Problem 2.
Ans:
The resource histogram and bar chart is given below:
Problem 3:
1. Ans
The bar chart for the early start time is given below:
Y ∗Y
Resource Moment = ∑
2
= 2*3*3/2 + 7*9*9/2 + 2*11*11/2 + 4*2*2/2 + 5*4*4/2
= 461.5
2. Ans
For the theoretical minimum moment:
Total labours = 119
Total days = 20
Labors per day = 119/20 = 5.95
Now,
Theoretical minimum moment = 20*5.95*5.95/2 = 354.025
3.
The bar chart and histogram with the lowest resource moment is given below:
4 4 4 4 4
4
3 3 3 3
3
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Days
4.
When we have only 6 laborers per day, the project duration increase and becomes 27 days.