu 26/3/20
4 4 Topographical Survey/ SIP/ DIP 21 days Fri 3/1/20 Mon 3/2/20
5 5 Cable Detection 30 days Fri 3/1/20 Fri 14/2/20
6 6 ECM Design and Submission 45 days Fri 3/1/20 Fri 6/3/20
7 7 Physical site survey and 60 days Fri 3/1/20 Fri 27/3/20
investigation (Trial Holes)
8 8 Design Drawing and Materials 60 days Fri 3/1/20 Fri 27/3/20
Submission
9 9 Submission of Conceptual 21 days Fri 3/1/20 Mon 3/2/20
Design AIP
10 10 Submission of Preliminary Design30 days Mon 3/2/20 Mon 16/3/20
11 11 Submission of Clearance to 21 days Tue 17/3/20 Wed 15/4/20
Techincal Agencies and Relevant
Authorities
12 12 Submission of Final Design to 21 days Thu 16/4/20 Fri 15/5/20
LTA/ SMRT
13 13 BCA Application for Permit to 21 days Fri 15/5/20 Mon 15/6/20
Commence Works
14 14 Materials submission to LTA and 21 days Fri 15/5/20 Mon 15/6/20
approval
15 15 Physical Works 400 days Tue 16/6/20 Tue 28/12/21
16 16 Bus Parking 365 days Tue 16/6/20 Tue 9/11/21
17 17 Site Clearance 60 days Tue 16/6/20 Tue 8/9/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Programme.mpp
Summary Manual Summary Rollup Progress
Date: Wed 12/6/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID ID Task Task Name Duration Start Finish 2020 2021 2022
Mode H2 H1 H2 H1 H2 H1
18 18 Construction of Drain 120 days Thu 16/7/20 Thu 31/12/20
19 19 Construction of Kerb 120 days Mon 3/8/20 Mon 18/1/21
20 20 Construction of Semi Rigid 90 days Fri 18/9/20 Fri 22/1/21
Pavement
21 21 Construction of Motorcycle 45 days Sat 21/11/20 Fri 22/1/21
Parking Lots
22 22 Thermoplastic Painting and 30 days Fri 11/12/20 Fri 22/1/21
Other Signage
23 23 Facilities 250 days Sat 23/1/21 Fri 7/1/22
24 24 Construction of Foundation 90 days Sat 23/1/21 Fri 28/5/21
25 25 Intallation of Safety Bollards 30 days Sat 29/5/21 Fri 9/7/21
26 26 Casting of Slab 60 days Sat 10/7/21 Fri 1/10/21
27 27 Installation of Steel Sturctures 120 days Sat 2/10/21 Fri 18/3/22
28 28 Installation of Roof 60 days Fri 19/3/21 Fri 11/6/21
29 29 Construction of facilities room 90 days Sat 12/6/21 Fri 15/10/21
30 30 Architectural Works and others 90 days Sat 16/10/21 Fri 18/2/22
31 31 Electrical Works 180 days Sat 15/5/21 Fri 21/1/22
32 32 LV Main Swtichboard, Sub 90 days Sat 15/5/21 Fri 17/9/21
Switchboards, DB, Power Points
33 33 Light System incld cabling and 90 days Sat 18/9/21 Fri 21/1/22
ducting
34 34 Equipotential System, LPS, EPS 90 days Sat 18/9/21 Fri 21/1/22
35 35 Telecome System, CCTV 90 days Thu 9/9/21 Thu 13/1/22
36 36 Mechanical Works 180 days Thu 15/4/21 Thu 23/12/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Programme.mpp
Summary Manual Summary Rollup Progress
Date: Wed 12/6/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID ID Task Task Name Duration Start Finish 2020 2021 2022
Mode H2 H1 H2 H1 H2 H1
37 37 Airconditioning, Ducting 150 days Thu 15/4/21 Thu 11/11/21
38 38 Mechanical Ventilation System 120 days Thu 15/4/21 Thu 30/9/21
39 39 Plumbing and Sanitary Works 180 days Mon 15/3/21Mon 22/11/21
40 40 TOP & CSC 115 days Mon 22/11/21Mon 2/5/22
41 41 As Built Drawings 60 days Tue 23/11/21Tue 15/2/22
42 42 BCA TOP 60 days Tue 23/11/21Tue 15/2/22
43 43 BCA CSC 60 days Wed 15/12/21Wed 9/3/22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Programme.mpp