SHABAN Booklet 11th Edition
SHABAN Booklet 11th Edition
SHABAN Booklet 11th Edition
SHABAN
CIVIL
ENGINEERS
BOOKLET
www.shabanbooklet.com
Prepared by Consultant Civil Engineer:
Majed SHABAN
11TH Edition
___________________________
Mobile No. for Viber and WhatsApp:
+964 770 446 1234
IRAQI -KURDISTAN REGION , Erbil
Notes :
1- For land scaping works and cleaning
works the surface layer should be
removed for min. (15) cm thickness.
2- For raft foundations top soil should be
removed also for Min. (30-50) cm depth.
3- For Deep foundations the subsoil also to
be removed until reaching hard layers.
4- For Pile foundation, piles should reach
the parent material layer or the bed rock
layer according to soil investigations.
Expansion Joint
Isolation filler
////////////////////////////
concrete structure
Section Kg / 6 m
Length
Angle 20x20 x 3mm Thick 6.0
Angle 25x25 x 3mm Thick 7.0
Angle 40x40 x 4mm Thick 14.0
Angle 50x50 x 5mm Thick 25.0
Angle 60x60 x 6mm Thick 32.4
Channel 75 x 36 x 6 mm 47.0
Channel 100 x 50 x 6 mm 62.0
Channel 120 x 55 x 7 mm 75.0
I-section 100 mm Height 50.0
I-section 140 mm Height 82.0
I-section 160 mm Height 96.0
Flat steel 25mm x 3mm
4.0
Thickness
Flat steel 35mm x 6mm
9.0
Thickness
Notes:
1- All above weights are for a 6.0 -
meter steel section length.
2- Steel Bars Density = 7850 kg/m3
SHABAN 11th Edition - 19
Typical Plate weights
Alumin-
mm Inch Steel Copper
um
1.1 1/24 2.77 8.3 9.3
1.2 1/22 3.12 9.1 10.2
1.3 1/20 3.50 10 11.2
1.4 1/18 3.93 11.1 12.4
1.6 1/16 4.16 12.5 14.0
3.2 1/8 8.35 24.9 27.6
6.4 1/4 16.60 49.8 55.8
10 3/8 24.9 74.7 83.8
Notes :
1- All plate weights are in kg / m2
1- 2 - 1 / 24 - inch means gage24.
2- 3- mm & Inch are Plat Thickness.
3- 4- All these Mineral Plates are used
4- normally for construction purposes.
Notes :
1- L1 & L2 = Span of edge & intermediate panel.
2- Extended Tension steel bars inside walls is 6”.
3- Bend-up angle for all steel bars Inside the
slab or beam is 45o in both sides.
4-These values are used for both slabs and Beams.
5- Minimum. extended steel bars length inside the
wall = 12 x bar diameter.
Square 4 Ø 20 mm or 6 Column
Columns Ø 16 mm, with sections
up to (4) m stirrups 10 mm 30*30 cm
height @ 20cm spacing. 40*40 cm
- 27
4 No. 314 453 805 1018 1520 1964 2464 3217 4072 4536
- 28
10
No. 785 1131 2011 2545 3801 4910 6160 8043 10180 11341
- 29
cm
15
5.24 7.54 13.40 16.93 25.33 32.72 41.07 53.62 67.87 75.61
- 30
cm 2.23 3.23 5.74 7.26 10.86 14.03 17.60 22.98 29.09 32.41
30
Ø 10 40 75 75
mm
Ø 12 45 85 85
mm
Hook 180˚
Hook 90˚
Bar Size D 180˚ 90˚
(mm) (mm) L (mm) L (mm)
Ø 10 60 65 120
Ø 12 72 65 145
Ø 16 96 65 195
Ø 20 120 80 240
Ø 25 150 100 300
Ø 28 224 115 340
h b tf tw
Section mm mm mm mm kg/m
IPE 100 100 55 5.7 4.1 8.10
IPE 140 140 73 6.9 4.7 12.9
IPE 200 200 100 8.5 5.6 22.4
IPE 240 240 120 9.8 6.2 29.4
IPE 300 300 150 10.7 7.1 41.4
IPE 360 360 170 12.7 8.0 56.0
IPE 400 400 180 13.5 8.6 63.6
IPE 500 500 200 16.0 10.2 90.7
IPE 600 600 220 19.0 12.0 122.0
W H tw tf kg/m
Section
mm mm mm mm
HW 100 100 100 6 8 16.9
HW 150 150 150 7 10 31.1
HW 175 175 175 7.5 11 40.4
HW 200 200 200 8 12 49.9
HW 250 244 252 11 11 63.8
HW 300 294 302 12 12 83.5
HW 300 300 300 10 15 93.0
HW 300 300 305 15 15 104.8
HW 350 338 351 13 13 104.6
HW 350 350 357 19 19 154.2
HW 400 388 402 15 15 140.1
HW 500 492 465 15 20 202.5
S H
D Column Girder
span height Section Section
In (m)
H
(m) (m)
- 35
IPE- 200
10 - 15 5-6 1.5 - 2 IPE- 240
IPE- 240
S
IPE- 240
15 - 20 6–8 2 – 2.5 IPE- 300
IPE- 300
IPE- 300
20 – 30 8 – 10 2.5 – 3 IPE- 360
IPE- 360
IPE- 360
30 – 40 10 –12 2.5 – 3.5 IPE- 400
IPE- 400
Steel Structure Diagram
BUILDINGS
Dining.
- 42
Bathroom. 1.80 1.50
W.C. 1.10 0.80
Min. Residential Buildings
b L b
Slabs on walls 15 cm
Lintels 20 cm
Beams
Spans up to 3.5 m 20 cm
Spans up to 5.5 m 30 cm
Spans up to 7.5 m 40 cm
Note:
Beams bottom width is between 2/3
to ½ of its depth (D) but not less
than 1/3 of its D, and basically 3/5
of D is used.
b= Bearing sitting length of slab or
beam on walls or columns.
D= Slab, beam thickness or depth.
Slab or beam--------
D span b
R H= Stair Height
W = Stair length
q = Stair slope angle
Rules:
1- 2R + T = 584 to 660 mm
2- H / R = No. of stairs.
3- W = (T x No. of stairs)
4- Max. q = 42 o
Min. q = 20 o
Min. T = 215 mm
Max. R = 200 mm
5- Min. step width (80) cm for houses
& for buildings & offices is (100) cm.
Z – shape reinforcing
Recommendations:
1- Continuous Foundation thickness = T
2- Min. Y = T, No. of steps not limited.
3- Min. X= 2Y but not less than 30 cm
4- Use inclined Z – shape steel for the
the connection between the foundation
levels A & B and use the same type of
reinforcement used in the foundation
of the Bottom reinforcing mesh.
5- Min overlap of z-shape with original
foundation reinforcement is:
(40 – 60) * (bar diameter)
But not less than ( 30 ) cm in any case.
Notes:
1- t & b are the width and thickness
of the column section.
2- if (t) is equal to or less than (5 b)
the section will be considered a
Column, but if it is more than (5 b)
it will be considered a Shear wall.
3-In case (t) is between (3 - 5 b), it
can be considered both, based on
shear forces direction which are
subjected to the column section.
Notes:
1- Min. longitudinal grade for roads is
0.5% in snowy countries, and
0.3% for non-snowy countries.
2- Max. Highway Ramp grade = 8%.
3- In case of grades higher than 9%,
In hilly areas, extra length or
arches to be added to the road
profile so that to reduce the high
grades of the road in these areas.
B
2:3 slope
R
R = Right of the road is the width of the
- 69
including side ditches width & is equal to:
R= B + 2 (A x 3 / 2 + 3 + 1.5 + 1) meters
B= Fill or cut width, A= Fill or cut height.
3- Air voids in
Marshall 3- 6 3- 5 3- 5
specimen (%)
4- Air voids in
mineral
12 13 14
aggregate
(%), min.
5- Immersion-
Compression
Index of
70 70 70
Retained
Strength (%),
min.
/////////////////////////////////////
E.
A B CL
Q
R
S = 2R Arc Cos. (R - E) / R
- 86
Compacted Thick Compacted Thick Compacted Thick
30 cm Min. 50 cm Min. 60 cm Min.
Bridges and
Culverts
SHABAN 11th Edition - 88
Bridge Collapse due to
foundation Pier’s failure
SHABAN 11th Edition - 89
Types of BRIDGES
Type Span (m) Material
Multi or Less Than Concrete,
single hole 6 Steel,
Culvert Masonry
Small Girder 7 – 15 Conc., Steel
Medium 15 - 50 Conc., Steel,
Girder composite
Large Girder 50 – 150 Pre-stressed
multi spans Conc., Steel
Cable 150 – 250 Pre-stressed
Stayed Conc., Steel
Suspension 250-1400 Steel cables
Truss 90 - 550 Steel sections
Arch 90 – 500 Concrete,
Masonry
Note:
After completion of any major Bridge
structures, the loading test should be
applied to it, and it should satisfy all the
required design loads & Max. Allowable
Deflections before opening it to traffic.
Total Longitudinal
Joint Movement
Type Min in mm Max in mm
Buried joint under
1. continuous surface 5 20
Gap joint with
2.
poured sealant
5 12
Gap joint with a
3.
flexible member
5 50
4. Open gap joint 5 60
Fully cantilevered
5.
toothed plates
50 -
6. Special joints 100 -
Note : The Max. allowed Vertical Movement
Between the two Sides of bridge Joint is (3) mm.
H/3 f H/3
D ////////////
d
0.40 H
Notes:
1- Min. Footings Excavation,
D = 80 cm.
2- Min. Footing Thickness,
d = 50 cm.
3- Min. f = 20 cm.
4-Inside Wall casting mass Concrete
can be filled with 30 % stones.
5-Drain PVC (4)” pipes each 1 by 1 m
are needed, with filter layer behind
and along the complete wall height.
c- Construction joint:
Normally it is constructed after 1-day work or
after stopping concrete casting .
formed edge
with key
old cast new cast
////////////////////////////
Type of culverts :
1- Pipe culvert from concrete, steel and
high-density PVC.
2- Box from Masonry & concrete.
3- Arch from masonry and concrete.
4- Slab culvert from reinforced
Concrete and, or steel sections.
Tests :
Cement physical and chemical
properties, Concrete Slump, strength, and
temp., Steel Tensile strength, sand and
gravel gradation, stone masonry strength
& water absorption,
Under Soil tests and bearing capacity.
Notes:
1- Use a Inspection pipe (6.0)” diam.
2- Use a Manhole cover (40 x 40) cm.
3- Partition Wall to be constructed
for dividing the septic tank into two
parts with crossing opening for
fluid passing between the 2 parts.
4- Adding Free board 30 cm over the
Depth D, Total depth = D + 30 cm.
1.0 m graded
Boulder max. size 5cm
60 – 80 cm width
Slotted drain pipe
Notes:
1-Above typical deep filter can be used
for Both Road sides in shoulders and
In the buildings Surroundings.
2- Drain slotted pipes type can be from
concrete, PVC, or steel, dia. 40-50 cm.
3- Pipe bed slope for Draining should be
not less than 0.5 %, not more than 5%.
4- Covered Manholes are required every
Certain distance for Checking purpose.
Notes :
1- For excavations with high water table
levels, a dewatering system is
required to dry water seepage inside
the excavations by digging deep
pumping wells around the building.
2- Lateral support for excavation sides
is needed from perpendicular steel
or wood inserted sheet piles.
3- The dewatering process should be
continued till finishing all the building
structures inside the excavations.
Lean concrete
Base 20 cm Crushed stone 10 cm
B
//////////////////////////// Q
////////////////////////
4H
Weir is a barrier across the width of a
river that alters the flow characteristics
of water and usually results in a change
in the height of the river level and flow.
To calculate its discharge :
Q = C B H 3/2
Above is Basin formula which is used
for rectangular weirs sections.
Q = discharge in m3 /sec.
C = Flow coefficient for the structure
(on average a figure of 0.62)
B = weir transverse width in (m)
H = height of water over flow in (m)
slump
Concrete member mm.
Max. Min.
Reinforced foundations
footings and walls 100 50
Plain non-reinforced footings
and sub-walls. 75 25
Beams, Shear walls and
reinforced slabs 125 30
Building columns 125 75
Rigid concrete Pavements
and slabs 50 25
Mass concrete structures
50 25
huge foundations , Dams.
- 132
Concrete Mixtures
Notes:
1. Above table is for the dry materials
& quantities are per (50kg) cement
Bag , which volume=0.035 m3 .
2. For wet sand & gravel use less w/c
ratio quantities for the mixture.
3. Use mechanical vibrators directly
after placing concrete mixture on
site, especially for the reinforced concrete
mixtures works on site.
Member d
Roof and floor slabs without
L / 25
supporting beams
Light beams with small
L /15
effective spans
Notes:
1- L is the span of the beam or slab in mm.
2- The width of a beam should be at least :
= Beam length / 32
3- d= Beam or slab depth in millimeters.
12.5 ¾ ¾-1½
or less
28 to 74 ½-3 3–6
74
or more 1½-3 6
Estimation
SHABAN 11th Edition - 148
AREAS
1-Sector of Circle:
A= (q / 360) * π r2
q = Angle in degree q
r = radius r
2- Ellipse:
A=1/4 * Major Axis * Minor Axis*π
3- Parabola:
A = 2/3 * B * H H
B = base
H= Height.
4-Tripozoidal:
A= ½ (b1 +b2) * h B
b2= b1+a+c
h = Height
5- Circle:
A = π * r2 ,
r = radius
A2 H
A1
3- Spherical segment:
V= ╥ h2 (r-h/3)
r = radius
h=height of the segment.
╥ = 3.14 h
r
4- Ball: Volume = 4/3 ╥ r3
Co = 5 / 9 (F o – 32)
C = Centigrade , F = Fahrenheit.
2- Quantities Estimation:
Concrete works V= 0.67 * (C+S +G)
Cement Mortar Vm = 0. 75 (C+S)
Gypsum Mortar Vm =Area * thick *1.1
Stone Masonry Vm = 0.30( V )
Bricks Masonry Vm = 0.23 ( V )
Concrete Blocks Vm = 0.13 ( V )
V =Total Volume, Vm= Mortar volume.
C, S, G = cement, sand & gravel vol.
3- Simpson Rule:
1-Site Preparation 2%
and excavation
2-Foundations 4%
3-Masonry works under 4%
ground level.
4-Masonry works above 18%
ground level.
5-Roofing and curtains 10%
6-Flooring and tiles 9%
7-Doors and windows 9%
8-Internal finishing 13%
9-External finishing 10%
10-Water supply + Gas 3%
net system (LPG)
11-Sanitary works 5%
12-Air-conditioning 3%
13-Electrification + fire 5%
alarm + CCTV cam.
14- Mechanical and fire 5%
fighting works.
Total 100 %
SHABAN 11th Edition - 152
Approx Roads Items cost %
% of
ITEM Total
1-Site exploring, satellite 1%
photos, & road route options.
2- Soil investigation reports, 2%
and boreholes.
3- Hydraulic study for culverts 1%
and bridges structures.
4- Digitizing satellite photos and 1%
complete surveying works
5- Designs work profile and 8%
cross sections with BOQ
6- Design of retaining walls and 3%
hydraulic structures.
7- Assigning right of road. 1%
8- Retaining walls and Earth cut 26%
and fill excavations work.
9-Hydraulic structures work. 18%
10-All road pavement layers. 34%
11-Finishing works, traffic signs, 5%
painting and guard rail.
Total 100 %
1- Bricks size
(7x11x23) cm 450 -
cement mortar1:3
2- Concrete
Blocks size 73 -
(15x20x40) cm.
3- Sand bricks
410 -
(20x10x5) cm.
4- Light weight
Blocks size. - 7
(50x30x20) cm
5- Tiles size
- 45
(15 x 15) cm
6- Tiles size
- 25
(20 x 20) cm
7- Tiles size
- 16
(25 x 25) cm
8- Tiles size
- 12
(30 x 30) cm
TOTAOL AMOUNT
5 – 10 6000
10 - 15 8000
15 - 25 12000
32 – 40 18000
40 – 50 24000
65 - 90 34000
130 – 140 48000
185 – 230 72000
Notes:
• Above figures are for Normal houses,
with 3.0 height and normal insulation.
• For better insulation deduct 10 % BTU
• For very sunny houses add 10 % BTU
• For crowded rooms add 600 BTU per
every extra person inside the room.
• For hot kitchens add an Extra 400 BTU.
No. of A B C D
Persons KG m m m m
5 340 1.3 1.0 1.7 1.3
6 408 1.3 1.2 1.8 1.5
8 544 1.5 1.3 1.9 1.6
12 884 1.9 1.5 2.3 1.9
Isolation
Sound Levels in dB
Source Decibel dB
Whisper 30
Rainfall 50
Conservation 60 – Normal Level
Factory 80
Jet Engine 130
Wall Insulation
d1 d2
a2 b2 Fig: 2
A B Q
d1+d2 d3
Error(e) =
(a2 - b2) - (a1 - b1) / (d1 + d2)
1-At Fig 1, Put the level at point P and
Take levels at A & B, read a1, b1
2-At Fig 2, read levels at A & B, while
the level instrument is at Q point,
read a2, b2.
3-Calculate e, allowable error(e) is = to
+, - 0.5 mm per each 10 m length.
4- d1, d2, & d3 are about 25 m.l each.
5- C = 0.0675 K2
C= Leveling curvature correction factor
in meters due to earth's surface.
K= Leveled Distance in Kilometers.
E
e
AB , AD , DB.
De = (0.5) DB
AC = (0.5) AB
DE = (0.5) AD
C
A
R
B
DC , EF , ef are
perpendicular on
R=Radius, DC= (AB)2 /8R , EF & ef = DC/4
- 193
3- Find DC, EF, e and f, from above equation.
4- Locate points (E, F, D ,e, f).
5-Draw curve (A,F,D,f ,B) , then you will get curve .
Horizontal curve Setting
Total Station
Live Load
No. USE
kg/m2
1 Apparemntments 750
2 Balconies 500
3 Party halls 500
4 Hospitals 400
5 Hotels 650
6 offices 475
7 Schools 350
8 Stores – Light 600
9 Stores – Heavy 1250
10 Libraries 350
11 Theaters 300
12 Stairs & Exit ways 400
13 Mosques 375
14 Industries Halls 1450
15 Machine Rooms 1350
To: ---------------------------------------------
Subject: ---------------------------------------
Dear Sir:
---------------------------------------------
---------------------------------------------------
--------------------------------------------.
With best regards
Signature
Engineer Name
Cc:
- Main office – for information
- Project File
_____________________________________________
Info@sadaconsult.com
www.sadaconsult.com
IRAQI- Kurdistan, Erbil – Ainkawa
Adasheer Str., +964-770-446-1234
www.shabanbooklet.com