SUBJECT : ADDITIVE / DEDUCTIVE COST FOR STP (CHANGE FROM CHB TO CONCRETE STRUCTURE)
ARCHITECT : AR. PAOLO VALENCIA
OWNER : ALVIN UY
DATE : JANUARY 14, 2021
In compliance with your request appertaining to construction of the aforementioned project, please find herewith our proposal for undertaking the following scope of works for Change orders
/ Additional works.
MATERIAL LABOR
NO DESCRIPTION QTY UNIT MATERIAL COST LABOR COST AMOUNT
UNIT PRICE UNIT PRICE
I REVISED COST (OSM - REBAR & CONCRETE)
1 ADDITIVE REBAR, CONCRETE, & FOMWORKS FOR STP
Rebar 1,115.07 kgs OSM OSM 11.00 12,265.77 12,265.77
Concrete 10.12 cu.m OSM OSM 850.00 8,600.13 8,600.13
Formworks 101.14 sq.m 250.00 25,284.00 350.00 35,397.60 60,681.60
Waterproofing (Cementitious) 58.80 sq.m 350.00 20,580.00 275.00 16,170.00 36,750.00
II ORIGINAL COST
1 DEDEUCTIVE REBAR, CONCRETE, CHB
Rebar 731.92 kgs 55.00 40,255.85 11.00 8,051.17 48,307.02
Concrete 4.01 cu.m 4,300.00 17,229.24 850.00 3,405.78 20,635.02
Formworks 11.34 sq.m 250.00 2,835.00 350.00 3,969.00 6,804.00
CHB 48.38 sq.m 743.64 35,980.28 417.60 20,205.16 56,185.44
Plastering 61.61 sq.m 230.42 14,197.10 450.09 27,731.85 41,928.94
___________________
Engr. Paul Vincent Go
Go Squared Contractors Inc.
________________________
Alvin Uy
Owner