Problem 1

Problem 2.

Ans:
The resource histogram and bar chart is given below:
Problem 3:

1. Ans
The bar chart for the early start time is given below:

The resource histogram for early start time is given below:

Y ∗Y
Resource Moment = ∑
2
= 2*3*3/2 + 7*9*9/2 + 2*11*11/2 + 4*2*2/2 + 5*4*4/2

= 461.5
2. Ans
For the theoretical minimum moment:
Total labours = 119
Total days = 20
Labors per day = 119/20 = 5.95
Now,
Theoretical minimum moment = 20*5.95*5.95/2 = 354.025

3.

The lowest resource moment we can achieve is 397.5

The bar chart and histogram with the lowest resource moment is given below:

The resource histogram for lowest resource moment is given below:

Resource histogram for Lowest Resource Moment


7
6 6 6 6
6
5 5 5 5 5 5 5
5
Number of labors

4 4 4 4 4
4
3 3 3 3
3

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Days
4.

When we have only 6 laborers per day, the project duration increase and becomes 27 days.

The bar graph of the solution is given below: