POMI
POMI
POMI
General Rules
1 This Standard Method of Measurement provides a uniform basis for measuring building works and embodies the essentials of good practice. Bills of
quantities shall fully describe and accurately represent the quantity and quality of the works to be carried out. More detailed information than is required by
these rules shall be given where necessary in order to define the precise nature and extent of the required work.
1. Introduction
Generally
2.1
The rules in this document are set out in tables. Each section of the rules comprises information (to be) provided, classification tables and supplementary
rules. The tabulated rules are written in the present tense.
2.2 Horizontal lines divide the classification table and supplementary rules into zones to which different rules apply.
Classification tables
2.3 Within the classification table where a broken line is shown, the rules given above and below the broken line may be used as alternatives.
2.4 In referring to columns in classification tables the measurement unit column has been disregarded.
2.5 The left hand column of the classification table lists descriptive features commonly encountered in building works. The next column lists further sub-groups
into which each main group of items shall be divided and similarly the third column provides for further division. The lists in these columns are not intended
to be exhaustive.
2.6 Each item description shall identify the work with respectto one descriptive feature drawn from each of the first three columns in the classification table
2. Use of the tabulated and as many of the descriptive features in the fourth column as are applicable to the item. The general principle does not apply to Preliminaries in that it
rules will be necessary to select as many descriptive features as appropriate from each column.
2.7 Where the abbreviation (nr) is given in the classification table the quantity shall be stated in the item description.
Supplementary rules
2.8 Within the supplementary rules everything above the horizontal line, which is immediately below the classification table heading, is applicable throughout
that table.
2.9 Measurement rules set out when work shall be measured and the method by which quantities shall be computed.
2.10 Definition rules define the extent and limits of the work represented by a word or expression used in the rules and in a bill of quantities prepared in
accordance with the rules.
2.11 Coverage rules draw attention to particular incidental work which shall be deemed to be included in the appropriate items in a bill of quantities to the
extent that such work is included in the tender documents. Where the coverage rules include materials they shall be mentioned in the item descriptions.
2.12 The column headed Supplementary Information contains rules governing the information which shall be given in addition to the information given as a
2. Use of the tabulated result of the application of rule 2.6.
rules 2.13 A separate item shall be given for any work which differs from other work with respect to any matter listed as supplementary information.
3.1 Work shall be measured net as fixed in position except where otherwise stated in a measurement rule applicable to the work.
3.2 Dimensions used in calculating quantities shall be taken to the nearest 10mm (i.e. 5mm and over shall be regarded as 10mm and less than 5mm shall be
disregarded).
3.3 Quantities measured in tonnes shall be given to two places of decimals. Other quantities shall be given to the nearest whole unit except that any quantity
less than one unit shall be given as one unit.
3.4 Unless otherwise stated, where minimum deductions for voids are dealt with in this document they shall refer only to openings or wants which are within
the boundaries of measured areas. Openings or wants which are at the boundaries of measured areas shall always be the subject of deduction irrespective of
3. Quantities size.
3:5 The requirement to measure separate items for widths not exceeding a stated limit shall not apply where these widths are caused by voids.
4.1 Dimensions shall be stated in descriptions generally in the sequence length, width, height. Where ambiguity could arise, the dimensions shall be identified.
4.2 Information required by the application of rules 2.6 and 2.12 may be given in documents (e.g. drawings or specification) separate from the bills of
quantities if a precise and unique cross reference is given in its place in the description of the item concerned. This rule does not allow the aggregation of a
number of measured items which are otherwise required to be measured separately by these rules, except as provided by rule 9.1.
4.3 Headings to groups of items in a bill of quantities shall be read as part of the descriptions of the items to which the headings apply.
4.4 The use of a hyphen between two dimensions in this document or in a bill of quantities shall mean a range of dimensions exceeding the first dimension
stated but not exceeding the second.
4.5 Each work section of a bill of quantities shall begin with a description stating the nature and location of the work unless evident from the drawn or other
information required to be provided by these rules.
4.6 Unless otherwise specifically stated in a bill of quantities or herein, the following shall be deemed to be included with all items:
(a) Labour and all costs in connection therewith.
(b) Materials, goods and all costs in connnection therewith.
(c) Assembling, fitting and fixing materials and goods in position.
(d) Plant and all costs in connection therewith.
4. Descriptions (e) Waste of materials and all costs in connection with disposal.
(f) Square cutting.
(g) Establishment charges, overhead charges and profit.
4.7 A dimensioned description for an item in the bill of quantities shall define the item and state all the dimensions necessary to identify the shape and size of
the item or its components.
5.1 Location drawings:
(a) Block Plan: shall identify the site and locate the outlines of the building works in relation to a town plan or other context.
(b) Site Plan: shall locate the position of the building works in relation to setting out points, means of access and general layout of the site.
(c) Plans, Sections and Elevations: shall show the position occupied by the various spaces in a building and the general construction and location of the
principal elements.
5.2 Component drawings: shall show the information necessary for manufacture and assembly of a component.
5.3 Dimensioned diagrams: shall show the shape and dimensions of the work covered by an item and may be used in a bill of quantities in place of a
dimensioned description, but not in place of an item otherwise required to be measured.
5. Drawn information 5.4 Schedules which provide the required information shall be deemed to be drawings as required under these rules.
6.1 A precise and unique cross-reference to a catalogue or to a standard specification may be given in an item description instead of the description required
by rules 2.6 and 2.12 or instead of a component drawing.
6. Catalogued or standard
components
7.1 Work of each of the following special types shall be separately identified:
(a) Work on or in existing building — see general rule 13.
(b) Work to be carried out and subsequently removed (other than temporary works).
(c) Work outside the curtilage of the site.
(d) Work carried out in or under water shall be so described stating whether canal, river or sea water and (where applicable) the mean Spring levels of high
7. Work of special types and low water.
(e) Work carried out in compressed air shall be so described stating the pressure and the method of entry and exit.
8.1 Method of fixing shall only be measured and described where required by the rules in each Work Section. Where fixing through vulnerable materials is
required to be identified, such materials are deemed to include those listed in rule 8.3 (e).
8.2 Where the nature of the base is required to be identified each type of base shall be identified separately.
8.3 Where the nature of the background is required to be identified the item description shall state one of the following:
(a) Timber, which shall be deemed to include manufactured building boards.
(b) Masonry, which shall be deemed to include concrete, brick, block and stone.
(c) Metal.
(d) Metal faced materials.
(e) Vulnerable materials, which shall be deemed to include glass, marble, mosaic, tiled finishes and the like.
9.1 Notwithstanding the requirement of clause 4.2, work to be manufactured off site may be combined into one item even though the rules require items to
be measured separately, provided the items in question are all incorporated into the composite item off site. The item description shall identify the resulting
composite item and the item shall be deemed to include breaking down for transport and installation and subsequent
9. Composite items re-assembly.
10.1 Where work can be described and given in items in accordance with these rules but the quantity of work required cannot be accurately determined, an
estimate of the quantity shall be given and identified as an approximate quantity.
10.2 Where work cannot be described and given in items in accordance with these rules it shall be given as a Provisional Sum and identified as for either
defined or undefined work as appropriate.
10.3 A Provisional Sum for defined work is a sum provided for work which is not completely designed but for which the following information shall be
provided:
(a) The nature and construction of the work.
(b) Astatement of how and where the work is fixed to the building and what other work is to be fixed thereto.
(c) A quantity or quantities which indicate the scope and extent of the work.
(d) Any specific limitations and the like identified in Section A35.
10. Procedure where the 10.4 Where Provisional Sums are given for defined work the Contractor will be deemed to have made due allowance in programming, planning and pricing
drawn and Preliminaries. Any such allowance will only be subject to adjustment in those circumstances where a variation in respect of other work measured in detail in
specification information accordance with the rules would give rise to adjustment.
required by these 10.5 A Provisional Sum for undefined work is a sum provided for work where the information required in accordance with rule 10.3 cannot be given.
rules is not available 10.6 Where Provisional Sums are given for undefined work the Contractor will be deemed not to have made any allowance in programming, planning and
pricing Preliminaries.
11.1 Rules of measurement adopted for work not covered by these rules shall be stated in a bill of quantities. Such rules shall, as far as possible, conform with
11. Work not covered those given in this document for similar work.
12.1 The following symbols and abbreviations are used in this method of measurement:
m = metre
m2 = square metre
m3 = cubic metre
mm = millimetre
nr = number
kg = kilogramme
t = tonne
h = hour
pcsum = PrimeCost Sum
provsum = Provisional Sum
> = exceeding
2 = equal to or exceeding
= = not exceeding
< = less than
% = percentage
- = hyphen (see rule 4.4)
12. Symbols and 12.2 Cross references within the classification tables are given in the form:
abbreviations Work Section Number from first Number from Second Number from third Number from fourth
number =: column « column .« column » column
Example:
D20:2.2.2.1
Excavation and filling
Excavating
To reduce levels
Maximum depth < 1.00m
Commencing level stated where > 0.25m below existing ground level.
12.3 An asterisk within a cross reference represents all entries in the column in which it appears.
12.4 The digit 0 within a cross reference represents no entries in the column in which it appears.
13.1 Work to existing buildings shall be so described. Such work is defined as work on, or in, or immediately under work existing before the current project.
13.2 The additional rules for work to existing buildings are to be read in conjunction with the preceding rules in the appropriate Work Sections.
13.3 A description of the additional Preliminaries/General conditions which are pertinent to the work to the existing building shall be given, drawing attention to
13. Work to existing any specific requirements due to the nature of the work.
buildings
14.1 Where the rules require work to be described as curved with the radii stated details shall be given of the curved work including if concave or convex, if
conical or spherical, if to more than one radius and shall state the radius or radii.
14.2 The radius stated shall be the mean radius measured to the centre line of the material unless otherwise stated.
14. General definitions
POMI SMM 07 NRM 02 CESMM 04
Published -June 1979, Published by RICS Published -June 1998, Published by RICS First Revision publised-2013, Second Edition - Oct 2021 First Revision publised-1976, 2nd - 1985, 3rd-1991, 4th-2012
Total 17 Sections, GP,A to H, J to R. Total 23 Content, A to H, J to Y. (I & O MISSING) Work Section-41 Sections Class-26, Published by Institution of Civil Engineers
Section GP General Principles A Preliminaries/General conditions Work section 1: Preliminaries
Section A GENERAL REQUIREMENTS B Complete buildings/structures/units Work section 2: Off-site manufactured materials, components or buildings
Section B - SITE WORK C Existing site/buildings/services Work section 3: Demolitions
Section C - CONCRETE WORK D Groundwork Work section 4: Alterations, repairs and conservation
Section D- MASONRY E In situ concrete/large precast concrete Work section 5: Excavating and filling
Section E-METAL WORK F Masonry Work section 6: Ground remediation and soil stabilisation
Section F-WOOD WORK G Structural carcassing metal/timber Work section 7: Piling
Section G-THERMAL AND MOISTURE PROTECTION H Cladding/covering Work section 8: Underpinning
Section H- DOORS AND WINDOWS J Waterproofing Work section 9: Diaphragm walls and embedded retaining walls
Section J - FINISHES K Linings/Sheathing/Dry partitioning Work section 10: Crib walls, gabions and reinforced earth
Section K - ACCESSORIES L Windows/doors/stairs Work section 11: In-situ concrete works
Section L - EQUIPMENT M Surface finishes Work section 12: Precast/composite concrete
Section M - FURNISHINGS N Furniture/fittings Work section 13: Precast concrete
Section N - SPECIAL CONSTRUCTION P Building fabric sundries Work section 14: Masonry
Section P - CONVEYING SYSTEMS Q Paving/Planting/Fencing/Site furniture Work section 15: Structural metalwork
Section Q - MECHANICAL ENGINEERING INSTALLATIONS R Disposal systems Work section 16: Carpentry
Section R - ELECTRICAL ENGINEERING INSTALLATIONS S Piped supply systems Work section 17: Sheet roof coverings
T Mechanical heating/cooling/refrigeration systems Work section 18: Tile and slate roof and wall coverings
U Ventilation/Air conditioning systems Work section 19: Waterproofing
V Electrical supply/power/lighting systems Work section 20: Proprietary walls, linings and partitions
W Communications/Security/Controls systems Work section 21: Cladding and covering
X Transport systems Work section 22: General joinery
Y Mechanical and Electrical services measurement Work section 23: Windows, screens and lights
Work section 24: Doors, shutters and hatches
Work section 25: Stairs, walkways and balustrades
Work section 26: Metalwork
Work section 27: Glazing
Section A GENERAL REQUIREMENTS Work section 28: Floor, wall, ceiling and roof finishings
A1 Conditions of contract Work section 29: Decoration
A2 Specification Work section 30: Suspended ceilings
A3 Restrictions Work section 31: Insulation, fire stopping and fire protection
A4 Contractor's administrative arrangements Work section 32: Furniture, fittings and equipment
A5 Constructional plant Work section 33: Drainage above ground
A6 Employer's facilities Work section 34: Drainage below ground
A7 Contractor's facilities Work section 35: Site works
A8 Temporary works Work section 36: Fencing
A9 Sundry items Work section 37: Soft landscaping
Work section 38: Mechanical services
Work section 39: Electrical services
Work section 40: Transportation systems
Work section 41: Builder’s work in connection with mechanical, electrical and
transportation installations
Site accommodation for the employer and the employer’s representatives where
separate from main contractor’s site accommodation, including:
• site offices
• sanitary accommodation
B1 Site exploration generally • welfare facilities
• foundations to site accommodation
• temporary drainage to accommodation
• temporary services
• intruder alarms. Item Fixed charge
The type and extent of accommodation to be provided should
B1.1 Site observations, site tests and laboratory tests shall be given as an item. be stated, with each type separately quantified.
B1.2 Samples, site observations, site tests, a oratory tests an analyses shall be given as an item, 1 Bringing to site and installing, including all temporary drainage,
B1.3 Providing reports shall be given as an item. services and intruder alarms.
B2.1 Excavating trial holes shall be measured by depth, taken along the centre line, stating the number and the maximum
B2 Trial holes depth below commencing level.(nr)
B2.2 Earthwork support which is not at the discretion of the contractor shall be measured by depth. (nr) 2 Adaptations/alterations during works.
B3.1 Driving boreholes shall be measured by depth,raking boreholes shall be so described (nr).
B3 Boreholes (including pumping test wells) B3.2 Lining which is not at the discretion of the contractor shall be measured by depth (m).
B3.3 Cap pings shall be enumerated (nr). 3 Dismantling and removing from site, including rectifying any damage.
B5.1 The location of each item shall be given. Unless otherwise stated, old materials shall be understood to become the
property of the contractor and shall be cleared away; old materials required to remain the property of the employer shall be so
described.
B5 Demolitions and alterations B5.2 Removing individual fittings, fixtures, engineering installations or the like from an existing structure shall each be given as
an item.
B5.3 Demolishing individual structures (or part thereof) shall each be given as an item; alternatively, demolishing all structures 1 Site accommodation, furniture and equipment,
on a site may be given as an item. telecommunication and IT
B5.4 Cutting openings in existing structures and alterations to existing structures shall each be given as an item; making good all systems for the employer and the employer
1 Site accommodation.
work damaged shall be understood to be included. representatives where an integral part of the
(Employer )
B5.5 Temporary screens and roofs shall be given as an item. 5 Cleaning. main contractor’s site accommodation (included
in B.5 Contractor’s cost items: site establishment,
week Time-related as appropriate).
B6.1 Shoring incidental to demolitions and alterations, together with clearing away and making good all work damaged, shall be
understood to be included.
B6 Shoring B6.2 Shoring (other than that incidental to demolitions and alterations) shall be given as an item, stating the location; clearing
away and making good all work damaged shall be understood to be included.
B6.3 Particulars shall be given where the design of the shoring is not at the discretion of the contractor. Item
B6.4 Shoring which is required by the specification to be left in position shall be so described. 6 Charges.
B7.1 Work in underpinning shall be given under an appropriate heading, stating the location.
B7.2 Unless otherwise stated, work shall be measured in accordance with the appropriate sections of this document.
B7.3 Temporary support shall be given as an item; particulars shall be given where the design of the temporary support is not at
the discretion of the contractor.
B7.4 Excavation shall be measured by volume, taken to the outside line of the projecting foundations or to the outside line of
the new foundations (whichever is the greater), classified as follows:
B7 Underpinning 1. Excavation in preliminary trenches down to the base of the existing foundations (m3)
2. Excavation below the base of the existing foundations (m3)
B7.5 Cutting away projecting foundations shall be measured by length (m).
B9.1 Unless otherwise stated, excavation shall be measured by volume (m 3) as the void which is to be occupied by the
permanent construction, or vertically above any part of the permanent construction, classified as follows:
1. Oversite excavation to remove top soil, stating the average depth
2. Excavation to reduce levels
B9 Excavation 3. Excavation in cuttings item Fixed charge
4. Basement excavation
5. Trench excavation to receive foundations, which shall include pile caps and ground beams
6. Pit excavation to receive foundation bases, stating the number Furniture and equipment for the employer and the employer’s representatives
7. Excavation for diaphragm walls, stating the width of the permanent construction and the type of support fluid. where separate from main contractor’s site accommodation. For example, desks,
chairs, meeting table and chairs, cupboards, kettles, coffee maker, photocopier
B9.2 Excavation of trenches for service pipes, drain pipes, cables or the like shall each be measured by length (m), stating the
average depth; disposal and filling shall be understood to be included. and consumables.
B9.3 For excavation in tunnelling see clause B24. 1 Bringing to site and installing.
2 Furniture and
B10 Dredging B10.1 Dredging shall be measured by volume (m 3), stating the location and limits; unless otherwise stated, measurement shall equipment.
be understood to be taken from soundings. 2 Cleaning.
Time-related
B11.1 Disposal of material arising from excavation, dredging or tunnelling shall be measured by volume (m 3) as equal to the week
charge
B11 Disposal volume of excavation, dredging or tunnelling and each shall be classified as follows:
1. Backfilled into excavation
2. Backfilled in making up levels
3. Backfilled oversite to make up levels, giving details of special contouring, embankments or the like
4. Removed, which shall include providing a suitable tip. 3 Charges.
B12.1 Filling material (other than that arising from excavation, dredging or tunnelling) shall be measured by volume (m 3) as
B12 Filling equal to the void to be filled, classified as follows: item
1. Filled into excavation
2. Filled in making up levels
3. Filled oversite to make up levels, giving details of special contouring, embankments or the like. 4 Dismantling and removing from site. Fixed charge
Telecommunication and IT systems for the employer and the employer’s
representatives where separate from main contractor’s site accommodation,
B13 Piling generally B13.1 For the purposes of measurement, driven piling shall include timber, precast concrete or metal piles. including telephones, mobile phones, photocopier, computers, printers, scanners nr
B13.2 Other piling systems (for example, preformed casing with concrete filling) shall be measured in accordance with the and consumables.
principles for driven piling or bored piling as may be appropriate. 1 Purchase charges.
B13.3 Unless otherwise stated, reinforcement shall be measured in accordance with Section C. Fixed charge
B14.1 Supplying piles shall be measured by length (m), stating the number; reinforcement shall be given separately. 2 Hire charges. Time-related
B14.2 Heads and shoes shall be enumerated (nr). charge
B14.3 Driving piles shall be measured by length (m), taken from the pile point in contact with the ground when pitched to the
B14 Driven piling pile point when driven, stating the number; driving piles on rake shall be so described.
B14.4 Cutting off tops of piles and connections for lengthening piles shall be enumerated (nr).
3 Telecommunications
and IT systems.
3 Consumables.
week
B15.1 Boring for piles shall be measured by length (m), taken from the formation level of the ground to the bottom of the pile
hole, stating the number; the measurement shall include for blind boring when the pile top is to be below the formation level
B15 Bored piling of the ground.
B15.2 Boring through rock shall be measured by length (m) as extra over boring for piles (that is, the length of boring through
rock shall be measured but no deduction shall be made from the total length of boring).
B15.3 Linings for piles shall be measured by length(m).
B15.4 Disposal of material arising from boring shall be measured in accordance with clause B11 (m3).
B15.5 Concrete filling shall be measured by volume (m3).
B15.6 Cutting off tops of piles and forming enlarged bases shall be enumerated (nr).
B16.1 The measurements for sheet piling shall be taken along the centre line.
B16.2 Supplying sheet piling shall be measured by area (m 2), taken as the area when in final position.
B16 Sheet piling B16.3 Corner piles or the like shall be measured by length(m). B.2 Employer’s requirements: site records
B16.4 Driving sheet piling shall be measured by area (m 2), taken from the formation level of the ground to the bottom edge of
the sheet piling when driven; strutting and waling and withdrawing sheet piling shall be understood to be included.
B16.5 Cutting sheet piling shall be measured by length (m).
B16.6 Sheet piling which is required by the specification to be left in position shall be so described.
B17 Performance designed piling
B17.1 Performance designed piles shall be enumerated (nr); reinforcement and disposal of material arising from boring shall be
understood to be included.
B17.2 Details shall be given when the pile top is to be below the formation level of the ground.
B18 Testing piling B18.1 Testing piling, which shall include trial piles and testing working piles, shall be given as an item. 1 Site records. 1 Operation and maintenance manuals.
2 Compilation of health and safety file.
B19.1 Drain pipes shall be measured by length(m), taken along the centre line over all fittings; drain pipes within inspection
chambers or the like shall be so described and shall be understood to drainage include fixings and supports.
B19 Underground drainage B19.2 Drain fittings in the length (for example, bends, junctions) shall be enumerated (nr), grouped together for each size of
pipe and described as 'fittings'.
B19.3 Drain accessories (for example, gullies, traps) shall be enumerated (nr); concrete surrounds and additional excavation
shall be understood to be included.
B19.4 Concrete beds and coverings for drain pipes shall each be measured by length (m), stating the diameter of the pipe;
surrounds to vertical pipes shall be so described and shall be understood to include formwork.
B19.5 Inspection chambers or the like shall be enumerated (nr); alternatively, they may be measured in accordance \\'ith the
relevant sections of this document and given under an appropriate heading.
B19.6 Connections to existing drains shall be enumerated (nr), subject to clause GP8.
item Fixed charge
2 Web-based 1 Provision of system.
B20 Paving and surfacing B20.1 Paving and surfacing shall be measured by area (m2). information
B20.2 Expansion joints and \\'ater stops shall be measured by length (m).
B20.3 Channels, curbs, edgings or the like shall be measured by length (m); curved work shall be so described. management system.
2 Data uploading.
B21.1 Fencing, which shall include posts and supports in the length, shall be measured by length (m); excavating pits, disposal
and filling shall be understood to be included.
B21 Fencing B21.2 Special posts (for example, gate posts, straining posts) shall be enumerated (nr); excavating pits, disposal and filling shall
be understood to be included.
B21.3 Gates, barriers or the like shall be enumerated (nr).
B21.4 Finishes shall be measured in accordance with Section J.
management system.
B24.1 Excavation shall be measured by volume (m 3) as the void which is to be occupied, including the volume of permanent
linings, grouped as may be appropriate to identify different lengths and classified as follows:
1. Straight tunnels
B24 Tunnel excavation 2. Straight shafts
3. Curved tunnels
4. Curved shafts
5. Tapered tunnels
6. Tapered shafts
7. Other cavities, which shall include transitions, breakaways and intersections between shafts and tunnels.
B24.2 Forward probing shall be measured by length (m), stating the number of probes.
B24.3 For disposal see clause B11. 1 Handover
item Fixed charge
requirements. 2 Provision of spare parts for maintenance of building engineering services.
B25 Tunnel linings B25.1 Poured concrete linings shall be measured by area (m 2), stating whether spray or cast concrete, classified as follows:
1. lining
2. Secondary lining.
B25.2 Preformed segmental tunnel linings shall be enumerated (nr).
3 Provision of tools and portable indicating instruments for the operation and
maintenance of building engineering services systems.
B26.1 Timber supports shall be measured by volume (m3).
B26 Tunnel support and stabilisation B26.2 Sprayed concrete supports and reinforcement shall be measured by area (m2).
B26.3 Rock bolts shall be measured by length (m).
B26.4 Face packers shall be enumerated (nr).
B26.5 Metal arch supports shall be measured by weight (kg/ton).
B26.6 Injection of grout materials shall be measured by weight (kg/ton).
2 Operation and 1 Operation and maintenance of building engineering services installations,
maintenance services. mechanical plant and equipment, etc. during the defects liability period, period for
rectifying defects, maintenance period or other specified period (i.e. additional
services that are normally required by the contract).
Time-related
week
charge
3 Landscape 1 Maintenance of internal and external planting.
management services.
week (number of
staff by number
of hours per Time-related
week charge
by number of
weeks)
1 Managing director, regional director, operations director, commercial director, 1 Visiting management and staff for which
SECTION C - CONCRETE WORK
etc. an allowance has been made in the main
2 Quality manager. contractor’s overheads.
C1.1 Reinforced poured concrete and plain poured concrete shall each be so described.
C1 Generally C1.2 Poured concrete required by the specification to be placed, compacted, cured or otherwise treated in a particular manner
shall be so described.
C1.3 No deduction shall be made for voids less than 1.00 m3, nor for the volume of any reinforcement or structural metal
enclosed in the concrete, except that voids caused by boxed or tubular structural metalwork shall always be deducted.
C1.4 Unless otherwise described, horizontal surfaces of concrete shall be understood to be tamped.
C2.1 Unless otherwise stated, poured concrete shall be measured by volume (m 3), classified as follows: 3 Contracts/commercial manager.
1. Foundations, which shall include combined or isolated bases
2. Pile caps, which shall include ground beams
3. Blinding
4. Beds, which shall include roads and footpaths, stating the thickness
5. Suspended slabs, which shall include floors, landings, roofs or the like, stating the thickness
6. Walls, which shall include attached columns, stating the thickness
7. Columns, which shall include casing to metal stancheons
8. Beams (measured below the slab), which shall include lintels and casing to metal beams
9. Staircases, which shall include steps and strings
10. Diaphragm walls
C2 Poured concrete 11. Other classifications (for example, tunnel linings, bridge abutments) as may be appropriate.
C2.2 Poured concrete suspended slabs of special construction, including floors, landings, roofs or the like, shall be measured by
area(m2); coffered and troughed slabs shall be so described, giving details of solid margins or the like.
C2.3 Where an item is required to be measured by volume (m 3) and the thickness stated, then items of differing thickness may week (number of
be grouped together, provided that the range of the different thicknesses is stated. staff by number
of hours per Time-related
week charge
by number of
weeks)
C3.1 The weight of bar reinforcement shall be the net weight (kg/ton) without addition for rolling margin, supports, spacers or 4 Health and safety manager.
tying wire.
C3.2 Bar reinforcement shall be measured by weight, stating the diameter; bars of differing diameters shall be given separately.
C3.3 Fabric reinforcement shall be measured by area (m 2), without addition for laps.
C3 Reinforcement C3.4 Reinforcement shall be given as an item where the detailed design work is the responsibility of the contractor.
2 Visiting management
C4.1 Unless otherwise stated, shuttering shall be measured by area, taken as the net area in contact with the finished face of 5 Environmental manager/consultant.
concrete, classified as follows: and staff.
1. Soffits; shuttering to soffits of special construction shall be so described
2. Sloping soffits, which shall include soffits of staircases
3. Sloping upper surfaces, which shall include surfaces more than 15° from horizontal
4. Sides of foundations, which shall include bases, pile caps and ground beams
5. Sides of walls, which shall include attached columns
6. Returns to walls, which shall include ends, projections and reveals of openings or recesses
7. Sides and soffits of beams, which shall include lintels and breaks in soffits; isolated beams shall be so described
8. Sides and soffits of sloping beams, which shall include lintels and breaks in soffits; isolated beams shall be so described
9. Sides of columns
10. Staircases, which shall include treads, risers and strings but exclude soffits
11. Other classifications (for example, tunnel linings, bridges, bridge abutments) as may be appropriate.
C4.2 Shuttering to edges, which shall include face of curb or upstand or break in upper surface of floor, shall be measured by
length (m); items of differing height may be grouped together, provided that the range of different heights is stated.
C4.3 Grooves, which shall include throats, rebates, chamfers or the like, 2500 mm2 sectional area or over shall be measured by
length (m); grooves less than 2500 mm2 sectional area shall be understood to be included.
C4 Shuttering C4.4 Shuttering may be enumerated where it is more appropriate to do so (for example, decorative features).
C4.5 Shuttering which is required by the specification to be left in position shall be so described.
C4.6 Shuttering to curved, conical and spherical surfaces shall each be so described.
C4.7 Shuttering to provide a special finish shall be so described.
C4.8 Unless otherwise stated, if the volume of concrete has not been deducted, shuttering to the faces of a void shall be
understood to be included.
item
C7.1 Surfaces finished to falls or cross-falls shall be measured by area (m2).
C7 Sundries C7.2 Surface finishes shall be measured by area (m2), except that tamped finishes shall be understood to be included.
C7.3 Expansion material or the like shall be measured by area(m2).
C7.4 Designed joints, water stops, cast-in channels or the like shall be measured by length(m).
C7.5 Forming sinkings, channels or the like shall be measured by length (m) and, where appropriate, the item may include
additional excavation, hardcore, shuttering and concrete; alternatively, they may be enumerated(nr).
C7.6 Fixings, ties, inserts or the like shall be enumerated (nr); alternatively, they may be measured by area(m2).
C7.7 Mortices, holes or the like shall be understood to be included.
3 Team building costs.
4 Other extraordinary support costs.
week (number
5 Day transport. of days per week Time-related
by number charge
6 Personnel transport (i.e. transportation of work operatives to site).
of weeks)
7 Temporary living accommodation (e.g. long/medium-term
accommodation costs). week (number of
staff by number
8 Subsistence payments. of days per week
by number
of weeks)
Time-related
charge
week (number of
staff by number
of days per week
9 Out of normal hours working, including non-productive by number
SECTION D - MASONRY of weeks)
overtime allowances.
4 Staff travel. Costs associated with off-site visits such as: Fixed charge
1 visits to employer’s and consultants’ offices
2 visits to subcontractors’ offices/works or visits to main contractors’ offices/works
D1 Generally nr (number of
(preliminaries (works package contract)) occasions)
3 overseas visits and
D1.1 Sloping, battering and curved work shall each be so described. 4 accommodation charges and overnight expenses.
D1.2 Reinforced masonry shall be so described.
D2.1 Walls and piers shall be measured by area (m2), classified as follows:
1. Walls; integral piers shall be measured as walls of combined pier and wall thickness
2. Walls built against other construction
3. Cavity walls measured as a composite item, including skins and cavity; alternatively, the skins and cavity may each be
measured by area(m2). Closing cavity walls at ends or around openings shall be understood to be included
4. Isolated piers.
D2 Walls and piers D2.2 Faced or fair faced work shall each be so described; alternatively, it may be measured as extra over walls, stating whether B.5 Contractor’s cost items: site establishment
faced or fair faced on one or both sides (that is, the area of faced or fair faced work shall be measured but no deduction shall
be made from the area of walling on which the faced or fair faced work occurs).
1 Site accommodation. Main contractor’s and common user temporary site accommodation 1 Employer’s accommodation, where not an
such as: integral part of the main contractor’s site
• offices accommodation
• conference/meeting rooms (included in B.1 Employer’s requirements: site
• canteens and kitchens accommodation).
• drying rooms 2 Temporary bases, foundations and provision of
drainage
• toilets and washrooms and services to temporary site accommodation
• first aid room (included in component
• laboratories 2 of this table).
D3 Sills, etc. • workshops 3 Service provider’s charges for temporary
• secure stores services (included in B.15 Contractor’s cost items:
fees and charges).
• compounds, including containers for material storage
4 Rates for temporary services (included in B.15
• security control room and
Contractor’s cost items: fees and charges).
• stairs and office staging.
For preliminaries (works package contract): works package contractor’s project-specific
site accommodation.
The type and extent of accommodation to be provided should be
D3.1 Sills, copings, oversailing or receding courses or the like shall be measured by length (m). stated, with each type separately quantified.
D3.2 Arches shall be measured by length(m).
D4.1 Reinforcement shall be measured in accordance with clause C3; alternatively, fabric reinforcement may be measured by 1 Purchase charges. Fixed charge
D4 Reinforcement item
length(m).
2 Hire charges. Time-related
D5.1 Concrete filling to cavities shall be measured by area(m2). charge
D5 Sundries D5.2 Expansion joints or the like shall be measured by length (m).
D5.3 Air bricks or the like shall be enumerated (nr). week
3 Employer’s accommodation, where this is an integral part of the main contractor’s site
accommodation.
4 Delivery of temporary site accommodation to site and erection, construction and Fixed charge
item
removal of temporary site accommodation.
5 Temporary accommodation made available by the employer. week
Time-related
charge
6 Intruder alarms. item Fixed charge
7 Land/property rental where site accommodation is located off-site. week
Time-related
charge
SECTION E - METALWORK 8 Alterations and adaptations to site accommodation, including partitioning, doors,
painting and decorating, etc.
9 Relocation and alterations of temporary accommodation during construction stage.
E1.1 The weight of metalwork shall be the net weight, without addition for rolling margin or welding material and without
E1 Generally deduction for holes, splay cuts, notches or the like.
E1.2 Welded, riveted or bolted work shall each be so described.
10 Reinstating temporary site accommodation to original condition before removal from
site.
E2.1 Unless otherwise stated, structural metalwork shall be measured by weight (kg/ton), classified as follows: item Fixed charge
1. Grillages
2. Beams
E2 Structural metalwork 3. Stanchions
4. Portal frames, stating the number
5. Roof trusses, stating the number
6. Support steelwork, which shall include sheeting rails, braces, struts or the like
7. Other classifications, as may be appropriate.
E2.2 Fittings (for example, caps, brackets) shall be given as an item.
E2.3 Fixings (for example, bolts, distance pieces, rivets) shall be given as an item.
E2.4 Wedging and grouting bases or the like shall be enumerated (nr).
E2.5 Holding down bolts or the like shall be enumerated (nr); temporary boxes and grouting shall be understood to be included.
E2.6 Protective treatment shall be given as an item.
11 Removal of site accommodation and temporary works in connection with site
E3.1 Floor plates, duct covers, sheet metal coverings and linings or the like shall be measured by area (m2). accommodation.
E3 Non-structural metalwork E3.2 Bearers, balustrades, handrails (except where included with a staircase), frames or the like shall be measured by length
(m).
E3.3 Matwell frames, cat ladders, gates, staircases or the like shall be enumerated (nr).
2 Temporary works in 1 Temporary bases and foundations for site accommodation, including maintenance and 1 Fixed charge 1 Provision of temporary services to site
connection with site reinstatement of existing surfaces on completion of the works. 2 Time-related establishment (included in
establishment. charge B.6 Contractor’s cost items:
temporary services).
2 Provision of temporary drainage to site
establishment (included in
m2 B.6 Contractor’s cost items:
temporary services).
3 Hoardings, fans, fencing, etc. to site
boundaries and to form site compounds (included
in B.7 Contractor’s cost items: security).
F3.1 Unless otherwise stated, boarding and flooring shall be measured by area (m2), without addition for joints or laps,
classified as follows:
F3 Boarding and flooring 1. Floors, which shall include landings
2. Walls, which shall include returns, reveals of openings or recesses and attached and unattached columns
3. Ceilings, which shall include attached and unattached beams and soffits of staircases
4. Roofs, which shall include tops and cheeks of dormers and sides and bottoms of gutters, stating whether flat, sloping or
vertical; firring pieces and bearers shall be understood to be included.
F3.2 Eaves and verge boards, which shall include fascias, barge boards or the like, shall be measured by length (m).
F3.3 Fillets and rolls shall be measured by length(m).
F4.1 Open-spaced grounds and battens shall be measured by area(m2), taken overall. 5 Canteen furniture, including maintenance.
F4 Grounds and battens
F4.2 Individual grounds and battens shall be measured by length(m).
F5 Framework 6 Canteen equipment, including purchase/rental, maintenance and other running costs.
F5.1 Framework shall be measured by area(m2), taken overall; alternatively, it may be measured by length.
item
7 Floor coverings, including maintenance.
F7 Composite items F7.1 Unless otherwise stated, composite items (which shall mean items which might be fabricated off-site whether or not they
are fabricated off-site) shall be enumerated (nr); all metal work or the like shall be understood to be included.
F7.2 Any associated work (for example, decorations) shall be measured in accordance with the relevant sections of this
document.
F8 Sundry items F8.1 Finished surfaces on sawn items shall be measured by length(m). 9 Heaters, including maintenance of heaters.
F9.1 Metalwork items associated with woodwork shall be enumerated (nr); alternatively, waterbars or the like may be 10 Other office equipment, including maintenance.
F9 Metalwork
measured by length(m).
F10 Ironmongery F10.1 Units or sets of ironmongery shall be enumerated(nr). 11 Removal of furniture and equipment.
12 Maintenance furniture and floor covering.
4 IT systems. 1 Computer hardware, including purchase/rental, installation, initial set up, maintenance 1 Fixed charge 1 Computer and printer consumables (included in
and running costs, such as: 2 Time-related component 5 of this table).
• desktop and laptop computers charge 2 Document management, including electronic
• CAD stations data management systems (EDMS) (included in
• server and network equipment component 6 of this table).
• printers and plotters item
• other computer system hardware.
G2.l Unless otherwise stated, roofing, tanking, waterproof coverings, linings or the like shall be measured by area(m2),
classified as follows:
1. Flat coverings nr
G2 Coverings and linings 2. Sloping coverings
3. Vertical coverings.
G2.2 Eaves, ridges, skirtings, fascias, flashings, aprons or the like shall be measured by length (m); alternatively, skirtings, fascias
or the like to composite roofing may be measured by area (m2).
G2.3 Roof lights, ventilators, soaker collars, special roofing sheets or the like shall be enumerated(nr); alternatively, special
roofing sheets may be measured as extra over roofing (that is, the special roofing sheets shall be measured but no deduction
shall be made from the roofing in which the special sheeting occurs).
G3 Damp-proof courses G3.1 Damp-proof courses shall be measured by length(m); alternatively, they may be measured by area(m2). 8 Line calls charges. Time-related
week charge
G4 Insulation G4.1 Insulation shall be measured by area; alternatively, it may be described with items of composite roofing. 9 IT support and maintenance.
5 Consumables and 1 Stationery. Time-related
services. 2 Computer and printer consumables (e.g. ink cartridges). charge
3 Postage.
4 Courier charges.
5 Tea, coffee, water bottles, etc.
SECTION H - DOORS AND WINDOWS 6 First aid consumables.
7 Photocopier consumables (e.g. paper and toners).
H1.1 Doors shall be enumerated(nr).
H1 Doors week
H1.2 Jambs, heads, sills, mullions, transomes or the like shall be measured by length (m); alternatively, frame and lining sets
may be enumerated (nr).
H2.1 Windows, skylights or the like, together with their frames, shall be enumerated (nr); sub-frames of a different material 8 Fax consumables (e.g. paper and toners).
H2 Windows
shall be separately enumeraled (nr) or may be measured by length (m).
9 Drawing printer consumables (e.g. ink cartridges).
H3.1 Screens, borrowed lights, curtain walling or the like shall be measured by area(m2); alternatively, they may be
H3 Screens enumerated(nr).
H5.1 Unless otherwise stated, glass shall be measured by area(m2); panes of irregular shape shall be measured as the smallest
rectangle from which such irregular shape can be cut.
H5 Glass
H5.2 Sealed factory-glazed units shall be enumerated(nr).
H5.3 Glass louvres shall be enumerated(nr); alternatively, they may be measured by length(m), stating the number.
H5.4 Glass panes of special shape or with decorative treatment shall be enumerated (nr).
2 Safety and information notice boards.
item
H6.1 Patent glazing shall be measured by area(m2), classified as follows:
1. Roofs
H6 Patent glazing 2. Skylights, which shall include lantern lights
3. Vertical surfaces.
J2 Backgrounds J2.1 Backgrounds shall be measured by area(m2); backgrounds for floor, wall or ceiling finishes shall each be so described. week
J2.2 Poured backgrounds (for example, screeds) shall each be given separately, stating the surface finish.
J2.3 Pre-formed backgrounds (for example, plasterboard, expanded metal lathing) shall each be given separately.
2 Temporary gas supply. 1 Gas connection. 1 Fixed charge
2 Time-related
charge
J3.1 Unless otherwise stated, finishing shall be measured by area (m2), classified as follows:
J3 Finishings 1. Floors, which shall include landings nr
2. Walls, which shall include returns, reveals of openings or recesses and attached and unattached columns
3. Ceilings, which shall include attached and unattached beams and soffits of staircases
4. Staircases, which shall include treads, risers and edges of landings but exclude soffits.
J3.2 Skirtings, bands, strings, coverings to kerbs, mouldings, coves, channels or the like shall be measured by length (m).
4.1 Non-slip inserts, dividing strips, metal angle beads, lathing at junction of differing backgrounds or the like shall be measured 2 Distribution equipment, installation and adaptations.
J4 Sundries item
by length (m); alternatively, they may be described with the items in which they occur.
3 Charges.
J5.1 Suspended ceilings shall be measured by area(m2), classified as follows:
J5 Suspended ceilings 1. Ceilings stating the drop
2. Sides and soffits of beams or upstands.
4 Bottled gas.
item
SECTION L - EQUIPMENT 7 Drainage installation and adaptations.
8 Disposal charges (i.e. rates). Time-related
charge
L1.1 For the purposes of identification, equipment to be measured in accordance with the principles in this section shall be
defined as specialist equipment related solely to the function of a building or department (for example. food preparation or
L1 Generally service equipment, laboratory equipment, stage equipment). week
L1.2 Each category of equipment shall be given as an item; alternatively, individual items of equipment may be enumerated
(nr).
9 Disposal costs (i.e. tanker charges).
B.7 Contractor’s cost items: security (preliminaries (main contract) only)
1 Security staff. 1 Security guards (day and night). by number of hours Time-related 1 Security staff accommodation (included in B.5
per week by charge
2 Watch patrols (day and night). Contractor’s cost items: site establishment).
number
2 Security equipment. 1 Site pass issue equipment, including maintenance and removal. 1 Fixed charge
2 Site pass consumables. 2 Time-related
SECTION M - FURNISHINGS 3 CCTV surveillance installation, including maintenance and removal. charge
4 Temporary vehicle control barriers, including maintenance and removal. nr
M1.1 For the purposes of identification, furnishings to be measured in accordance with the principles in this section shall be item
defined as loose furniture, fittings or the like related to the occupation and use of a building or department (for example, rugs,
M1 Generally curtains, artwork, ashtrays, furnishing accessories).
M1.2 Each category of furnishing shall be given as an item; alternatively, individual items of furnishing may be enumerated (nr)
or measured by length(m), as may be appropriate.
3 Hoardings, fences and 1 Perimeter hoardings and fencing, etc. to site boundaries and to form site compounds. 1 Fixed charge
M2 Curtain track m
M2.1 Curtain track shall be measured by length(m); hooks, gliders, stops or the like shall be understood to be included. gates. 2 Time-related
2 Access gates, including frames and ironmongery. nr charge
3 Painting of hoardings, fencing, gates, etc. m
4 Temporary doors.
nr
5 Modification to line of hoarding and fencing during construction.
6 Dismantling and removal of hoarding, fencing, gates, etc. m
B.8 Contractor’s cost items: safety and environmental protection
1 Safety programme. Works required to satisfy requirements of CDM Regulations: nr (number of staff 1 Health and safety manager/officers (included in
1 Health and safety manager/officers. by number of hours B.4 Contractor’s cost items: management and
Time-related
per week by staff).
charge
number 2 Welfare facilities (included in B.5 Contractor’s
of weeks) cost items: site establishment).
SECTION N - SPECIAL CONSTRUCTION 2 Safety audits, including safety audits carried out by an external consultant. nr 1 Fixed charge
3 Staff safety training. 2 Time-related
charge
N1 Generally N1.1 For the purposes of identification, special construction to be measured in accordance with the principles in this section
shall be defined as either enclosures of a specialist construction (for example. air supported or geodetic structures,
prefabricated buildings) or installations of a specialist nature (for example, radiation protection).
item
N2.1 Enclosures shall be enumerated(nr); work within the enclosure, not being part of the enclosure construction, shall be 4 Site safety incentive scheme.
N2 Enclosures
measured in accordance with the relevant sections of this document.
N3.1 Installations shall each be given as an item; alternatively, they may be measured in accordance with the relevant sections 5 Notices and information to neighbours.
N3 Installations
of this document.
6 Personal protective equipment (PPE), including for the employer and consultants.
nr (sets)
7 PPE for multi-service gangs.
8 Fire points.
9 Temporary fire alarms. nr
10 Fire extinguishers.
SECTION P - CONVEYING SYSTEMS 11 Statutory safety signage. item
P1 Generally P1.1 Lifts, hoists, conveyors, escalators or the like shall be enumerated (nr). 12 Nurse. Time-related
13 Traffic marshals. charge
nr (number of staff
by number of hours
P2.1 An item shall be given for each of the following: per week by
P2 Sundries 1. Supports, which shall include fixings, anchors, insulating blocks and anti-vibration devices number
2. Identification, which shall include plates, discs,labels, charts and colour coding of weeks)
3. Testing and commissioning, which shall include operating completed installations and providing fuel and power
4. Tools and spares, which shall include loose keys and consumable stores
5. Documents, which shall include drawings, operating instructions and maintenance manuals.
2 Barriers and safety 1 Guard rails and edge protection (e.g. to edges of suspended slabs and roofs).
scaffolding.
P3.1 An item shall be given for incidental work, which shall include:
1. Co-ordination with other engineering installations
2. Cutting or forming holes, mortices, chases or the like and making good finishings
P3 Work incidental to conveying systems 3. Building in or cutting and pinning brackets or the like and making good finishings.
P3.2 Protective painting and decorative painting shall each be given as an item for each system and shall include:
1. Removing protective coating or wrapping
2. Cleaning and polishing exposed surfaces. item
P3.3 Other incidental work shall be measured in accordance with the relevant sections of this document and grouped under an
appropriate heading.
2 Temporary staircase balustrades (i.e. to new staircases during construction).
3 Lift shaft protection.
4 Protection to holes and openings in ground floor slabs, suspended slabs, etc.
5 Debris netting/plastic sheeting. 1 Fixed charge
6 Fan protection. 2 Time-related
7 Scaffold inspections. nr charge
SECTION Q - MECHANICAL ENGINEERING INSTALLATIONS 8 Hoist run-offs.
9 Protective walkways.
Q1.1 Installations shall be classified by function and given separately under an appropriate heading.
Q1 Generally
Q1.2 Installations shall be measured in accordance with the relevant clauses in this section; alternatively, they may be
enumerated(nr) on a locational basis (for example, cold water installation to ground floor).
10 Other safety measures.
item
Q2.1 Pipes and gutters shall be measured by length(m), taken along the centre line over all fittings.
Q2 Pipework and gutterwork Q2.2 Fittings to small pipes (that is, pipes with an internal diameter of 60mm or less) shall be understood to be included.
Fittings (except joints in the running length) to large pipes (that is, pipes with an internal diameter exceeding 60mm) and to
gutters shall be enumerated(nr), grouped together for each size of pipe or gutter and described as 'fittings'.
Q2.3 Valves, traps, expansion compensators or the like shall be enumerated(nr); sleeve~, cover-plates or the like shall be
understood to be included.
3 Environmental 1 Control of pollution.
protection measures
Q3.1 Rectangular ductwork shall be measured by weight(kg/ton), based upon the area calculated as the length (m), taken along
the centre line over all fittings, times the net girth of nominal dimensions. Blank ends shall be added to the area for
Q3 Ductwork weighting(kg/ton) but no deduction shall be made for intersections or openings; extra weight for seams, stiffeners, supports,
fixings or the like shall be understood to be included.
Q3.2 Circular, oval and flexible ductwork shall be measured by length(m), taken along the centre line over all fittings.
Q3.3 Fittings to rectangular ductwork shall be understood to be included; fittings to circular and oval ductwork (excluding test
holes and covers) shall be enumerated(nr), grouped together for each size of duct and described as 'fittings'.
Q3.4 Dampers, grilles, flexible connectors or the like shall be enumerated(nr). 1 Fixed charge
item 2 Time-related
2 Residual control of noise.
charge
Q4.1 Sanitary fittings, tanks, fans, pumps, hoods, air-handling units or the like shall be enumerated(nr).
Q4 Equipment
Q4.2 Continuous convectors or the like shall be measured by length(m).
Q5.1 Sensing or activating devices (for example, thermostats, humidistats, motorised valves), control panels, air compressors
and receivers or the like shall be enumerated(nr).
Q5 Automatic controls
Q5.2 Wiring, pneumatic tubing, isolators, starters, relays or the like associated with automatic controls shall be understood to
be included.
Q5.3 Alternatively, automatic control systems shall be given as an item for each installation but equipment common to more
than one system shall be enumerated(nr).
4 Environmental manager/consultant. nr (number of staff
by number of hours
Q6 Connections to supply mains Time-related
per week by
charge
number
Q6.1 Connections to supply mains shall be enumerated(nr), subject to clause GP8. of weeks)
5 Environmental audits, including safety audits carried out by external consultant.
Q7.1 Insulation to pipework shall be measured by length(m), taken along the centre line over all fittings.
Q7.2 Insulation to rectangular ductwork shall be measured by area(m2), calculated as described In clause Q3; additional 1 Fixed charge
Q7 Insulation, including linings and protective coverings insulation to flanges or the like shall be understood to be included. nr 2 Time-related
charge
Q7.3 Insulation to circular, oval and flexible ductwork shall be measured by length(m), taken along the centre line over all
fittings.
R1.1 Installations and auxiliary installations shall be classified by function and given separately under an appropriate heading.
R1 Generally R1.2 Installations shall be measured in accordance with the relevant clauses in this section; alternatively, they may be
enumerated(nr) on a locational basis (for example, lighting installation to ground floor).
R1.3 The references herein to 'cable' shall be understood to Include tape, bus-bar trunking or the like.
R1.4 The references herein to 'conduit' shall be understood to include trunking, cable tray, ducting or the like.
3 Maintenance of grids.
R2.1 For the purposes of measurement, 'main' is defined as the ‘incoming supply to the main distribution board within a
building or complex'.
R2 Main circuits
R2.2 Cable shall be measured by length(m).
R3.2 Cable and conduit to individual sub-main circuits shall be enumerated(nr) and separately identified as may be appropriate;
alternatively, sub-main circuits may be measured in accordance with clause R2.
5 Instruments for setting out.
R4.1 Cable and conduit to termination points shall be enumerated (nr), classified as follows:
1. Lighting points
R4 Final sub-circuits and auxiliary installations 2. Lighting switch points, stating whether one-way, two-way or intermediate
3. General purpose socket outlets; multi-gang socket outlets or the like shall count as one point
4. Equipment points, stating type of equipment or the electrical rating; contactors, starters or the like shall be measured
separately as equipment points
5. Auxiliary installation points (for example, bell push, telephone outlet).
3 Protection of works. 1 Protection of finished works to project handover. item 1 Fixed charge
R5 Accessories
R5.1 Ceiling roses and pendants, lighting switches, socket outlets, bell pushes or the like shall be enumerated (nr). 2 Time-related
2 Protection of stairs, balustrades, etc. works to project handover. charge
R6 Control gear
R6.1 Switchgear, distribution gear, contactors, starters, composite switchboards or the like shall be enumerated (nr).
3 Protection of fittings and furnishings works to project handover.
R7.1 Transformers, generators, standby power cubicles, luminaries, external lighting columns, clocks,
R7 Equipment loudspeakers, bells or the like shall be enumerated(nr).
R7.2 Controls, which shall include accessories and interconnecting cables. shall be measured in accordance with the relevant
clauses in this section; alternatively, they may be. included with the items of equipment.
R8 Connections to supply mains R8.1 Connections to supply mains shall be enumerated(nr), subject to clause GP8. 4 Protection of entrance doors and frames works to project handover.
R9 Sundries R9.1 Sundries shall be measured in accordance with clause P2. 5 Protection of lift cars and doors works to project handover.
R10 Work incidental to electrical engineering installations R10.1 Work incidental to electrical engineering installations shall be measured in accordance with clause P3 6 Protection of specifically vulnerable products to project handover.
7 Protection of all sundry items.
4 Samples. 1 Provision of samples. item 1 Fixed charge
CESMM 04 2 Provision of sample room. 2 Time-related
3 Mock-ups and sample panels. charge
4 Testing of samples/mock-ups, including testing fees.
5 On-site laboratory equipment.
6 Mock-ups of prefabricated units (e.g. residential units, student
accommodation units, hotel accommodation, etc.).
5 Environmental control 1 Dry out building. 1 Fixed charge
of building 2 Temporary heating/cooling. 2 Time-related
item charge
3 Temporary waterproofing, including over roofs.
4 Temporary enclosures.
B.10 Contractor’s cost items: mechanical plant
1 General. Common user mechanical plant and equipment used in construction operations. Plant and equipment used for specific
construction operations, such as:
1 earthmoving plant
2 piling plant
3 paving and surfacing plant
4 wheel spinners, and road sweepers (included in
B.14 Contractor’s cost items: cleaning) and
5 access scaffolding (included in B.11
Contractor’s cost items: temporary works).
2 Tower cranes. The type of craneage to be provided should be stated, with each type separately 1 Temporary electrical supply to tower
quantified. week crane (included in B.6 Contractor’s cost items:
1 Hire charges. Time-related temporary services).
charge
2 Crane operator. week (number of
3 Overtime for crane and operator. staff by number of
hours per week by
4 Piles for tower crane bases, including maintenance removal. nr 1 Fixed charge
5 Temporary bases for tower cranes, including anchors, maintenance, removal and 2 Time-related
reinstatement on completion (size, in m , should be stated).
2 charge
6 Ties. week Time-related
charge
7 Connections to temporary electrical supply. nr Fixed charge
8 Bring to site, erection, test and commission.
9 Periodic safety checks/inspections. week Time-related
charge
10 Dismantling and removing from site. nr Fixed charge
11 Other costs specific to tower cranes such as: item 1 Fixed charge
• chain pack and sundries 2 Time-related
• relief operator charge
• banksman and
• access cage.
12 Temporary voids in building structure for craneage, hoists, etc. nr Fixed charge
including filling voids after removal.
3 Mobile cranes. The type of craneage to be provided should be stated, with each type separately 1Fixed charge
quantified. week 2Time-related
1 Mobile crane hire charges, including driver/operator charges. charge
2 Attendance. nr (number of
hours per visit
by number of
visits)
3 Other costs specific to mobile crane hire. item
4 Hoists. The type of hoist to be provided should be stated, with each type 1 Temporary services to hoist installations
separately quantified. Time-related
week (included in B.6 Contractor’s cost items:
charge
1 Goods and passenger hoists, including protection cages and embedment frames. temporary services).
2 Hoist bases. nr 1 Fixed charge
2 Time-related
charge
4 Hoists. 1 Temporary services to hoist installations
(included in B.6 Contractor’s cost items:
temporary services).
B.16 Contractor’s cost items: site services (preliminaries (main contract) only)
1 Temporary works. 1 Temporary works that are not specific to an element. 1 Fixed charge 1 Temporary screens in connection with minor
item/nr/m/ m /m
2 3
2 Time-related demolition works and alteration works.
charge 2 Supports to small openings cut into existing
walls or after removal of internal walls, etc. in
2 Multi-service gang. 1 Ganger.
connection with minor demolition works and
2 Labour. alteration works.
3 Forklift driver. week (number of 3 Temporary or semi-permanent support for
staff by number of Time-related unstable structures or facades – facade retention
4 Service gang plant and transport.
hours per week by charge works (i.e. structures not
number of weeks) to be demolished).
3 Temporary works. m2 1 Roofs. 1 Weatherproof. 1 Method of construction if not at the discretion of 1 To ensure the full extent and scope of this
2 Screens. 2 Watertight. the contractor. work, the surveyor may need to provide
3 Floors. 3 Dustproof. 2 Maintaining, duration stated. additional information if not readily ascertained
3 Adapting during the course of works. from the drawings.
4 Roads. 4 Fireproof.
5 Any other requirement, 4 Clearing away.
type stated. 5 Disposing of rainwater, details stated.
6 Providing openings, details stated.
9 Preparing existing nr 1 Dimensioned 1 Description should be 1 Nature of existing structure to receive new 1 This will include preparing structural steel
structures for connection description. sufficient to determine work. sections for attachment to new steel framing,
or attachment of new scope and location. etc.
work.
11 Repointing joints. m 1 Nature of 1 Materials required stated. 1 Width and depth stated. 1 Removal of existing joint material and
existing joint. preparation of exposed surfaces is included.
2 Type of pointing.
12 Repointing. m /m/ nr
2
1 Thickness 1 Nature of existing 1 Composition and mix of mortar and/or other 1 Types of surface would include brickwork,
stated. surface. joint material(s). blockwork, stonework, etc.
2 Width and 2 Size of existing 2 Areas each less than 1m should be
2
15 Re-dressing existing m/nr 1 Girth and 1 Dimensioned description 1 Raking out existing joint. 1 The girths and lengths stated are net. No
flashings, etc. thickness stated. of flashing. 2 Repointing with new material, method and type allowance should be made for additional
2 Length, width 2 Description of of pointing material stated. materials required for labours.
and thickness new profile. 2 Removal, cleaning, re-shaping, trimming and
stated. re-fixing existing flashing is included.
16 Damp-proof m 1 Method of 1 Centres or spacings of 1 Chemical. 1 Work should include making good holes and
course renewal. renewal or drilling holes. 2 Injection mortar. finishes on completion.
17 Damp-proof insertion stated. 2 Localised removal 3 Electro osmosis. 2 Overall removal of finishes before this work
course insertion. 2 Nature and of finishes. would be measured elsewhere.
4 Other mechanical methods.
thickness of
existing wall.
3 Nature of
existing finishes
where applicable.
4 Thickness or
depth of treatment.
23 Decontamination. item 1 Removal of 1 Scope and location of 1 Preparatory works. 1 Enough information should be given to fully
toxic/hazardous work. describe the cause of the contamination or
materials. 2 Type of contamination/ infestation and to allow the contractor to fully
2 Decontamination infestation/fungus treat the condition.
of existing to be treated. 2 Excluding decontamination of existing
premises. ground; this work is measured in work section
3 Infestation 5.
removal/
eradication
4 Fungus removal/
eradication.
24 Temporary works. m2 1 Roofs. 1 Weatherproof. 1 Method of construction if not at the discretion of 1 To ensure the full extent and scope of this
2 Screens. 2 Watertight. the contractor. work the surveyor may need to provide
3 Floors. 3 Dustproof. 2 Maintaining, duration stated. additional information if not readily ascertained
3 Adapting during course of works. from the drawings.
4 Roads. 4 Fireproof.
5 Any other requirement, 4 Clearing away.
type stated. 5 Disposing of rainwater, details stated.
6 Providing openings, details stated.
3 Remove hard 1 Destination stated. 1 Method of breaking up if not left to the 1 This excludes any hardcore beds below the
surface paving, 2 Type of paving stated. discretion of the contractor. pavings.
thickness stated. 2 Removal of the hardcore is treated as
reduced level excavation.
4 Remove specific 1 Enough dimensioned 1 This includes any existing items on site not
items. description to identify size designated to remain,
and location of each item. including all types of rubbish such as
abandoned cars, fridges, etc.
2 This excludes all but the simplest of building
structures. Demolition of these is covered in
work section 3.
3 Removal of any associated foundations,
fixings, supports, fastenings, etc. is included.
6 Excavation, starting m3 1 Bulk excavation. 1 Not exceeding 2m deep. 1 Details of obstructions in ground to be stated. 1 Bulk excavation includes excavating to reduce
level stated if not original 2 Over 2m not exceeding levels or to form basements, pools, ponds, etc.
ground level. 4m deep. For clarity, each type of excavation may be
3 Thereafter in stages of measured and described separately.
2m. 2 Obstructions will be piles, manholes, etc. that
should be undisturbed.
7 Extra over all types of m3 1 Excavating in. 1 Hazardous material, 1 A hazardous material is any material that
excavation irrespective of details stated. requires special precautions when handling,
depth. 2 Non-hazardous material, transporting or disposing.
details stated. 2 Groundwater is any water encountered below
3 Below groundwater level. the established water table level. It does not
4 In running water. include water from underground streams,
broken drains or culverts or water arising from
5 Unstable ground.
surface flooding.
3 Running water is a spring, stream or river.
4 Unstable ground is running silt, running sand,
loose ground, etc.
m3 2 Breaking up. 1 Rock. 1 Rock is any hard material that can only be
2 Reinforced concrete. removed by the use of wedges, rock hammers,
3 Concrete. special plant or explosives due to its size or
location.
4 Masonry or stonework.
2 A boulder ≤ 5m in volume or one that can be
3
m 3 Excavating 1 Type, size and depth of 1 Nature of precaution required. 1 These items are measured where there is a
alongside existing service stated. risk of the existing service being affected by the
underground excavation process. The method of protection is
services. left to the discretion of the contractor.
2 If in doubt the surveyor should measure an
item giving the nature of the live service.
nr 4 Excavating
across existing
underground
services.
8 Support to face(s) of m2 1 Maximum depth 1 Location stated, including 1 Method of forming support where not left to the 1 The measurement of support to excavations
excavation. stated, in 1m depth proximity to roads, discretion of the contractor. is to all faces of all excavations over 250mm
stages. buildings and services. 2 Left in place. deep,
3 Distance between opposing faces less than unless the propping and supporting of
2m. excavation faces is measured in other work
sections.
4 Distance between opposing faces 2–4m.
2 The measured area includes all additional
5 Distance between opposing faces over 4m.
excavation, backfilling, disposal, etc. to facilitate
6 Curved work. the supports being installed.
3 The measured area includes the installation,
maintenance and
subsequent removal of the supports.
4 The measured area includes any design
necessary for the works.
5 Depths are measured from the starting level
to the bottom of excavation, with the starting
level being stated if not the formation level for
the works.
6 Works in groundwater and unstable ground
are included.
9 Disposal. item 1 Groundwater. 1 Depth below original 1 If the post-contract water level differs from the 1 The method and place of discharge left to the
ground level stated. pre-contract level, the measurements should be discretion of the contractor unless stated
2 Polluted water described revised accordingly. otherwise.
if known.
m3 2 Excavated 1 Destination if not at the 1 Irrespective of where excavated material
material off site. contractor’s discretion. originates.
2 Hazardous material.
3 Non-hazardous material
where it needs to be
disposed of at a specific
location.
10 Retaining excavated m3 1 Topsoil 1 To temporary spoil 1 Specified handling, details 1 If the distance to spoil heap is not stated, the
material on site. 2 All other heaps. stated. location is left to the discretion of the contractor.
excavated 2 Average distance to spoil
material. heap stated.
11 Filling obtained from m2 1 Final thickness of 1 Source, distance, 1 Treatment of material before depositing in final 1 This includes topsoil and any other material
excavated material. filling not destination and method location. from the excavations that have been specified
exceeding 500mm stated. to remain on site.
deep, finished 2 Maximum or average 2 The thickness stated will be that after
thickness stated. depth of layers stated. compaction.
3 Destinations will comprise general areas to
make up levels, backfilling foundations,
landscaping areas, planter beds, etc.
4 Compacting layers and surfaces are included
irrespective of depth and number of layers.
5 Source will be either direct from excavations
or from temporary spoil heaps.
m3 2 Final thickness of
filling exceeding
500mm deep.
12 Imported filling. m3 1 Blinding bed not 1 Level, to falls, cross falls 1 Destination stated. 1 All types of surface treatments are included.
exceeding 50mm or cambers stated. 2 Maximum or average depth of layers stated. 2 The thickness stated will be that after
thick, finished 2 Sloping not exceeding compaction.
thickness stated. 15 from horizontal.
0
3 Compacting layers and surfaces are included
3 Sloping over 15 from
0
irrespective of depth and number of layers.
horizontal.
m2 2 Over 500mm
wide,
thickness or gauge
stated.
20 Cutting off tops of nr 1 Size stated. 1 Cutting off tops of piles includes preparation
piles, irrespective of and integration of reinforcement into pile cap or
length. ground beam and disposal of
all debris.
Work section 6: Ground remediation and soil stabilisation
Information that should be provided: and conservation
1 ground conditions
2 groundwater level(s) and date(s) established Item or work to Unit Level one Level two Level three Notes
3 nature of any known non-hazardous or hazardous contamination on the site or in the ground be measured
4 starting level of each type of excavation
1 Site dewatering. item 1 Area of site to be 1 Method of disposal of 1 Pre-contract 1 Each type of remedial work should be
Works and materials included: dewatered. water stated if not at water level. accompanied by a full description of the
1 disposal off site of all surplus excavated material
2 disposal of all surface water 2 Maximum depth discretion of contractor. 2 Level to which groundwater should be lowered proposed works including limits on the
of boreholes. to and maintained at. extent, the proximity of adjoining building,
3 support to faces of excavation unless not at the discretion of the contractor restrictions on method, sequence and timing.
4 working space
5 excavation and filling for temporary works unless not at the discretion of the contractor
6 levelling, grading, trimming and compacting surfaces exposed by the excavations
7 curved work 2 Sterilisation. m3 1 Maximum depth 1 Method of sterilisation
8 multiple handling of excavated materials on site unless specified of ground to be stated.
treated.
Notes:
1 The groundwater level should be re-established at the time each excavation is carried out and is defined as the post-contract
groundwater level. 3 Chemical neutralising. m3 1 Maximum depth 1 Method of neutralisation
2 Groundwater levels subject to periodic changes due to tidal or similar effects should be so described, giving the mean high of ground to be stated.
and low water levels. treated.
cement.
5 Vibro-compacted m 1 Nominal
piles. diameter.
2 Total number
stated.
6 Vibro-compacted trench m 1 Nominal width
fill. and depth stated.
7 Extra over piling. nr 1 Enlarged bases. 1 Type of piling stated. 1 This work includes everything necessary to
2 Enlarged heads. 2 Diameter or size of form the enlargement, including disposal of
enlargement stated. additional spoil.
m 3 Pile extensions. 1 Total number stated. 1 Preparing head of pile to receive extension is
2 Total concreted length. included.
8 Reinforcement to t 1 Nominal size 1 Reinforcement includes tying wire and
in-situ concrete piles. and type of bars spacers plus links and binders that are
stated. incorporated at the discretion of the contractor.
2 Types of bars include plain, deformed and
helical.
9 Breaking through hr 1 Rig standing. 1 This is only measured where the obstruction
obstructions. is encountered abovethe founding stratum of
the pile.
10 Disposal of excavated m3 1 Off site. 1 Hazardous material. 1 The volume calculated is the nominal cross-
materials. 2 On site. 2 Non-hazardous material section by the pile lengths.
where it needs to be 2 The volume of enlarged heads and bases is
disposed of in a specific included.
location.
3 Destination of spoil if not
at the contractor’s
discretion.
4 Reinforcement. t
5 Brickwork or m2
blockwork.
6 Tanking. m2
m2 3 Breaking up hard
surface
pavings, thickness
stated.
4 Earth reinforcement. m2 1 Mesh. 1 Horizontal. 1 Method of anchoring stated. 1 The area is measured in contact with base
2 Fabric. 2 Sloping. 2 Minimum laps stated. and excludes laps.
3 Curved on plan, radius 3 Final facing, details stated. 2 Assembling, tying, fixing, stacking and
stated tensioning is included.
3 No deductions made for voids
≤ 1m .
2
Work section 11: In-situ concrete works
In this work section: Item or work to Unit Level one Level two Level three Notes
• in-situ concrete
• surface finishes to in-situ concrete be measured
• formwork
Plain in-situ concrete
• reinforcement
• designed joints in in-situ concrete Reinforced in-situ concrete
• accessories cast in to in-situ concrete Fibre reinforced in-situ concrete
• in-situ concrete sundries.
Sprayed in-situ concrete
Notes: 1 Mass concrete. m3 1 Any thickness. 1 In filling voids. 1 Poured on or against earth or unblinded 1 Mass concrete is any unreinforced bulk
1 work in substructures, superstructures or external works should be stated in headings or descriptions 2 In trench filling. hardcore. concrete not measured elsewhere.
2 watertight work should be described. 2 The volumes of each type of mass concrete
3 In any other situation,
details stated. work may be aggregated or given separately.
Works and materials are included:
1 concrete volume is measured net
2 no allowance in volume should be made for deflection of formwork
3 deductions are not made for reinforcement, steel sections, cast-in accessories or voids < 0.05m3 except voids in troughed and 2 Horizontal work. m3 1 ≤ 300mm thick. 1 In blinding. 1 Poured on or against earth or unblinded 1 Horizontal work includes blinding, beds,
coffered slabs 2 > 300mm thick. 2 In structures. hardcore. foundations, pile caps, column bases, ground
4 concrete is cast into formwork unless otherwise described 2 Reinforced > 5%. beams, slabs, coffered and troughed slabs,
5 concrete is finished as struck from basic finish formwork landings, beams, attached beams, beam
6 all top surfaces and soffits should finish casings, shear heads, upstands whose height is
horizontal unless otherwise stated less than or equal to three times their width,
7 all top surfaces are finished tamped. kerbs and copings.
Notes: 2 The volumes of each type of horizontal work
1 This applies to concrete laid on ribbed metal may be aggregated or given separately.
decking as well as other types of formwork. 3 Work laid in bays should be so described
giving average area of bays.
3 Sloping work < 15 .0 m3 1 ≤ 300mm thick. 1 In blinding. 1 Poured on or against earth or unblinded 1 Sloping work includes blinding, beds, slabs,
4 Sloping work > 15 .0
2 > 300mm thick. 2 In structures. hardcore. steps and staircases, kerbs and copings.
3 In staircases. 2 Reinforced > 5%. 2 This includes any attached beams, upstands,
shear heads or similar.
3 The volumes of each type of sloping work
may be aggregated
or given separately.
4 Work laid in bays should be so described
giving the average area of bays.
5 Vertical work. m3 1 ≤ 300mm thick. 1 In structures. 1 Reinforced > 5%. 1 Vertical work includes columns, attached
2 > 300mm thick. columns, column casings, walls, retaining walls,
filling to hollow walls, parapets or upstand
beams where the height is greater than three
times the width.
2 The volumes of each type of vertical work
may be aggregated
or given separately.
7 Sprayed in-situ m2 1 Thickness 1 Slabs. 1 Tops. 1 The method of application and finish should
concrete. stated. 2 Soffits. be stated in the description.
3 Curved.
2 Walls. 1 Curved.
3 Beams.
4 Columns.
Surface finishes to in-situ concrete.
8 Trowelling. m2 1 To top surfaces. 1 Sloping. 1 Application of surface hardeners, sealers, dust
9 Power floating. 2 To faces. 2 Falls. proofers, waterproofers, carborundum grains, etc.
10 Hacking. 3 To soffits. 3 Crossfalls. should be so described.
11 Grinding.
12 Any other surface
treatment not left to
discretion of the
contractor.
required.
9 All square, raking and curved cutting is
included.
10 All holes, boxings, recesses, rebates,
chamfers, nibs, channels, etc. are included.
14 Sides of foundations m/m 2
1 ≤ 500mm high,
and bases. width stated.
15 Edges of horizontal 2 > 500mm high.
work.
16 Soffits of m2 1 For concrete 1 Propping ≤ 3m high. 1 Sloping one-way. 1 This includes suspended slabs and stair
horizontal work. ≤ 300mm thick. 2 Propping over 3m but 2 Sloping two ways. landings.
17 Soffits of troughed or 2 For concrete 300 not exceeding 4.5m high. 2 Through propping should be described if not
waffled horizontal work, to 450mm thick. 3 And thereafter left to the discretion of the contractor.
details described. 3 For concrete in 1.5m stages. 3 This includes work to soffits of slabs
18 Soffits of sloping > 450mm thick. ramps, steps, staircases, etc.
work.
19 Sides and soffits m2 1 Regular, shape 1 The shape is regular unless described as
of isolated beams. stated. otherwise.
20 Sides and soffits 2 Irregular shaped, 2 An irregular shape is any shape other than
of attached beams. dimensioned square or rectangular.
21 Sides of upstand description or 3 This includes concrete casings to steel
beams. diagram. beams and columns.
22 Sides of isolated
columns, nr stated.
23 Sides of attached
columns.
23 Faces of walls and m2 1 Vertical. 1 Rate of batter to be 1 Work to single sides should be so described.
other vertical work. 2 Battered one stated.
face.
3 Battered both
faces.
24 Extra over. nr 1 Openings for 1 ≤ 5m . 2
1 All additional labour and material needed to
doors, etc. 2 5m to 10m .
2 2 form the opening is included.
thickness of wall 3 > 10m . 2
stated.
25 Wall ends, soffits m/m 2
1 ≤ 500mm wide, 1 This excludes ends and soffits of walls
and steps in walls. width created by the formation of an opening. These
stated. are included in the item for forming the opening.
2 > 500mm wide.
26 Staircase strings, etc. m 1 Maximum width
stated.
27 Staircase risers, etc. m 1 Vertical, width
stated.
2 Undercut, width
stated.
28 Sloping top surfaces. m2 1 ≤ 15 .
0
2 > 15 .
0
38 Plain. m 1 Dimensioned 1 Horizontal. 1 Plain joints are those that do not require
39 Formed. description. 2 Vertical. formwork.
40 Cut. 2 Total depth 3 Curved, radius stated. 2 Formed joints including formwork.
stated. 3 All preparation, cleaners, primers and sealers
are included.
4 All angles, ends and intersections are
included whether they are formed, welded or
purpose made.
Accessories cast into in-situ concrete 1 Kind, quality of materials and size or
manufacturers reference should be stated.
41 Type or proprietary m /m/ nr
2
1 Dimensioned 1 If linear or superficial 1 Cast-in accessories include anchor bolts,
reference stated. description. quantities are used, the anchor boxes, fixing bolts, dowels, column
description should include guards, isolated glass blocks and any
any appropriate spacing otherancillary item that is specified to be cast
dimensions. inas the concrete work proceeds.
2 Cast-in accessories exclude reinforcement,
tying wire, distance blocks, spacers, chairs,
structural steel members, hollow blocks, filler
blocks, void formers, permanent formwork,
joints and all components around which
concrete is cast but that are not fixed in position
by the contractor.
7 pre-tensioning or pre-stressing
8 filled ends
9 all grouting 2 Designed joints. m 1 Dimensioned 1 Type and sizes of filling 1 Joints formed at the discretion of the
10 margins ≤ 500mm wide. description. and contractor are not measured.
sealant stated.
5 Designed joints. m 1 Dimensioned 1 Type and sizes of filling 1 Joints formed at the discretion of the
description. and contractor are not measured.
sealant stated.
6 Holding down or tie nr 1 Dimensioned 1 Material type stated. 1 Method of fixing.
straps. description or 2 Protective coating stated.
proprietary
reference number.
7 centering or other forms of temporary support type stated. 5 Thickness stated for tapering walls is the
8 labour in eaves filling mean thickness.
9 labours in returns, ends and angles 6 No deductions should be made for voids or
10 centering built-in items with a cross-sectional area equal
11 overhand work to or less than 0.50m2.
12 bonding ends of walls to other work 7 The thickness stated for diaphragm walls is
13 all extra material required for bonding the total thickness of both skins and cavity void.
14 additional material in laps
15 preparation of all surfaces to receive subsequent applications.
Notes:
1 All walling is measured on the centre line irrespective of construction.
2 Thicknesses stated are nominal.
3 Work is vertical unless otherwise described.
4 All wall dimensions exclude applied finishes.
4 Isolated piers, isolated m 1 Dimensioned 1 Vertical. 1 Isolated piers are when their length on plan is
5 No deductions will be made for voids or built-in items with a cross sectional area less than 0.50m2.
casings, chimney stacks, description or 2 Battered. equal to or less than four times their thickness
columns. dimensioned 3 Curved, radius stated. except where caused by openings.
diagram. 2 No deductions should be made for flues, etc.
equal to or less than 0.10m2
in a cross-sectional area.
7 Bands, dimensioned m 1 Flush. 1 Vertical. 1 Entirely of stretchers. 1 Bands are brick-on-edge bands,
description. 2 Sunk, depth of 2 Raking. 2 Entirely of headers. brick-on-end bands, basket pattern bands,
set back stated. 3 Horizontal. 3 Alternate headers/ stretchers. moulded or splayed cappings, moulded string
3 Projecting, depth courses, moulded cornices, etc.
4 Curved, mean radius on 4 Other bond.
of set forward face.
stated.
13 Special purpose nr 1 Dimensioned 1 Function stated. 1 Descriptions of stones are given as the
blocks or stones. description. smallest block from which each item can be
obtained, having regard in the case of natural
stone to the plane in which the stone is required
to be laid with relation to its quarry bed. The
dimensions are taken over one mortar bed and
one mortar joint.
14 Forming cavity. m2 1 Width and 1 Type and spacing of ties. 1 These two items of work may be measured
method of forming. together as a composite item when between
two masonry skins.
15 Cavity insulation. m2 1 Type and 1 Method of installing or
thickness. fixing.
16 Damp-proof courses m 1 Gauge or 1 Vertical. 1 Damp-proof courses include:
≤ 300mm wide. thickness. 2 Raking. a forming laps, ends and angles
2 Number of 3 Horizontal. b pointing exposed edges and
layers. 4 Curved, mean radius on
3 Composition and face stated. c bonding to damp-proof membranes, etc.
mix of bedding 5 Stepped.
17 Damp-proof courses > m2 materials.
300mm wide.
18 Pre-formed m
cavity trays.
19 Joint reinforcement. m 1 Width stated.
20 Fillets. m 1 Width and 1 Weather.
thickness stated. 2 Angle.
3 Other.
21 Pointing. m 1 Width and depth 1 Type of finish. 1 This relates to the pointing of joints,
of joint to be flashings, frames, etc.
pointed.
22 Joints. m 1 Width and 1 Type of filler, sealant, pointing, method of 1 Joints are only measured where their
thickness stated. application and preparation. composition and position are designed.
2 Ties, centres stated.
3 Channels.
23 Wedging and pinning. m 1 Width and
thickness stated.
24 Creasing. m 1 Width stated.
2 Number of
courses.
25 Proprietary and nr 1 Dimensioned 1 Proprietary reference or 1 Method of forming, 1 These items include all necessary forming of
individual spot items. description or catalogue number where building in or fixing. openings or pockets, liners, cavity closers,
dimensioned applicable. damp-proof courses, fixings and fastenings and
diagram. builder’s work in connection with any
associated mechanical or electrical
connections.
2 This will include items such as windposts,
head restraint channels, steel lintels, wall end
ties, wall end bonding channels, cappings,
chimney pots, finials, boiler seats, soot doors,
plinths, steps, winders, landings, bases, key
blocks, air bricks, ventilator gratings, flue
blocks, fire backs and sides, grates, carved
bricks, blocks or stones, quoin stones, jamb
stones, hearths, weep-hole formers, etc.
3 This list is not exhaustive. Any type of
individual shaped piece should be enumerated
and described either by a dimensioned
description, dimensioned diagram or by
reference to the specification or trade brochure.
2 Framed members, 1 Crane rails. 1 Details and centres of fixing clips and resilient
permanent erection on 1 Wires, cables, rods, ties and bars. pads should be stated.
site.
3 Isolated structural t 1 Plain member, 1 Dimensioned description 1 An isolated structural member is one not
members, fabrication. use stated. and weight per m. integrally connected to other structural
members.
4 Isolated structural nr 2 Built-up member,
members, permanent use stated.
erection on site.
5 Allowance t 1 Calculated 1 To framed members. 1 Fittings are components that allow members
for fittings. weight. 2 To isolated members. to be joined together or are other brackets,
2 Percentage supports, etc. that are supplied and attached,
allowance, either on or off site, to the main loadbearing
percentage stated. frame by the structural metal contractor.
6 Cold rolled purlins, m 1 Type and 1 Purlins and cladding 1 Method of fixing stated.
cladding rails, etc. method of rails.
fixing stated. 2 Sag rods.
2 Size or 3 Stays.
proprietary 4 Other.
reference stated.
7 Extra over steel nr 1 Forming cranks 1 Dimension of member
member for: in members, type stated.
stated.
8 Profiled metal decking, m2 1 Height not 1 Shear studs, size and 1 Method 1 This work is only measured here when it
type and/or profile stated. exceeding 5m. spacing stated. of fixing. forms part of the structural steel package
2 Height exceeding otherwise it would be measured in accordance
5m but with the rules for permanent formwork.
not exceeding 2 Heights are always measured from finished
10m. floor level unless otherwise stated.
3 And so on in 5m 3 The area of metal decking is
increments. calculated as the finished area
of concrete cast onto the decking.
9 Extra over for: m 1 Edge trims; size, 1 Straight. 1 Ends, angles, intersections are all included.
girth, profile or 2 Raking.
proprietary 3 Curved, radius stated.
reference stated.
2 Curved cutting.
10 Holding down bolts or nr 1 Type and 1 Anchor plates, frames, 1 Supply only.
assemblies. diameter stated. members, tubes, cones and
any other associated
accessory stated.
11 Special bolts. nr 1 Type and 1 Background if other than 1 Special bolts are all bolts and fasteners other
diameter stated. structural steel. than grade 4.6 black bolts and
holding down assemblies.
12 Connections to nr 1 Details stated. 1 All labours on new and existing steel are
existing steel and other included.
members or structures. 2 Labours on non-steel structures
are measured elsewhere.
13 Trial erection. t 1 Details and 1 These are only measured when not at the
location stated. discretion of the contractor.
2 The information given in the description
should include items such as the number of
erectable pieces and number of site welds. This
information may be given by reference to
drawing(s).
Works and materials included: 3 Extra over for forming. m 1 Height stated. 1 Lengths should be the net length of each
1 underlay in contact with the covering 1 Height stated. 1 Type stated. labour.
2 all rough and fair cutting and waste 2 All additional sheet material required to form
1 Width and height stated. 1 Wood core.
3 extra material required for bonding the labour item should be included.
4 extra material in laps and dressings 2 Hollow.
3 All additional underlay, insulation and surface
5 extra material for curved work 1 Length stated.
6 all ends, angles and intersections either formed or proprietary finish should be included.
7 forming all rough and fair grooves, throats, mortices, chases, rebates, holes, stops, mitres and the like labours 1 Length stated.
8 raking out joints to insert flashings 1 Height stated.
9 labours in returns, ends and angles 4 Boundary work, m 1 Net girth stated. 1 Abutments. 1 Horizontal. 1 Boundary work to voids is only
10 work in isolated areas
11 work in forming voids and holes ≤ 1m2.
location and method of 2 Average net girth 2 Eaves. 2 Vertical. measured where the void is >1m . 2
forming described. stated, number of 3 Ridges. 3 Raking. 2 Boundary work is work associated with
Notes: lengths stated. 4 Verges. 4 Curved, radius stated. closing off or finishing off sheet roofing at the
1 The areas and lengths measured are net in contact with base. external perimeter, at the
5 Valleys. 5 Stepped.
This includes following the profile of all rolls, steps, upstands and downstands, etc. abutment with different materials or the
6 Hips. 6 Preformed. perimeter of openings and voids.
7 Vertical angles. 7 Sloping.
5 Flashings. m 1 Net girth stated. 1 Flashings. 1 Horizontal. 1 Flashings include undercloaks, rough and fair
2 Aprons. 2 Sloping. cutting, bedding, pointing, ends, angles,
3 Sills. 3 Vertical. intersections, welted, beaded or shaped edges
and all dressings.
4 Weatherings. 4 Raking.
5 Cappings. 5 Curved, radius stated.
6 Hips. 6 Stepped.
7 Kerbs. 7 Preformed.
8 Ridges.
9 Linings to openings.
6 Gutters. m 1 Net girth stated. 1 Sloping. 1 Nature of base. 1 The length is the mean length
7 Valleys. 2 Stepped. 2 Spacing of structural supports. measured over all fittings.
3 Curved, radius stated. 3 Preformed. 2 Gutter and valley work includes all dressings
4 Secret. required to form the profile, with all joints, laps,
seams, brackets, undercloaks and other
5 Tapered.
associated linings, outlets, overflows, ends,
angles, intersections, bedding, pointing, fixings,
etc.
3 The maximum and minimum girth of tapered
gutters or valleys should be given.
8 Spot items. nr 1 Dimensioned 1 Catchpits. 1 Nature of base. 1 Spot item work includes joints, dressing and
diagram or 2 Sumps. 2 Spacing of structural supports. bonding to surrounding work, undercloaks and
dimensioned 3 Outlets. 3 Preformed. other associated linings, ends, angles, bedding,
description. pointing, fixings, etc.
4 Hatch covers.
5 Canopy covers.
6 Collars or sleeves around
pipes, etc.
7 Other, type stated.
9 Fittings. nr 1 Dimensioned 1 Ventilators. 1 Nature of base. 1 Fittings include joints, dressing and bonding
description. 2 Finials. 2 Method of fixing where not at to surrounding work, undercloaks and other
3 Gas terminals. the discretion of the contractor. associated linings, ends, angles, bedding,
pointing, fixings, etc.
4 Hip irons.
2 Proprietary references may be given in lieu of
5 Soakers.
a dimensioned description.
6 Saddles.
7 Rooflights.
8 Other, type stated.
Work section 18: Tile and slate roof and wall coverings
In this work section: Item or work to Unit Level one Level two Level three Notes
• plain tiling
• interlocking tiling be measured
• fibre cement slating
• natural slating 1 Roof coverings. m2 1 Pitch stated. 1 Underlays and battens. 1 Curved, radii stated. 1 Coverings include underlays, battens and
• natural or artificial stone slating 2 Wall coverings. 2 Vertical. 2 Conical, maximum and minimum radii stated. work in forming voids ≤ 1m . 2
• any other type of tile, slate, slab or block roof or wall covering.
3 Boundary work, m 1 Dimensioned 1 Abutments. 1 Horizontal. 1 Boundary work includes undercloaks, rough
Works and materials included: location and method of description stating 2 Eaves. 2 Sloping. and fair cutting,
1 all rough and fair square, raking and curved cutting forming described. net girth. bedding, pointing, ends, angles and
3 Ridges. 3 Raking.
2 all ends and angles either formed or proprietary intersections.
3 extra material for curved work 4 Verges. 4 Vertical.
2 Boundary work to voids is only measured
4 forming all rough and fair grooves, throats, mortices, chases, rebates, holes, stops, mitres and similar labours 5 Valleys. 5 Curved, radius stated.
5 raking out joints to form a key where
6 Hips. 6 Stepped. the void exceeds 1m .
6 raking out joints to insert flashings
2
7 labours in returns, ends and angles 7 Vertical angles. 7 Preformed. 3 Boundary work is work associated with
8 all extra material required for bonding closing off or finishing off tile or slate roofing at
9 additional material in laps the external perimeter, at the abutment with
10 work in forming voids and holes ≤ 1m2. different materials or the perimeter of openings
and voids.
4 Valleys include everything necessary to form
and line the valley excluding any sheet metal.
Sheet metal linings should be measured in work
section 17.
4 Fittings. nr 1 Dimensioned 1 Ventilators. 1 Nature of base. 1 Proprietary references may be given in lieu of
description. 2 Finials. 2 Method of fixing where not at the discretion of a dimensioned description.
3 Gas terminals. the contractor.
4 Hip irons.
5 Soakers.
6 Saddles.
7 Rooflights.
8 Other, type stated.
6 all preparation to background necessary to form a key, including raking out joints, scabbling or the application of a bonding 5 Aprons. 3 Vertical. 2 Boundary work is work associated with
agent. 6 Other boundary work. 4 Raking. closing off or finishing off the waterproofing at
5 Curved, radius stated. the external perimeter, at the abutment with
6 Stepped. different materials or the perimeter of openings
and voids.
3 Boundary work includes undercloaks,
insulation, strip ventilators, rough and
fair cutting, bedding, pointing, laps, seams,
ends, angles, intersections,rolls, upstands,
downstands, dressings and wedgings.
4 Boundary work includes fair edges, rounded
edges, drips and arrises.
7 Gutters. m 1 Net girth on face. 1 Sloping. 1 Nature of base. 1 The length is the mean length
8 Channels. 2 Stepped. 2 Number of coats or layers. measured over all fittings.
3 Curved. 3 Spacing of structural supports. 2 Lining and covering work includes all
9 Valleys. 4 Secret. dressings required to form the profile, joints,
10 Kerbs. 5 Tapered. brackets, undercloaks and other associated
linings, outlets, overflows, ends, angles,
intersections, bedding, pointing, etc.
3 The maximum and minimum girth of tapered
gutters should be given.
11 Internal angle m 1 Width by height
fillets. stated.
12 Spot items. nr 1 Dimensioned 1 Catch pits. 1 Spot item work includes joints, dressing and
diagram or 2 Sumps. bonding to surrounding work, undercloaks
dimensioned 3 Outlets. and other associated linings, ends, angles
description. bedding, pointing, fixings, etc.
4 Hatch covers.
5 Canopy covers.
6 Collars or sleeves around
pipes, etc.
7 Other, type stated.
13 Fittings. nr 1 Dimensioned 1 Ventilators. 1 Nature of base. 1 Fittings include joints, dressing and bonding
14 Edge trim. m description. 2 Other, type stated. 2 Number of coats or layers. to surrounding work, undercloaks and other
3 Method of fixing where not at the discretion of associated linings, ends, angles bedding,
the contractor. pointing, fixings, etc.
2 Proprietary references may be given in lieu of
a dimensioned description.
Work section 20: Proprietary walls, linings and partitions
In this work section: Item or work to Unit Level one Level two Level three Notes
• metal framed systems to walls and ceilings
• drylining and partitioning systems to walls and ceilings be measured
• structural framed systems (SFS) to walls
1 Proprietary metal m2 1 Finished 1 Insulation. 1 No deductions for voids ≤ 1m . 2
Notes: framed system to form thickness stated. 2 Vapour barriers. 2 The average height will be calculated for each
1 The finish is that which is applied as part of the normal proprietary system. Any finish to be walls. 2 Height or 3 Sublinings. length of partition with a sloping head measured
subsequently made by a different trade should be measured separately under the relevant rules. 2 Structural framed average height between junctions.
4 Finish.
2 Examples of proprietary finishes are taped joints, slurry coats, etc. systems to form walls. stated in 1m
3 Skim coats or other wet trade finishes are measured in work section 28. increments. 5 Glazing.
3 Total length 6 Curved, radius stated.
Works and materials included: stated measured
1 all work is internal unless otherwise stated along centre line.
2 all rough and fair cutting
3 extra material for curved work
4 additional framing to support fittings 3 Proprietary metal m2 1 Over 300mm 1 Insulation. 1 Fixed directly to structural soffit. 1 The adjacent structure such as secondary
5 ends, fair ends and abutments with adjoining work framed system to form wide on face. 2 Vapour barriers. 2 Supported on adjacent structure, span stated in steel framing or timber framing is measured
6 working around columns, beams and services where the outer face of the work is continuous. ceilings. elsewhere.
Notes: 3 Sublinings. 1m increments.
m 2 Not exceeding
1 This refers to the final location of the work. 4 Finish.
300mm wide on
face. 5 Curved, radius stated.
6 Sloping.
7 Convex or concave,
radius stated.
4 Extra over for m2 1 Lining, details 1 This will apply to partitions that
different. stated. have areas of different linings or finishes than
2 Finish, details specified in the general description heading. It
stated. will not apply to different forms of construction
or components. These differences will require
separate items measured.
5 Extra over for forming nr 1 Not exceeding 1 Lined, details stated. 1 Non-proprietary materials are not included
openings. 1m .
2
2 Unlined. (e.g. timber grounds or inserts would be
2 1–2.50m . 2
3 Opening type (e.g. measured in work section 16).
3 2.50–5m . 2
window, door). 2 Lined openings are those lined as part of this
4 Exceeding 5m in 2
work.
further
increments of
2.50m .2
6 Extra over for non- m 1 Dimensioned 1 Heads, details stated. 1 Nature of base. 1 Non-standard details are those that involve
standard perimeter description or 2 Soles, details stated. the use of components that are not used in the
details. proprietary 3 Abutments, details main body of work, such as deflection heads,
reference. acoustic seals, fire seals, etc.
7 Extra over for angles. m stated.
1 Tee.
8 Extra over for junctions. m 2 Cross.
9 Extra over for access nr 1 Dimensioned 1 Details stated. 1 Details include type of frame, ironmongery,
panels. description or finish, insulation, fire rating and proprietary
proprietary reference number where applicable.
reference.
10 Fair ends to partitions. m 1 Thickness of 1 Finish and/or trims. 1 Fair ends are only measured where the
partition stated. exposed end is finished with the same finish as
the face(s) or with a trim that is an integral part
of the partition system.
2 Fair ends include all extra work and materials
involved.
ceilings.
14 Proprietary linings to m 1 Girth not
columns. exceeding 300mm,
15 Proprietary linings to m nr of faces stated.
beams. 2 Girth 300–
600mm,
16 Proprietary linings to m
nr of faces stated.
bulkheads.
3 Girth 600–
17 Extra over for forming nr 1 Not exceeding 1 Lined, details stated. 1 This includes openings for doors, windows,
openings. 2.50m .2
2 Unlined. screens, etc.
2 2.50–5m . 2
3 Exceeding 5m in 2
further
increments of
2.50m .2
18 Extra over for non- m 1 Dimensioned 1 Heads, details stated. 1 Nature of base. 1 Non-standard details are those that involve
standard perimeter description or 2 Soles, details stated. the use of components that are not used in the
details. proprietary 3 Abutments, details main body of work such as deflection heads,
reference. acoustic seals, fire seals, etc.
19 Extra over for angles. m stated.
10 Opening perimeters. m 1 Dimensioned 1 Heads. 1 Horizontal. 1 Opening work is associated with closing off or
description. 2 Jambs. 2 Vertical. finishing off claddings and coverings at the
2 Proprietary 3 Sills. 3 Sloping. perimeter of an opening or a void.
reference. 4 Flashing pieces. 4 Raking.
5 Curved, radius stated.
6 Stepped.
7 Preformed.
12 Boarding, sheeting, m2 1 Thickness. 1 Floors. 1 Method of fixing. 1 These include fully or partially glazed
panelling over 600mm 2 Walls. 2 Method of jointing. partitions and screens whether proprietary or
wide. 3 Ceilings. 3 Nature of base. site constructed and not otherwise included in
work section 20.
13 Boarding, sheeting, m 1 Width and
panelling not exceeding thickness.
600mm wide.
14 Proprietary partitions,
panels and cubicles.
15 Partitions. m 1 Height and 1 Off-site applied finish. 1 Method of jointing 1 The linear measurement is
thickness stated. 2 On-site applied finish. and fixing. the mean length measured along the centre line
2 Proprietary 2 Curved, radius stated. of the partition.
name or reference 3 Nature of background. 2 The length is measured through and over all
stated. obstructions and openings.
4 Integral services.
3 Partitions include all integral components,
fixings, joints, factory applied trims, holes and
mortices.
16 Items extra over the nr 1 Openings, size 1 Blanks. 1 Openings include everything necessary to
partition they occur in. stated. 2 Doors. form the opening with their associated integral
3 Window. components, glass, doors, ironmongery, linings
and factory-applied trims.
4 Glazed panels.
5 Access panels.
m 2 Trims, 1 Trims are only measured as
dimensioned separate items if fixed on site.
description.
17 Duct panels, nr 1 Overall size 1 Subframes, details 1 Method of fixing. 1 All ancillary items needed to connect the
sanitaryware back panels, stated. stated. 2 Nature of background. sanitary appliances to the M&E installations are
etc. 2 Thickness included.
stated. 2 Associated sanitaryware items are not
included in these items but should be measured
in accordance with the rules of work section 32.
18 Cubicle partition sets. nr 1 Dimensioned 1 Complete cubicles, 1 Nature of background. 1 Cubicle sets include all integral frames,
diagram or number of bays stated. 2 Method of fixing to panels, doors, factory- applied trims,
dimensioned background. connections, fixings and fastenings complete
description. with support legs, brackets
and standard ironmongery.
20 Infill panels and m2 1 Thickness 1 Curved, stating radius. 1 Work is internal unless it is described as
sheets, number stated. stated. 2 Panels exceeding size of external.
normal manufactured unit. 2 Infill panels include bedding compounds,
3 Panels requiring special sealants, intumescent compounds and strips,
treatment to edges. distance pieces, location and setting blocks and
fixings.
24 Type of item, unit or nr 1 Method of fixing. 1 Ironmongery includes fixing with screws to
set stated. 2 Nature of base. match and preparing the base to receive it.
2 Shelf brackets and associated
fittings will be measured here.
2 Doors nr 1 Dimensioned 1 Fire resistance 1 Method of fixing if not left to 1 Each leaf of a multi-leafed door
3 Roller shutters. description or performance. the discretion of the contractor. is counted as one door.
4 Collapsible gates. diagram. 2 Factory glazed. 2 Glass may be incorporated into the
5 Sliding folding
partitions. associated work
6 Hatches. following the items set out below.
7 Strong room
doors.
8 Grilles.
9 Door frames. m 1 Dimensioned 1 Labours described. 1 Frames and linings includes jambs, heads,
10 Door linings. overall sills, mullions and transoms.
11 Door stops. cross-section
12 Associated fire description.
stops.
13 Associated
smoke stops.
Glazing.
14 Glass, type stated. nr 1 Thickness of 1 Shape if other than 1 Bent, direction stated. 1 Glass includes plastic or any type of material
15 Louvre blades. glass or overall square or rectangular. 2 Method of glazing or securing. glazed into openings except glass blocks.
Ironmongery. thickness of sealed 2 Airspace(s) width(s) of 2 The size given for irregular panes should be
16 Type of item, unit or nr 1 Method of fixing. 1 Type and quality 1 Ironmongery includes fixing with screws to
set stated. 2 Nature of base. of materials and fixings. match and preparing the base to receive it.
2 Surface finish.
3 Constituent parts of the
units or sets.
In this section: Work section 25: Stairs, walkways and balustrades
• timber, metal, plastic staircases
• walkways and gantries Item or work to Unit Level one Level two Level three Notes
• balustrades, barriers, guardrails. be measured
Works and materials included: 1 Staircase, type stated. nr 1 Dimensioned 1 Hatch doors where part of the loft ladder 1 Staircases include attached balustrades and
1 all ramps, wreaths, bends, plain ends, ornamental ends and similar labours description. component. newel posts.
2 linings, nosings, cover moulds, trims, etc. where an integral part of the unit
3 soffit linings, spandrel panels, etc. where an integral part of the unit 2 Loft ladders. 2 Component 2 Any trims, etc. fixed to the unit after
4 ironmongery where an integral part of the unit drawing reference. installation should be measured in accordance
3 Ladders.
5 finishes applied off site with the items in work section 22.
4 Extra over for: 1 Quarter landing. 1 Dimensioned description.
6 fixings, fastenings, blockings, wedges, bolts, brackets, cleats, etc.
nr
2 Half landing.
5 Catwalks. m 1 Dimensioned 1 Curved, radius stated. 1 Method of fixing
6 Walkways. description. or support.
7 Balustrades. m/nr 1 Dimensioned 1 Curved, radius stated. 2 Infill
1 Background.
panels, 1 These items are measured when not forming
8 Handrails. description. detail stated. an integral part of a staircase unit.
9 Barriers. 2 Component 2 Method of fixing 2 These items include all integral rails, infill
drawing reference. or support. panels, ironmongery, factory-applied finishes,
10 Guard rails.
3 Background. fixings and fastenings.
11 Balcony units.
12 Extra over for: nr 1 Opening
portions, size and
details stated.
Works and materials included: 1 Glass, type stated. nr 1 Thickness of 1 Shape if other than 1 Bent, direction stated. 1 Glass includes laminated, toughened, double
1 all raking and curved cutting 2 Sealed glazed units, glass or overall square or rectangular. 2 Method of glazing or securing, details stated. or triple glazing units, lead, acrylic,
2 all polished and bevelled edges unless given in the description type of glass stated. thickness of sealed 2 Airspace(s) width(s) of 3 Edge treatment. polycarbonate, etc. or any other type of material
3 drilling holes. 3 Louvre blades, type of unit. double/triple glazed units. glazed into openings except glass blocks.
glass stated. 2 Pane size. 3 Gas filling of airspaces. 2 Glass blocks are measured in accordance
with the items in work section 14.
3 The size given for irregular panes should be
the smallest rectangular size from which the
pane can be obtained.
4 Extra over for: nr 1 Grinding. 1 Plain work, pane size 1 Detailed description 1 This information may be given by reference to
2 Sandblasting. stated. of work including extent of work over the pane. detailed drawings.
3 Acid etching. 2 Design work, pane size
stated.
4 Embossing.
5 Engraving.
5 Lead light glazing, type nr 1 Thickness of 1 Pane sizes where regular 1 Bent, direction stated. 1 The pattern will be described as regular,
of glass stated. glass. shape. 2 Method of glazing or securing, details stated. diamond or irregular.
2 Overall window 2 Spacings of lead cames. 3 Edge treatment. 2 Cames are the H-shaped lead strips that are
or light size. 3 Pattern of lead cames. soldered together to form the lead glazed
panes.
6 Saddle bars. m 1 Diameter and 1 Method of fixing 1 Method of attaching to lead light glazing. 1 Saddle bars are metal rods used to
length stated. to window surround. strengthen and provide support to large lead
glazed panes. These bars are usually built into
the window surround.
7 Mirrors. nr 1 Dimensioned 1 Edge description. 1 Nature of background. 1 Edges can be plain, rounded, bevelled, etc.
description. 2 Pattern, method of 2 Method of fixing,
forming described. details stated.
8 Removing existing nr 1 Type of frame or 1 Panes ≤ 1m . 2
1 Method of disposal of debris where not at the
glass and preparing frame surround. 2 Panes 1–2m . 2 discretion of the contractor.
or surround to receive 2 Type of glass to 3 Panes 2–3m . 2 2 Materials to be kept
new glass. be removed. for re-use.
4 Panes 3–4m . 2
In this work section: Work section 28: Floor, wall, ceiling and roof finishings
• in-situ, tiled, block, mosaic, sheet, applied liquid or planted finishes.
Item or work to Unit Level one Level two Level three Notes
Notes: be measured
1 The area measured is net in contact with the base.
2 Widths stated are the width of each finished face. 1 Screeds, beds and m/m 2
1 ≤ 600mm wide. 1 Level and to falls only 1 Surface finish. 1 Thicknesses stated are the thickness
3 There should be no deduction for voids ≤ 1m2.
4 No allowance should be made in the net area for laps, dressings or any other labour.
toppings, thickness and 2 > 600mm wide. ≤ 15 from horizontal.
0
2 Nature of background. exclusive of
number of coats stated. 2 To falls, cross falls and 3 Backings and beddings, adhesives, keys, grooves, etc.
5 All work is internal unless stated as external.
slopes ≤ 15 from 0
thickness stated. 2 Underlays include plasterboard or other rigid
Works and materials included: 2 Finish to floors, type of m/m 2
1 ≤ 600mm wide. horizontal. 4 Underlays, type and thickness stated. sheet lathing.
3 Tiles should be laid with their long edges
1 all rough and fair square, raking and curved cutting and waste finish and overall 2 > 600mm wide. 3 To falls, cross falls and 5 Insulation, type and thickness stated.
2 all ends and angles either formed or proprietary thickness stated. slopes > 15 from horizontal. vertical or parallel to the long axis of the floor or
6 Laid in one operation with its base.
0
8 Finish to isolated
columns, type of finish
and overall thickness
stated.
9 Finish to ceilings, type m/m 2
1 ≤ 600mm wide. 1 Over 3.50m above 1 The height of the ceiling is measured from
of finish and overall 2 > 600mm wide. structural floor level. structural floor level to soffit of finished ceiling
thickness stated. or isolated beam.
10 Finish to isolated m/m 2
1 ≤ 600mm wide. 2 The width is the width of each face.
beams, type of finish and 2 > 600mm wide.
overall thickness stated.
11 Finish to treads. m 1 Net width stated. 1 Curved, radius stated. 1 Nature of background. 1 Ends, angles and outlets are included.
2 Insets described.
12 Finish to risers. m 1 Net width stated. 1 Curved, radius stated. 1 Nature of background.
2 Undercut.
13 Finish to strings and m 1 Net width or girth 1 Raking. 1 Nature of background.
aprons. on face stated. 2 Sloping.
3 Curved, radius stated.
1 Ends, angles and outlets are included.
25 Movement joints. m 1 Dimensioned 1 Method of fixing. 1 Movement joints include expansion joints.
26 Cover strips. description. 2 Nature of background. 2 Function of beads include angle beads, stop
27 Dividing strips. beads, shadow gap beads, casing beads, etc.
28 Beads, function
stated.
29 Nosings.
35 Accessories. nr 1 Dimensioned 1 Method of fixing. 1 Nature of background. 1 Accessories include access panels, special
description. panels in raised access floors, vent grilles,
ornaments, etc.
36 Precast plaster m 1 Dimensioned 1 Method of fixing. 1 Nature of background. 1 The dimensioned description should fully
components. description or describe the component including stating the
proprietary end use such as cornice, moulded band,
reference. architrave, etc.
of location or girth.
10 Ceilings and beams. 2 Areas > 1m . 2 stated. 2 Work to ceilings or beams over 3.5m but not
11 Borders. exceeding 5m above finished floor level and 1 Mitres, ends angles, scribing or cutting is
thereafter in 3m stages. included.
12 Motifs. nr 1 Dimensioned
description or
diagram.
In this work section: Work section 30: Suspended ceilings
• demountable suspended ceilings
• solid suspended ceilings. Item or work to Unit Level one Level two Level three Notes
be measured
Notes:
1 All work is internal unless described as external. 1 Ceilings. m2 1 Depth of 1 Type and thickness of 1 Patterned, details stated. 1 The area measured is that on the exposed
2 Secondary steel or timber support work is measured elsewhere.
2 Plenum ceilings. suspension lining. 2 Sloping. face.
3 Beams. ≤ 150mm. 2 Method of fixing lining 3 Curved, radius and plane of curve stated. 2 The depth of suspension is measured from
Works and materials included:
1 working over and around obstructions 4 Bulkheads. 2 Depth of to suspension. 4 Suspension obstructed by services. the underside of the main structural soffit or
2 all cutting suspension 3 Integral insulation. secondary support work to back surface of
5 Trims at regular intervals in area of ceiling,
3 forming openings and holes 150–500mm. 4 Integral vapour barrier. lining.
details stated.
4 all additional support work including bridging for fittings 3 Depth thereafter 5 Height of work exceeding 3 The height of work is measured from the
5 all extra work required for work described as patterned. in 500mm stages. finished floor level to the face of the ceiling.
Notes: 3.50m above finished floor
level in 1.50m stages. 4 Where ceilings are suspended from sloping,
1 Integral fittings are those designed to be incorporated into the ceiling structure. curved or irregular structures with an average
5 Isolated strips. m 1 Width ≤ 600mm. depth of suspension should be stated.
2 Width thereafter
in 300mm stages.
6 Upstands. m 1 Height ≤
600mm.
2 Height thereafter
in 300mm stages.
7 Access panels. nr 1 Dimensioned 1 Composition. 1 Method of locking. 1 Access panels include all additional support
description. 2 Method of fixing. work, framing, edge trim and fixings.
2 Proprietary
reference.
8 Edge trims. m 1 Dimensioned 1 Plain. 1 Centres of fixing. 1 Plain trims are those fixed
9 Angle trims. description. 2 Floating. 2 Nature of background. to the structure.
2 Floating trims are those
fixed to the ceiling system.
3 Trims include ends and angles.
10 Fire barriers. m/m 2
1 Dimensioned 1 Fire rating where 1 Method of fixing 1 Fire barriers include all support work, scribing
description. required. in position. or forming to fit, angles, ends and working
2 Thickness 2 Obstructed by services stated. around structures, support work
stated. and services.
11 Collars for services nr 1 Diameter of pipe. 1 Pipes. 1 Length of sleeve each side of barrier stated. 1 Collars are only measured here where they
passing through fire 2 Size of trunking. 2 Trunking. 2 Fire rating. are integral to the fire barrier. If they are not
barriers. integral they should be measured
in accordance with the items in work section 40.
Works and materials included: 3 Quilts. partition framing or similar 3 Sloping. 3 The area of joists, rafters, partition framing or
1 all cutting 4 Loose. members, centres of 4 Soffit. similar members is deducted when the material
2 working around or over all members and services. members stated. is laid between such members.
3 Laid between joists, 4 Sloping is the upper surface that is not
rafters, partition framing horizontal.
or similar members, centres 5 Soffits are the underside of any
of members stated. horizontal or sloping structure.
m 2 Purpose and 4 Location stated
dimensioned
description.
5 Sprayed. m2 1 Thickness 1 Nature of background.
stated.
6 Filling cavities. m2 1 Thickness 1 Mineral fibre. 1 Internal. 1 Drilling holes in the structure to allow injection
stated. 2 Plastic beads. 2 External. of material and subsequent making good is
3 Cellulose fibre. included.
4 Expanding foam.
5 Other type of blown or
injected material.
7 Fire stops, type stated. m 1 Dimensioned 1 Horizontal. 1 Method of fixing.
description. 2 Vertical. 2 Background when mechanically fixed.
2 Fire rating. 3 Raking.
4 Stepped.
5 Curved, radius stated.
8 Fire sleeves, collars, nr 1 Dimensioned 1 Method of fixing.
etc. description. 2 Background when mechanically fixed.
2 Fire rating.
4 Pipe sleeves through nr 1 Type and 1 Type of structure being 1 Method of fixing and packing. 1 All making good including fire
walls, floors and ceilings. nominal diameter passed through described. 2 Handing to others for fixing. stopping is included.
of pipe.
2 Length of sleeve
or thickness of
structure being
passed through.
3 Fire rating.
5 Gutters. m 1 Nominal size. 1 Straight, curved, flexible. 1 Method of fixing 1 Measured over all fittings.
2 Extendable. to background.
3 Method of jointing.
10 Testing and item 1 Installation 1 Attendance required. 1 Preparatory operations stated. 1 All fuel and power used is included.
commissioning. stated. 2 Insurances required by 2 Stage tests (nr) listed and purpose stated. 2 Provision of test certificates
employer. is included.
11 Preparing drawings. item 1 Number of 1 Method stated. 1 Working drawings.
12 Operating manuals item copies stated. 2 Information to be shown 2 As fitted drawings.
and instructions. stated.
6 Excavating
below groundwater
level.
m 7 Next to existing 1 This should be measured where precautions
live services. are specifically required. The method of
protection is left to the
nr 8 Around existing discretion of the contractor.
live services
crossing trench.
m3 3 Breaking out
hard
materials.
4 Excavating in
and removing
hazardous
materials.
5 Excavating in
running silt,
running sand or
other unstable
ground.
6 Excavating
below ground
water level.
stated. horizontal.
2 Not exceeding 3 To slopes > 15 from horizontal.
0
300mm wide,
thickness and
width stated.
4 Method of application.
5 Surface treatment or finish.
6 Special curing
of finished work.
1 Thickness and 3 Linings to channels. 7 Horizontal. 1 Arrises, coves, ends, angles and outlets are
girth on face 8 To falls. included.
stated.
13 Gravel, hoggin and m /m 2
1 Over 300mm 1 Roads. 1 Level and to falls only. 1 The area measured is that in contact with the
woodchip. wide, thickness 2 Pavings. 2 To falls and crossfalls and slopes ≤ 15 from
0 base.
stated. horizontal.
2 Not exceeding 3 To slopes > 15 from horizontal.
0
300mm wide,
thickness and
width stated.
4 Method of application.
5 Surface treatment or finish.
6 Special curing of finished
work.
14 Interlocking brick and m /m 2
1 Over 300mm 1 Roads. 1 Bedding, thickness stated. 1 Setting pavings into recessed manhole
blocks, slabs, bricks, wide. 2 Pavings. 2 Level and to falls only. covers is included.
blocks, setts and cobbles. 2 Not exceeding 3 Treads. 3 To falls, crossfalls and slopes 2 All cutting and fitting is
300mm wide, 4 Risers. ≤ 15 from horizontal.
0
included.
thickness and
4 To slopes > 15 3 Excavation and disposal is included.
width stated. 5 Margins or bands. 0
from horizontal.
6 Channels. 5 Laid in bays, average size of bays stated. 4 Ends, angles, outlets and intersections are
included
6 Joint pattern stated.
7 Curved, radius stated.
8 Foundation and haunching.
m 3 Thickness and 7 Linings to channels. 9 Horizontal. 5 Arrises, coves, ends, angles and outlets are
girth on face 10 To falls. included.
stated.
m /m 3 2
3 Breaking out 1 Rock. 1 Rock is any hard material that can only be
existing. 2 Concrete. removed with wedges, rock hammers, special
4 Breaking up 3 Reinforced concrete. plant or explosives due to its size or location.
existing hard 2 A boulder ≤ 5m in volume or one that can be
4 Brickwork, blockwork or
3
5 Trees. nr 1 Botanical name. 1 British Standard (BS)size 1 Planting in cultivated 1 Supports and ties are included.
designation and root or grassed areas prepared by others should be 2 BS size includes standard,
system stated. stated including all necessary reinstatement. advanced nursery stock
2 Girth, height and clear 2 Planting indoors should be stated. or semi-mature types.
stem and root system 3 Details of initial cut back should be stated. 3 Young nursery stock includes seedlings,
stated. 4 Details of watering should be stated. transplants and whips.
6 Young nursery stock nr 3 Height and root system 5 Backfill type should be stated if not the material
trees. stated. arising from excavations.
7 Shrubs. nr
8 Hedge plants. nr 4 Height stated.
m 5 Height, spacing, number
of rows
and layout stated.
9 Plants. nr 6 Size stated.
m2 7 Size and number per m 2
stated.
10 Bulbs, corms and nr 8 Size stated
tubers. m2 9 Size and weight per m 2
stated.
11 Plant containers. nr 1 Dimensioned 1 Linings, type stated. 1 Method of fixing.
description.
12 Protection. m 1 Temporary 1 Ultimate ownership, 1 Permanent fencing is measured in
fencing, type and details stated. accordance with the rules
duration stated. of work section 36.
nr 2 Tree guards, 2 Type stated. 1 Method of fixing stated.
dimensioned
description.
nr 3 Wrappings, 3 Chemical application 2 Method of fixing stated.
height of wrapping stated.
and girth of tree
stated.
nr 3 Assembly of
composite items of
primary equipment.
2 Terminal equipment nr 1 System. 1 Location of installation – 1 Type, size, capacity, load, rating, special 1 Terminal equipment and fittings are defined
and fittings. roofs, high or low level in finishes, casings, in-fills, associated integrated or as any item to which a system is distributed to,
plantrooms, risers or remote ancillaries, controls, e.g. heat emitters, grilles, fan coil units, etc.
service ducts, high or low indicators or components, anti- vibration
level on floors. mountings, acoustic performance/treatment and
method of fixing.
3 Pipework. m 1 Material, finish, 1 Location of installation – 1 Generally, all pipework should be measured
nominal diameter, roofs, high or low level in inclusive of all fittings, i.e. unions, connectors,
method of jointing, plantrooms, risers or flanges, bends, tees, junctions, reducers, test
fixings and service ducts, high or low points, bosses, sockets, tappings, etc.
background level on floors, in trenches. 2 Unless measured separately,
for fixing. all fittings are included.
6 Ventilation ducts. 1 Material, finish, 1 Location of installation – 1 Generally, all ductwork should be measured
section shape, roofs, high or low level in inclusive of all fittings, i.e. connectors, flanges,
dimensions, plantrooms, risers or bends, tees, junctions, reducers, spigots, test
method of jointing, service ducts, high or low holes, etc.
fixings and level on floors.
background for
fixing.
2 Unless
measured
separately, all
fittings are to be
included.
7 Alternative – duct nr 1 Type, material, 1 Joints, flanges, bends, tees, sets, junctions,
fittings. finish, shape, reducers, spigots, test holes, etc.
dimensions,
method of jointing.
9 Insulation and fire nr 1 Type, material, 1 Location of installation – 1 To equipment and fittings.
protection. finish. roofs, high or low level in
plantrooms, risers
or service ducts, high or
low level on floors, in
trenches.
m 2 Thickness, 1 To pipework. 1 Generally, all insulation to pipework should be
material, finish, measured inclusive of all fittings, i.e. unions,
nominal diameter connectors, flanges, bends,
of pipe. tees, sets, junctions, reducers, test points,
bosses, sockets, tappings, etc.
3 Unless
measured
separately,
all fittings are
included.
10 Alternative – nr 1 Type, material, 1 Unions, connectors, flanges, bends, tees,
insulation and fire finish, nominal sets, junctions, reducers, test points, bosses,
protection to pipe fittings. diameter, method sockets, tappings, etc.
of jointing.
11 Insulation and fire nr 1 Type, material, 1 Valves, strainers, expansion bellows, gullies,
protection to pipe finish, nominal outlets, tundishes, traps, pipe sleeves, etc.
ancillaries. diameter, method
of jointing.
12 Insulation and fire m2 1 Thickness, 1 Location of installation – 1 Generally, all insulation to ductwork should be
protection to ventilation material, finish, roofs, high or low level in measured inclusive of all fittings, i.e.
ducts. duct dimensions. plantrooms, risers or connectors, flanges, bends, tees, sets,
service ducts, high or low junctions, reducers, spigots, test holes, etc. on
level on floors, the external girth of the duct to be insulated.
in trenches.
2 Unless
measured
separately,
insulation and fire
protection to all
fittings is included.
3 Assembly of
composite items of
primary equipment.
2 Terminal nr 1 System. 1 Type, size, capacity, 1 Location of installation – 1 Terminal equipment and
load,
equipment and rating, special finishes, roofs, high or low level fittings are defined as any item
fittings. casings, in-fills, associated in plantrooms, risers or service to which a system is distributed
2 Unless
measured
separately, all
fittings are deemed
to be included.
4 Alternative – cable nr 1 Type, material, 1 Joint boxes, connectors, flanges, bends, tees,
containment fittings. finish, shape, sets, junctions, reducers, spigots, fire barriers,
dimensions, etc.
method of jointing.
6 Cable terminations and nr 1 Type, rating, 1 This includes all pots, seals, glands, lugs,
joints. size, number of connector blocks and shrouds.
cores, material,
armouring,
sheathing.
7 Final circuits. nr 1 Cable type, 1 Location of installation – 1 This includes all containment not measured
rating, size, roofs, high or low level in separately, junction boxes, terminations, pots,
material, plantrooms, risers seals, glands, lugs, connector blocks and
sheathing, number or service ducts, high shrouds.
and type of points. or low level on floors. 2 This includes fixing containment or cables in
chases, surface or suspended from soffits.
8 Modular wiring nr 1 Cable type, 1 This includes all containment not measured
systems. rating, size, separately, junction boxes, terminations, pots,
material, seals, glands, lugs, connector blocks and
sheathing, number shrouds.
and type of points. 2 This includes fixing containment or cables in
chases, surface or suspended from soffits.
1 Unless
measured
separately,
all fittings are
included.
10 Alternative – nr 1 Type, material, 1 Connectors, flanges, bends, tees, sets,
busbar fittings. finish, shape, junctions, feeder units, tap-off boxes fire
dimensions, barriers, etc.
method of jointing. 2 Joints, flanges, bends, tees, sets, junctions,
reducers, spigots, test holes, etc.
11 Tapes. m 1 Type, rating, 1 Location of installation – 1 This includes all connections, joints, test
size, material, roofs, high or low level in clamps.
sheathing, method plantrooms, risers
of jointing, fixings or service ducts, high or
and background low level on floors, in
for fixing. trenches.
15 Testing. item
16 Commissioning. item
17 System validation. item
18 Operation and item
maintenance manuals.
19 Drawing preparation. item 1 Classification of 1 Installation, coordination, as installed and
drawings. record drawings.
20 Training. item
21 Loose ancillaries. item 1 Keys, tools,
spares, chemicals.
nr 2 Off-load and
position
primary equipment.
nr 3 Assembly of
composite items of
primary equipment.
item 5 Interface with 1 Type of system. 1 Nature of interface. 1 Systems supplied and installed by others will
and connection to include telephones, intercoms, fire alarm, etc.
systems supplied
and installed by
others.
7 Catenary cables. m 1 Size and type 1 Eye bolts, details stated. 1 The length is net with no allowance made for
stated. 2 Shackles, details stated. sag.
3 Straining screws, details
stated.
14 Items extra over m2 1 Breaking up hard 1 Reinstating to match 1 The measurement of these extra over items
service runs irrespective surface existing, details stated. should be based on the designed width of beds
of depth or pipe size. pavings, thickness 2 Relaying turf previously in the trench. In the absence of a bed, the width
stated. set aside. should be
2 Lifting and calculated as the nominal size of the service
preserving turf, plus 300mm, subject to a minimum width of
thickness stated. 500mm.
m3 3 Breaking out 3 Details stated. 1 Hard material is any material that can only be
hard materials. removed by special plant or explosives due to
4 Excavating in its size, position or consistency.
and removing
hazardous
material.
5 Excavating in
running silt,
running sand or
other unstable
ground.
6 Excavating
below groundwater
level.
m 7 Next to existing 1 This should be measured where precautions
live services. are required.
2 The method of protection is left to the
nr 8 Around existing discretion of the contractor.
live services
crossing trench.
15 Pipe duct fittings. nr 1 Dimensioned 1 Type stated. 1 Method of jointing to pipe ducts. 1 Pipe duct fittings include bends, junctions,
description. inspection pipes, stop ends, etc. and
connections to pipes.
16 Accessories. nr 1 Dimensioned 1 Accessories include all integral and or
description. associated fittings and connections to pipes.
17 Manholes. nr 1 Detailed 1 Base slab thickness. 1 Size stated is the maximum internal size of
18 Access chambers. description stating 2 Wall thickness. the chamber.
19 Valve chambers. maximum internal 3 Cover slab dimensions. 2 Rocker joints are included.
size of chamber.
20 Inspection chambers. 4 Intermediate slab
2 Depth from top
21 Surface boxes. surface of cover to
dimensions.
22 Stopcock pits. top surface of base 5 Internal finish.
or invert level in 6 External finish.
250mm stages. 7 Cover and frame, type
3 Proprietary stated.
chambers boxes,
etc., details stated.
23 Extra over the m2 1 Breaking up hard 1 Making good around edges of surfaces is
excavation for: surface included.
pavings, thickness
stated.
2 Lifting and
preserving turf,
thickness stated.
m3 3 Breaking out
hard materials.
4 Excavating in
and removing
hazardous
material.
5 Excavating in
running silt,
running sand or
other unstable
ground.
6 Excavating
below groundwater
level.
24 Marker posts. nr 1 Dimensioned 1 Identification plates, 1 Method of fixing, 1 Excavation, disposal of spoil and concrete for
25 Marker plates. description. details details stated. base is included.
stated.
2 Lettering required.
26 Connections. item 1 Details stated.
27 Testing and item 1 Detailed 1 Attendance required. 1 Provision of water and other supplies is
commissioning. description. 2 Instruments and included.
2 Type of test and equipment to be provided. 2 Provision of test certificates
standard to be is included.
achieved.
POMI
Published -June 1979, Published by RICS
Total 17 Sections, GP,A to H, J to R. (I & O MISSING )
Section A GENERAL REQUIREMENTS
Section B - SITE WORK
Section C - CONCRETE WORK
Section D- MASONRY
Section E-METAL WORK
Section F-WOOD WORK
Section G-THERMAL AND MOISTURE PROTECTION
Section H- DOORS AND WINDOWS
Section J - FINISHES
Section K - ACCESSORIES
Section L - EQUIPMENT
Section M - FURNISHINGS
Section N - SPECIAL CONSTRUCTION
Section P - CONVEYING SYSTEMS
Section Q - MECHANICAL ENGINEERING INSTALLATIONS
Section R - ELECTRICAL ENGINEERING INSTALLATIONS
Section A GENERAL REQUIREMENTS
A1 Conditions of contract
A1.1 A schedule of the clause headings shall be set out in the bills of quantities.
A1.2 Where there is an appendix to the conditions of contract requiring insertions to
be made, a schedule of the insertions shall be set out in the bills of quantities.
A2 Specification
A2.1 Where the specification contains clauses related to any of the following
General Requirements, the bills of
quantities shall make reference to the appropriate clauses.
A3 Restrictions
1. Access to and possession or use of the site
2. Limitations of working space
3. Limitations of working hours
4. The maintenance of existing services on, under or over the site
5. The execution or completion of the work in any specific order, sections or phases
6. Items of a like nature.
A4 Contractor's administrative arrangements
1. Site administration
2. Supervision
3. Security
4. Safety, health and welfare of workpeople
5. Transport of workpeople.
A5 Constructional plant
1. Small plant and tools
2. Scaffolding
3. Cranes and lifting plant
4. Site transport
5. Plant required for specific trades.
A6 Employer's facilities
1. Temporary accommodation (for example, offices, laboratories, living
accommodation), including heating, cooling, lighting, furnishing, attendance or
related facilities
2. Telephones, including costs of calls; alternatively, the cost of calls may be given as
a sum
3. Vehicles
4. Attendance of staff (for example, drivers, laboratory assistants)
5. Equipment (for example, surveyor laboratory equipment)
6. Special requirements for programmes or progress charts
7. Any other facilities (for example, progress photographs, signboards).
A7 Contractor's facilities
1. Accommodation and buildings, including offices, laboratories, compounds, stores,
messrooms and living
accommodation
2. Temporary fencing, including hoardings, screens, roofs and guardrails
3. Temporary roads, including hardstandings and crossings
4. Water for the works; particulars shall be given if water will be supplied to the
contractor
5. Lighting and power for the works; particulars shall be given if current will be
supplied to the contractor
6. Temporary telephones.
A8 Temporary works
1. Traffic diversion
2. Access roads
3. Bridges
4. Cofferdams
5. Pumping
6. De-watering
7. Compressed air for tunnelling.
A9 Sundry items
1. Testing of materials
2. Testing of the works
3. Protecting the works from inclement weather
4. Removing rubbish, protective casings and coverings and cleaning the works at
completion
5. Traffic regulations
6. Maintenance of public and private roads '
7. Drying the works
8. Control of noise and pollution
9. All statutory obligations
SMM 07
Published -June 1998, Published by RICS
Total 23 Content, A to H, J to Y. (I & O MISSING)
A Preliminaries/General conditions
B Complete buildings/structures/units
C Existing site/buildings/services
D Groundwork
E In situ concrete/large precast concrete
F Masonry
G Structural carcassing metal/timber
H Cladding/covering
J Waterproofing
K Linings/Sheathing/Dry partitioning
L Windows/doors/stairs
M Surface finishes
N Furniture/fittings
P Building fabric sundries
Q Paving/Planting/Fencing/Site furniture
R Disposal systems
S Piped supply systems
T Mechanical heating/cooling/refrigeration systems
U Ventilation/Air conditioning systems
V Electrical supply/power/lighting systems
W Communications/Security/Controls systems
X Transport systems
Y Mechanical and Electrical services measurement
A Preliminaries/General conditions
A10 Project particulars
1 Name, nature and location (Item)
2 Names and addresses of Employer and Consultants (Item)
A31 Employer's requirements: Provision, content and use of documents (FC & TRC ) , (Item)
1 Employer's requirements or limitations
A35 Employer's requirements: Specific limitations on method/sequence/timing/use of site (FC & TRC ) , (Item)
1 Design constraints
2 Method and sequence of work
3 Access
4 Use of the site
5 Use or disposal of materials found
6 Start of work
7 Working hours
8 Others
A37 Employer's requirements: Operation/ Maintenance of the finished building (FC & TRC ) , (Item)
Employer's requirements or limitations.
40 Contractor's general cost items: Management and staff (FC & TRC ) , (Item)
Management and staff includes management, trades supervision, engineering, programming
and production, quantity surveying support staff and the like.
A41 Contractor's general cost items: Site accommodation (FC & TRC ) , (Item)
Include Site accommodation includes offices, laboratories, cabins, stores, compounds,
canteens, sanitary facilities and the like
A42 Contractor's general cost items: Services and facilities Services and facilities (FC & TRC ) , (Item)
1 Power
2 Lighting
3 Fuels
4 Water
5 Telephone and administration
6 Safety, health and welfare
7 Storage of materials
8 Rubbish disposal
9 Cleaning
10 Orying out
11 Protection of work in all sections
12 Security
13 Maintain public and private roads
14 Small plant and tools
15 Others
16 General attendance on nominated sub-contractors
17 General attendance of Nominated sub-contractors in respect of the requirements of the Joint Fire Code
The items listed are not exhaustive and are for the convenience of pricing only
A43 Contractor's general cost items: Mechanical plant (FC & TRC ) , (Item)
1 Cranes
2 Hoists
3 Personnel transport
4 Transport
5 Earthmoving plant
6 Concrete plant
7 Piling plant
8 Paving and surfacing plant
9 Others
The items listed are not exhaustive and are for the convenience of pricing only
A44 Contractor's general cost items: Temporary works (FC & TRC ) , (Item)
1 Temporary roads
2 Temporary walkways
3 Access scatfolding
4 Support scaffolding and propping
5 Hoardings, fans, fencing etc.
6 Hardstanding
7 Traffic regulations
8 Others
The items listed are not exhaustive and are for the convenience of pricing only
D10 Work by statutory authorities includes work by public companies responsible for statutory
work when executing their statutory duty
A55 Dayworks
1 Labour : Prov.Sum
2 Materials : Prov.Sum
3 Plant : Prov.Sum
NRM 02
NRM 02, First Revision publised-2013, Second Edition - Oct 2021
Work Section-41 Sections
Definitions
Bill of quantities (BQ) A list of items that gives detailed identifying descriptions and firm quantities of the work comprising a contract.
Construction information Information used to construct the building systems on site. This information can be prepared by the design team or a specialist subcontractor and must comprise
prescriptive information. See also the definitions of building systems and prescriptive information.
Cost target In the context of bills of quantities (BQs), the cost target is the total expenditure for an element or works package.
Credit A refund offered by the contractor to the employer in return for the benefit of taking ownership of materials, goods, items, mechanical and electrical plant,
equipment, etc. arising from demolition or strip-out works.
Daywork The method of valuing work on the basis of the time spent by the contractor’s team, the materials used and the plant employed.
Defined provisional sum A sum provided for work that is not completely designed but for which the following information is provided:
• the nature and construction of the work
• a statement of how and where the work is fixed to the building, and what other work should be fixed
• a quantity or quantities that indicate the scope and extent of the work, and
• any specific limitations, etc. identified.
Descriptive information The means by which the design team describe a building system or component in a manner that enables a specialist subcontractor to design the system or
component.
Design team Architects, engineers and technology specialists responsible for the conceptual design aspects and developing these into drawings, specifications and
instructions required for construction of the building or facility and associated processes. The design team is a part of the project team.
Director’s adjustment A reduction or addition to the tender price derived by the specific contractor’s estimating team, offered by the director(s) of the maintenance contractor.
Element A major part of a group element (e.g. the elements that create group element 3: Internal finishes are 3.1: Wall finishes, 3.2: Floor finishes and 3.3: Ceiling
finishes).
A separate cost target can be established for each element.
Note also the use of the term ‘cost group’ or ‘cost sub- group’ in the context of ICMS.
Final specifications The specifications issued at RIBA Stage 4 (Technical Design). These specifications can be descriptive or prescriptive.
Fixed charge Work for which the cost should be considered independently from the duration.
Group element The main headings used to describe the facets of an elemental cost plan.
Note also the use of the term ‘cost group’ or ‘cost sub- group’ in the context of ICMS.
Main contractor (or prime contractor) The primary/principal contractor appointed by the client to coordinate the construction/site production phase of a project, which may involve more than one
subcontractor. The term prime contractor is often used to mean main contractor in central civil government and the defence sector. The terms are used
synonymously, irrespective of the contract strategy used (e.g. traditional, design and build, design and construct, design and manage or management
contracting).
Main contractor’s overheads The main contractor’s costs associated with head office administration proportioned to each building contract plus the main contractor’s return on capital
and profit investment.
Main contractor’s preliminaries Items that cannot be allocated to a specific element, sub-element or component.
Manufacturing information Information prepared for the manufacture of building systems and/or components during RIBA Stage 4 (Technical Design).
Other project costs Costs that are not necessarily directly associated with the cost of constructing the building, but form part of the total cost of the building project to the employer
(e.g. land acquisition costs, fees for letting agents, marketing costs and contributions associated with planning permission).
Post-tender estimate A cost estimate carried out after the evaluation of tenders to corroborate the funds required by the employer to complete the building maintenance contract.
Pre-tender estimate A cost estimate prepared immediately before calling tenders for servicing, maintenance and life cycle replacement works.
Prescriptive information Complete, instructive information used to manufacture and construct building systems and components, produced by the design team or the construction team.
Prime cost sum (PC sum) A sum of money included in a unit rate to be expended on materials or goods from suppliers (e.g. supply-only ceramic wall tiles at £50/m , supply-only door
2
Project A single, or a series of, construction intervention(s) with a single purpose or common purposes to create a single asset or a series of assets commissioned by a
client, or group of clients, with defined start and end dates. A project may comprise several sub-projects.
Project information Information, including models, documents, specifications, schedules and spreadsheets, issued between parties during each RIBA Stage and in formal
information exchanges at the end of each RIBA Stage.
Project team Client/employer, project manager, quantity surveyor/ cost manager, design team and all other consultants responsible for the delivery of the building project on
time, on cost and to the required performance criteria (design and quality). The project team includes the main contractor where one has been engaged by the
employer to provide pre-construction services.
Provisional quantity A quantity that cannot be accurately determined (i.e. an estimate of the quantity).
Provisional sum A sum of money set aside to carry out work that cannot be fully described and given in quantified items in accordance with the tabulated rules of measurement.
A provisional sum should be identified as either defined or undefined (see definitions of defined provisional sum and undefined provisional sum).
Residual risk (or retained risk) The risks retained by the client. Could also be defined by reference to the effect of uncertainty on objectives (ISO 31000). An uncertain event or condition that,
should
RIBA Plan of Work itRefers
occur,towill
RIBAhave
Plananofimpact
Work, aonframework
project objectives or the
setting out business
stagesgoals.
of a building project. It consists of eight Stages. The RIBA Plan of Work specifies the tasks to be
undertaken by the project team at each Stage.
RIBA Stage The stage the project is at. The RIBA Plan of Work consists of eight Stages identified by the numbers 0 to 7. Tendering and the awarding of works contracts is
treated as a variable task, as they depend on the selected procurement route and can occur at any time between Stages.
Site area (SA) The total area of the site within the site title boundaries (or the total area within the site title boundaries defined by the client as the site for the building),
measured on a horizontal plane.
Statutory undertaker Organisations such as water, gas, electricity and telecommunications companies that are authorised by statute to construct and operate public utility
undertakings.
Subcontractor A contractor who undertakes specific work within the building project. They are known as specialist-, works-, trade-, works package- and labour-only
subcontractors.
Sub-project A subdivision of a project that can be described by a single set of attributes and values.
Temporary works Non-permanent work or activity that is necessary for the completion of permanent construction work.
Time-related charge A charge for work, the cost of which should be considered dependent on duration.
Undefined provisional sum A sum provided for work that is not completely designed, but for which the information required for a defined provisional sum cannot be provided.
Work breakdown structure (WBS) In the context of BQs, the WBS is used to subdivide a building project into meaningful elements or works packages.
Works package contractor A specialist contractor who undertakes identifiable aspects of maintenance or replacement work, e.g. maintenance of non-specialist mechanical and electrical
engineering services; maintenance of specialist installations (such as building management systems and fuel installations); maintenance of building fabric,
structure, finishes and fittings, furnishings and equipment; landscaping management and grounds maintenance works; or labour-only. Depending on the contract
strategy, works contractors can be employed directly by the client or by the maintenance contractor.
Works package contractor preliminaries Preliminaries that relate specifically to the work that is carried out by a works package contractor.
2.2 Benefits of a bill of quantities 2.3 Types of bills of quantities 2.3.1 Firm bill of quantities 2.3.2 Approximate bill of quantities
Irrespective of which contract strategy is used, at some • firm (to obtain a lump sum price for a fully designed The reliability of the tender price will increase in relation Approximate BQs are used when there is not enough
stage in the procurement process, one party – whether building project) or to the accuracy of the quantities provided (i.e. the more detail to prepare a firm BQ, or where it is decided by the
that is the client’s quantity surveyor/cost manager or the • approximate (subject to remeasurement as built). precisely the work is measured and described). In theory, client that the time or cost of producing a firm BQ is not
main contractor – will need to quantify the extent of if there were warranted.
works to be executed for the purpose of: no design changes, a firm BQ would provide a price at the Such contracts do not provide a lump sum price, but
• obtaining a price for completing building works tender stage, which would equal the rather tender price totals (i.e. a quantified schedule of
• valuing the extent of work completed, for the purposes final cost. rates), since the quantities are subject to remeasurement
of payment on completion by the quantity surveyor/cost manager.
• valuing variations in the content or extent of building These contracts are usually subject to greater variation
works or than lump sum contracts and therefore should only be
• supporting applications for tax or other financial used where time is a limiting factor or where there is
incentives. great uncertainty in certain elements, such as major
excavation and earthworks.
Procurement strategy Basis of invitation documents Prepared by BQs usually comprise the following sections:
• form of tender (including certificate of bona fide
Traditional lump sum Firm BQ Client’s quantity surveyor/cost manager. tender)
Approximate BQ • summary
• preliminaries
Design and build Employer’s requirements Client’s project team (normally the client’s quantity • measured works
surveyor/cost manager). • non-measurable works
Note: Quantification of the employer’s requirements • provisional sums
will be carried out either by the main contractor or • contractor-designed works
works package contractor, who will prepare a firm or • risks
approximate BQ or quantified schedules of work as • credits (for materials arising from the works)
appropriate. • dayworks (provisional) and
• annexes.
• Voids:
– unless otherwise stated, minimum deductions for voids
refer only to openings or wants
within the boundaries of the measured work
– always deduct openings or wants at the boundaries of
measured areas, irrespective of
size
– do not measure separate items for widths not
exceeding a stated limit where these
widths are caused by voids.
Appendix A: Guidance on the preparation of bill of
quantities
A1 Bill of quantities breakdown structure
There a number of different breakdown structures for a BQ. They each have their own advantages and disadvantages. However, computerised BQ production systems with
Elemental breakdown structure
multiple sort facilities can be used to generate different BQ formats and make it easy to trace items – as long as items have been properly codified (refer to section 2.8
BillofNo.
(Codification bill1of quantities)).
Preliminaries (main contract)
Bill No. 2 Facilitating works
Bill No. 3 Substructure
Bill No. 4 Superstructure
Bill No. 5 Internal finishes
Bill No. 6 Fittings, furnishings and equipment
Bill No. 7 Services
Bill No. 8 External works
Bill No. 9 Risks
Bill No. 10 Provisional sums
Bill No. 11 Credits
Bill No. 12 Daywork (provisional)
Figure A.1: Elemental BQ breakdown structures for a simple building project
easier for the quantity surveyor/cost manager to analyse a contractor’s tender price and collect real- time cost data for future use.
b Work
Work section:
section Measurement
breakdown and description is divided into the work sections listed in NRM 2 (refer to Part 3 of these rules).
structure
Bill No. 1 Preliminaries
Bill No. 2 Off-site manufactured materials, components or buildings
Bill No. 3 Demolitions
Bill No. 4 Alterations, repairs and conservation
Bill No. 5 Excavating and filling
Bill No. 6 Ground remediation and soil stabilisation
Bill No. 7 Piling
Bill No. 8 Underpinning
Bill No. 9 Diaphragm walls and embedded retaining walls
Bill No. 10 Crib walls, gabions and reinforced earth
Bill No. 11 In-situ concrete works
Bill No. 12 Precast/composite concrete
Bill No. 13 Precast concrete
Bill No. 14 Masonry
Bill No. 15 Structural metalwork
Bill No. 16 Carpentry
Bill No. 17 Sheet roof coverings
Bill No. 18 Tile and slate roof and wall coverings
Bill No. 19 Waterproofing
Bill No. 20 Proprietary walls, linings and partitions
Bill No. 21 Cladding and covering
Bill No. 22 General joinery
Bill No. 23 Windows, screens and lights
Bill No. 24 Doors, shutters and hatches
Bill No. 25 Stairs, walkways and balustrades
Bill No. 26 Metalwork
Bill No. 27 Glazing
Bill No. 28 Floor, wall, ceiling and roof finishings
Bill No. 29 Decoration
Bill No. 30 Suspended ceilings
Bill No. 31 Insulation, fire stopping and fire protection
Bill No. 32 Furniture, fittings and equipment
Bill No. 33 Drainage above ground
Bill No. 34 Drainage below ground
Bill No. 35 Site works
Bill No. 36 Fencing
Bill No. 37 Soft landscaping
Bill No. 38 Mechanical services
Bill No. 39 Electrical services
Bill No. 40 Transportation systems
Bill No. 41 Builder’s work in connection with mechanical, electrical and
Bill No. 42 transportation installations
Risks
Bill No. 43 Provisional sums
Bill No. 44 Credits
Bill No. 45 Daywork (provisional)
Figure A.2: Work section BQ breakdown structures for a simple building project
c
This Work package:
breakdown Measurement
structure and description
is often preferred is divided
by contractors into
for the employer,
purpose quantity
of pricing as surveyor/ cost manager
all alike products or contractor
and components aredefined
groupedwork packages,
together whichever
(e.g. the is applicable.
reinforced concrete
Works packages can be based on either a specific-trade (e.g. concrete work, brickwork and blockwork, roof coverings, painting and decorating, and wall tiling) or a single
Work section breakdown structure
Bill No. 1 Contractor’s preliminaries
Bill No. 2 Intrusive investigations
Bill No. 3 Demolition works
Bill No. 4 Groundworks
Bill No. 5 Piling
Bill No. 6 Concrete works
Bill No. 7 Roof coverings and roof drainage
Bill No. 8 External and internal structural walls
Bill No. 9 Cladding
Bill No. 10 Windows and external doors
Bill No. 11 Mastic
Bill No. 12 Non-structural walls and partitions
Bill No. 13 Joinery
Bill No. 14 Suspended ceilings
Bill No. 15 Architectural metalwork
Bill No. 16 Tiling
Bill No. 17 Painting and decorating
Bill No. 18 Floor coverings
Bill No. 19 Fittings, furnishings and equipment
Bill No. 20 Combined mechanical and electrical engineering services
Bill No. 21 Lifts and escalators
Bill No. 22 Facade access equipment
Bill No. 23 External works and drainage
Bill No. 24 Risks
Bill No. 25 Provisional sums
Bill No. 26 Credits
Bill No. 27 Daywork (provisional)
Figure A.3: Typical BQ breakdown structure for discrete work package
Again, codification of BQ items using computerised BQ systems will enable the resorting of items from elements to works packages for the purposes of tendering, and vice
versa for the purpose of overall cost control (refer to section 2.8 (Codification of bill of quantities)).
g Contractor-designed works should be incorporated under the applicable element or sub- element, after measured work, under a heading of ‘Contractor-designed work’. A price analysis
for contractor-designed work should be incorporated (see section 2.5.5).
h Items
d Provisional
withinsums
each should be listed
subdivision in (b)and
anddescribed
(c) shouldinbe
a separate
placed inbill.
order of value, least expensive first.
Bill No. 3 Superstructure
3.2.5 External walls
3.2.5.1 External walls above ground floor level
3.2.5.1.1 Common brickwork in cement: lime
3.2.5.1.1.1 mortar102.5mm
Walls (1:1:6) thick, brickwork; built 196 m2