Audit 2005
Audit 2005
66/2011)
NON RECOVERY ON ACCOUNT OF SECURITY DEPOSIT
AMOUNTING TO RS.7.633 MILLION FROM INDUSTRIAL
CONSUMER
Keeping in view the position explained above, the Draft Para may please be
dropped.
PARA NO. 20
The relevant record has been examined and observed that Agreement with M/s
Barqaab was executed exactly in the light of instructions contained in M.D (PEPCO) letter
No. _____________ dated _________ for the assignments / works pointed out by the Audit.
(Annex-A & B)
It is further added that only payment of those works has been made which have been
completed by the Consultants. The payment of pending works will be made only after
completion of work by M/s Barqaab.
Keeping in view the position explained above, the point may be dropped.
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
Keeping in view the position explained above, the Draft Para may please be
dropped.
No.____________/P&D/DRW/ Dated____/01/2011
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
As the applicant provided the paid copy of paid Demand Notice of Security,.
Therefore the audit point may please be dropped.
No.____________/P&D/DRW/ Dated____/02/2010
Hamid / TC-newconnection
4. Master file
No.____________/P&D/DRW/408/Skp. Dated____/1/2010
Hamid / tc-ext-3
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
Info: 1. Manager (O) Northern Circle LESCO ) to follow up and get the
2. Manager (O) Northern Circle LESCO ) recovery effected without
) further loss of time.
4. Master file
No.____________/P&D/DRW/311/Ist Dated_____/1/2010
Hamid/dak-5
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
Info: 1. Manager (O) Northern Circle LESCO ) to follow up and get the
2. Manager (O) Northern Circle LESCO ) recovery effected without
) further loss of time.
5. Master file
No.____________/P&D/DRW/311/Ist Dated_____/1/2010
Hamid/dak-5
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
No.____________/P&D/DRW/317/Ist Dated____/1/2010
Haimd/tc-newconn
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
Reference: Your office letter No. 1652/AP-2825, 1628/AP-2801, 1641/AP-2814 & No.
1654/AP-2827 all dated 3-12-2009.
The documents pertaining to 04 No. Advance Paras, received vide your above
referred letters are returned herewith in original as the same do not relate to this office.
Therefore the same may be sent to quarter concerned to proceed further.
No.______________/DRW/ Dated______/12/2009
Hamid Audit-2005
Final Notice
Subject: NON-PAYMENT OF LESS RECOVERED AMOUNT OF RS. 155,767/-
AGAINST NEW CONNECTION FOR 1050 KW LOAD IN THE NAME OF
SARDAR IQBAL S/O GHULAM HUSSAIN FOR M/S AL-HADEED
INDUSTRIES (STEEL FURNACE & RE-ROLLING MILLS) 16-KM
SHEIKHUPURA ROAD LAHORE AGAINST APP. NO. 326/B3/NEW DATED
3-1-2007
Despite elapse of period of one year, you have not deposited less recovered
amount of capital cost: Rs. 155,767/-, which was pointed out by the Audit. You are finally
requested to deposit the same with Finance Director LESCO within 10-days positively to
avoid disconnection of supply.
Info: 1. Finance Director LESCO. As soon as difference of capital cost Rs. 155,767/-
is realized in his account, the same may be transferred to LESCO Income
Account under intimation to this office .
4. Master file
No.____________/P&D/DRW/295/Ist Dated____/11/2009
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
No.____________/P&D/DRW/425/2nd Dated____/6/2008
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
FAX MESSAGE
Please issues Notices to the consumers to apply for extension of load in this
office under Tariff B-4 within 10-days, otherwise they may be restricted within their
sanctioned load by installing digital relay under intimation to this office.
No._____________/DRW/ Dated______/5/2009
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
FAX MESSAGE
Please issues Notices to the consumers to apply for extension of load in this
office under Tariff B-4, otherwise they may be restricted within their sanctioned load under
intimation to this office.
No._____________/DRW/ Dated______/5/2009
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
FAX MESSAGE
Please issues Notices to the consumers to apply for extension of load in this
office under Tariff B-4, otherwise they may be restricted within their sanctioned load under
intimation to this office.
No._____________/DRW/ Dated______/5/2009
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
Keeping in view the position explained above, the paras may please be settled.
No.____________/P&D/DRW/1061/LESCO Dated____/3/2009
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
Keeping in view the position explained above, the para may please be got
settled.
No.____________/P&D/DRW/228/2nd Dated____/1/2009
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
No.____________/P&D/DRW/309/2nd Dated____/1/2009
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
The requisite reply has already been given to Manager (Internal Audit)
LESCO vide this office No. 11343-53 dated 24-1-2009 & 11299-300/P&D/DM(M&R)
dated 23-1-2009. Photocopies of the same are being enclosed.
No.______________/DRW/ Dated______/1/2009
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
Reference: Your office letter No. 2413/AP-2543 dated 23-10-2008 and No. 2848 dated
5-12-2008.
The case has been examined and brief facts to the extent of Sundar Industrial
Estate are given as under:
1. Punjab Govt. set up an Industrial Estate at Sundar (PIE). Initially it was intimated
that total demand of Sundar Industrial Estate is 150 MW ( In three years) for which
they are planning to construct their own Power Plant of capacity 200-250 MW.
2. M/s PIE intended to construct their own grid station by installing 3 x 30/40 MVA
Power Transformers for catering initial 50% load requirement. However 132 kV
transmission line was to be constructed by LESCO for which Sponsors had already
deposited Rs. 1,17,00,000/-
3. In the first instance new connection of 4.8 MW load provisionally under tariff B-3
was allowed in 3/2006 through 2 No. 11 kV feeders by proposing installation of
10/13 MVA Power Transformer at 132 kV Chak-65 grid station for which M/s PIE
deposited estimated cost: Rs.50.82 Millions. Subsequently EOL from 4.8 MW to 10
MW was allowed.
4. Since the mode of supply of power to Sundar Industrial Estate was not covered under
the definition of any existing Tariff and Tariff C is also not applicable to Sundar
Industrial Estate being industrial nature of use; as such provisionally Tariff B-4 was
allowed. However the Sponsor has already been requested to take up the matter with
NEPRA for allowing special tariff.
5. The matter of services as pointed out Audit will be dealt with on receipt of decision
from NEPRA or competent authority.
No.____________/P&D/DRW/309/2nd Dated____/1/2009
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
Reference: Your office letter No. 2413/AP-2543 dated 23-10-2008 and No. 2848 dated
5-12-2008.
The case has been examined and brief facts to the extent of Sundar Industrial
Estate are given as under:
6. Punjab Govt. set up an Industrial Estate at Sundar (PIE). Initially it was intimated
that total demand of Sundar Industrial Estate is 150 MW ( In three years) for which
they are planning to construct their own Power Plant of capacity 200-250 MW.
7. M/s PIE intended to construct their own grid station by installing 3 x 30/40 MVA
Power Transformers for catering initial 50% load requirement. However 132 kV
transmission line was to be constructed by LESCO for which Sponsors had already
deposited Rs. 1,17,00,000/-
8. In the first instance new connection of 4.8 MW load provisionally under tariff B-3
was allowed in 3/2006 through 2 No. 11 kV feeders by proposing installation of
10/13 MVA Power Transformer at 132 kV Chak-65 grid station for which M/s PIE
deposited estimated cost: Rs.50.82 Millions. Subsequently EOL from 4.8 MW to 10
MW was allowed.
9. Since the mode of supply of power to Sundar Industrial Estate was not covered under
the definition of any existing Tariff and Tariff C is also not applicable to Sundar
Industrial Estate being industrial nature of use; as such provisionally Tariff B-4 was
allowed. However the Sponsor has already been requested to take up the matter with
NEPRA for allowing special tariff.
10. The matter of services as pointed out Audit will be dealt with on receipt of decision
from NEPRA or competent authority.
No.____________/P&D/DRW/309/2nd Dated____/1/2009
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
8. Master file
No.____________/P&D/DRW/1061/LESCO Dated____/12/2008
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
It is intimated that while preparing estimate for the subject extension of load,
an amount of Rs. 592,394/- (share cost of existing poles) was less recovered from you due
to computer mistake. Therefore Demand Notice of the requisite amount viz. Rs.592,394/- is
being enclosed, which may please be deposited with Finance Director LESCO under
intimation to this office.
To: Mr. Faraz Shafiq Alam S/O Mian Muhammad Shafiq Alam,
for M/s Alam Cotton Mills (Pvt.) Ltd.
6-KM Off Manga Raiwind Road, Lahore
Info: 1. Finance Director LESCO. As soon as difference of capital cost Rs. 592,394/-
is realized in his account, the same may be transferred to Sr. Manager
Construction LESCO through Credit Advice under intimation to this office.
2. Master file
No.____________/P&D/DRW/371/2nd Dated____/12/2008
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
10. M/s Jansons Engineering Survives, 3 rd Floor IEP Building 97-B/D-1 Main
Boulevard, Liberty Roundabout Gulberg-III, Lahore.
No.____________/P&D/DRW/1083/LESCO Dated____/11/2008
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
Hamid Audit-2005
Hamid / Audit
LESS RECOVERY OF CAPITAL COST DUE TO CALCULATION MISTAKE OF
RS.900/- M/S KSF TRIZONE
The relevant record has been examined and observed that although
dismantlement charges of Rs.900/- are less recovered due to typing error but Rs.1423/- are
recovered in excess in the same estimate on account of Barqaab charges which are not
recoverable on the amount sent to DM (O) and only leviable on the amount sent to
Sr. Manager Construction. Hence due to compensating error no loss has been sustained by
the department as such keeping in view the position explained above, the point may be
dropped.
UNDUE BENEFIT OF RS. 6.088 MILLION
TO THE CONSUEMR ON ACCOUNT OF CAPITAL COST
The relevant record has been examined and observed that Para is not based on
fact. Brief history of the case is as under:-
M/s Mayfair Textile was approved as B-3 connection with independent feeder during
07/1993 from Raiwind grid station on cost deposit of Rs.60,19,032/-. The firm left WAPDA
during 03/1996 and opted to receive supply from Kohi-Noor Genetic Ltd. During the
period of disconnection, the feeder; most of which ran along Rohi Nala either fell down into
the Nala or was subjected to various attempts by gangsters lost its identity and was utilized
in different parts by the field staff as such its Rehabilitation was not possible when M/s May
Fair intended to switch-over to LESCO system in 2000 and a new arrangement had to be
resorted-to in view of the fact that May Fair fell nearer to Chak-65 than Raiwind grid station
and had lesser operational problems with less line losses while remaining with Chak-65 grid
station.
As per incentive package for RCO of CPP consumers, new feeder was proposed for
Mayfair and the Rehabilitation cost was required to be borne by the department and as a
stop-gap arrangement 3500KW load of M/s Mayfair was connected with independent Shah
Nawaz feeder. Subsequently Yarn Textile (779 kW) and Empire Textile (1500 kW) were
also connected with Shah Nawaz feeder after recovering cost 0.96 Million and subsequently
load of M/s Mayfair was also extended from 2940 kW to 4200 kW on the same Shah Nawaz
feeder and M/s Shah Nawaz during the entire period kept on recording protests on this
unilateral onslaught.
Now M/s Shah Nawaz has also come-up with his applied extension of load from
2400KW to 3200KW, but with 4200KW of M/s Mayfair, technical parameters of the feeder
cross permissible limits with simulated extension of M/s Shah Nawaz and there is a need to
disassociate M/s Mayfair from 11 kV Shah Nawaz feeder so as to provide sufficient slot of
load for Shah Nawaz to accommodate its extension of load.
Accordingly as per approval of BOD, the case was processed cost and estimated cost
of proposed 11 kV feeder for M/s Mayfair at fresh rates of inventory comes to be Rs. comes
7.76 Million instead of Rs. 5.4 (previously worked out at old rates). As per
recommendations of Legal Director LESCO Rs.6.08 Million shall be borne by LESCO upto
load 2940 kW and remaining amount of Rs.1.67 Million upto load 4200 kW was recovered
from M/s Mayfair. However the final bearable cost by LESCO comes to (Rs.6.08-0.96M)
=Rs.5.12M instead of Rs.6.08 M.
Keeping in view the position explained above, the para may be dropped.
RECOMMENDATIONS OF LEGAL DIRECTOR LESCO REGARDING
CONSTRUCTIN OF 11 KV FEEDER FOR M/S MAFAIR TEXTILE
At Page-4 of the report, Legal Director LESCO opinioned that there is no
legal implication in construction of feeder for M/s Mayfair at LESCO’s cost on
the following grounds:
1. LESCO has utilized, for its benefit, the 11 kV feeder of approximately 10-KM length
which was constructed at the cost of M/s Mayfair to provide electricity to it premises.
2. It has been agreed vide clause-4 of the approval letters No. 7904-11/DRW/288/SE-3
dated 17-8-2000 and 6474-80 dated 6-2-2003 about reconnection of M/s Mayfair that
the proposed 11 kV feeder shall be constructed / extended upto the premises of M/s
Mayfair at departmental (LESCO’s) cost chargeable under head MOLD. This is
binding in nature.
3. The clause (v) of WAPDA policy letter No. 768-82/GMO/PA dated 8-9-2000 lays
down that the cost of stolen material of CPP consumer lines during the disconnection
period shall be borne by WAPDA. It means that the intention behind this was that
upon reconnection, the supply of energy to the CPP consumer was to be made by
rehabilitation, at WAPDA cost, of the line (feeder), which was constructed at the cost
of that consumer. In this case the rehabilitation of that line / feeder was not possible
as LESCO had already utilized that feeder almost entirely for its own benefit.
Therefore, by keeping in view this intention as well as the fact that no compensation /
refund was given to M/s MSM for utilization of its lines / feeder by LESO, provision
of electricity to it through lines / feeder constructed at LESCO cost is quite
justifiable. However LESCO is only bound to provide a load upto 2940 kW
at its own cost now, because the original feeder of M/s MSM which was
constructed at its cost and designed for this load was later on utilized by
LESCO. Any additional expenditure which may be incurred to upgrade
the proposed feeder for capacity of extended load of 4200 kW may be
taken from the consumer.
4. Since some portion of original feeder was not utilized by LESCO as it reportedly fell
in to Rohi Nala, therefore, if the cost of new feeder exceeds from the cost of feeder
utilized by LESCO, then it may be recovered from the consumer M/s Mayfair
Spinning Mills. It is further suggested that dues permissible for extension of load
may also be recovered from M/s STM for accommodating their request of EOL
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
FAX MESSAGE
Please refer to this office letter No. 6606-08 dated 13-9-2007 vide which a
copy of Audit Para No. 31 was sent to your office with the remarks to confirm that the
material mentioned in the Para is returned to store besides providing a copy of MRN. But
despite elapse of a period of about one year nothing has been heard from your end which
has been viewed seriously.
You are once again advised to look into the matter at personal level and
confirm that material mentioned in the Para has been returned to store. A copy of MRN may
also be supplied to this office immediately so that Audit Para may be got settled.
MATTER MOST URGENT
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
FAX MESSAGE
Please refer to this office letter No. 20861-62 dated 14-6-2008 vide which a
copy of Audit Para No. 17 was sent to your office for submission of appropriate reply but
the same is still awaited from your end.
The matter may be looked into at personal level and requisite report be sent to
this office without further loss of time so that the Para may be got dropped / settled from
Audit.
Hamid / Audit
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
FAX MESSAGE
Please refer to this office letter No. 20918-19 dated 14-6-2008 vide which a
copy of Audit Para No. 07 was sent to your office for submission of appropriate reply but
the same is still awaited from your end.
The matter may be looked into at personal level and requisite report be sent to
this office without further loss of time so that the Para may be got dropped / settled from
Audit.
Hamid / Audit
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
While going through the record, it has been observed that the Para is not based
on fact. The ban on new furnace connections was imposed verbally on the request of Steel
Melters Association and not by the Authority at its own. Furthermore extension of load in
the instant case was allowed for Steel Re-Rolling Mills which comes under different nature
of industry than furnace.
From the above it is clear that the para is not justified as such the same may be
dropped / settled.
Hamid / Audit
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
The relevant record has been examined and observed that Para is not based on
fact. Point-wise reply is given as under:
(i) The cost of grid station & transmission line is being recovered in installments
as per decision of Board of Directors LESCO. A copy of Minutes of BOD
meeting is being enclosed.
(ii) Since the consumer is already running a furnace connection for
4500 kW load, therefore levy of ban on such connections cannot be imposed.
It is further clarified that ban on new furnace connections was imposed on the
request of Steel Melters Association and not by the Authority.
Keeping in view the position explained above, the para may be dropped /
settled.
Enclosed please find herewith a copy of Audit Para No. 07, which is self-
explanatory and relates to your Circle.
Please go through the contents of enclosed Para and submit appropriate reply
so that the Para may be got dropped / settled from Audit.
Hamid / Audit
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
2. Para # 1,12 Less recovery of R&R As already intimated the case was
& 22/A charges: Rs.2,48,597/-. referred to Chief Engineer (O) Wapda
House, Lahore for clarification vide this
office No. 9934-35/DRW/203 Ist dated
16-12-2005. But despite reminder issued
vide No.5719-20 dated 28-8-2007 &
14536-37 dated 6-3-2008 no response
has been received till date. The case will
be decided on receipt of clarification
and your office will be informed
accordingly.
3. Para # 2 Undue benefit of capital As already intimated in order to bring
cost: Rs.20,77,441/- to the technical parameters within
the consumers due to specified limit reconductoring of 11 kV
revision of estimate. feeder amounting to Rs.90,869/- was
(M/s Bhatti Cotton) required. The work of reconductoring
has already been completed. After
adjustment of requisite amount an
Rs.311,130/- is still in hand. It is further
added that no undue benefit was given
to the consumer. Technical parameters
of the feeders are still within the
specified limit. A statement showing
progressive loss of the feeder is being
enclosed. Therefore the para may be
dropped.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
Hamid / Audit
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
Subject: AUDIT PARA NO. 1,12 & 22/A – NEW CONNECTION OF M/S JAVAID
INTERNATIONAL (PVT.) LTD. 17-KM SHEIKHUPURA ROAD LAHORE
Hamid / Audit
AUDIT PARA NO. 4 – CREDIT OF DISMANTLED CONDUCTOR
AMOUNTING TO Rs. 5,32,080
EOL of M/s New Shalimar Steel Industries (Pvt.) Ltd. from 2000 kW to
4500 kW was approved during 3/2005 vide CP-198. Since existing Dog conductor of 11 kV
independent feeder of the consumer was to be replaced with Osprey conductor. Therefore
credit of Dog conductor as per scrap value amounting to Rs.5,32,080/- was given in the
estimate. But Audit Party of Deputy Chief Auditor during the audit of this office pointed out
that credit given in the estimate was not in order and taken point on this score.
Accordingly the consumer was requested to deposit the requisite amount vide
this office No. 11611-12 dated 29-11-2006 (CP-148). But despite repeated reminders
consumer has not deposited the amount whereas Audit is pressing very hard for early
recovery of the requisite amount.
It is worth mentioning here that in 4/2007, consumer applied for EOL from
4.5 MW to 7 MW. In this regard the consumer has also deposited tentative cost of civil for
grid station amounting to Rs. 50 lac which was transferred to PD GSC by FD LESCO vide
CP-182.
2. Para # 1,12 Less recovery of R&R As already intimated the case was
& 22/A charges: Rs.2,48,597/-. referred to Chief Engineer (O) Wapda
House, Lahore for clarification vide this
office No. 9934-35/DRW/203 Ist dated
16-12-2005. But despite reminder issued
vide No.5719-20 dated 28-8-2007 &
14536-37 dated 6-3-2008 no response
has been received till date. The case will
be decided on receipt of clarification
and your office will be informed
accordingly.
3. Para # 2 Undue benefit of capital Only an amount of Rs.127,561/- was
cost: Rs.20,77,441/- to required for reconductoring of
the consumers due to 150-meter line length to bring the
revision of estimate. parameters within specified limit. The
(M/s Bhatti Cotton) work has already been completed. A
copy of financial closure received from
St. Manager Construction vide No. 888
dated 20-1-2006 is being enclosed
which reveals that an amount of
Rs.4,01,999/- is still in hand. On receipt
of consumer’s request for refund of
unspent amount, after adjustment of
Rs.127,561/- remaining amount will be
refunded; as such the para may be
settled because no recovery is involved
in this case.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-200)
E-mail: srmanpd@lesco.gov.pk
The case has been examined and observed that total amount of Draft Para as
mentioned in the subject was Rs.45,42,627/-, out of which D.G. Wapda has verified Rs.
43,39,173/-. Store Statement received alongwith the case reveals that dismantled 200 kVA
Transformer was returned to store and no mis-appropriation of material is involved in this
case as intimated by DM (O) Gulshan-e-Ravi Division, LESCO, Lahore. Therefore in order
to settle the remaining amount of Draft Para: Rs.2,03,458/-, Chief Executive Officer
LESCO has accorded Ex-post facto approval for the augmentation of 200 kVA Transformer
to 400 kVA Transformer. D.G. WAPDA Audit may be informed accordingly.
The case file received from your office is returned herewith in original.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-200)
E-mail: srmanpd@lesco.gov.pk
The reply to Audit Para No. 19 (copy enclosed) is given as under please:-
M/s Lahore Propylene Industry (Pvt.) Ltd. applied for Extension of load from
965 kW to 1800 kW in 3/2006. As per policy of the department the case was processed
through 11 kV independent feeder from 132 kV Manga Mandi grid station.
As 45-ft. spun poles have been installed in the interest of LESCO as such
recovery of total cost from the instant consumer is not justified, therefore, the para may please
be dropped.
The reply to Audit Para No. 21 (copy enclosed) is given as under please:-
M/s Dewan Faorque applied for new connection for 3000 kW in 4/2006. As
per policy of the department the case was processed through 11 kV independent feeder from
132 kV Bhaipheru grid station.
As 45-ft. spun poles have been installed in the interest of LESCO as such
recovery of total cost from the instant consumer is not justified, therefore, the para may please
be dropped.
The matter was referred to AM (CS) Phool Nagar, who vide his letter No.
1490 dated 3-9-2007 (copy enclosed) has confirmed that payment of installments of security
is being received regularly as per schedule.
2. Master file.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-270)
E-mail: srmanpd@lesco.gov.pk
Enclosed please find herewith a copy of Audit Para No. 32 regarding non-
confirmation of return of material removed while effecting ROL from 3350 kW to 505 kW
in the name of Mian Muhammad Yousaf Aziz for M/s Ittefaq Textile Mills approved by this
office vide Reference-1.
You are advised to look into the matter at personal level and confirm that
material mentioned in the enclosed letter has been returned to store. A copy of MRN may
also be supplied to this office immediately so that Audit Para may be got settled.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-270)
E-mail: srmanpd@lesco.gov.pk
Reference: This office letter No. 9934-35 dated 16-12-2005 (copy enclosed for ready
reference).
DA – As above Salah-ud-Din
CE/ Technical Director
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-270)
E-mail: srmanpd@lesco.gov.pk
FAX MESSAGE
Despite repeated reminders and elapse of a period of more than two years
copy of MRN of 630 kVA dismantled Transformer is still awaited from your end which has
been viewed seriously by Audit during meeting dated 27-8-2007.
You are advised to supply a copy of MRN upto 30 th August 2007. However if
L.S concerned fails to supply the same within stipulated period then his salary for the month
of August 2007 may not be released besides initiating disciplinary action against him.
Salah-ud-Din
CE/ Technical Director
Info: 1. Manager Internal Audit LESCO (Atten. Mr. Atta-ur-Rehman, Audit Officer)
3. Master file.
Please refer to this office letter No. 3670 dated 12-7-2006 vide which you
were advised to confirm return of material at estimate / credit value to the store through
return fax message but despite elapse of period of more that 6-months nothing has been
heard from your end which has been viewed seriously by Audit.
Please realize the gravity of situation and submit the requisite report by 13-2-
2007 without fail.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-200)
E-mail: srmanpd@lesco.gov.pk
While consolidating the latest status of all the cases, it is intimated that out of
total 12 No. connections, securities for the extended load have been paid by
8 No. consumers whereas 4 No. consumers have reduced their loads as manifested by the
MDI being recorded during the last one year which confirms containment of loads as
already conveyed vide this office letter given at Reference.1 (list attached).
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph: # 6308360 PBX: 6314616-20 (Ext.200)
E-mail: srmanpd@lesco.gov.pk
Deputy Manager (O) Township LESCO has repeatedly been sending Notices
for the containment of MDI to your approved limit of 4990 kW, since MDI recorded by him
has shown quite excess to the approved figure for more than two years.
Now with this sustained increase of MDI, Director General, Audit has taken
serious observation as such you are requested either to restrict your use of load upto 4990
kW or immediately move for consumer grid as applicable for industrial load exceeding
5000 kW.
Through this Notice; you are requested to proceed as per above and in case
of default, power supply to your premises will be disconnected right after 7-days without
any further Notice.
Info: 1. Manager Internal Audit LESCO with reference to the meeting held in this
office today as on 20-11-2006.
Perusal of enclosed list will indicate that out of total 12 No. connections,
securities for the extended load have been paid by 7 No. consumers whereas 4 No.
consumers have reduced their loads as manifested by the MDI being recorded during the
last one year which confirms containment of loads. Demand Notice for the remaining one
No. connection: M/s Shahkam has been issued and the consumer has promised to pay the
same within three days. Audit will be informed about the payment as soon as the same is
paid.
In view of above, it is requested that the Audit may be approached to settle the
Para or to atleast keep the status of the Para to Advance Para and not to convert the same to
Draft Para, as the needful of almost all the Nos. as indicated in the list has since been done
as per requirement of Audit serving a single connection, which, too, is in the process of
payment expected in 2/3 days maximum.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-200)
E-mail: srmanpd@lesco.gov.pk
Since the consumer has deposited security: Rs.57,750/- & R&R charges:
Rs.52,500/- as such the para may be dropped. Photocopies of paid Demand Notices are
being enclosed.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-270)
E-mail: srmanpd@lesco.gov.pk
Fax Message
Please refer to this office letter No. 3270-72 dated 6-7-2006 vide which you
were advised to issue final notice to deposit capital cost Rs.212,464/-& security
Rs.546,000/- within 10-days, failing which their supply may be disconnected.
The progress achieved in this regard may be faxed to this office immediately.
2. M/s N.P. Spinning (Pvt.) Ltd. 1.5 KM Lullyani Road Opp. Raiwind Grid
Station Raiwind.
3. Master file.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A Queens Road Lahore
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-200)
E-mail: srmanpd@lesco.gov.pk
Pleaser refer to your letter No. 2786-90 dated 27-7-2006 and intimate the
progress achieved so far.
Hamid / Audit-2005
Para No. 47
(1) . Previous owner Mr. Iftikhar Ahmad Malik lodged complaint NO. L/2392/03
with Wafaqi Mohtasib regarding refund of security deposited for new connection for a
load of 2056 kW. Wafaqi Mohtasib vide order dated 9-6-2004 decided the case as
under:-
2. LESCO / WAPDA preferred appeal against the decision of Wafaqi Mohtasib before
President of Pakistan. The decision of President of Pakistan is given as under:
“ The property of the company is not in law the property of the management /
shareholders. Thus, the premises where the Agency is supplying electricity
belongs to the company and not the old or new management / shareholders’’
3. In the light of above decision security deposited for the load of 2056 kW was not
refunded to the previous owner and only security for the extended load of 400 kW
(2056 kW – 2456kW) was recovered from the present occupier / owner.
have been advised to direct their Deputy Managers (Operation) to have a close watch on the
MDI of consumers and take action against the consumers who involved in
The subject consumer applied for EOL from 393 kW to 900 kW.
Since as per energy bill sanctioned load of the consumer is 375 kW as such he was advised
to apply for EOL from 375 kW to 900 kW but he failed to do so due to which application
was cancelled vide above referred letter.
Audit Party during the course of audit of this office has noticed that the
consumer has extended his load un-authorizedly upto 480 kW and has desired to recover
security and R&R charges for the extended load. Therefore Demand Notices for R&R
charges: Rs.52,500/- & security: Rs.57,750/- are being enclosed which may be got served to
consumer. If he fails to make within stipulated period, his connection may be disconnected
under intimation to this office.
Hamid / Cancelled
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-200)
E-mail: srmanpd@lesco.gov.pk
AM (CS) Raiwind vide his letter No. 2343-46 dated 15-7-2006 (copy
enclosed), the consumer has deposited the Demand Notice of security: Rs.18,20,000/- in
UBL Raiwind on 12-7-2006.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-200)
E-mail: srmanpd@lesco.gov.pk
Subject: AUDIT PARA NO. 22 – EOL OF M/S NAZIR PAPER & BOARD
MILLS (PVT.) LTD.
It is, therefore, requested that the subjected para may be settled / dropped.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-200)
E-mail: srmanpd@lesco.gov.pk
Reference: DM (O) Model Industrial Divn. LESCO letter No.2018-21 dated 8-7-06
addressed to you with its copies to this office and others.
Your case of extension of load from 3110 kW to 3610 kW, which was
approved vide this office No. 12165-69 dated 16-6-2003, is still pending just due to non-
provision of C.Ts of 300/5-Amps. as required in clause-10 of above referred approval letter.
You are finally requested to provide the requisite C.Ts to DM (O) Model
Industrial Division LESCO within 10-days positively, failing which this office will be
constrained to cancel the instant case of EOL besides initiating proceedings against running
un-authorized extension of load.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-270)
E-mail: srmanpd@lesco.gov.pk
FAX MESSAGE
On the other hand he is running un-authorized extension of load and his MDI
recorded from 8/2004 to 4/2006 is ranging from 440 kW to 3376 kW which has been
viewed seriously by Audit.
You are advised to issue final notice to the consumer and if fails to make
payment within 10-days, his supply may be disconnected under intimation to this office.
2. M/s N.P. Spinning (Pvt.) Ltd. 1.5 KM Lullyani Road Opp. Raiwind Grid
Station Raiwind to make payment of Demand Notices within
10-days to avoid disconnection of supply.
3. Master file.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
Ph:/Fax # 6308360 PBX: 6314616-20(Ext-270)
E-mail: srmanpd@lesco.gov.pk
You are advised to check the record and intimate the reason for not affecting
the SJO as mentioned in the above referred letter. Moreover if needful is yet to be done then
original documents may be sent to DM (O) Model Industrial Divn. LESCO for necessary
action as area now falls within his jurisdiction.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A Queens Road, Lahore
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
Enclosed please find herewith attested copy of AM (CS) Feroze Wala letter
No. 2908 dated 10-2-2005 vide which he has confirmed security in hand amounting to
Rs.80,650/- against the subject consumer. Therefore, the para may please be dropped.
DA – As above
Senior Manager (P&D)
Engr. Sadr-ul-Huda
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
Audit party during the audit of this office has pointed out that
un-due benefit has been given to consumers while sanctioning load at last boundary of
Tariff B3.
However if any consumer apply for extension of load under tariff B4 then the
case will be processed as per requirement of said tariff inclusive construction of grid station
etc. For instance recently M/s Paramount Engineering Works have now crossed the limit of
5000 kW, resultantly they have applied for EOL from 4950 kW to 6000 kW, therefore the
case will be processed as per requirements of tariff B4.
Please refer to this office Memo No. 9783-86 dated 13-12-2005 vide which
you were advised to confirm that security deposited by the previous owner has been
transferred in the account of present occupant, but nothing has been heard from your end till
date which has viewed seriously by Deputy Chief Auditor during the meeting held in this
office 12-4-2006
The needful may be done without further loss of time and record may be got
verified from Deputy Chief Auditor within a week’s time positively.
Further delay in this regard will not be tolerated and matter will be reported to
competent authority for taking suitable action against you.
Info: 1. Manager Internal Audit LESCO (Atten. Mr. Atta-ur-Rehman, Audit Officer)
4. Master file.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
FAX MESSAGE
Subject: AUDIT PARA NO. 22 – EOL OF M/S NAZIR PAPER & BOARD MILL
FROM 267 KW TO 607 KW AGAINST APP. NO. 431/I/EOL DATED 3-
7-2003
While effecting EOL of the subject consumer from 267 kW to 607 kW,
existing 400 kVA Transformer was required to be returned to store.
You are advised to supply a copy of MRN vide which 400 kVA Transformer
was returned to store for its onward submission to Deputy Chief Auditor LESCO as desired
by him during the meeting held in this office on 12-4-2006
Info: 1. Manager Internal Audit LESCO (Atten. Mr. Atta-ur-Rehman, Audit Officer)
2. DM (O) A.I. Town Divn. LESCO for information and necessary action.
3. Master file.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
The extension of load from 317 kW to 575 kW and change of name was
approved by this office vide No. 3534-43 dated 12-9-2003. The security for the total load
under B3 was recovered after adjustment of security already in hand
Rs. 125400/- deposited by the previous owner.
You are advised to confirm that previous security has been transferred in the
name of present occupant within two days, so that audit may be informed accordingly.
3. M/s Insaf Spinning (Pvt.) Ltd. 4-KM Faisalabad Road, Sheikhupura. The
Audit Party of Deputy Chief Auditor WAPDA/LESCO during the audit of this
office has pointed out that in connection with your case of EOL from 317 to
575 kW , Demand Notice of security Rs. 397,850/- was to be paid upto 10-4-
2004 but the same was paid on 24-4-2004 and has advised to recover the
surcharge on account of late payment. Therefore demand notice of Rs.3052/-
is being enclosed for its payment within stipulated period under intimation to
this office.
5. Master file.
In view of above, it is requested that amount Rs. 776.58 deducted from salary
for the month of 3/2006 may be refunded.
In this connection, it is stated that undersigned had been performing the duty
of Secretary LESCO in 7/99 and 8/99 and Telephone No. 6317226 was used purely for
official purpose. Therefore an amount of Rs.552.66 & Rs.223.92 may please be settled.
4. Master file.
The Audit Party vide Para No.21 during the audit of this office for the period
7/99 to 6/2000, has pointed out recovery of Rs.552.66 & Rs.223/- total
Rs.775.66 from the undersigned on account of telephone calls against Telephone
No.6317220 when I was posted in LESCO Headquarter as Secretary.
7. Master file.
It is learnt that Audit Party vide Para No.21 during the audit of this office for
the period 7/99 to 6/2000, has pointed out recovery of Rs.552.66 & Rs.223/- from the
undersigned on account of telephone calls when I was posted in LESCO Headquarter as
Secretary.
As agreed during the meeting, the matter was put up before worthy Chief
Executive Office LESCO, who has advised to direct the audit officer to attend this office for
discussion and to decide the case.
Therefore, please direct the Sr. Audit Officer to attend this office on
8-3-2006 at 10.00 AM.
REGISTERED MAIL
Please refer to this office letter No. 4867-69 dated 1-10-2005 vide which you
were requested to deposit difference of capital cost Rs.190,705/- in the office of Finance
Director LESCO, so that the work of 11 kV feeder may be completed. But needful is yet to
be done, which has been viewed seriously by Audit.
It is, therefore, once again requested to deposit the requisite amount within 10-
days to avoid any un-pleasant situation.
3. DM (O) Raiwind Divn. LESCO to contact the consumer and get the payment
made, so that not only the work of 11 kV feeder may be completed but audit
may also be informed accordingly.
4. Master file.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
FAX MESSAGE
Please refer to this office letter No. 5728-33 dated 25-11-2004 and confirmed
payment of difference of capital cost Rs.221,769/- from the Sponsor of subject Housing
Scheme, by return fax, so that the Audit may be informed accordingly.
3. Master file.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
During discussion in the meeting it was informed that the requisite amount
had already been charged in the estimate and as such the para was dropped (photocopy
enclosed).
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
As per Para-II 3(i) of MD (D) letter No. 2094-2118 dated 17-7-1995 (copy
enclosed) Demand Notices of security pertaining to Deposit Works are to be issued on
receipt of completion reports of the required work. As such in the instant case of EOL, on
receipt of completion report from Manager Construction LESCO, Demand Notice of
security Rs.761,390/- has been issued after adjustment of security already in hand
Rs.115,850/- as confirmed by AM (CS) Raiwind Divn. LESCO (copies enclosed). As soon
as payment is received, your office will be informed accordingly.
3. Master file.
Hamid Audit-2005
AUDIT PARA – CREDIT OF DISMANTLED CONDUCTOR Rs. 206640/-
The Audit Party of Deputy Chief Auditor during the audit of this office has pointed
out that un-authorized credit of Rs. 206,640/- has been given in the estimate while
processing EOL case of M/s Touqeer Steel Mills from 3000 kW to 4950 kW.
In this connection it is submitted that EOL of M/s Touqeer Steel Mills from 3000 kW
to 4950 kW was approved vide this office No. 1452-64 dated 3-2-2005 through 11 kV
independent feeder from 132 kV Bhogiwal Grid Station by proposing replacement of
existing Dog conductor with Osprey conductor.
During processing the case, it was observed that EOL of the said consumer from 650
kW to 3000 kW was effected in 9/2004 through 11 kV independent feeder with Dog
conductor on consumer cost. As the instant case of EOL from
3000 kW to 4950 kW was approved in 3/2005 i.e. just after 5/6 months of the previous EOL
. Therefore the credit of dismantled Dog conductor amounting to Rs.206,640/- was given on
per KG bases after confirmation from Field Store Manager, Shalamar with the approval of
CEO. The technical clearance along with demand notice of capital cost was issued vide this
office No. 1452-64 dated 3-2-2005 and consumer had already deposited the same
Rs.10,60,170/- in two installments. It is also pertinent to mention here that the dismantled
conductor which was installed only 6-months before can be utilized at any other project in
the interest of LESCO whereas credit of conductor Rs.206,640/- was given on weight per
K.G. basis which was less than the depreciated values which comes to be Rs.315,495/-.
Although the Audit was requested that no un-due benefit has been given to the
consumer and the point may be dropped. However during the meeting with Audit Officer, it
was agreed that the case will be again submitted to Chief Executive Officer for final
decision please. It is, therefore, recommended that audit point may not be accepted as
explained in Para-104.
The subject consumer had applied in this office for extension of load from
490 kW to 725 kW along with the Consent / NOC of M/s A.L. Textile (Pvt.) Ltd. wherein
they have intimated that M/s Fine Crysto Plast is their sister concern and they have no
objection if case of EOL is processed from their 11 kV independent feeder (copy enclosed).
Now Audit Party of Deputy Chief Auditor WAPDA/LESCO during the audit
of this office has pointed out that Renovation charges amounting to
Rs. 342,500/- are also recoverable in the light of GM (O) letter No. 11398-12 / GMO /
CEHQ dated 9-8-2003. But this office is of the view that renovation charges are recoverable
where cases of EOL / New connections are processed through LESCO’s owned feeders
whereas the instant case of EOL was approved through 11 kV independent feeder of their
sister concern.
In the light of discussion held with the Audit Party, the matter is being
referred to your office for necessary clarification at the earliest please.
The extension of load from 650 kW to 2000 kW and change of name was
approved by this office vide No. 7285-95 dated 12-11-2003. The security for the total load
under B3 was recovered after adjustment of security already in hand
Rs.591,500/- as the previous owner has surrendered his security in favour of new occupant.
You are advised to confirm that previous security has been transferred in the
name of present occupant within two days, so that audit may be informed accordingly.
4. Master file.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
REGISTERED
Subject: AUDIT NOTE – EXTENSION OF LOAD AGAINST APP. NO.
417/I/EOL DATED 12-5-2003 IN THE NAME OF SHER MUHAMMAD
CHAUDHRY S/O MUHAMMAD DIN FOR M/S PAK PANTHER
SPINNING MILLS LTD. MANGA RAIWIND ROAD LAHORE
(STOPGAP ARRANGEMENT)
During the course of audit, the Audit Party has pointed out that the cost of
following material was not recovered from you while approving the case of extension of
load from 3110 kW to 3610 kW:-
2. C.Ts. of 800/Amps.
3. 1 No. 450 KVAR Capacitors.
Accordingly the Demand Notice of Rs. 78,186/- is being enclosed for its
payment in the office of Finance Director LESCO within 10-days, failing which your
supply will be disconnected without any further notice.
The subject consumer had applied in this office for new industrial connection
for a load of 900 kW in 6/2003. The case was processed as per X-Y formula circulated by
the GM (CS) vide No. 863-80/DD(R&CP)/55716 dated 25-8-2005 and Demand Notice of
capital cost Rs. 10,32,052/- ( inclusive Rs. 594,352/- for reconductoring of 11 kV feeder)
was issued vide this office No. 115-24 dated 3-7-2003. The consumer had deposit the same
on 8-7-2003 and accordingly go-ahead signal for execution of work was issued vide No.
630-33 dated 12-7-2003. After completing all departmental formalities SCO was issued vide
No. 12737-45 dated 17-3-2004.
Now the Audit Party of Deputy Chief Auditor WAPDA/LESCO during the
audit of this office has pointed out that as in 8/2003 new policy of recovery of rehabilitation
charges was introduced vide GM (O) letter No. 11398-12/GMO/CEHQ dated 9-8-2003,
therefore the case should have been processed in the light of said letter and accordingly
difference of capital cost on account of rehabilitation charges which comes to be Rs.
175,995/- should have been recovered. However this office is of the view that as the
consumer had already deposited the D.N. of capital cost in 7/2003, therefore it is not
justified to revise the D.N. and recover difference of capital cost as per policy issued in
8/2003.
In the light of discussion held with the Audit Party, the matter is being
referred to your office for clarification at the earliest please.
FAX MESSAGE
Please refer to this office letter No. 9790-92 dated 13-12-2005 vide which you
were requested to provide a copy of revised estimate along with detail / technical clearance
etc. but the same is still awaited from your end which has been viewed very seriously by
Deputy Chief Auditor during the meeting held in this office on 12-4-2006.
You are requested to supply the detail of estimate by 15-4-2006 through fax.
Info: 1. Manager Internal Audit LESCO (Atten. Mr. Atta-ur-Rehman, Audit Officer)
3. Master file.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
The extension of load from 317 kW to 575 kW and change of name was
approved by this office vide No. 3534-43 dated 12-9-2003. The security for the total load
under B3 was recovered after adjustment of security already in hand
Rs. 125400/- deposited by the previous owner.
You are advised to confirm that previous security has been transferred in the
name of present occupant within two days, so that audit may be informed accordingly.
6. M/s Insaf Spinning (Pvt.) Ltd. 4-KM Faisalabad Road, Sheikhupura. The
Audit Party of Deputy Chief Auditor WAPDA/LESCO during the audit of this
office has pointed out that in connection with your case of EOL from 317 to
575 kW , Demand Notice of security Rs. 397,850/- was to be paid upto 10-4-
2004 but the same was paid on 24-4-2004 and has advised to recover the
surcharge on account of late payment. Therefore demand notice of Rs.3052/-
is being enclosed for its payment within stipulated period under intimation to
this office.
5. Master file.
The extension of load from 375 kW to 710 kW and change of name was
approved by this office vide No. 16790-801 dated 18-6-2004. The security for the total load
under B3 was recovered after adjustment of security already in hand
Rs. 206,250/- as the previous owner has surrendered his security in favour of new occupant.
You are advised to confirm that previous security has been transferred in the
name of present occupant within two days, so that audit may be informed accordingly.
4. Master file.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
Reference: Your office letter No. 57235-41 dated 20-9-2005 & No. 59464-69
dated 28-9-2005
The replies to Para No. 1, 2, 4, 5, 6, 8, 9, 11, 12, 17, 18, 19, 20, 21, 22, 23, 35,
36, 37, 39, 44 & 46 are being enclosed as desired in the above-referred
letter.
Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
1. Already settled.
2. As already informed vide this office letter No. 2140 dated 12-8-2005, M/s
Rehman Steel, Bund Road, Lahore has already deposited the remaining
amount of security with mark up Rs. 464,597/-. A copy of the same is again
enclosed with the request to drop the point.
3. A copy of relevant page of MDI Register, Batch No. 27 in respect of M/s Data
Textile is enclosed, as desired please.
No.___________/P&D/DMP-1/DRW/ Dated____/8/2005
Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
34-Nicholson Road, Lahore
Ph:/Fax # 9200933 PBX: 9200134-37 (Ext.311-313)
E-mail: srmanpd@lesco.gov.pk
REGISTERED
Subject: AUDIT NOTE – EXTENSION OF LOAD AGAINST APP. NO.
417/I/EOL DATED 12-5-2003 IN THE NAME OF SHER MUHAMMAD
CHAUDHRY S/O MUHAMMAD DIN FOR M/S PAK PANTHER
SPINNING MILLS LTD. MANGA RAIWIND ROAD LAHORE
(STOPGAP ARRANGEMENT)
During the course of audit, the Audit Party has pointed out that the cost of
following material was not recovered from you while approving the case of extension of
load from 3110 kW to 3610 kW:-
Accordingly the Demand Notice of Rs. 500,381/- is being enclosed for its
payment in the office of Finance Director LESCO within 10-days, failing which your
supply will be disconnected without any further notice.
Audit-2005
Para No. 18
EXTENSION OF LOAD OF M/S PAK PANTHER
SPINNING MILLS – NON-RECOVERY OF COST OF MATERIAL
As pointed by Audit, the Demand Notice of Rs. 500,381/- has been sent to M/s Pak
Panther. As soon as payment is made, Audit will be informed accordingly.
1. M/s Touqeer Steel Mills had applied for EOL 3000 kW to 4950 kW. During
processing of the case, it was observed that due to critical loading condition of 132
kV Bhogiwal grid station the EOL cannot be accommodated. However since the
installation of 4th Power Transformer at the said was under process, so the instant
case of EOL was approved by this office vide No. 1452-64 dated 3-2-2005 subject to
installation / commissioning of 4th Power Transformer with the capital cost Rs.
1060,170/- which was paid by the consumer in two installments with mark up. It is
worth mentioning here that a number of other New Connections / EOL has been
approved through the proposed 4th Power Transformer. Although the proposed 4th
Power Transformer has been installed but EOL of the instant consumer has not so far
been effected as the work of 11 kV feeder of the consumer has not been completed
by Sr. Manager Construction LESCO. Therefore, the question of any loss to the
Authority / LESCO as reported by the Audit Party does not arise.
It is pertinent to mention here that all DMs (O) have been advised to
watch the MDI recorded strictly and in case load exceeds beyond the sanctioned
load, the connection may be disconnected.
(a) EOL of M/s Touqeer Steel Mills from 3000 kW to 4950 kW was approved vide this
office No. 1452-64 dated 3-2-2005 subject to installation / commissioning of 4 th
Power Transformer. The estimate was prepared as per prevalent rates and the
consumer has already deposited the capital cost Rs. 1060,170/- in two installments
with mark up. Although the proposed 4 th Power Transformer has been installed but
EOL of the instant consumer has not so far been effected as the work of 11 kV feeder
of the consumer has not been completed by Sr. Manager Construction LESCO.
Therefore, the question of any loss to the Authority / LESCO as reported by the
Audit Party does not arise.
(c) As per clause 5(b) of the T.C. 137m 4/0 AWG cable has correctly been mentioned to
be replaced with 11 kV 500 MCM cable which include last two span with cable,
which is mandatory being Steel furnace.
As the instant EOL has not been effected, therefore the question of misappropriation
of existing 11 kV 4/0 AWG cable does not arise.
In reply to Audit Par, it is submitted that the above mentioned case was
sanctioned vide this office no. 115-24 dated 3-7-2003 and demand notice of capital cost was
issued to the consumer on the same date which was paid on 8-7-2003.
(ii) Capital cost Rs. 109,058/- realized by Finance Director LESCO vide No.3596-97
dated 24-9-2004 (copy attached).
(iii) Security Rs. 80,540/- confirmed by AM (CS) Ferozewala vide his letter dated 5-
7-2004 (copy attached).
On receipt of request of refund of shared cost from M/s Shafi Spinning Unit-1,
the case of refund was processed exactly in the light of Authority instructions, the detail of
which is as under:-
(i) Shared cost of existing feeder for M/s Shafi Spinning Unit-2 Rs.656,439/-
(ii) Refund cost of M/s Shafi Spinning Unit-1 Rs.468,216/-
(iii) Refund cost of M/s Fahad Javaid from Unit-2 Rs.188,223/-
Accordingly the case of refund of Rs. 468,216/- to M/s Shafi Spinning Unit-1
was approved by the Chief Executive Officer LESCO (copy attached).
The refund of shared cost of feeder was given exactly in the light of
Authority’s instructions and no undue benefit was given to consumer. It is, therefore
requested that the para may please be dropped.
2006
On receipt of request of refund of shared cost from M/s Shafi Spinning Unit-1,
the case of refund was processed exactly in the light of Authority instructions, the detail of
which is as under:-
(i) Shared cost of existing feeder for M/s Shafi Spinning Unit-2 Rs.656,439/-
(ii) Refund cost of M/s Shafi Spinning Unit-1 Rs.468,216/-
(iii) Refund cost of M/s Fahad Javaid from Unit-2 Rs.188,223/-
Accordingly the case of refund of Rs. 468,216/- to M/s Shafi Spinning Unit-1
was approved by the Chief Executive Officer LESCO (copy attached).
The refund of shared cost of feeder was given exactly in the light of
Authority’s instructions and no undue benefit was given to consumer. It is, therefore
requested that the para may please be dropped.
EXTENSION OF LOAD OF M/S BHATTI COTTON LINKS
(1) EOL of M/s Bhatti Cotton Links from 385 kW to 1405 kW (Net
extension 1020 kW) was approved through 11 kV proposed feeder
from 132 kV Raiwind grid station with capital cost: Rs.51,41,562/-.
(2) On payment of capital cost as confirmed by FD vide No. 2063-64 dated
31-1-2004, go-ahead signal for execution of work was issued vide No.
11042-46 dated 9-2-2004.
(3) As per Authority’s instructions, after completion of work D.N. updated
security: Rs.10,80,257/- was issued.
(4) After payment of D.N. of security and provision of Test Report &
NOC, SJO was issued vide No. 6207-14 dated 13-10-2005 was effected
on 10-11-2005.
(5) MDI from 7/2004 to 10/2005 is well within the sanctioned load of 385.
No delay on the part of this office has been occurred and EOL has been
effected after fulfillment of all departmental formalities, as such the para may be dropped.
CONSOLIDATION AND EXTENSION OF LOAD OF M/S SHAHKAM
INDUSTRIES
(2) On payment of capital cost as confirmed by FD vide No. 3175-76 dated 11-3-
2006, go-ahead signal for execution of work was issued vide No. 5003-10 dated
16-3-2006
(3) D.N. of security for the extended load of 2847 kW for Rs.25,90,770 has been
issued.
(4) The work is under execution and EOL will be effected after completion of work
in due course of time, as such the para may be dropped.
EXTENSION OF LOAD OF M/S N.P. SPINNING
(1) EOL of M/s Spinning from 3100 kW to 3700 kW (Net extension 600 kW) was
grid station with capital cost Rs.212,464/- & security Rs.546,000/-, but payment was
not made by the consumer. Now the consumer has switched over to self-generation.
1/ 2006 3360
2/2006 1432
3/2006 440
4/2006 480
(2) DM (O) concerned has been advised to issue final Notice to the consumer and in case
of non-payment within 10-days, the connection may be disconnected.
EOL OF M/S KHALID SHAFIQ SPINNING MILLS
(1) EOL of M/s Khalid Shafique Spinning Mills from 490 kW to 2000 kW (Net
extension 1510 kW) was approved through 11 kV proposed independent feeder from
132 kV Chak-65 grid station with capital cost: Rs.28,43,997/-.
(3) After payment of D.N. of security Rs.16,55,150/- and provision of Test Report &
NOC, SJO was issued vide No. 10299-305 dated 18-5-2006 which has already been
effected.
No delay on the part of this office has been occurred and EOL has been
effected after fulfillment of all departmental formalities, as such the para may be dropped.
RECONNECTION & UN-AUTHORIZED OF M/S EAST END EXPORT
1 Un-authorized EOL
Sanctioned load of the consumer is 4990 kW but he is running un-authorized EOL
upto 5600 kW. Manager / DM (O) have already been advised to get un-authorized
EOL regularized. As per past conduct of the consumer, he will not come for the
same. Therefore Manager/DM (O) have been advised to restrict the consumer to
exactly in line with the Authority’s instructions circulated by GM (CS) vide No. 162-
83 dated 15-2-2002 (copy attached) which was applicable for all type of industries
(1) EOL of M/s Lakson Tobacco Ltd. from 995 kW to 1500 kW (Net extension 505 kW)
was approved in 5/2004 through 11 kV proposed independent feeder from 132 kV
Qadirabad grid station with capital cost: Rs.16,37,296/-.
(3) After payment of D.N. of security Rs.459,550/- and provision of Test Report &
NOC, SJO was issued vide No. 717-726 dated 14-7-2005 which has already been
effected.
No delay on the part of this office has been occurred and EOL has been
effected after fulfillment of all departmental formalities, as such the para may be
dropped.
EOL OF M/S ICC TEXTILES LTD.
(1) EOL of M/s ICC Textiles Ltd. from 875 kW to 2275 kW (Net extension
1400 kW) was approved in 11/2004 through 11 kV grouped independent ICC feeder
from 132 kV Chung grid station.
(2) After payment of revised capital cost: Rs.59,867, security Rs.12,74,000/- SJO has
already been issued in 2/2005 for stopgap arrangement
(3) The consumer is well within the limit of his sanctioned load viz. 2275 kW, as such
the para may be dropped.
Audit Para No. 20
(1) New connection of M/s Be Be Jan for a load of 700 kW was approved in 11/2005
(2) After payment of capital cost Rs.867,820/-, go-ahead signal for execution of work
was issued on 14-2-2006.
(3) Security D.N. for Rs.637,000/- was issued on 22-2-2006, but payment is yet
awaited.
(4) Connection will be energized after payment of security and provision of Test
Report & NOC from Electrical Inspector Government of Punjab besides
observing other usual departmental formalities.
It is stated that during the financial year 2005-2006 1805 No. HT and 428 No.
LT PC Poles were got issued from Field Store Kasur & Chunian for installation of Industrial
/ Tubewell connections as well as 11 kV lines and maintenance works in various Divisions /
Sub-Divisions under Kasur Circle.
Inspected Audit Officer has objected that 74 No. LT & 39 No. Steel Structures
were utilized at various locations which is against the contradiction of the orders of Member
(Power).
In this regard it is stated that these structures have been utilized under
emergency conditions for maintenance of distribution system in far flung areas during
stormy / rainy season for restoration of supply in shortest duration. As it is very much
difficult to shift one or two PC Poles in far flung areas without the help of crane / trolla etc.
which was not provided to Kasur Circle.
It is stated that line losses in Rural Division Kasur were very high before
creation of Kasur Circle with effect from 1/2006. Efforts were made to reduce monthly as
well progressive line losses. At the end of June 2006 the progressive losses of Rural
Division Kasur were reduced from 29.8% to 28.1 %. The losses during 7/2006 has further
been reduced 3% more and in 8/2006 1 % more. Efforts are also being made to reduce the
losses below 20% at the end of 6/2007.
4. Reversing of tube well meters Full current static meters are being
installed on tube wells to avoid
reversing.
It is further added that disciplinary action against the following Officers have
already been initiated on account of excessive line losses:-
It is hoped that line losses in Rural Division Kasur will be further reduced at
the end of 6/2007. Therefore the Para may be settled please.
Audit has pointed out that 26 No. Transformers of various capacities were
damaged during warranty period under Kasur Circle during financial year
2005-2006.
In this regard, it is stated that these transformers were returned to Field Store
Chunian and Kasur through MRNs which were subsequently returned to Regional Store
Shalamar. These Transformers are to examine in Regional Store Shalamar and are to be
replaced from the concerned Firm without any cost. The cost is not being recovered from
the Manufacturing Firm but their replacement is received in Regional Store Shalamar. On
receipts from Firms these transformers are again released by CEO / Sr. Manager (MM) to
Field Stores for its utilization.
Since Operation Staff has no concern with the transformer damaged during
warranty period after getting replacement from Field Store, therefore para be settled
accordingly.
As already explained that 5 No. 450 KVAR Capacitors valuing Rs.0.319 Millions
were drawn from Field Store Chunian & Kasur for installation on 11 kV feeders having load
more than 200-Amps. to reduce technical loss.
The cost of these Capacitors have been booked to Head of Account ‘Maintenance of
Sub-Station’. It is further stated that these Capacitors are existing at sites and there is no
dismantlement / returnable to Store. Moreover no recovery is due from any person.
Fax Message
MDI data of the subject consumer from 1/2003 to 8/2006 may please be
supplied faxed to this office immediately.
2. Master file.
Hamid / Audit-2005
EOL OF M/S MALIK ENGINEERING NOOR ROAD LAHORE
(1400KW – 2400 KW)
(1) EOL of M/s Malik Engineering from 1400 kW to 2400 kW was approved vide T/O
No. 706-65 dated 6-11-2003 with capital cost Rs.20,28,423/- & security
Rs.9,10,000/-
(2) The work of 11 kV feeder was under execution and in the meantime the consumer
applied for further EOL from 2400 kW to 3400 kW. The case was processed,
however due to critical loading position of grid station, the case was approved
subject to installation of 3rd Power Transformer at 132 kV Badami Bagh grid station
vide this office No. 10500-09 dated 29-6-2005. Although the consumer has deposited
the security for the extended load: Rs. 910,000/- and also provided Test Report &
NOC but the EOL will be effected after commissioning of 3 rd Power Transformer at
the said grid station. However the consumer is being charged as per MDI recorded
on the metering equipment as such no revenue loss has been sustained by the
department. Therefore the para may be dropped.
DRAFT PARA NO. 89/2006 – NON-RECOVERY OF FIXED CHARGES
RS.29,07,184/- AGAINST REFERENCE NO. 24-1345-90013413 FROM MR.
MUHAMMAD RAFIQUE OF RKN STEEL FURNACE
(1) Extension of load of M/s RKN Steel from 612 kW to 3640 kW was approved in
3/1990 through existing 11 kV independent feeder from 132 kV Fateh Garh Grid
Station with capital cost: Rs.484,453/- & security: Rs.242,240/-. But consumer
deposited only security: Rs.242,240/- whereas capital cost was not paid due to which
his load could not be regularized.
(3) During year 2000, consumer deposited updated capital cost: Rs.21,35,240/-.
However since rates of security were also increased during year 1997 as such
consumer was advised to deposit enhanced security: Rs.19,37,920/- but he did not
deposit the same rather went into litigation and the matter is still subjudiced.
(4) During year 2003 the consumer applied for change of name and extension of load
from 612 kW to 4000 kW which was approved on 24-9-2003. Demand Notice of
capital cost: Rs.12,39,284/- was issued against which consumer filed another suit and
the matter is still subjudiced.
(5) The consumer was charged fixed charges upto 2/2003 and after 5/2005 on the basis
of 50% of 4000 kW billing demand for peak hours. But for the intervening period i.e.
3/2003 to 5/2005 the consumer could not be billed accordingly for which bill
amounting to Rs.29,87,184/- has been issued. As soon payment is made, audit will be
informed accordingly.
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
DA/As above
Chief Engineer (P&D)
(Engr. Rao Zamir-ud-Din)
Hamid / Audit-2005
5. While going through the record, it has been observed that 10/13 MVA spared Old
Power Transformers were utilized by LESCO against 6 No. Private Grid Station.
As per policy and practice in vogue 26% installation charges were included in the
estimates by PD (GSC) as per cost of old Transformers and the cases were
accordingly approved by the competent Authority i.e. CEO LESCO.
But Audit Party during audit has pointed out to recover 26 % installation
charges as per latest purchase price of the Power Transformers merely on the report of a
Committee constituted by this office vide Office Order 6275-81 dated 7-9-2007. But
competent authority did not decide to recover 26% installation charges as per latest
purchase price of the Power Transformers.
Keeping in view the position explained above, the para may please be
dropped.
M/s Siara Textile Mills (Pvt.) Ltd. who were originally being fed from 11 kV
independent feeder with Dog Conductor from 132 kV Warburton Grid Station has applied
in this for extension of load from 2700 kW to 3500 kW in 5/2013. While carrying out
technical analysis of existing 11 kV independent feeder of M/s Siara Textile Mills after
adding the applied extension of load, it was observed that the applied load cannot be
accommodated without reconductoring from Dog to Osprey.
Meanwhile Sapphire Unit 5 & 6 which were being fed from 11 kV Blessed
Textile Mills feeder were switched over from their 11 kV independent feeder to their own
grouped independent 132 kV consumer grid station. With this changed scenario M/s Siara
Textile Mills (Pvt.) Ltd. supplied NOC issued by M/s Sapphire Units 5 & 6 regarding use of
their spared 11 kV independent feeder with Osprey conductor by M/s Siara Textile Mills.
No.____________/P&D/DRW420/Skp. Dated____/08/2014
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph./Fax: 9204818
E-mail: srmanpd@lesco.gov.pk
The case has been examined and observed that Demand Notice of capital cost
by utilizing spared 11 kV independent feeder, on cost deposit basis, has been issued
correctly. It is also pertinent to mention here that spared 11 kV independent feeder with
Osprey conductor has been provided to you at your own request as it was not possible to
accommodated the applied load at your own existing 11 kV independent feeder without
reconductoring from Dog to Osprey.
Therefore Demand Notice already issued may please be deposited with Chief
Financial Officer LESCO. However if you are not willing to deposit the same then this
office may be informed accordingly so that your case for extension of load from 2700 kW to
3500 kW may be approved from your own original existing 11 kV feeder. In this way
existing Dog conductor is required to be replaced with Osprey conductor on cost deposit
basis to bring the technical parameters of the feeder within permissible limit as per rules and
instructions of the Department.
No.____________/P&D/DRW420/Skp. Dated____/08/2014
Audit-2005
The case has been examined and para-wise reply to the petition of consumer is
as under:
Para 1 & 2: M/s Siara Textile Mills (Pvt.) Ltd. having sanctioned 2700 kW load are being
fed through 11 kV independent Siara Textile feeder with Dog conductor
emanating from 132 kV Warburton grid station.
Para 3,4&5 In 5/2014 M/s Siara Textile Mills (Pvt.) Ltd. applied for extension of load
from 2700 kW to 3500 kW, which was registered in this office against
Application No. 67/EOL/B-III dated 31-5-2014. During processing the case, it
was observed that in order to accommodate the applied load reconductoring of
11 kV independent Siara feeder from Dog to Osprey conductor is mandatory
to bring the parameters within specified limit. In the meantime M/s Siara
Textile Mills (Pvt.) Ltd. submitted NOC from M/s Blessed Textile Mills
regarding utilizing their spared 11 kV independent feeder who were shifted at
their own 132 kV independent private grid station. Accordingly on the request
of M/s Siara Textile Mills (Pvt.) Ltd. the case of extension of load was
processed through spared 11 kV independent Blessed feeder and approval
letter alongwith Demand Notice of capital cost including cost of 11 kV feeder
at fresh rates as per prevailing policy in LESCO has been issued to consumer
vide No. 8792-99 dated 9-1-2014. It is further added that WAPDA
Notification No. 495-515/CS/DD(R&CP)/557 dated 11-7-2001 mentioned in
-2-
the petition is regarding to recover the proportionate cost from any consumer
to be grouped on 11 kV existing dedicated feeder less than 5000 kW load.
There is nothing mentioned anywhere that cost of existing material / 11 kV
feeder to be given to any consumer is not recoverable from him simply on
provision of NOC from any consumer.
Para 6,7 & 8 As stated above, the Demand Notice of capital cost has correctly been issued
by providing them 11 kV constructed dedicated feeder with Osprey conductor
as a good gesture. However if M/s Siara Textile Mills (Pvt.) Ltd. are not
willing to deposit the same then their extension of load from 2700 kW to 3500
kW can be approved through their own 11 kV existing feeder by proposing
reconductoring from Dog to Osprey to bring the technical parameters within
specified limits. It is further added that the case of extension of load was
approved in 1/2014. Now as per changed scenario at site, LESCO intends to
utilize the spared 11 kV Blessed feeder for its own use due to critical loading
condition of LESCO’s feeders in the vicinity.
To: Director,
NEPRA, Consumer Affairs Division,
NEPRA Office Building,
Attaturk Avenue (East) Sector G-5/1
Islamabad.
No.____________/P&D/DRW420/Skp. Dated____/09/2014
Audit-2005
The case has been examined and para-wise reply to the petition of consumer is
as under:
Para 1 & 2: M/s Siara Textile Mills (Pvt.) Ltd. having sanctioned 2700 kW load are being
fed through 11 kV independent Siara Textile feeder with Dog conductor
emanating from 132 kV Warburton grid station.
Para 3,4&5 In 5/2014 M/s Siara Textile Mills (Pvt.) Ltd. applied for extension of load
from 2700 kW to 3500 kW, which was registered in this office against
Application No. 67/EOL/B-III dated 31-5-2014. During processing the case, it
was observed that in order to accommodate the applied load reconductoring of
11 kV independent Siara feeder from Dog to Osprey conductor is mandatory
to bring the parameters within specified limit. In the meantime M/s Siara
Textile Mills (Pvt.) Ltd. submitted NOC from M/s Blessed Textile Mills
regarding utilizing their spared 11 kV independent feeder who were shifted at
their own 132 kV independent private grid station. Accordingly on the request
of M/s Siara Textile Mills (Pvt.) Ltd. the case of extension of load was
processed through spared 11 kV independent Blessed feeder and approval
letter alongwith Demand Notice of capital cost including cost of 11 kV feeder
at fresh rates as per prevailing policy in LESCO has been issued to consumer
vide No. 8792-99 dated 9-1-2014. It is further added that WAPDA
Notification No. 495-515/CS/DD(R&CP)/557 dated 11-7-2001 mentioned in
-2-
the petition is regarding to recover the proportionate cost from any consumer
to be grouped on 11 kV existing dedicated feeder less than 5000 kW load.
There is nothing mentioned anywhere that cost of existing material / 11 kV
spared feeder to be given to any consumer is not recoverable from him simply
on provision of NOC from any consumer.
Para 6,7 & 8 As stated above, the Demand Notice of capital cost has correctly been issued
by providing them already constructed 11 kV dedicated feeder with Osprey
conductor on cost deposit basis.
It is pertinent to mention here that now on the request of M/s Siara Textile
Mills (Pvt.) Ltd. dated 11-9-2014, due date of already issued Demand Notices of capital cost
for Rs.47,77,950/- and security for Rs.23,84,000/- have been extended upto 26-9-2014.
Accordingly after payment of both the Demand Notices SJO for implementation of required
extension of load from 2700 kW to 3500 has been issued by this office vide No. 4383-89
dated 14-10-2014.
Photocopies of paid Demand Notices and SJO issued by this office are being
enclosed for your kind perusal.
DA / As above
Chief Executive Officer
( Rao Zamir-ud-Din )
No.____________/P&D/DRW420/Skp. Dated____/10/2014
Audit-2005
DA / As above
Chief Executive Officer
( Rao Zamir-ud-Din )
DA / As above
No.____________/P&D/DRW420/Skp. Dated____/11/2014
Audit-2005
Subject: BRIEF HISTORY OF COMPLAINT FILED BY M/S SIARA TEXTILE
MILLS (PVT.) LTD. AGAINST PAYMENT OF SPARED DEDICATED
FEEDER
1 M/s Siara Textile Mills (Pvt.) Ltd. who were previously being fed through
their own 11 kV independent Siara Textile feeder with Dog conductor
emanating from 132 kV Warburton grid station applied for extension of load
from 2700 kW to 3500 kW in 5/2014 (CP-79).
2 As it was in the knowledge of M/s Siara Textile that further load cannot be
accommodated on their existing feeder without its reconductoring from Dog
to Osprey, so they provided NOC from M/s Sapphire regarding utilizing their
spared feeder by M/s Siara Textile.
4. M/s Siara Textile vide letter dated 11-7-2014 (CP-95) requested LESCO to
give them spared 11 kV feeder free of cost. This office vide letter dated 11-8-
2014 (CP-96) replied that case of EOL has been approved through spared
feeder instead of their own existing feeder. However if they are not willing to
deposit the same, this office may be informed so that case of EOL may be
processed through their own existing 11 kV feeder.
5. M/s Siara Textile lodged complaint to NEPRA vide CP-99 that as per NEPRA
rules and WAPDA Notification No. 495-515 / CS / DD (R&CP) / 557 dated
11-7-2001, cost of feeder is not recoverable from them.
6. Detailed reply was submitted vide CP-116 wherein it was also clarified that
above Notification is regarding to recover the proportionate cost from any
consumer to be grouped on 11 kV existing dedicated feeder less than 5000
kW load and there is nothing mentioned anywhere that cost of existing
material / 11 kV spared feeder to be given to any consumer is not recoverable
from him simply on provision of NOC from any consumer.
It is further submitted that M/s Adil Textile is not a similar case as mentioned
in letter under reference. In case of M/s Adil Textile, M/s MGM Corporation who is a
running consumer from their own existing 11 kV independent feeder has given NOC for
grouping M/s Adil Textile on their 11 kV independent feeder. Accordingly the case was
processed and Demand Notice of capital cost amounting Rs.32,30,233/- was issued to M/s
Adil Textile, who also deposited the same on 4-4-2014. But subsequently M/s MGM
withdrawn their NOC and also filed Civil Suit against the said grouping; as such further
proceeding in this case has been stopped (photocopies of relevant documents are attached).
But in the subject case, M/s Siara Textile has tried to get the spared 11 kV feeder
free of cost whereas this office has already clarified that a fter switching over of M/s
Sapphire Fibers Ltd. from 11 kV independent spared feeder to their own 132 kV
independent grid station, the spared 11 kV feeder became the property of WAPDA/LESCO
automatically as per clause 8 of Abridged Conditions of Supply.
DA / As above
Chief Engineer (P&D)
( Rao Zamir-ud-Din )
No.____________/P&D/DRW420/Skp. Dated______/2/2015
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph./Fax: 99204818
E-mail: srmanpd@lesco.gov.pk
Info: 1. Manager (Op) LESCO Central Circle ) to ensure recovery even at the pain
2. Manager (Op.) LESCO Sheikhupura ) disconnection under intimation to
) this office.
3. PD (GSC) LESCO.
4. Master file.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph./Fax: 99204818
E-mail: srmanpd@lesco.gov.pk
Necessary instructions regarding recovery of 25% grid sharing cost from the
individual plot owners at the time of giving new connections and maintenance of record by
the concerned Divisional Accountant had already been issued by this office vide No. 1808-
15 dated 10-2-2005 (Photo copy enclosed). As Divisional Accountants are working under
the control of Chief Financial Officer LESCO, therefore the para may be referred to CFO.
DA/As above
Chief Engineer (P&D)
(Engr. Rao Zamir-ud-Din)
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph./Fax: 99204818
E-mail: srmanpd@lesco.gov.pk
Please get the record checked and let this office know whether 26 %
installation charges have been recovered from the above consumer according to price of
New 10/13 MVA Power Transformer or otherwise. If installation charges have been
recovered at the price of old 10/13 MVA Power Transformer, then difference of actual
amount to be recovered may be intimated to this office within a week’s time positively.
DA/As above
Chief Engineer (P&D )
( Rao Zamir-ud-Din )
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph./Fax: 99204818
E-mail: srmanpd@lesco.gov.pk
Enclosed please find herewith a copy of letter No. 2954/AP No. 3886 dated
3-3-2015 received from Manager (Internal Audit) LESCO, Lahore, which is self
explanatory.
Please go through the contents of enclosed letter and direct your Divisional
Accountants to get their record verified from D.G Wapda Audit, Sunny View, Lahore
before conversion of Inspection Report into Draft Paras.
DA/As above
Chief Engineer (P&D)
( Rao Zamir-ud-Din )
To:
Chief Financial Officer LESCO
2. Master file.
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph./Fax: 99204818
E-mail: srmanpd@lesco.gov.pk
Hamid / Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
It is further submitted that security has already been updated as per prevailing
rates and no loss in this regard has been occurred to the Government Exchequer
(Photocopies of paid Demand Notices are attached).
Keeping in view the position explained above, it is requested that the Audit
Para may please be dropped.
DA/As above
Chief Engineer (P&D )
( Rao Zamir-ud-Din )
Info: 1. The Secretary, Ministry of Water & Power, Main Sectt. Block-A Islamabad.
2. The Managing Director (PEPCO) Wapda House, Lahore.
3. The Chief Auditor (PEPCO) Al-Jannat Building, Bank Square, Neela
Gumbad, Lahore
5. Deputy Director (AIR Section) Local.
4. Master file.
Subject: DRAFT PARA NO. 17/2004 BASED ON A.P. NO. 2473 (I) REGARDING
MISAPPROPRIATION OF WAPDA MATERIAL OF RS. 16.34 (M) & ITS
INSTALLATION IN PRIVATE HOUSING SCHEMES FOR THE PERIOD
7/2002 TP 6/2003
Reference: DM (O) A.I. Town Divn. LESCO letter No. 21775-77 dated 10-12-2014.
The concerned officials of your offices may be deputed to get the record
verified & para settled from D.G Audit WAPDA. They may also be advised to visit this
office on any working day to obtain the relevant record from the respective files of the
following Housing Schemes:
1. OPF Housing Scheme.
2. Mohafiz Town.
3. Gosha-e-Ahbab (Ph-II) Housing Scheme.
4. PASSCO Employees Coop. Housing Society.
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph./Fax: 99204818-19
During scrutiny the files of industrial connections received back from Audit
Party of your office, carrying out audit in this office recently, Noting file of M/s Haier
Company (Pvt.) Ltd. found missing.
Therefore Incharge Audit Party concerned may please be advised to trace out
and return the said file to this office immediately.
No.__________________/P&D/DRW/ Dated______/08/2016
Hamid / TC-newconnection
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
Keeping in view the position explained above, the paras may please be settled.
No._____________/DRW/ Dated______/10/2016
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
No._____________/DRW/ Dated______/10/2016
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
It has been intimated by the Record Keeper of this office that Noting file of
M/s Haier Company and case file of Central Jail Kasur were not returned to him by the
audit staff. Therefore concerned staff of your office may please be advised to trace out and
return the above files to this office.
No._____________/DRW/546/2nd Dated______/10/2016
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
Enclosed please find herewith a copy of D.G. WAPDA Audit letter No.
AR/PDP No. 215/2016-17/AR:2016-17/445 dated 24-10-2016 alongwith a copy of PDP No.
215/2016-17 based on Audit Para No. 04 of Inspection Report on the accounts of Manager
(Op.) Northern Circle LESCO.
You are advised to go through the contents of enclosed letters and submit
reply / get the para settled within stipulated period as desired therein under intimation to all
concerned. There should be no slackness on any account.
DA/As above
MATTER MOST URGENT
Chief Engineer (P&D)
( Mazhar-ul-Ibad )
No._____________/DRW/HDM/AR Dated______/11/2016
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
DA/As above
Chief Engineer (P&D)
( Mazhar-ul-Ibad )
No._____________/DRW/ Dated______/2/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
In this connection please refer to this office letter No. 1364-65 dated
31-7-2012 vide which detail reply has already been submitted to your office. However a
copy of the same is again enclosed herewith, with the request that the para may please be
dropped in view the position explained therein.
DA/As above
Chief Engineer (P&D)
( Mazhar-ul-Ibad )
No._____________/DRW/ Dated______/2/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
In this connection please refer to this office letter No. 1366-70 dated
31-7-2012 vide which detail reply has already been submitted to your office. However a
copy of the same is again enclosed herewith, with the request that the para may please be
dropped in view the position explained therein.
DA/As above
Chief Engineer (P&D)
( Mazhar-ul-Ibad )
No._____________/DRW/ Dated______/2/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
It is intimated that detailed reply to above para has already been submitted to
your office. However a copy of the same is again enclosed herewith, with the request that
the para may please be dropped in view the position explained therein.
DA/As above
Chief Engineer (P&D)
( Mazhar-ul-Ibad )
No._____________/DRW/ Dated______/2/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
It is intimated that detailed reply to above para has already been submitted to
your office. However a copy of the same is again enclosed herewith, with the request that
the para may please be dropped in view the position explained therein.
DA/As above
Chief Engineer (P&D)
( Mazhar-ul-Ibad )
No._____________/DRW/ Dated______/2/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
The Demand Notice of security for Rs. 1,32,80,000/- was issued to consumer
vide No. 1342 dated 7-12-2012, which was paid in MCB Warburton Distt. Nankana on
12-12-2012. A copy of paid Demand Notice alongwith copy AM (CS) Nankana letter No.
2012 dated 13-12-2012 is being enclosed with the request that since consumer had already
paid the security, therefore the para may please be dropped.
DA/As above
Chief Engineer (P&D)
( Mazhar-ul-Ibad )
No._____________/DRW/ Dated______/2/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
As desired in the above referred letter, a copy of this office letter No. 1366-70
dated 31-7-2012 vide which detailed reply has already been submitted to your office, is
again enclosed herewith.
Keeping in view the position explained in the above referred letter, the para
may please be got settled under intimation to all concerned.
DA/As above
Chief Engineer (P&D)
( Mohsin Raza )
No._____________/DRW/ Dated______/4/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
As desired in the above referred letter, a copy of this office letter No. 1364-65
dated 31-7-2012 vide which detailed reply has already been submitted to your office, is
again enclosed herewith.
Keeping in view the position explained in the above referred letter, the para
may please be got settled under intimation to all concerned.
DA/As above
Chief Engineer (P&D)
( Mohsin Raza )
No._____________/DRW/ Dated______/4/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
As desired in the above referred letter, latest status of following 07 No. cases
is given as under:
Keeping view the position explained above, the para may please be got
settled as already requested by this office vide letter No. 18264 dated 23-2-2017 (copy
enclosed).
DA/As above
Chief Engineer (P&D)
( Mohsin Raza Khan )
No._____________/DRW/ Dated______/4/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
Info: 1. Manager (Internal Audit) 132 kV grid station, K-Block Model Town,
Lahore with reference to above.
2. Master file.
No._____________/DRW/ Dated______/4/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
The record has been checked and observed there was no delay occurred in
energization of connection of M/s Mughal Steel. On receipt of completion report / financial
closure of the work from PD (GSC) LESCO vide his letter No. 7161-63 dated 15-3-2013
SJO for implementation of extension of load from 4500 kW to 19,990 kW was issued by
this office vide No. 21402-18 dated 28-3-2013.
However as per report of PD (GSC) LESCO received vide his letter No. 3802-
04 dated 4-5-2011, execution of work of 132 kV transmission line was delayed due to
Right-Of-Way problem. As per clause – 13 of approval letter issued by this office vide letter
No. 21402-18 dated 24-6-2008 it was the responsibility of consumer to clear the
Right-of-way problems. Therefore when he get the matter / problem resolved the work was
taken in hand by PD (GSC) LESCO. Photocopies of relevant documents are enclosed.
From the above, it is clear that there is no delay on the part of LESCO rather
the work was delayed due to non-clearance of Right-of-Way problem in time by the
consumer. Therefore the para may please be got settled / dropped.
DA/As above
Chief Engineer (P&D)
( Mohsin Raza Khan )
In this regard, it is intimated that this office is only approving the cases of
external electrification of Housing Societies and Shopping Plazas etc. whereas the work of
execution of external electrification relates to PD (Construction) LESCO.
No._____________/DRW/ Dated______/6/2017
Hamid Audit-2005
Audit Para No. 20
(1) New connection of M/s Be Be Jan for a load of 700 kW was approved in 11/2005
(2) After payment of capital cost Rs.867,820/-, go-ahead signal for execution of work
was issued on 14-2-2006.
(3) Security D.N. for Rs.637,000/- was issued on 22-2-2006, but payment is yet
awaited.
(4) Connection will be energized after payment of security and provision of Test
Report & NOC from Electrical Inspector Government of Punjab besides
observing other usual departmental formalities.
From the above, it is clear that case was processed and approved as per policy
instructions of the department and no un-due benefit was provided to the Sponsor.
Therefore the para may please be dropped.
You are advised to get the Para dropped by providing the detail / documents
of dismantled material to Audit as mentioned in the above referred letter without further loss
of time under intimation to this office.
No._____________/DRW/ Dated______/7/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
Keeping in view the position explained above, the paras may please be settled.
DA/As above
Chief Engineer (P&D)
( Mohsin Raza Khan )
No._____________/DRW/ Dated______/10/2017
Hamid Audit-2005
Point-wise reply to Audit observations placed at CP-8 is given as under:
5. T/F No. 3 is 132 / 66 kVA. Hence the same cannot be used for 11 kV. As mentioned
at NP / 10 – 12 sufficient load is available to accommodate the load of instant
applicant because present maximum loading of Power T/F T-1 during year 2017 is
55%.
6. As shown on the sketch placed at CP-4 locations of both the premises are a distance
apart (1.35 KM). Therefore instant case of new connection for 1500 kW has been
processed by grouping and extending approximately 1-KM 11 kV line with Osprey
conductor from existing kV independent KSF Trizone feeder in the light of
instructions issued by Member (Power) vide # 495-515 dated 11-7-2001 (CP-7)
regarding “Supply of Power through 11 kV & 33 kV feeders”, clause-d of which
is re-produced below:
“New Industrial connections with applied load less than 5000 kW are also
Permissible from an existing 11 kV dedicated industrial feeders subject to
the conditions that technical parameters remain within permissible
limits.”
Since observations of the Audit have been attended, therefore instant case of
new connection for 1500 kW load may please be forwarded to competent authority for
approval as per NP/ 16 – 17. It cannot be asked to both the industries for independent grid
because these are not in the same one premises.
It cannot be
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
Subject: ADVANCE PARA NO. 16(1) (2003-2004) (P&D) BASED ON PARA NO.
1 OF AIR FOR THE PERIOD 2003-2004
In this connection please refer to this office letter No. 20271-74 dated
29-5-2012 vide which photocopies of technical clearances alongwith paid Demand Notices
of security have already been sent to your office for onward submission to DG (Audit)
WAPDA. However the copies are again enclosed for ready reference.
Keeping in view the position explained above, the para may please be got
dropped / settled.
DA/As above
No._____________/DRW/ Dated______/11/2017
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
Info: 1. Manager M&T (East) ) alongwith a copy of above list for information
2. Manager M&T (West) ) and necessary action.
3. Manager Internal Audit LESCO for information please.
4. XENs, Ferozewala, Badami Bagh, Baghbanpura, Ravi Road, Shalamar &
Muridke Divns. alongwith list for necessary action as above.
5. Master file.
No._____________/DRW/ Dated______/1/2018
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
Please attend the above meeting fully prepared alongwith relevant record.
9
Chief Engineer (P&D)
( Mohsin Raza Khan )
No._____________/DRW/ Dated______/1/2018
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
DA/Demand Notice
Chief Engineer (P&D)
( Mohsin Raza Khan )
No._____________/DRW/467/Skp. Dated______/2/2018
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
CERTIFICATE
(Regarding Audit Para NO. 4.2.3)
________________________
________________________
________________________
________________________
COUNTERSIGNED
DA/As above
Chief Engineer (P&D)
(Mohsin Raza Khan )
No._____________/DRW/ Dated______/7/2018
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
Reference: Your letter No. DCAL/AP-II/CORR/58 dated 18-10-2018 & No. DCAL/AP-
11/CORR/59 dated 15-10-2018.
No._____________/DRW/519/Skp. Dated______/10/2018
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
The record has been checked and observed that reply to the following Paras
has already been sent to your office (copies attached):
AP No. Period
1. 1216 2010-11
2. 1243 2010-11
3. 1901 2010-11
4. 74(2151) 2014-15
5. 17(1162) 2010-11
6. 50(1182) 2010-11
7. 1254(131) 2010-11
8. 10(298) 2004-05
9. 15(2214) 99-2000
10. 16 (01) 2003-04
Manager (P&D)
LESCO Lahore
No._____________/ Dated______/02/2019
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 99204820-30 (Ext. 200) Ph:99204818 Fax:99204819
E-mail: srmanpd@lesco.gov.pk
No.________________/DRW/ Dated______/4/2019
Hamid Audit-2005
LAHORE ELECTRIC SUPPLY COMPANY LIMITED
TECHNICAL DIRECTORATE
22-A QUEENS ROAD LAHORE
PBX: 9204820-30 (Ext. 200) Ph:9204818 Fax:9204819
E-mail: srmanpd@lesco.gov.pk
No._____________/DRW/ Dated______/6/2019
Hamid Audit-2005