BILL OF QUANTITIES
PROJECT TITLE: PROPOSED RENOVATION OF BUNGALOW AND CONSTRUCTION OF TWO-STOREY RESIDENTIAL BUILDING
ITEM NO. DESCRIPTION QTY UNIT UNIT COST TOTAL COST UNIT COST TOTAL COST AMOUNT
I. CIVIL WORKS
A. SITE WORK
5 OTHER
B. EARTHWORKS
1 EXCAVATION
1.2 TIE BEAMS 8.50 CU.M. ₱0.00 ₱0.00 ₱500.00 ₱4,250.00 ₱4,250.00
1.3 SEPTIC TANK 11.25 CU.M. ₱0.00 ₱0.00 ₱2,500.00 ₱28,125.00 ₱28,125.00
2 SOIL TREATMENT (1L) 1.00 BOTTLE ₱4,000.00 ₱4,000.00 ₱1,800.00 ₱1,800.00 ₱5,800.00
3 GRADING AND TAMPERING 0.00 SQM ₱0.00 ₱0.00 ₱250.00 ₱0.00 ₱0.00
4 FILL AND BACKFILL 26.40 CU.M. ₱0.00 ₱0.00 ₱250.00 ₱6,600.00 ₱6,600.00
COLUMNS
BEAMS
ROOF BEAMS
1
PLASTERING WORKS
4 10mm X 6.0m DEFORMED BARS 75.00 PCS ₱155.00 ₱11,625.00 ₱69.75 ₱5,231.25 ₱16,856.25
5 #16 TIE WIRES 7.50 KGS ₱90.00 ₱675.00 ₱40.50 ₱303.75 ₱978.75
4 10mm X 6.0m DEFORMED BARS 161.00 PCS ₱155.00 ₱24,955.00 ₱69.75 ₱11,229.75 ₱36,184.75
5 #16 TIE WIRES 16.10 KGS ₱90.00 ₱1,449.00 ₱40.50 ₱652.05 ₱2,101.05
WALL FOOTING
4 10mm X 6.0m DEFORMED BARS 74.00 PCS ₱155.00 ₱11,470.00 ₱69.75 ₱5,161.50 ₱16,631.50
5 #16 TIE WIRES 7.40 KGS ₱90.00 ₱666.00 ₱40.50 ₱299.70 ₱965.70
SEPTIC TANK
4 10mm X 6.0m DEFORMED BARS 105.00 PCS ₱155.00 ₱16,275.00 ₱69.75 ₱7,323.75 ₱23,598.75
5 6” THK (NON-LOAD BEARING) 343.00 PCS ₱21.00 ₱7,203.00 ₱9.45 ₱3,241.35 ₱10,444.35
6 #16 TIE WIRES 10.50 KGS ₱90.00 ₱945.00 ₱40.50 ₱425.25 ₱1,370.25
D. FORM WORKS
COCO LUMBER (ASSORTED) 1,148.00 BD FT ₱40.00 ₱45,920.00 ₱18.00 ₱20,664.00 ₱66,584.00
3/4” MARINE- STA. CLARA 33.00 PCS ₱2,400.00 ₱79,200.00 ₱1,080.00 ₱35,640.00 ₱114,840.00
CWN, ASSORTED 18.00 KGS ₱110.00 ₱1,980.00 ₱49.50 ₱891.00 ₱2,871.00
#16 G.I TIE WIRE 94.00 KGS ₱90.00 ₱8,460.00 ₱40.50 ₱3,807.00 ₱12,267.00
SUB-TOTAL ₱135,560.00 ₱61,002.00 ₱196,562.00
E. REBARWORKS
1 16mm X 6.0m DEFORMED BARS 394.00 PCS ₱377.00 ₱148,538.00 ₱169.65 ₱66,842.10 ₱215,380.10
2 12mm X 6.0m DEFORMED BARS 54.00 PCS ₱217.00 ₱11,718.00 ₱97.65 ₱5,273.10 ₱16,991.10
3 10mm X 6.0m DEFORMED BARS 365.00 PCS ₱155.00 ₱56,575.00 ₱69.75 ₱25,458.75 ₱82,033.75
4 #16 TIE WIRES 147.00 KGS ₱90.00 ₱13,230.00 ₱40.50 ₱5,953.50 ₱19,183.50
5 OTHER
F. MASONRY WORKS
1 CHB #5 (NON-LOAD BEARING) 1,684.00 PCS ₱21.00 ₱35,364.00 ₱9.45 ₱15,913.80 ₱51,277.80
2 CHB #4 (NON-LOAD BEARING) 763.00 PCS ₱17.00 ₱12,971.00 ₱7.65 ₱5,836.95 ₱18,807.95
5 #16 TIE WIRES 9.00 BAGS ₱90.00 ₱810.00 ₱40.50 ₱364.50 ₱1,174.50
2
6 10mm X 6.0m DEFORMED BARS 236.00 PCS ₱155.00 ₱36,580.00 ₱69.75 ₱16,461.00 ₱53,041.00
2 BUILDING
7 4mm THK. 12’ CORRUGATED GI 80.00 PCS ₱1,150.00 ₱92,000.00 ₱517.50 ₱41,400.00 ₱133,400.00
SHEET
8 5mm X 8FT BOX TYPE GUTTER 29.00 PCS ₱600.00 ₱17,400.00 ₱270.00 ₱7,830.00 ₱25,230.00
9 5mm X 8FT BOX TYPE INSIDE 0.00 PCS ₱600.00 ₱0.00 ₱270.00 ₱0.00 ₱0.00
GUTTER
12 3” PVC ORANGE PIPE- DOWN 12.00 PCS ₱450.00 5,400.00 ₱202.50 2,430.00 ₱7,830.00
SPOUT
13 NELTEX PVC SOLVENT CEMENT 5.00 ₱300.00 1,500.00 ₱135.00 675.00 ₱2,175.00
400CC
14 2x6 G.I TUBULAR 24.00 PCS ₱1,701.00 ₱40,824.00 ₱765.45 ₱18,370.80 ₱59,194.80
15 2x4 G.I TUBULAR 18.00 PCS ₱1,166.00 ₱20,988.00 ₱524.70 ₱9,444.60 ₱30,432.60
18 WELDING MACHINE (RENTAL) 1.00 LOT ₱2,000.00 ₱2,000.00 ₱900.00 ₱900.00 ₱2,900.00
TRENCH CANAL WITH GRILLS 28.00 M ₱450.00 ₱12,600.00 ₱202.50 ₱5,670.00 ₱18,270.00
TOILET FIXTURES
PANEL BOARD WITH BREAKERS 13.00 SET ₱1,550.00 ₱20,150.00 ₱697.50 ₱9,067.50 ₱29,217.50
PANEL BOARD WITH BREAKERS 6.00 SET ₱1,550.00 ₱9,300.00 ₱697.50 ₱4,185.00 ₱13,485.00
3
RENOVATION
GEN. FLOOR AREA 60X60 CERAMIC TILES- GLOSS 175.00 PCS OSM 45% LABOR FOR INSTALLTION
NEW CONSTRUCTION
V. PAINTING WORKS
EXTERIOR AND INTERIOR 591.00 SQM ₱350.00 ₱206,850.00 ₱157.50 ₱93,082.50 ₱299,932.50
VII. TINSMITH
GATE 2x4 G.I TUBULAR 18.00 PCS ₱1,166.00 ₱20,988.00 ₱524.70 ₱9,444.60 ₱30,432.60
16MM ROUND BAR 28.00 GAL ₱490.00 ₱13,720.00 ₱220.50 ₱6,174.00 ₱19,894.00
WELDING MACHINE (RENTAL) 1.00 LOT ₱2,000.00 ₱2,000.00 ₱900.00 ₱900.00 ₱2,900.00
MADE-SHIFT LOCK SET 4.00 SET ₱1,500.00 ₱6,000.00 ₱675.00 ₱2,700.00 ₱8,700.00
BALCONY BALUSTERS (STAINLESS STEEL) 1.00 SET OSM 45% LABOR FOR INSTALLTION
STAIRCASE BALUSTERS (STAINLESS STEEL) 1.00 SET OSM 45% LABOR FOR INSTALLTION
STAIRCASE 2X4 CHANNEL BAR 6.00 PCS ₱1,650.00 ₱9,900.00 ₱742.50 ₱4,455.00 ₱14,355.00
2X2X1/4 ANGLE BAR 15.00 PCS ₱480.00 ₱7,200.00 ₱216.00 ₱3,240.00 ₱10,440.00
1.2X0.3X2” THK WOODEN PLANK 17.00 PCS ₱400.00 ₱6,800.00 ₱180.00 ₱3,060.00 ₱9,860.00
WELDING MACHINE (RENTAL) 1.00 LOT ₱2,000.00 ₱2,000.00 ₱900.00 ₱900.00 ₱2,900.00
RENOVATION 10MM THK FIBER CEMENT 35.00 PCS ₱410.00 ₱14,350.00 ₱184.50 ₱6,457.50 ₱20,807.50
BOARD M.R
4
5
Table 1
SPECIFICATIONS
₱2,297,780.68
DESCRIPTION
SITE WORK
MOBILIZATION
TEMPORARY FACILITIES
ENCLOSURE
DEMOLITION
OTHER
EARTHWORKS
EXCAVATION
OTHER (LAYOUT)
CONCRETING WORKS
PORTLAND CEMENT
S1-SAND
GRAVEL 3/4”
6
PLASTERING WORKS
PORTLAND CEMENT
WHITE SAND
FORM WORKS/SCAFFOLDINGS/
INSTALLTIONS/DISMANTLING
REBARWORKS
OTHER
MASONRY WORKS
6” THK 700PSI
4” THK 700PSI
PORTLAND CEMENT
S1-SAND
7
ROOFING WORKS/SKY LIGHT
HOUSING UNIT
BLIND RIVET
SILICON SEALANT
WELDING ROD
PLUMBING WORKS
KITCHEN SINK
SHOWER
WATER CLOSET
WASHING MACHINE
LAVATORY
GARDEN HOSE
ELECTRICAL WORKS
AIRCON ROUGH IN
CONVENIENCE OUTLET
(UNIVERSAL)
LIGHTING OUTLET
(RECEPTABLES-ORDINARY)
CONDUIT PIPE
8
60X60 CERAMIC TILES- GLOSS
PATTERNED FLOOR
TILE ADHESIVE
PORTLAND CEMENT
DIAMOND BLADE
GRINDER (RENTAL)
PAINTING WORKS
INTERIOR PAINT
TINSMITH
WELDING ROD
CYLINDRICAL HINGE
CEILING WORKS
METAL FURRING
CARRYING CHANNEL
BLIND RIVET
METAL FURRING
CARRYING CHANNEL
BLIND RIVET
9
10
PROPOSED RENOVATION OF BUNGALOW WITH MEZZANINE
BLOCK 3 AND 4 WEST GOVERNOR HEIGHTS 2 BARANGAY CABUCO, TRESE MARTIRES, CAVITE
PROVINCE
PHASE 1
SPECIFICATIONS:
SITE WORK: MOBILIZATION INCLUDES TRANSPORTATION FOR MAN POWER, TOOLS AND
EQUIPMENT, AND SCAFFOLDING (RENTAL ONLY); TEMPORARY FACILITIES SUCH AS WATER BILL
AND ELECTRICITY BILL WILL BE SHOULDERED BY THE CLIENT; SITE ENCLOSURE WILL NO
LONGER BE NECESSARY; DEMOLITION INCLUDES DISMANTLING OF EXISTING ROOF AND
PURLINS, PARTITION WALL AND EXISTING TOILET AND BATH.
EARTHWORKS: EXCAVATE 2- 60CM X 60CM X 100CM FOR THE GARAGE GATE COLUMN; POUR
SOIL TREAT 30 MINUTES BEFORE CONCRETING; BACK FILL AND TAMPER GARAGE COLUMN
AFTER CONCRETING OF FOOTING AND PEDESTAL; GRADE TO APPROPRIATE SLOPE GARAGE
AREA (20CM SLOPE TO ROAD).
CONCRETING: USE ONE-BAGGER MIXER; RATIO 1:3:5 MIX FOR GARAGE, TOILET ETC.;
11
PLASTERING: FINISH COAT ON ALL INTERIOR WALLS
REBAR WORKS: ASSEMBLE 16MM- MAIN BAR FOR ROOF BEAM AND COLUMN 1- A&B;
ASSEMBLE 16MM- MAIN BARS FOR LINTEL BEAM AT 2.75METERS HEIGHT WITH TOTAL
PERIMETER OF MORE OR LESS 13METERS; ASSEMBLE 12MM- TEMPERATURE BAR SPACING @
10CM ON SUSPENDED SLAB/MEZZANINE; ASSEMBLE 10MM- TENSILE BAR SPACING @ 10CM
ON SUSPENDED SLAB/MEZZANINE; ASSEMBLE 10MM- FOR VERTICAL TIES AND STIRRUPS ON
COLUMN 1-A&B, MORE OR LESS 13 METERS LINTEL BEAM AND MORE OR LESS 21METERS
ROOF BEAM; TIE WIRE TO CONNECT.
MASONRY: INSTALL 8” THK CHB FROM NGL TO 3.10M HT. WITH TOTAL PERIMETER OF MORE OR
LESS 16METERS, AND 6.75M HT WITH TOTAL WIDTH OF 4METERS; INSTALL 6” THK CHB FROM
SECOND FLR LINE TO SOFFIT OF ROOF BEAM BEAM WITH TOTAL PERIMETER OF MORE OR
LESS 21METERS; INSTALL 4” THK CHB FROM NGL TO 4.0M HT WITH TOTAL PERIMETER OF
MORE OR LESS 12METERS; USE RATIO 1 (CEMENT) : 3 (SAND-S1) FOR MORTAR BED. PROVIDE
10MM REBAR AT 600MM SPACING FOR DOWELS AND 10MM REBAR HORIZONTAL SUPPORT AT
EVERY 3 COURSE OF CHB REGARDLESS OF THICKNESS.
12
ROOFING: INSTALL 5MM THK. LONG SPAN RIB TYPE GI SHEET WITH 2 1/2 LAPPING ON TOP OF
2X6 GI TUBULAR (LONGER SPAN) AND 2X4 GI TUBULAR (SHORTER SPAN) WITH MAXIMUM
SPACING OF 60CM BOTH WAYS, OBSERVE SEAM WELD FOR LAPPING AND FILLET WELD FOR
CORNER CONNECTION; FASTEN SHEETS WITH METAL TECH SCREW AT 12’ TO 18” DISTANCE;
INSTALL 5MM X 8FEET END CAPS ON CORNER EDGES AND SEAL GAPS WITH SILICON SEALANT
(ROOFING USE); CONNECT ROOFING ACCESSORIES WITH BLIND RIVET; PROVIDE 3” ROUND
HOLE ON ONE SIDE (SLOPE) OF INSIDE GUTTER; ATTACH MADE-SHIFT TALE PIECE TO 3” PVC
PIPE TO DOWN SPOUT; NELTEX SOLVENT CEMENT TO CONNECT PVC.
PLUMBING: INSTALL ALL WATER LINE AND SEWER LINE INCLUDING TAPPING TO EXISTING
SEPTIC TANK; ALL FIXTURES AND FURNITURES SHALL BE PURCHASED BY THE CLIENT;
SHOWER INCLUDES SHOWER HEAD, SHOWER VALVE, FAUCET, FLOOR DRAIN; WASHING
MACHINE INCLUDES FLOOR DRAIN; WATER CLOSET INCLUDES FLOOR DRAIN; CONCRETED
TRENCH CANAL WITH REMOVABLE GRILL COVER MEASURING 3.87METERS LONG, 30CM WIDE
AND 50CM DEEP.
13
TILING: ALL 60X60 CERAMIC TILES PLACED 0-0 GAP AND FASTENED TO WALL USING PORTLAND
CEMENT WITH ADHESIVE; WALL VINYL TILES FASTENED TO FLOOR USING NO-MORE NAIL OR
RUGBY (CONTACT CEMENT).
PAINTING: INTERIOR WALL BE PREPARED WITH NEUTRALIZER, PAINT FLAT LATEX PRIMER,
BEFORE 2 COATS OF ELASTOMERIC PAINT; INTERIOR PAINT INCLUDES CEILING OF MEZZANINE
AND TOILET AND BATH; EXTERIOR WALL NO TREATMENT, PAINT WITH VERSATEX PAINT FOR
ANAY FINISH LOOK AND TOP COAT WITH 1 COAT OF DESIRED COLOR FINISH.
TINSMITH WORKS:PAINT STEEL MATERIALS WITH EPOXY GREY BEFORE WELDING AND
ASSEMBLING; USE 2X6 G.I TUBULAR STEEL AS BODY FRAME, CUT AT 45DEGREED USING MITER
BOX AND SEAM WELD TOGETHER; PLACE G.I PLAIN SHEET ON TOP OF EACH WING USING
TUCK WELD; TO LOCK, LOCK WITH MADE SHIFT LOCK SET; TO FASTEN TO GATE COLUMN, USE
CYLINDRICAL HINGE 3 PCS PER PANEL/SWING.
TINSMITH WORKS (DESIGN ON THAT LEDGE): PAINT STEEL MATERIALS WITH EPOXY GREY
BEFORE WELDING AND ASSEMBLING; USE 2 X2 G.I. TUBULAR STEEL, CUTTED WITH 45
DEGREES ON CORNER AND FASTENED TOGETHER USING SEAM WELD AS BODY FRAME; WELD
1X3 FLAT BARS PLACED VERTICALLY 10MM APART ; TO MAKE ACCESSIBLE, PROVIDE 1M X
DETERMINED WIDTH AS OPERABLE DOOR FOR AIRCON MAINTENANCE.
CEILING WORKS: FOR CEILING FRAME, USE METAL FURRING AT .60M SPACING BOTH WAYS
ATTACHED TO CARRYING CHANNEL WITH W-CLIP AT 1.20M SPACING ON SHORTER SPAN; FOR
HANGERS, USE CARRYING CHANNEL 1 FOOT AWAY FROM INTERSECTION; FASTENED METAL
UNITS USING BLIND RIVET; FASTENED 10MM THK FIBER CEMENT BOARD TO CEILING FRAME
WITH 21PCS OF BLIND RIVET EACH PANEL; SAME PROCESS TO MEZZANINE CEILING.
14
15
Table 1
Ar. Dona Kristle Boado Purchase Order No. 001
Ref. No.:
Delivery Address: PINAGBAYANAN, PUROK 3, FOREST PARK VILLE ST., PILA LAGUNA
Pick up: -
Terms: -
1 bag S1-SAND