FMDS0100
FMDS0100
FMDS0100
Table of Contents
Page
©2000-2023 Factory Mutual Insurance Company. All rights reserved. No part of this document may be reproduced,
stored in a retrieval system, or transmitted, in whole or in part, in any form or by any means, electronic, mechanical,
photocopying, recording, or otherwise, without written permission of Factory Mutual Insurance Company.
1-0 Safeguards During Construction
Page 2 FM Global Property Loss Prevention Data Sheets
List of Figures
Fig. 2.3.1.3. Example of Bracing Details for an Unreinforced Masonry Wall ............................................... 6
Fig. 2.3.1.10. Concrete shell structures .......................................................................................................... 7
Fig. 3.1.14.1. Wind damage to steel frame. This framework is only one of many that did not have
adequate cable bracing. ........................................................................................................ 14
List of Tables
Table 3.1.14.1. Permissible Minimum Diameters for Steel Pipe Braces ...................................................... 15
1.0 SCOPE
This data sheet examines the hazards associated with construction, alteration, and demolition operations.
The following recommended precautions will greatly reduce the danger of fire, explosions, water and wind
damage, and collapse.
This document also provides general site selection and guidance recommendations for permanent design
loads and design considerations for achieving highly protected risk (HPR). HPR guidance focuses on various
property protection concerns, which may exceed life safety concerns covered by building and fire code
requirements. Other reference documents are listed in Section 4.0.
1.1 Hazards
For hazard information refer to Understanding the Hazard (UTH) publication, Alteration, Demolition and
Construction Operation (P0309).
1.2 Changes
July 2023. Interim revision. The following changes were made:
A. Referenced data sheets that should be applied in site selection and building design.
B. Added guidance for the use of FM Approved debris barriers.
C. Referenced ASCE 37 for temporary design loads during construction.
D. Expanded guidance for bracing building framework during construction and sequencing construction
connections and braces, including references to association documents for specific construction types.
E. Added guidance regarding the use of noncombustible or limited combustible construction materials.
2.1 Introduction
In designing a new facility or building, consider all features that affect fire and explosion safety and resistance
to natural hazards. The essentials of firesafe construction are described in this section.
damaged areas of coating promptly. Ensure fire-resistant material used for framing or lintels on Maximum
Foreseeable Loss (MFL) fire walls is durable enough that it cannot be easily scraped off.
2.2.1.8 If construction or contents are combustible, subdivide high value contents; or separate manufacturing
and storage areas with fire walls (see Data Sheet 1-42, Maximum Foreseeable Loss Limiting Factors) that
have adequately protected openings to limit fire damage.
2.2.1.9 Provide space between important buildings and adjacent property and between individual important
buildings to reduce potential fire exposure. See Data Sheet 1-20, Protection Against Exterior Fire Exposure,
Data Sheet 1-22, Maximum Foreseeable Loss and Data Sheet 1-42, Maximum Foreseeable Loss Limiting
Factors.
2.2.1.10 Provide damage-limiting construction for processes having an explosion (deflagration) hazard due
to ignitable liquids, gases or combustible dust, as defined in all applicable 7-series data sheets. Design these
buildings according to Data Sheet 1-44, Damage-Limiting Construction. This will minimize damage to the
building framing and the attached sprinkler system. Blast barricades may be needed for potential detonations
(see Data Sheet 7-28, Energetic Materials), as recommended.
2.2.1.11 For industrial occupancies, choose construction that will not contribute to the spread of fire. Do not
construct important buildings (those housing valuable contents or subject to significant business interruption)
with wood walls, wood joisted floors or roofs, combustible hollow spaces or quick-burning interior finishes
(see Data Sheet 1-57, Plastics in Construction, and Data Sheet 1-60, Asphalt-Coated Metal and Protected
Metal Buildings). Basements and crawl spaces are more conducive to fire spread, present problems of
accessibility, ventilation and drainage, and have poor loss experience. Such spaces are not suitable for
combustible storage, and the fire spread potential is greatly increased if ignitable liquids or gases enter. Use
FM Approved ductwork and pipe insulation as listed in the Approval Guide. Also see Data Sheet 7-78,
Industrial Exhaust Systems.
2.2.1.12 For the design of roof construction, see Data Sheet 1-29, Roof Deck Securement and Above-Deck
Roof Components and 1-31, Panel Roof Systems. Use FM Approved roof assemblies as listed in RoofNav.
Roof strength and drainage should be designed for snow and rain loads as discussed in Data Sheet 1-54,
Roof Loads and Drainage. Use wall assemblies, other than concrete or masonry, that are FM Approved (per
FM 4881) and meet wind criteria as noted in Data Sheet 1-28.
2.2.1.13 Where roof mounted solar panels are planned, use FM Approved roof mounted solar assemblies
as listed in RoofNav; and follow design and installation guidance as noted in Data Sheet 1-15, Roof Mounted
Solar Photovoltaic Panels.
2.2.1.14 Mass Engineered Timber (MET) and Other Wood Structures
Fire-resistive, non-combustible or limited-combustibility structures are preferred over wood structures
because of the inherent fire risk of wood. When wood construction is to be used, follow the guidance in
Sections 2.2.1.14.1 through 2.2.1.14.3.
2.2.1.14.1 Follow the guidance in Data Sheet 1-36, Mass Engineered Timber, as well as in Sections 2.2.1.14.2
through 2.1.1.14.3.
2.2.1.14.2 Sequence the construction of wood structures over three stories as follows:
A. Conduct an analysis that considers fire exposure to adjacent structures.
B. Determine the maximum number of combustible stories that can be constructed before installing passive
fire protection and/or placing sprinklers in service, considering the width and height of each exposed story.
C. Consider the separation distance to other structures, and the maximum incident heat flux to which
the target building can be safely exposed based on the less resistant of either the wall construction type,
the type of glass windows or the roof construction. For additional information, see Data Sheet 1-20,
Protection Against Exterior Fire Exposure.
2.2.1.14.3 Do not use torch-applied roof systems under any circumstances.
2.2.2. Protection
2.2.2.1 In multistory buildings, enclose stairs, elevator wells, conveyors and chutes with walls and doors
having a fire rating as recommended for the construction on which they are installed per Data Sheet 1-3,
High-Rise Buildings, or 1-42, Maximum Foreseeable Loss Limiting Factors. Alternatively, for assemblies other
than MFL subdivisions, provide water spray protection at openings to help prevent upward spread of fire
and smoke from story to story. Construct balconies entirely of noncombustible or limited-combustible materials
(e.g., Class 1). For existing combustible balconies, provide sprinkler protection as outlined in Data Sheets
1-12, Ceilings and Concealed Spaces, and 2-0, Installation Guidelines for Automatic Sprinklers.
2.2.2.2 Provide complete automatic sprinkler protection in accordance with applicable data sheets for
combustible construction or occupancy.
2.2.2.3 Secure the property, and provide alarm systems and programs as outlined in Data Sheet 9-1,
Supervision of Property.
2.2.2.4 Where smoke and heat vents are required by local code, see Data Sheet 2-0 and 1-10, Interaction
of Sprinklers, Smoke and Heat Vents, and Draft Curtains, to ensure that vents and draft curtains do not
adversely affect sprinkler operation.
2.3.1 Construction
2.3.1.1 Use noncombustible or limited-combustible construction for temporary trailers, sheds and offices when
they are located within or near the building being constructed or renovated. When the temporary structure
or its contents are combustible, locate the structure at least 50 ft (15 m) away from main buildings and at least
30 ft (9 m) apart from each other. When providing such separation is not possible, protect the temporary
structures with automatic sprinklers.
2.3.1.2 Design the structure to withstand expected loads during construction in accordance with ASCE 37
(see Section 4.0), or similar standard in countries outside the United States.
2.3.1.3 Brace building framing and walls not yet tied to building framing in accordance with model and/or
local building codes, as well as per recommended industry practice for the type of construction materials
involved. Organizations and documents referenced in Section 4.0 may be used, but documents used need
not be limited to those published. Also see Section 3.1.14.
For example:
• For bracing of wood construction – refer to APA: The Engineered Wood Association
• For steel framing – refer to the American Institute of Steel Construction (AISC) documents and training,
including ANSI/AISC 303-22, An American National Standard Code of Standard Practice for Steel
Buildings and Bridges
Unless a steel framework under construction is properly braced to a heavy existing structure (such as a
building or retaining wall) or permanent bracing has been installed, provide temporary cable “X” bracing.
Unless special design considerations exist as noted in AISC guidance, provide “X” bracing in every third bay
of all column lines. Brace framework in all four directions. If connections for cable “X” bracing have not been
provided, install them in the field. Ensure bracing is in the plane of column center lines. Connect all beams
and girders to the columns prior to bracing.
The erector is responsible for stability during each phase/sequence of construction.
Incomplete structures may not be stable without temporary measures during construction.
For concrete masonry walls bracing guidance, see the reference in Section 4.3 by the National Concrete
Masonry Association (NCMA).
For concrete walls and other general OSHA requirements, see the reference in Section 4.3.
When walls of hollow masonry units under construction do not have lateral support to resist wind, brace them
in accordance with Figure 2.3.1.3 (see Section 3.1.14.4). Walls should be braced on both sides.
Brace walls of tilt-up precast concrete on both sides by lean-to steel pipe braces until their permanent
securement is completed. Ensure slenderness ratio (L/r) of braces does not exceed 200, where L = length
of brace and r = least radius of gyration, both in inches.
2.3.1.4 Install only as much roof insulation as can be covered with roof covering in a single working day, or
prior to the expected start of inclement weather. Seal loose roof cover edges at the end of each day to
minimize potential moisture damage. Asphalt or coal tar (where allowed) can be used for built-up roof (BUR)
Weld
o
Wo
6x6
Top brace=10 ft. (12 in.
.
3 in
in. les
lts
2x6
bo
o
6 in
for /16 H
Splice
5/8
pieces
11
e
.
3 in
rac
odb
Wo
Cable tightening
6x6
device
8x8-6 ft.
Excavate to firm bearing Long timber
covers; proprietary sealers are available for single-ply roof covers. Do not allow water to run in the deck
ribs under completed roof sections. Follow manufacturer’s recommendations.
Distribute temporary storage of all materials on the roof awaiting installation to prevent overloading the roof
in localized areas (e.g., gravel, paver blocks).
Complete the installation of all permanent roof covers, flashing, walls, and other openings prior to the start
of any interior work that may be damaged by rain, moisture or mildew. Such interior work includes, but is not
limited to, fire protective coatings, gypsum board, ceiling tiles, interior finish materials, and materials or
equipment related to the occupancy, etc. Where water or moisture has entered the building, ensure it is
thoroughly cleaned and dried prior to the start of interior work.
2.3.1.5 Use only metal (see Section 3.1.7) formwork or scaffolding, or limited quantities of combustible
formwork or scaffolding, unless used or stored in areas protected by automatic sprinklers.
2.3.1.6 Ensure formwork used to temporarily support cast-in-place concrete is designed by a qualified civil
or structural engineer to prevent excessive sagging or collapse prior to setting of the concrete.
To minimize wind damage to roof coverings under construction, install the perimeter flashing assembly as
soon as possible after the perimeter section of the roof cover has been installed. If the edge of the insulation
and covering must be exposed for short periods of time, weight all temporary edges with closely spaced
concrete blocks, or equivalent, until the flashing is completed.
2.3.1.7 As soon as practical after the building envelope has been enclosed, construct proposed fire walls.
Install fire-resistant seals for pipe, cable and duct penetrations, and expansion and control joints in floors and
fire walls.
2.3.1.8 Take precautions with temporary ditches. Provide earthen diking at edges of the ditch to help prevent
adjacent yard area runoff from entering the ditch. Of particular concern are buildings that have basements
and frequently undergo expansions (such as hospitals). Provide temporary waterproofing at building
entrances. Temporary diking within the ditch may be needed depending on its area, expected rainfall intensity
and slope. Use extreme caution when excavating near existing underground utilities such as gas, water or
electrical lines. Ensure equipment operators are assisted by personnel on the ground in such cases.
2.3.1.9 Whenever a trash chute is used for debris removal, install it on the outside of the building. Ensure
its construction is noncombustible. Ensure the main artery of the chute is as straight as possible to help
prevent accumulations or clogging within the chute.
2.3.1.10.1 Cover the entire fabric membrane evenly with polyurethane foam. Ensure mixing and application
of the polyurethane foam is done only by experienced mechanics. Adjust the spray equipment regularly
according to temperature changes to provide proper composition and density.
2.3.1.10.2 Provide adequate reinforcement as determined by an experienced structural engineer.
2.3.1.10.3 Use an airlock with doors at each end of the entrance to the fabric membrane. Use double blowers
for reliability in pressurization of the fabric membrane. Provide a diesel or gasoline engine backup to electric
motors to prevent collapse during power failure.
2.3.1.10.4 Apply the concrete at proper pressures. Even application in the proper thickness is essential.
2.3.1.10.5 Do not start construction when high wind, heavy rain, or snow is expected. This can deform the
fabric membrane and may cause vibrations resulting in the separation of freshly placed concrete.
2.3.1.10.6 Careful design is necessary with large structures to avoid failure during construction. Cables may
be needed to brace some fabric membranes, particularly those of 280 ft (85 m) or more in diameter.
The following applies to structures more than 150 ft (45 m) in diameter:
• Ensure the design considers the necessary air pressure needed and the maximum allowable working
stress the coated fabric membrane can withstand
• Ensure the density of the polyurethane foam is 2 to 3 lb/ft3 (32 to 48 kg/m3) and complies with the
referenced ASTM E-108 listing.
2.3.1.10.7 Do not restrain the shells, such as by attachment to interior walls/partitions. This could result in
cracking when thermal expansion of the shell occurs.
2.3.1.10.8 Ensure the exposed outer surface of the shell structure has adequate resistance to exterior fire
exposure. Ensure the assembly has an ASTM E-108 rating for an unlimited slope or 5 in./ft (23 degrees) slope
as recommended in Data Sheet 1-29, Above-Deck Roof Components. Ensure the polyurethane foam has
a flame spread of 75 or less based on the ASTM E-84 test (see Data Sheet 1-4, Fire Tests); however, ensure
the flame spread does not exceed that listed for the respective ASTM E-108 rating needed.
2.3.2 Occupancy
2.3.2.1 Store compressed flammable gases in portable cylinders as outlined in Data Sheet 7-50, Compressed
Gases in Cylinders. When used on site, secure cylinders well to prevent them tipping or falling from upper
floors or roofs. Ensure ignitable liquid storage and use complies with Data Sheets 7-29, Ignitable Liquid
Storage in Portable Containers, and 7-32, Ignitable Liquid Operations.
2.3.2.2 Ensure construction-related electrical wiring and equipment for light, heat, and power is in accordance
with National Fire Protection Association (NFPA) Standard No. 70, National Electrical Code.
2.3.3 Protection
2.3.3.1 Install and activate automatic sprinkler and standpipe protection as soon as possible after the building
shell has been constructed and before combustibles are introduced.
2.3.3.2 Extend capped standpipes with hose connections upward as the various floors are constructed.
Ensure a conspicuously marked fire service pumper connection is available outside of the building at street
level. Notify the public fire service of the connection’s existence as soon as it is in service.
2.3.3.3 Install cooling tower sprinkler systems as soon as possible during new construction and leave in
service whenever maintenance or alterations are in process. When this is not practical, provide charged hose
lines.
2.3.3.4 When alterations such as roofing operations are conducted where there is an existing sprinkler system,
and debris barriers are to be installed to shield the occupancy below from debris, all the following apply:
A. Use an FM Approved Debris Barrier tested in accordance with FM 4652 and installed as listed in the
Approval Guide. The thickness of the barrier should not exceed that in the listing.
B. Install the debris barrier below the underside of roof framing members, such that the distance between
the debris barrier and the sprinkler deflectors is between 1.5 and 10 ft (0.46 and 3.0 m). Debris barriers
should be located at least 8 ft (2.4 m) above the floor).
C. Debris barriers should only be used over occupancies with limited combustible loading. This includes
the HC-1 and HC-2 occupancies as defined Table 2.2.2 and Appendix C of Data Sheet 3-26, Fire
Protection for Nonstorage Occupancies.
D. Use the debris barrier under roofs with a maximum slope of 10°.
E. The debris barrier is only for temporary use (less than 180 days) and should be removed as soon as
work above the sprinklers that would impact the occupancy below is completed.
2.3.3.5 Store containers and aerosol cans used in construction and alteration that have ignitable liquid
contents in FM Approved storage cabinets for ignitable liquids.
2.3.6.5 Avoid flame cutting in combustible buildings. Do not employ this technique when cutting through
combustible walls, floors or roofs.
2.3.6.6 Locate tar and asphalt kettles in a safe place. Locate them outside buildings on the ground with
bitumen pumped to the roof. A less desirable location would be on a noncombustible roof without combustible
roof covering or insulation below or nearby. Constantly supervise kettles to prevent them from boiling over
and igniting. Check thermometers on kettles for accuracy, and closely control temperatures. Provide steel
covers of at least 14 ga. (0.075 in. [2 mm]) thickness to close by gravity and smother flames in case of fire.
Check kettles in use at the end of each day.
2.4 Demolition
Recommendations 2.4.1 through 2.4.4, as well as those in Section 2.3 apply to structures undergoing
demolition.
2.4.1 Occupancy
2.4.1.1 Drain ignitable liquids from tanks, piping, and machinery in a safe manner and remove the residue
from the building. Remove the tanks also.
2.4.2 Protection
2.4.2.1 Keep automatic sprinklers in service as long as possible or as long as conditions necessitating
sprinklers exist (combustible construction or contents). In cold weather, where wet pipe sprinkler systems
are provided, maintain heat in sprinklered areas or install dry pipe valves where practical. Take sprinkler piping
out of service section by section, to the extent practical, and cap as demolition progresses.
Limit sprinkler control valve operation to authorized personnel who will notify concerned parties. Check the
sprinkler control valve at the end of each workday to ensure it is open.
2.4.2.2 Where standpipes for fire hose are provided, maintain them in service as described above in Section
2.5.1.1. Use charged hose lines in areas where sprinklers are out of service, near temporary combustible
debris accumulations, roofing operations, cooling towers, and cutting operations.
2.4.2.3 If explosives are used, such as in demolition by implosion, provide 1 ½ in. to 2 ½ in. (38 mm to
64 mm) charged hose lines capable of reaching all areas in the vicinity of the demolition site.
Ensure demolition by implosion is performed only by engineers and contractors who are experienced in this
work.
Consider the effects of building debris impacting on the ground. In some cases, and especially with multi-story
buildings, the placement of sand at streel level surrounding the structure may be needed to dampen the
force of impact with the ground.
Analyze the exposure to adjacent buildings and provide protection as necessary. Isolate underground services
in the area during the implosion. Ensure the demolition engineer determines if seismic activity in the area
should be monitored throughout the implosion to help determine if the impact had the potential to cause
damage to underground services or adjacent structures.
2.4.2.4 Keep horizontal and vertical fire subdivisionand fire doors intact until demolition progresses to them;
this helps limit potential fire-spread and retains heat.
2.4.2.5 To the extent practical, protect remaining structures from flying debris during demolition, such as by
temporarily covering nearby windows with plywood.
2.4.4 Utilities
2.4.4.1 Shut off and cap gas supplies at a point outside the building prior to the start of demolition.
2.4.4.2 Reduce electrical service to a minimum and mark to identify which circuits are energized. Physically
disconnect and positively lock out discontinued lines.
Noncombustible – a material that has passed ASTM E136 or ASTM E2652. Materials that are inherently
noncombustible, such as steel, concrete, masonry and glass, do not need to be tested.
Limited Combustible – materials or assemblies that meet one of the following criteria:
a) Are FM Approved as Class 1 based on an FM Approval Examination Standard
b) Has a potential heat value ≤ 3500 BTU/lb. per NFPA 259 and has a Flame Spread Index (FSI) ≤ 25
based on the ASTM E84 test
c) Has a potential heat value ≤ 3500 BTU/lb per NFPA 259, has a structural base of noncombustible
material and a surfacing ≤ 1/8 in. (3.2 mm)thick and having a FSI ≤ 50 based on the ASTM E84 test
d) When tested to ASTM E2965 with an incident heat flux of 75 kW/m2 for 20 minutes, has a peak heat
release rate that does not exceed 150 kW/m2 for longer than 10 seconds, and a total heat release not
exceeding 8 MJ/m2.
if exposed to wind, and keep the floor around them free from all combustible material. Secure combustible
material so wind does not blow it against heaters and cause ignition. Check temporary heaters to ensure they
are turned off at the end of the work day. If intended for continuous operation, have the heaters checked
at least hourly if watch service is provided.
Locate portable kerosene heaters with built-in fans to circulate heated air outside buildings under construction
and far away from combustible material. Ensure a capable employee operates and maintains the heaters,
following all safeguards recommended by the manufacturer. Locate a minimum 15 lb (6.8 kg) portable dry
chemical extinguisher near all entrances to heated areas. Kerosene heaters are much safer than those
burning gasoline, which are prohibited by some fire regulations and not recommended. Gas-fired, electric,
or steam heaters are preferred.
structure or in the open, not inside main buildings. Handle low-flashpoint liquids, such as gasoline and alcohol,
in maximum 5 gal (20 L), FM Approved safety cans only. Keep delivery trucks carrying ignitable liquids outside
buildings.
3.1.13 Wind
The number of wind losses to buildings under construction is approximately equal to the number of fire losses.
Most wind damage at construction projects has involved masonry walls, roof coverings, framework, or forms.
Plan construction so framing is adequately braced and walls can be anchored to the building framework
as soon as they are erected; otherwise, temporary shoring may be necessary as recommended in Section
2.0. Proper methods of roof application are extremely important, particularly on insulated steel-deck roofs. Do
not store construction materials on a roof overnight since they can be blown away by moderate winds. Ensure
roofing in construction is properly secured or weighted down at the close of the day’s work to prevent damage
to these materials and blockage of drains that may lead to collapse or roof leakage. Construction forms should
be suitably secured. Bolt the steelwork securely enough to withstand a severe windstorm. Anchor roof-
mounted equipment to the structure immediately after it is set on the roof. Take extra precautions whenever
severe winds are predicted, and be prepared for sudden, unpredictable storms.
Fig. 3.1.14.1. Wind damage to steel frame. This framework is only one of many that did not have adequate cable bracing.
One form of simple structure consists of two columns supporting the ends of a beam or truss. A series of
these structures tied together by longitudinal beams, such as girts on walls and purlins on the roof, make up
the frame (skeleton) of the building. Erection of the first structure or frame is critical, as there is no other
structure of similar kind to brace against. After the columns are bolted to the foundation, bracing the erected
frame by temporary struts or cables will stabilize it and prevent it from being blown over by wind forces. Other
braced frames placed at right angles to the first erected frame will stabilize the framework in the other
direction.
The erecting contractor is responsible for installation of some type of bracing to prevent collapse during
construction. Installation of bracing is facilitated when end-connecting plates (to which the bracing will be
attached) have been shop welded to the steelwork. Cable bracing can be effectively tightened by jacks or
turnbuckles and is needed only in a few of the total bays.
When any column line of the structural frame has permanent diagonal bracing, installation of the bracing
members as the structure is erected will be sufficient to act as temporary bracing, providing the column base
plates are securely bolted down, and the beams are connected to the tops of the columns. Some column
lines, however, may not have permanent bracing; so temporary bracing is needed.
Buckling of a brace or other compression member may be prevented by designing the member according
to specifications by the American Institute of Steel Construction (AISC) or comparable standard.
The AISC specifications limit the L/r ratio of steel braces to a maximum of 200, where L is the length of the
brace in inches and r is the smallest radius of gyration for the brace, equal to (I/A)0.5 (I = the moment of
inertia, A is the area of the section). The radius of gyration may be found in structural engineering handbooks.
Table 3.1.14.1 gives acceptable minimum pipe diameters based upon the above specification.
braced at that level. The process can be continued until the wall is finished. The compression force in the
brace needs to be transferred to both the ground and masonry wall. Bracing is normally placed at about 30
degrees with the vertical.
3.1.14.4 Bracing Procedure
The bracing system shown in Figure 1 is capable of resisting winds of approximately 55 mph (24 m/s) from
either direction.
Anchor two ¾ in. (19 mm) steel eye bolts, one on each side, in the concrete foundation wall every 16 ft
(4.9 m). It is extremely important that the bolts and braces are installed directly opposite each other. If the
anchors were not installed when the wall was poured, holes can be drilled through the wall for 1 in. (25 mm)
diameter through bolts.
After the pair of braces is erected, install the cables on both sides and tighten simultaneously. This will create
a compression force in the braces that will seat the ground timbers and also stabilize the braces. If the timbers
settle an inch (25 mm) or more, shims or blocking installed at the base of the brace may be necessary to
prevent the top of the brace from moving significantly downward on the wall.
Ensure spacing of both upper and lower braces is 32 ft (9.8 m). Place the upper braces halfway between
the lower braces.
Ensure interior partitions are self-supporting and not rigidly attached to the shell. Any restraint caused by
such attachment could result in cracking when thermal expansion of the shell occurs.
3.1.16 Excavation
Excavation adjacent to buildings has caused losses. In some cases, walls have collapsed due to the loss
of stability provided by the adjacent soil. Where large ditches are to be excavated next to a structure, have
a civil or structural engineer ensure that either the excavation will not adversely affect the structure or that
adequate temporary bracing is provided. Ditches, particularly those dug for piping entering the adjacent
building, can allow rainwater to enter the building, damaging it and its contents. Take precautions to prevent
a loss due to rainwater that would directly enter the ditch or run off into the ditch and enter the building.
4.0 REFERENCES
4.1 FM Global
Data Sheet 1-1, Firesafe Building Construction and Materials
Data Sheet 1-2, Earthquakes
Data Sheet 1-3, High-Rise Buildings
Data Sheet 1-4, Fire Tests
Data Sheet 1-10, Interaction of Sprinklers, Smoke and Heat Vents, and Draft Curtains
Data Sheet 1-12, Ceilings and Concealed Spaces
Data Sheet 1-13, Chimneys
Data Sheet 1-15, Roof Mounted Solar Photovoltaic Panels
Data Sheet 1-17, Reflective Ceiling Insulation
Data Sheet 1-20, Protection Against Exterior Fire Exposure
Data Sheet 1-21, Fire Resistance of Building Assemblies
Data Sheet 1-22, Maximum Foreseeable Loss
Data Sheet 1-24, Protection Against Liquid Damage
Data Sheet 1-28, Wind Design
Data Sheet 1-29, Steel Deck Securement and Above-Deck Roof Components
Data Sheet 1-30, Repair of Wind Damaged Single and Multi-Ply Roof Systems
Data Sheet 1-31, Panel Roof Systems
Data Sheet 1-32, Inspection and Maintenance of Roof Assemblies Data Sheet 1-33, Safeguarding Torch-
Applied Roof Insulation
Data Sheet 1-34, Hail
Data Sheet 1-36, Mass Engineered Timber
Data Sheet 1-40, Flood
Data Sheet 1-42, MFL Limiting Factors
Data Sheet 1-44, Damage-Limiting Construction
Data Sheet 1-49, Perimeter Flashing
Data Sheet 1-54, Roof Loads and Drainage
Data Sheet 1-57, Plastics in Construction
Data Sheet 1-59, Fabric and Membrane Structures
Data Sheet 1-60, Asphalt-Coated/Protected Metal Buildings
Data Sheet 1-61, Fire-Retardant Treated Wood
Data Sheet 1-62, Cranes
Data Sheet 2-0, Installation Guidelines for Automatic Sprinklers
Data Sheet 3-26, Fire Protection for Nonstorage Occupancies
Data Sheet 4-4N, Standpipe and Hose Systems
Data Sheet 4-5, Portable Extinguishers
Data Sheet 7-28, Energetic Materials
Data Sheet 7-29, Ignitable Liquid Storage in Portable Containers
Data Sheet 7-32, Ignitable Liquid Operations
Data Sheet 7-50, Compressed Gases in Portable Cylinders
Data Sheet 7-78, Industrial Exhaust Systems
Data Sheet 7-83, Drainage Systems for Ignitable Liquids
Data Sheet 9-1, Supervision of Property
Data Sheet 9-19, Wildland Fire
Data Sheet 10-3, Hot Work Management
4.1.1 FM Approvals
Approval Guide, an on-line publication of FM Approvals
ANSI/FM 4950, American National Standard for Evaluating Welding Pads, Welding Blankets and Welding
Curtains for Hot Work Operations
FM 4652 Examination Standard for Debris Barriers
RoofNav, an on-line resource of FM Approvals
APA: The Engineered Wood Association, APA System Report SR-102E, APA Simplified Wall Bracing Method
Using Wood Structural Panel Continuous Sheathing, April 2020
National Concrete Masonry Association (NCMA)
TEK 03-04C, Bracing Concrete Masonry Walls Under Construction, revised 2014
Occupational Health and Safety Association (OSHA),
OSHA Title 29, Code of Federal Regulations, Standard 1926.704
Precast/Prestressed Concrete Institute (PCI), Precast Insulated Sandwich Panels, (FIB-84-17)
Note: For locations outside the United States, reference comparable international standards.