Appendix 5 - AON Diagram
Appendix 5 - AON Diagram
Appendix 5 - AON Diagram
Start: ID: 3
Finish: Dur:
Res:
Building Permit
Start: Wed 23-04-12ID: 8
Finish: Wed 23-04-12Dur: 1 day
Res:
Progress Report
Shop D rawing Demolition shop drawing Architectural shop drawing Structural Shop drawing
Sta rt: 23-04-13 ID: 11 Start: Thu 23-04-13 ID: 12 Start: Fri 23-04-28 ID: 13 Start: Fri 23-04-28 ID: 14
Finish: 23-05-12 Dur: 30 days Finish: Thu 23-04-27 Dur: 15 days Finish: Fri 23-05-12 Dur: 15 days Finish: Fri 23-05-12 Dur: 15 days
Comp: 0% Re s: Res: Res:
Samples submittal
Start: Sat 23-0 5-13 ID: 19
Finish: Sun 23-06-11 Dur: 30 days
Res:
QA QC Plan
Start: Thu 23-04-13 ID: 22
Finish: Sat 23-04-22 Dur: 10 days
Re s:
HSE Plan
Start: Thu 23-04-13 ID: 23
Finish: Sat 23-04-22 Dur: 10 days
Re s:
Temporary Drainage
Start: Sat 23-0 5-13 ID: 30
Finish: Sat 23-05-13 Dur: 1 day
Res:
Scaffolding
Start: Sat 23-0 5-13 ID: 36
Finish: Sat 23-05-13 Dur: 1 day
Res:
Hoisting
Start: Sat 23-0 5-13 ID: 37
Finish: Sat 23-05-13 Dur: 1 day
Res:
Materials Storage
Start: Sat 23-0 5-13 ID: 38
Finish: Fri 23-06-02 Dur: 21 days
Res:
Sanitary facilities
Start: Sat 23-0 5-13 ID: 39
Finish: Sat 23-05-27 Dur: 15 days
Res:
Construction signage
Start: Sat 23-0 5-13 ID: 41
Finish: Fri 23-05-19 Dur: 7 days
Res:
Construction parking
Start: Sat 23-0 5-13 ID: 42
Finish: M on 23-05-22Dur: 10 days
Res:
Construction Access
Start: Sat 23-0 5-13 ID: 43
Finish: M on 23-05-22Dur: 10 days
Res:
G- Building Sitework G10.Site preparation G1020.Site demo lit ion Building Demolition (Second Floor) Building Demolition (Ground Floor) BUILDING DEMOLIT ION FOOTINGS AND FOUNDATIONS
Start: 23-04-13 ID: 46 Start: 23-06-12 ID: 47 Start: 23-06-12 ID: 48 Start: Mon 23-06-12ID: 49 Start: Tue 23-06-13 ID : 50 Start: We d 23-06-14ID: 51
Finish: 23-07-10 Dur: 89 days Finish: 23-07-10 Dur: 29 days Finish: 23-06-30 Dur: 19 days Finish: Mon 23-06-12Dur: 1 day Finish: Tue 23-0 6-13Dur: 1 day Finish: Fri 23-06-30 Dur: 17 days
Comp: 0% Comp: 0% Comp: 0% Res: Res: Res:
A-Subst ructure A10-Foundations A1010-Standard Foundat ions Vapor retarde r foundation PileCap1 Structural concrete, formw ork, rebar PileCap2 Structura l concre te, formwork, re bar Strip Footing1 Structural concrete, formwork, re bar Strip Footing2 Structural concrete, formwork, reba r Strip Footing3 Structural concrete, formwork, rebar Footing Wa ll Structural concrete, formwork, rebar Reinforcing steel Gra de Beams Grade Be ams Founda tion(concrete,formwork)
Start: 23-07-11 ID: 58 Start: 23-07-11 I D: 59 Sta rt: 23-07-11 ID: 60 Start: Tue 23-0 7-11 ID: 61 Start: Thu 23-08-03 ID: 62 Start: Fri 23-08 -04 I D: 63 Start: Sat 23-08-12 ID: 64 Start: Sun 23-08-13 ID: 65 Start: Mon 23-08-14ID: 66 Start: Tue 23-08-22 ID: 67 Start: Sun 23-09-10 ID: 68 Start: Tue 23-09-12 ID: 69
Finish: 23-09-27 Dur: 79 days F inish: 23-09-27 Dur: 79 days Finish: 23-09-13 Dur: 65 days Finish: Fri 23-07-28 Dur: 18 days Finish: Thu 23-08-03Dur: 1 day Finish: Fri 23-08-04 D ur: 1 day Finish: Sat 23-08-12 Dur: 1 day Finish: Sun 23-0 8-13 Dur: 1 day Finish: Mon 23-08-14Dur: 1 day Finish: Sat 23-09-02 Dur: 12 days Finish: Mon 23-09-11Dur: 2 days Finish: Wed 23-09-13Dur: 2 days
Comp: 0% C om p: 0% Comp: 0% Res: Res: Res: Re s: Res: Res: Re s: Res: Res:
A1030-Slab on grade Slab re inforcing steel Structural concrete, Formwork, slab on grade Structural concrete, Concrete, slab on grade
Sta rt: 23-09-21 ID: 70 Start: Thu 23-09-21 ID: 71 Start: Sun 23-09-24 ID: 72 Start: Tue 23-0 9-26 ID: 73
Finish: 23-09-27 Dur: 7 da ys Finish: Sat 23-09 -23 Dur: 3 days Finish: Mon 23-09-25Dur: 2 days Finish: Wed 23-09-27Dur: 2 days
Comp: 0% Res: Res: Res:
B-Shell B10-Sup erstructure B1010-Floor Construction Installation of Columns (Basement) Installa tion of Beam (Groundfloor)
Start: 23-10-05 ID: 74 Start: 23-10-05 I D: 75 Sta rt: 23-10-05 ID: 76 Start: Thu 23-10-05 ID: 77 Start: Thu 23-1 0-12 ID : 80
Finish: 24-03-29 Dur: 177 days F inish: 23-12-09 Dur: 66 days Finish: 23-12-05 Dur: 62 days Finish: Wed 23-10-11Dur: 7 days Finish: Fri 23-10-20 Dur: 9 days
Comp: 0% C om p: 0% Comp: 0% Res: Res:
B1020-Roof Co nstruction steel deck (ground floor) Placing Concre te (ground floor) Form in Place (ground floor)
Sta rt: 23-10-21 ID: 83 Start: Sat 23-1 0-21 ID: 84 Start: M on 23-10-23ID: 85 Start: Thu 23-1 0-26 ID : 86
Finish: 23-12-09 Dur: 50 days Finish: Sun 23-10-22 Dur: 2 days Finish: Wed 23-10-25Dur: 3 days Finish: Fri 23-10-27 Dur: 2 days
Comp: 0% Res: Res: Res:
B2020-Exterior Windows
Sta rt: 24-03-27 ID: 98
Finish: 24-03-29 Dur: 3 da ys
Comp: 0%
B2030-Exterior Doo rs
Sta rt: 24-02-27 ID: 100
Finish: 24-03-27 Dur: 30 days
Comp: 0%
B3020-Roof Openings
Sta rt: 23-12-24 ID: 106
Finish: 23-12-24 Dur: 1 da y
Comp: 0%
C1020-Interior doors
Sta rt: 25-08-15 ID: 113
Finish: 25-08-20 Dur: 6 da ys
Comp: 0%
C1030-FITTING
Sta rt: 25-08-21 ID: 117
Finish: 25-08-24 Dur: 4 da ys
Comp: 0%
C30-FINISHIES C3010-WALL
Start: 25-05-08 I D: 126 Sta rt: 25-05-08 ID: 127
F inish: 25-08-14 Dur: 99 days Finish: 25-06-28 Dur: 52 days
C om p: 0% Comp: 0%
C3020-FLOOR
Sta rt: 25-07-16 ID: 134
Finish: 25-08-14 Dur: 30 days
Comp: 0%
C3030-CAILING
Sta rt: 25-06-22 ID: 138
Finish: 25-07-15 Dur: 24 days
Comp: 0%
D3040-Distribution Systems
Sta rt: 25-03-08 ID: 168
Finish: 25-04-19 Dur: 43 days
Comp: 0%
Page 1
Installation of Columns (secondfloor) Installation of Beam (Roof)
Start: Tue 23-1 1-28 ID: 79 Start: Wed 23-11-29ID: 82
Finish: Tue 23-11-28 Dur: 1 day Finish: Tue 23-12-05 Dur: 7 days
Res: Res:
Roofing
Start: Thu 23-1 2-21 ID: 1 05
Finish: Sat 23-12-23 Dur: 3 days
Res:
Skylight
Start: Sun 23-1 2-24 ID: 107
Finish: Sun 23-12-24 Dur: 1 day
Res:
Ele va tor A
Start: Tue 25-03-04 ID: 1 46
Finish: Sun 25-0 3-23 Dur: 20 days
Res:
Water Pumps Hot water Heater Domestic water Piping (Cooper) Domestic water Piping (PVC) Hot water Piping Drainage Piping (Cooper) Drainage Piping (PVC)
Start: Sun 24-07-07 ID: 155 Start: Sat 24-07-27 ID: 1 56 Start: Fri 24-08-02 ID: 157 Start: M on 24-09-02ID: 158 Start: Mon 24-09-16ID: 159 Start: Thu 24-10-17 ID: 160 Start: Sat 24-11-02 ID: 161
Finish: Fri 24-07 -26 Dur: 2 0 days Finish: Thu 24-08-01 Dur: 6 days Finish: Sun 24-09-01 Dur: 31 days Finish: Sun 24-09-15 Dur: 14 days Finish: Wed 24-10-16Dur: 31 days Finish: Fri 24-11-01 Dur: 16 days Finish: Mon 24-11-11Dur: 10 days
Res: Res: Res: Res: Res: Res: Res:
Roof Draina ge
Start: Tue 24-11-12 ID : 1 63
Finish: Tue 24-1 1-12 Dur: 1 day
Res:
100 amp Panelboard 225 amp Panel LV Cabling MV Cabling Switch devices, 3 way Ground Floor Switch devices, 3 way Se cond Floor Switch de vices, 3 way Basement
Start: Thu 24-11-21 ID: 186 Start: Wed 24-12-18ID: 187 Start: Thu 25-01-02 ID: 188 Start: Wed 25-02-05ID: 189 Start: Fri 25-02-28 ID: 1 90 Start: Sun 25-0 3-02 ID: 191 Start: Mon 25-03-03ID: 192
Finish: Tue 24-12-17 Dur: 2 7 days Finish: Wed 25-01-01Dur: 15 days Finish: Tue 25-02-04 Dur: 34 days Finish: Thu 25-0 2-27 Dur: 2 3 days Finish: Sat 25-0 3-01 Dur: 2 days Finish: Sun 25-03-02 Dur: 1 day Finish: Mon 25-03-03Dur: 1 day
Res: Res: Res: Res: Res: Res: Re s:
Page 2
Demobilization
Start: Mon 25-08-25ID: 45
Finish: Mon 25-08-25Dur: 1 day
Res:
Installation of Doors Basement Installation of Doors Ground Floor Insta llation of D oors Second Floor
Start: Fri 25-08-15 ID: 114 Start: Mon 25-08-18ID: 115 Start: Wed 25-08-20I D: 116
Finish: Sun 25-08-17 Dur: 3 days Finish: Tue 25-08-19 Dur: 2 days Finish: Wed 25-08-20D ur: 1 day
Res: Res: Res:
Bituminous membrane Ceiling Suspension Systems GYPSUM BOARD on ceilings Acoustial ceiling
Start: Sun 25-06-22 ID: 139 Start: We d 25-06-25ID: 140 Start: Mon 25-07-07ID: 141 Start: Wed 25-0 7-09ID : 142
Finish: Tue 25-0 6-24Dur: 3 days Finish: Sun 25-07-06 Dur: 12 days Finish: Tue 25-07-08 Dur: 2 days Finish: Tue 25-0 7-15Dur: 7 days
Res: Res: Res: Res:
Elevator B
Start: Mon 25-03-24ID: 147
Finish: Sat 25-04-12 Dur: 20 days
Res:
Ductworks Gate valves Butterfly va lves Hot water storage tank Geotextile subsurface & clear stone potable water Expansion Tank Expansion Ta nk
Start: Sat 25-03-08 ID: 16 9 Start: Wed 25-03-19I D: 170 Start: Sat 25-03-29 ID: 171 Start: Tue 25-04-08 ID: 172 Start: Sun 25-04-13 ID: 173 Start: Mon 25-04-14ID: 174 Start: Sat 25-04-19 ID: 175
Finish: Tue 25-03-18 Dur: 11 days Finish: Fri 25-03-28 D ur: 10 days Finish: Mon 25-04-07Dur: 10 days Finish: Sat 25-0 4-12 Dur: 5 days Finish: Sun 25-04-13 Dur: 1 day Finish: Fri 25-04-18 Dur: 5 days Finish: Sat 25-0 4-19 Dur: 1 day
Res: Res: Re s: Res: Res: Re s: Res:
Exhaust Fan
Start: Wed 25-04-30ID: 179
Finish: Fri 25-05-02 Dur: 3 days
Re s:
Emergency light and exit sign Ground Floor Emergency light and e xit sign Second Floor Eme rge ncy light and exit sign Basement LED 15W LED 25W LED 45W
Start: Mon 25-04-07ID: 195 Start: Thu 25-04-10 ID: 196 Start: Fri 25-04 -11 I D: 197 Start: Sat 25-04-12 ID: 198 Start: Sun 25-04-13 ID: 199 Start: Mon 25-04-14ID: 200
Finish: Wed 25-04-09Dur: 3 days Finish: Thu 25-04-10Dur: 1 day Finish: Fri 25-04-11 D ur: 1 day Finish: Sat 25-04-12 Dur: 1 day Finish: Sun 25-0 4-13 Dur: 1 day Finish: Mon 25-04-14Dur: 1 day
Res: Res: Res: Re s: Res: Res:
Communication devices Communication cabling Detection systems, signal bell, Ground Floor Detection systems, signal bell, Second Floor Detection syste ms, signa l bell, Basement
Start: Tue 25-04-15 ID: 202 Start: Wed 25-04-16ID: 203 Start: Fri 25-05 -02 I D: 204 Start: Mon 25-05-05ID: 205 Start: Wed 25-05-07ID: 206
Finish: Tue 25-04-15 Dur: 1 day Finish: Thu 25-05-01Dur: 16 days Finish: Sun 25-05-04D ur: 3 days Finish: Tue 25-05-06 Dur: 2 days Finish: Wed 25-05-07Dur: 1 day
Re s: Res: Res: Re s: Res:
Page 3