Method Statement Sheet: Electrical work and MEP services installation, Testing and commissioning Risk Assessment Reference:
APPROVED BY
Assessor(s) – Name Position Signature Date
Name Position Signature Date
Plant/Equipment : Mobile crane, telehandler, DG, Panels, Electrical DB Task Specific PPE : HI viz jacket, Safety shoes, Goggles, Nose mask, Foreman :
Earplugs, Insulated footwear, insulated PVC hand
Tools/Materials : Hand tools, Electrical cable, Testing Equipment gloves, Safety Harness
Consumables other resources – power/water etc : Power Supply Permits : Work at height, Isolation-LOTO, permit to lift, Foreman or :
permit to dig/demolish Signoff as specified
Electrical trained persons should be selected as per criteria of ESSW procedure Pm/Site execution
1. Electrical Team set up
requirement. Team
Only trained and qualified electrical engineer and electrician should be selected for
electrical work.
Trained electrician & engineer should have electrical license. Pm/Site execution
Team
Electrical workers, Electrical shock to Competency assessment should be done for electrical team and appointment letter Pm/Site execution
Engineers, and Untrained electrical person Electrocution /
team for the task. 3 4 12 should be issued to electrical team (Electrical Engineer & electrician) Team 2 2 4
other person. Property damage
Subcontractor electricians should be assessed, and authorization letters
shall be issued.
Medical checkup should be done properly, and electrical team should be medical fit Pm/Site execution
for work. Team
All electrical team should be trained regarding CPR procedures.
Electrical team should be trained and conduct the M1, M2 and M3 and isolation Pm/Site execution
Team
Risk Assessment
Electrical team should know about COP & PSS compliance requirement. Pm/Site execution
Team
RCBO or MCB together with RCD must be provided and functional for all electrical
distribution installations and portable panels.
Electrical equipment shall have correct safety guarding and protective devices in
place (e.g., weatherproof materials, cover plates, earthling, RCD’s etc.).
All electrical supply points shall be provided with a means of effective isolation and
Earth leakage from Electrical
sock/Electrocution, lock out.
Pm/Site execution
panels Fire, injury to person 3 4 12 Electrostatic earthling to be ensured for all electrical panels. 2 3 6
Team
and damage to All temporary distribution boards must be externally earthed an adequately secured
property in position.
Rubber mats to be provided in front of Electrical Panels
Electric Shock First Aid procedures to be displayed on the panel front doors.
SLD to be pasted over the panels.
Fire extinguisher to be kept near the electrical panel
Electrical panels for outdoor applications should preferably of IP 67 rating. If not,
proper shed to be provided.
Electrocution, injury to Electrical distribution installations must be weatherproof and have RCBO/MCB and Pm/Site execution
Water & Dust
person and damage 3 4 12 2 2 4
Ingress to Panel RCD protection. Team
to property
Electrical panels shall be placed away from water (curing) pipelines and away
from shaft openings.
Panels, cables, circuit breakers etc. to be procured from approved vendors / makes.
Continuity & Insulation resistance test to be carried out for cables.
Incoming of all panels to be provided with an RCBO (up to 63A). Above 63A, MCCB
along with ELR to be provided.
Point for isolation to be provided in all panels and the same to be labelled properly.
2. Installation of Electrical
All outgoings should go through an RCBO (up to 63A). Above 63A, MCCB along
panels Electrical
Sub-standard Panels with ELR to be provided.
sock/Electrocution,
& Cables Pm / Site
Fire, injury to person 3 4 12 Bus bar material and thickness should be based on the current rating of the panels 2 3 6
execution Team
and damage to Insulation to be done on bus bars.
property Point to be available for earth lead connections
Locking arrangement should be available
Phase color codes to be followed for internal wiring works.
All Distribution boards must comply LIN standards & PSS 5.
Manual pallets trolley should not be used for handling of Electrical panels as
per PSS 64.
Damages on cable Electrical 3 4 12 Continuity & Insulation resistance test to be carried out for cables. Pm / Site 2 3 6
sock/Electrocution, Cables must be sufficiently insulated, sheathed, or armored, have protection from execution Team
Fire, injury to person chemical damage and where necessary additional protection, e.g. guarding, to
and damage to
property prevent mechanical damage.
Risk Assessment
All underground and overhead cables must be located or arranged so they are not in
the way of activities on site (i.e., redirected, buried with sufficient ground clearance).
Socket outlets for distribution cables should be located as close to the working point
as possible to prevent the need for long trailing wires.
Avoid cable laying through sharp edges.
Protection to be provided to cables based on the area of laying.
Specific signage for the routed/laid cable to be displayed
Use PVC insulated hook or start routing of cable.
Don’t route the cable through the vehicle movement access.
Maintain 1.5meters to routing the cable through the fencing.
Double compression glands to be used for termination works.
Electrical Holes made on panels should be according to the gland size.
Loose termination of sock/Electrocution, Lugs to be used for termination works.
cables Pm / Site
Fire, injury to person 3 4 12 2 3 6
Lug material & size to match with the cable conductor execution Team
and damage to
property Tightness to be ensured for all terminations
Armored cables shall be properly earthed with glands for panel earthing.
Working on Live Electrical Power supply to be terminated before any new connection works.
panels for Measuring sock/Electrocution, Isolation permit and LOTO system to be followed Pm / Site
the test record Fire, injury to person 3 4 12 2 3 6
Appropriate electrical resistant hand gloves to be used during measuring test on live execution Team
and damage to
property electrical panels.ie: Phase sequence Test, Voltage test, Amp Test etc.
Weight of the cable drum to be checked and Jack to be selected accordingly.
Length of the bar used in cable jack to be enough to avoid slippage of drum while
Involved workers Injury to person and lifting. Pm / Site
Failure of Cable Jack 3 3 9 2 2 4
and staff damage to property Ensure area around the cable drum is barricaded. execution Team
Cable pulling through shaft area shall be followed mechanical devices for
pulling with positive ties on each level.
3. Cable Pulling Working near Fall from height, Ensure hard barricade in place at the edges of excavation
Pm / Site
excavation area and fatality and serious 3 4 12 Use safety harness hooked to approved anchorage point while working near the 2 2 4
execution Team
floor edges injury. edges.
Electrical
Exposed electrical sock/Electrocution, Cables to be laid over proper cable stands Pm / Site
cables along edges Fire, injury to person 3 4 12 2 2 4
Display awareness signage’s. execution Team
may get damaged and damage to
property
4. Underground Cable laying Involved workers Excavation without Damage electrical 3 4 12 “Permit to Dig / Demolish” to be obtained Pm / Site 2 3 6
and staff/operator scanning cables and electrical Updated UG services plan from surveyor has to be followed for Identification of execution Team
underground shock to person, services.
services Electrocution, fire and Plan is to be followed for approximate idea of services not to pin point the location.
damage to property Area is to be thoroughly scanned for the UG services as per manufacturer
recommendations.
Only trained and competent person to do the scanning of underground services
If there are multiple services than scanning for particular service is to be done using
multiple scanning modes to pinpoint the service.
Services should be clearly marked on the ground using paint and pegs.
Risk Assessment
Water ingress to Electrical shock to Panels & sockets used outdoors should be weatherproof (IP55 and above).
Electricians, panels/industrial person, Electrocution, Pm / Site
Supervisors, sockets 3 4 12 Female industrial sockets to be maintained with caps in closed position 2 2 4
fire and damage to Proper canopy to be ensured as per the requirement execution Team
workers
property
Risk Assessment
Check and ensure no bare conductor electrical lines (EB supply) passing through our
site premises.
No overhead cables shall be laid at the vehicle access routes.
Contact overhead Check for rerouting of electrical cables/vehicle access way.
power lines. Cables shall be laid over the height of all possible vehicles, operating on the project
Nearby Electrocution
premises.
working/walking Goal posts/height markers with clear height restrictions should be in place at the
5. Overhead Cables laying Cables hit by vehicles Pm / Site
over vehicle access ways and damaged cables.
Class 1 Risk 4 4 16 vehicle access routes wherever cables are running. 2 3 6
execution Team
Mobile plant/vehicle Signage boards and reflective tapes shall be placed for clear view purposes.
operators Fall of cables due to Property damage
Intermediate Supports to provide cables to prevent sagging and lowering of cables
vehicle contact height.
Cables shall be identified and marked in the logistics plan.
All drivers/operators shall be communicated regarding locations of cables and height
restrictions.
6. Testing of Temp electrical Electricians, Untested temp Electrical shock to 3 4 12 Follow Isolation permit and LOTO system for testing and commissioning of Temp Pm / Site 2 3 6
services Supervisors, electrical services. person, Electrocution, electrical services execution Team
workers Sub standard fire and damage to
property Competent and appointed persons to do the testing of electrical services before use.
electrical testing
A test before touch (not live) must be completed:
equipment.
I. prior to, or commencing
Substandard circuit
breakers. work on any electrical
equipment
II. A Permit to Work shall be required to Check that circuits are dead
before working on electrical equipment, i.e. Test Before Touch.
III. All exposed electrical parts and
conductors, including earthing
conductors must be treated as
live until proven
Personnel MUST NOT remove the installed manufacturers safety guarding,
protective covers, plates, or shrouds, without confirmation through a "Test before
touch" procedure, by use of an approved non-contact voltage tester. (LA-HSE-COP-
001 Rev. 001 - Electrical Works)
Personnel MUST ensure that after "Test before touch with a Non-Contact Voltage
Tester" is completed, that a mandatory test by use of a calibrated 'multi-Meter" is
undertaken to confirm that no potential energy is stored within the circuit.
Review and Enhance the existing “Buddy System” to minimize “Human Error – Slips
& Lapses”, where personnel are working in areas that are classed as "Energized".
Electrical Teams must be monitored (on a daily basis) to ensure that basic electrical
compliance checks (testing) are being completed to the approved industry standard.
Those involved in testing and commissioning must fully understand the potential
risks of "Arc Flash", and that appropriate PPE (Dependent on Risk Profile) is worn at
all times.
The following test equipment shall be used and recorded on record Sheet which
come under Category 4 or Category 5, ensure all test equipment are calibrated and
certificates are in place.
I. 1000 Volt Insulation Tester
II. Phase Sequence Meter.
III. Digital Multimeter
IV. Digital Clamp meter
Risk Assessment
Electrical shock to Never carry out any repair works on live line.
Repair works without person, Electrocution, Isolation permit to be followed
Electricians, following Isolation fire and damage to Switch off the power & apply LOTO before starting repair works Pm / Site
Supervisors, procedure property 3 4 12 2 3 6
Conduct “Live Test” using Multi meter, before commencing any works. execution Team
workers
Buddy system to be implemented
Only competent and authorized electricians to carry out repairing works
Electricians, Defective Power Electrical shock to 3 4 12 All power tools to be inspected and tagged by authorized persons before using at Pm / Site 2 3 6
Supervisors tools person, Electrocution, site. execution Team
fire and damage to
property Tagging to done according to color coding system.
Only trained and authorized person to operate power tools.
Only double insulated power tools are allowed at site
Ensure all power tools/equipment are having safe guard and protective devices in
place.
Power to these tools to be taken through an RCBO.
Quarterly inspection of power tools to be carried out.
Risk Assessment