AESO Measurement System Standard1
AESO Measurement System Standard1
AESO Measurement System Standard1
Revisions
1.0 Updated to include new in-situ testing Chris Connoly, P.Eng. Sept 18, 2007
requirements and changes to the data
provision process and data format.
Page 2 of 59
Table Of Contents
1.0 INTRODUCTION................................................................................................................ 6
1.1 Purpose...................................................................................................................6
1.2 Application ..............................................................................................................6
1.3 Definitions...............................................................................................................6
1.4 Modifications ..........................................................................................................6
1.5 Requirements For Review ...................................................................................6
1.6 Stakeholder Review Committee .........................................................................7
2.0 ROLES & ACCOUNTABILITIES .................................................................................... 8
2.1 Scope ......................................................................................................................8
2.2 Overview.................................................................................................................8
2.3 Measurement System...........................................................................................8
2.4 Data Centre ............................................................................................................9
2.5 Data Systems.........................................................................................................9
2.6 Metering Systems..................................................................................................9
3.0 MEASUREMENT SYSTEM............................................................................................ 10
3.1 Scope ....................................................................................................................10
3.2 Functional Overview ...........................................................................................10
3.3 Service Requirements ........................................................................................10
3.3.1 Measurement Point Definition Record................................................................. 10
3.3.2 Audits .................................................................................................................. 11
3.3.3 Check Metering ................................................................................................... 11
3.3.4 Disputes .............................................................................................................. 11
4.0 DATA CENTRE................................................................................................................ 13
4.1 Scope ....................................................................................................................13
Functional Overview .......................................................................................................13
4.3 System Requirements ........................................................................................13
4.3.1 Data Collection .................................................................................................... 13
4.3.2 Data Processing .................................................................................................. 14
4.3.3 Data Storage ....................................................................................................... 14
4.3.4 Data Access ........................................................................................................ 14
5.0 METERING DATA SERVICES...................................................................................... 15
Page 3 of 59
5.1 Purpose.................................................................................................................15
5.2 Service Scope......................................................................................................15
5.3 Service Requirements ........................................................................................15
5.3.1 Data Collection .................................................................................................... 15
5.3.2 Data Validation, Verification, Estimation & Editing .............................................. 15
5.3.3 Data Storage ....................................................................................................... 16
5.3.4 Data Processing .................................................................................................. 16
5.3.5 Data Transfer ...................................................................................................... 16
5.3.6 General................................................................................................................ 16
6.0 METERING SYSTEM SERVICES ................................................................................ 18
6.1 Purpose.................................................................................................................18
6.2 Service Scope......................................................................................................18
6.3 System Requirements ........................................................................................18
6.3.1 General................................................................................................................ 19
6.3.2 Measurement Transformers ................................................................................ 19
6.3.3 Meter ................................................................................................................... 20
6.3.4 Recorder.............................................................................................................. 21
6.3.5 Remote Communications Equipment .................................................................. 21
6.4 Service Requirements ........................................................................................21
6.4.1 General................................................................................................................ 22
6.4.2 Security & Access ............................................................................................... 22
6.4.3 Testing................................................................................................................. 23
6.4.4 Restoration .......................................................................................................... 25
6.4.5 Alternative Metering Data Sources...................................................................... 25
APPENDIX 1 SCHEDULE OF ACCURACIES FOR METERING EQUIPMENT
APPROVED UNDER SECTION 9(1) OF THE ELECTRICITY AND
GAS INSPECTION ACT ........................................................................... 27
(NON-DISPENSATED METERING EQUIPMENT) .............................................................. 27
APPENDIX 2 SCHEDULE OF ACCURACIES FOR METERS APPROVED UNDER
SECTION 9(3) OF THE ELECTRICITY AND GAS INSPECTION ACT
....................................................................................................................... 28
(DISPENSATED METERING EQUIPMENT) ........................................................................ 28
APPENDIX 3 GENERALLY ACCEPTED UTILITY METERING PRACTICES......... 29
APPENDIX 4 END-TO-END COMMISSIONING PROCESSES ................................. 31
Page 4 of 59
Page 5 of 59
1.0 INTRODUCTION
1.1 PURPOSE
The purpose of this Standard is to define the accountabilities and obligations of
the:
(a) AESO, and
(b) Metering Service Providers, and
(c) Metering Data Providers
1.2 APPLICATION
This Standard applies to the AESO and any Metering Data Providers and
Metering Service Providers who currently have a valid service agreement
with the AESO.
1.3 DEFINITIONS
Defined terms are indicated in bold italic typeface. Appendix 11 contains all of
the definitions in this Standard.
1.4 MODIFICATIONS
In respect to this Standard, the AESO must:
(a) make and manage all changes and additions to the Standard;
(b) seek and consider the input and feedback of any affected parties
prior to making changes or additions to the Standard;
(c) make this Standard publicly available via the AESO’s website.
Page 6 of 59
Page 7 of 59
2.1 SCOPE
The purpose of this section is to define the general accountabilities associated
with the various roles involved in the operation of the Measurement System.
2.2 OVERVIEW
The roles and accountabilities associated with the Measurement System can
be viewed as follows:
Measurement System
AESO
Page 8 of 59
Page 9 of 59
3.1 SCOPE
The purpose of this section is to define the system and service requirements
related to the provision of measurement system services.
Data Metering
Centre Data System(s) System(s)
Measurement System
In respect to the measurement point definition record, the AESO will have
operational policies, procedures and/or processes that:
Page 10 of 59
(a) ensure that the measurement point that it defines for a Data
Recipient meets the business requirements of the Data Recipient;
(b) define the number and type of measurement points that it requires
in order to receive the measurement data from the Data Systems;
(c) define the attributes (location, polarity,…) of any and all
measurement points that it requires in order to receive the
measurement data from the Data Systems;
(d) specify the measurement point definition record by which real
metering data and/or estimated data is manipulated to produce
measurement data;
(e) allow the AESO to exempt any metering point from requiring
metering equipment when, in the AESO’s opinion, the cost of
providing metering equipment would be unjustified with respect to
the commensurate gain in the accuracy of the associated
measurement data.
3.3.2 Audits
In respect to a request by any person requesting to audit measurement
data, the AESO will establish if such a person is an affected party with
respect to the measurement data and, if so, will:
(a) coordinate the efforts of all parties required to acquire the requested
measurement data;
(b) make whatever arrangements or agreements are necessary to
ensure the security of the provided measurement data;
(c) assess the cost(s) associated with providing the measurement data
and, if warranted, levy and recover those costs in a mutually
agreeable manner.
3.3.4 Disputes
The AESO will coordinate the resolution of any and all disputes that arise
and are related to the accuracy of the measurement data. Such disputes
will be administered in accordance with the following guidelines:
Page 11 of 59
(a) Any disputes that arise with respect to measurement data must be
communicated in writing to the AESO by the Data Recipient filing
the dispute;
(b) Whenever possible disputes will be resolved by mutual agreement
between the AESO and all affected parties;
(c) In the event that a resolution by mutual agreement, as per (b) above,
cannot be reached within twenty (20) business days of being first
communicated to the AESO, as per (a) above, the dispute may then
be raised by either the AESO or any affected party to:
Page 12 of 59
4.1 SCOPE
The purpose of this section is to define the system and service requirements
related to the provision of data centre services.
FUNCTIONAL OVERVIEW
The data centre can be represented as follows:
Data
Collection,
Processing Data
& Internet System(s)
Storage DropChute
Data Centre
Page 14 of 59
5.1 PURPOSE
The purpose of this section is to define the metering data services that are
required of a Metering Data Provider.
Page 15 of 59
(b) provide email notification to the AESO of any situation that requires, or
has the potential to require, the on-going estimation or editing of
metering data.
5.3.6 General
(a) provide email notification to the AESO of any significant events or
issues that may adversely impact the ability of the Metering Data
Provider to meet any of its obligations with respect to the provision of
metering data services, and
(b) cooperate with the Metering System Provider to complete any and all
testing required to confirm the correct operation of the data system or
the metering system, and
Page 16 of 59
(c) cooperate with the AESO in conducting audits of the metering data or
measurement data, and
(d) cooperate with the AESO in the resolution of disputes related to
measurement data, and
(e) cooperate with the AESO in conducting reviews and revisions of
measurement point definition records for measurement points
specified as part of any and all metering data services agreements
to which the Metering Data Provider is party, and
(f) ensure all systems used to meet the requirements of this Standard are
secure from unauthorized access, and
(g) provide access to the metering data to only those persons or entities
that are specifically granted access to the metering data as per the
applicable metering data services agreements.
Page 17 of 59
6.1 PURPOSE
The purpose of this section is to define the metering system services that are
required of a Metering System Provider.
Page 18 of 59
(f) involve the Metering Data Provider in the design and installation process to
whatever degree may be necessary to ensure that the data system is fully
functional and operational;
(g) inform the Metering Data Provider of any modifications to any aspect of the
metering system(s) that could, either directly or as a consequence, affect
the ability of the Metering Data Provider to gain access to or acquire the
metering data in a timely and efficient manner;
(h) gain the express written approval of the AESO to provide, or cause to be
used, any metering point(s), metering data or readings that are not
otherwise allowed for by this Standard including, but not necessarily be
limited to the use of, readings from unsealed interval meters, check
meters, non-interval meters etc;
(i) ensure that the metering system is configured, installed and operated in
accordance with generally accepted Canadian utility metering practices as
per Appendix 3;
(j) be commissioned in accordance with the process set out in Appendix 4.
6.3.1 General
The metering equipment must:
(a) conform to the most recent version of the Electricity and Gas
Inspection Act and this Standard;
(b) be suitable for use in the environmental conditions reasonably
expected to occur, at the installation site, over the course of a typical
year;
(c) be appropriate for the power system characteristics reasonably
expected to exist at the installation site under all power system
conditions and events;
(d) have a single ground point.
(e) have an accuracy class rating that equals or exceeds the values
specified in Appendix 1 for non-dispensated metering equipment;
6.3.3 Meter
The meter must:
(a) be Measurement Canada approved under Section 9(1), Section 9(2) or
Section 9(3) of the Electricity and Gas Inspection Act;
(b) be (re)verified and sealed in accordance with the Electricity and Gas
Inspections Act subject to the terms and conditions of any applicable
dispensation(s).
(c) measure all quantities required to determine active energy and
reactive energy transferred in both directions at the metering point;
(d) provide a separate register to maintain the continuously cumulative
readings of the active energy and reactive energy transferred in the
required directions at the metering point;
(e) provide reasonable security against unauthorized access for all
methods of local access to the meter;
(f) provide a communications port if the meter provides the remote
communications equipment interface;
(g) have an accuracy class rating for active energy measurement that
equals or exceeds the values specified in Appendix 1 for non-
dispensated metering equipment and Appendix 2 for dispensated
metering equipment;
(h) have an accuracy class rating for reactive energy measurement that
equals or exceeds the values specified in Appendix 1 for non-
dispensated metering equipment and Appendix 2 for dispensated
metering equipment.
(i) be labeled as being loss compensated if transformer and/or line losses
are calculated internally by the meter and affect displayed and/or
recorded energy values;
Page 20 of 59
(j) be labeled with an overall multiplier if the meter bases it’s displayed or
recorded energy values on unity current transformer and/or potential
transformer ratios;
6.3.4 Recorder
The recorder may be or may not be an integral part of the meter but must:
(a) be Measurement Canada approved under Section 9(1), Section 9(2) or
Section 9(3) of the Electricity and Gas Inspection Act;
(b) be (re)verified and sealed in accordance with the Electricity and Gas
Inspections Act subject to the terms and conditions of any applicable
dispensation(s);
(c) include an interval time-stamping clock, if the recorder provides the
interval data time-stamping function, capable of maintaining the
interval boundaries within 60 seconds of the hour and every quarter
hour thereafter;
(d) have sufficient storage to store interval data for a period of at least
fourteen (14) days;
(e) retain readings and, if applicable, all clock functions for at least
fourteen (14) days in the absence of line power;
(f) provide reasonable security against unauthorized access for all
methods of local access to the recorder;
(g) provide a communications port if the recorder provides the remote
communications equipment interface.
Page 21 of 59
6.4.1 General
The Metering System Provider must:
(a) provide written notification to the AESO of any situation pertaining to
the integrity or operation of the metering system that will result, or has
the potential to result, in the continued loss or corruption of metering
data;
(b) provide reasonable response to a Metering Data Provider's requests
related to the checking or repair of any remote communications
equipment that affects that Metering Data Provider's ability to acquire
the metering data in a timely and efficient manner;
6.4.3 Testing
In relation to general matters related to metering equipment and metering
system testing, the Metering System Provider must:
(a) pay the costs of all tests on its metering equipment. Testing costs
will be reimbursed by the AESO to the Metering System Provider for
any and all test(s), not defined by this Standard, that were specifically
requested by the AESO where such test(s) show that the metering
equipment complies with the relevant sections of this Standard.
Page 23 of 59
(b) ensure that the meter and/or recorder are tested and sealed as
required by Measurement Canada and that the meter complies with
the accuracy requirements in Section 6.3.3 of this Standard prior to
placing such meter or recorder into service;
(c) provide written notification of, and test results for, any re-tested
meter that demonstrates an error of measurement of more than three
(3) times the error permitted in Section 6.3.3 of this Standard to the
AESO within five (5) business days of the test results first becoming
available;
(d) maintain a record of all metering equipment tests to verify that its
metering equipment complies with this Standard (including details of
the equipment tested, measurement point, the reference standards
used, test procedure, meter register readings, test certificate and test
results);
(e) at the request of the AESO, undertake and complete tests on any
metering equipment, specified by the AESO, within thirty (30)
business days of receiving such a request;
(f) at the request of the AESO, forward a copy of the test results related to
any metering equipment, specified by the AESO, within thirty (30)
business days of receiving such a request;
(m)at the request of the AESO, forward a copy of the test results related to
a metering system, as specified by the AESO, within thirty (30)
business days of receiving such a request;
6.4.4 Restoration
A metering system is considered to have failed if:
(a) any of the associated metering equipment has failed in a manner that
causes the metering system to be unable to measure, record or
transfer the metering data as required by this Standard;
(b) any of the associated metering equipment is found to operate in a
manner, or under any condition, that compromises, or has the potential
to compromise, the ability of the metering system to measure, record
or transfer the metering data as required by this Standard;
(c) any of the associated metering equipment fails to pass any of the
tests as required by this Standard;
(d) the AESO deems the metering system to have failed.
Page 25 of 59
(b) assist the Metering Data Provider and AESO in establishing a basis
from which to estimate or adjust the metering data or measurement
data based upon the best available information until either an
alternative metering data source is established or the failed metering
system is restored.
Page 26 of 59
Metering Point
Capacity Watthour Meter Varhour Meter Measurement
(MVA) Accuracy Class Accuracy Class Transformers
Accuracy Class
Notes:
1. The columns apply to requirements set out in Section 6.3.2 and 6.3.3.
3. This schedule applies only to all new metering systems installed on or after July 1,
2004.
Page 27 of 59
Meter Accuracy
Notes:
Page 28 of 59
• A test switch is provided that enables the isolation of potentials and the shorting
of all currents to the meter
• Meters/recorders have a backup battery (or other) system that will maintain data
and clock integrity for no less than 14 days in the absence of line power.
• Instrument transformers are not over burdened by the meter and any other
devices/wiring that may be included as part of the instrument transformer/meter
circuit.
• Meters that have unity PT and or CT ratios have the appropriate multiplier
labeled.
Page 29 of 59
• Metering enclosures that contain voltages in excess of 120V are clearly labeled as
containing ‘High Voltage’ (277/480, 347/600).
• Metering system wiring diagrams should either be included within the metering
enclosure or available upon request.
Page 30 of 59
Yes
Yes
Yes
TFO energizes the facility
such that energy is
Energize
transferred through the new
metering point.
Stop
Page 31 of 59
A <1 6 years
B 1 up to 10 3 years
C 10 up to 20 2 years
D 20 up to 50 1 year
E 50 + 6 months
Page 32 of 59
1. Confirm that the metering equipment installed matches that documented on the
current Measurement Point Definition Record. To be performed on all
equipment at installation, and on visible equipment afterwards. Meters must
always be verified, while Current Transformers (CTs) and Potential Tranformers
(PTs) may not be accessible.
2. Check the wiring connections:
a. on all equipment at installation or on the changing of instrument
transformers, check that the wiring connections from the meter to each
piece of metering equipment are correct.
b. during scheduled tests, a visual inspection of the meter connection wiring
to ensure that appropriate connections apply must be performed.
3. Check to confirm that the inventory taken during the test matches the inventory in
the metering system provider main database and the inventory that was last
submitted to the AESO for that point. The meter number must always be
explicitly confirmed. To be performed on all equipment at installation, whenever
equipment is changed and during regularly scheduled tests.
4. Check of the CT ratios by all of the following:
a. Injection test. To be performed at installation or lab tested prior to
installation.
b. Comparison of primary clip on to metering secondary, only if a primary clip
on is physically possible. To be performed during all tests.
c. Comparison of metering secondary to a second independent source (such
as protection). To be performed during all tests.
5. Check of the CT performance by measuring the burden of the CT circuit to
ensure that it falls within manufacturing accuracy specifications. To be
performed at installation. The burden may also be calculated from drawings and
specs when additional pieces of equipment are added to the CT circuit.
6. Check to confirm that the voltage reading is reasonable compared to the rated
voltage. To be performed during all tests.
Page 33 of 59
7. Check to confirm that the meter has a valid seal from Measurement Canada, in
accordance with Measurement Canada requirements. To be performed during
all tests.
8. Check of power measurements compared to test equipment validated against a
test standard for reasonability. To be performed during all tests. There may be
limitations to this test when there is extremely low load, or rapidly fluctuating
load. If the analyzer can accept pulses this should be used to calculate the
accuracy (works well under fluctuating loads).
9. Check of the central data collection system (i.e. MV-90 operators) to ensure that
the load measured on site in engineering units based on the test equipment
validated against a test standard (ie PT x CT x test standard measurement) is
within reason of the load recorded by the data collection system (ie MV-90), and
that the channel mapping in the central data collection system match those of the
meter. To be performed during all tests. There may be limitations to this test
when there is extremely low load, or rapidly fluctuating load.
The above test procedures do not limit any other tests that the meter system provider
may wish to perform.
The Metering System Test Form must contain the following components:
a) The AESO’s Real Metering Point ID associated with the metering system, as
referred to in the Measurement Point Definition Records.
b) The date the test was performed on the metering system.
c) A list of which tests specified in Appendix 5 Section 2 were performed, and an
explanation for any tests that were not performed.
d) A list of which tests specified in the Testing Procedures passed, and an
explanation of any test that did not pass, including planned/taken remedial
action.
The above information must be filed with the AESO electronically in a standardized
form, available on the AESO website.
Page 34 of 59
Upon receipt of the Metering System Test Report the AESO will:
a) File the report in an AESO tracking system.
b) Issue a Request For Information to the metering system provider for any tests
that have failed. The information requested by the AESO may vary depending
on the nature of the failure described in the Metering System Test Form.
c) File the report with the EUB.
The information described in part a) to part e) must be filed with the AESO electronically
in a standardized form, available on the AESO website. The information for part f) and
part g) may be filed in a format chosen by the metering system provider.
Page 35 of 59
Upon receipt of the Annual Metering Systems Testing Compliance Plan, the AESO will
communicate the following to the metering system provider and the EUB no later than
March 1st:
a) Conditions or requirements not met in the submitted Annual Metering Systems
Testing Compliance Plan.
b) Acceptance of the Annual Metering Systems Testing Compliance Plan as any
conditions and requirements identified in a) are met.
c) A summary of Metering Systems from the previous calendar year that were not
tested in compliance with either Appendix 5 Section 1 or 2.
Page 36 of 59
With respect to the in-situ test records for metering systems a Metering System
Provider must:
(a) store the in-situ test reports for a period of no less than six (6) years, and
(b) provide the AESO with a copy of any requested in-situ test reports or metering
system wiring diagrams within five (5) business days of that request.
Page 37 of 59
The provider of check metering must notify the Metering System Provider of its
intention to install check metering at least ninety (90) days prior to the installation
date and must ensure that its check metering complies with the requirements of
this Standard.
An owner of metering equipment forming part of check metering must notify the
Metering System Provider of any transfer of its check metering to another
affected party.
The Metering System Provider who owns or controls the site at which the
metering point is located must co-operate with any affected party connected at
that metering point wishing to install check metering at that site.
The Metering System Provider who owns or controls the site at which the
metering point is located has the right to remove from service the check metering
causing physical problems with the measurement system metering equipment.
The Metering System Provider must notify the affected party as soon as
reasonably possible that the parties equipment has been removed from service.
The Metering System Provider who owns or controls the site at which the
metering point is located must install, operate and maintain the check metering
equipment for the affected party and charge all reasonable costs to the affected
party.
The Metering System Provider and the affected party must have an agreement
for all costs prior to commencing any check metering work.
Page 38 of 59
FILE FORMAT
The daily system measurement files, as sent from the Metering Data Providers to
the Data Centre, must have the format as described in schedule B.6.2.4 System Level
Measurement Data Provision of the Settlement System Code.
Notes:
1. All measurement data must be transferred as fifteen minute interval data
regardless of the interval at which it may have been metered, recorded or
aggregated.
2. Measurement data (zero or non-zero) must be transferred for every interval of
every hour of every day for all active measurement points.
3. There should only be 96 records per day per measurement point transferred on all
days that are not also days on which DST time changes take place. There should
be 92 records (in 23 hours) transferred per measurement point on the spring DST
time change day and 100 records (in 25 hours) transferred per measurement point
on the fall DST time change day.
4. The term "net energy" implies the difference between the amount of energy transfer
that took place in one direction at a measurement point in a particular fifteen
minute interval and the amount of like energy transfer that took place in the
opposite direction at that same measurement point during the same fifteen minute
interval.
5. The naming of daily files will be as described in schedule B.4.2 File Naming
Convention of the Settlement System Code.
6. The MWh and MVARh source flags are defined as follows:
M: The value is derived from metered data only (normal condition).
E: The value is derived, in whole or in part, from estimated data due to the
failure of a metering system or data system (abnormal condition).
Page 39 of 59
For non-business days, the daily schedule may be postponed to the first
business day following the non-business day(s). Any Metering Data Provider
choosing this option will provide a daily file for the previous day and for each
postponed day.
Monthly
A Metering Data Provider has the option to provide the previous month's
reconciled measurement data to the Data Centre; however, this measurement
data must be received by the Data Centre Provider by 23:59 on the 7th
business day following the last day of the month to be settled, as described in
section 4.4.3 (A)Initial Monthly Settlement of the Settlement System Code
After the 8th business day, changes to the measurement data will be accepted
only by exception and approval of the Measurement System Provider.
Page 40 of 59
V2E2 OVERVIEW
Start
Validation
Validation
failed No
?
Yes
Verification
Validation
failure No
valid
?
Yes
Estimation
&
Editing
Stop
Page 41 of 59
Page 42 of 59
VALIDATION
Start
Quantity
validation
No
passed
?
Quality Validation Tests
Compulsory
Maximum Transfer Capacity Yes
Optional
Unusually High Peak
Quality
Unusually Low Load Factor
Validation
Zero Interval
Testing
Interval Step
Demand Limit
Energy Limit
Load Factor Limit
Voltage Unbalance
Other MDP Tests
Quality
validation
No
passed
?
Yes
Stop
Page 43 of 59
Page 44 of 59
VERIFICATION
Start
Investigate the
failed validation
test result(s) and
assess the validity
of the validation
failure.
Validation
failure No
valid
?
Yes
Validation Validation
Failure Failure
Valid Invalid
Validation Failure
Document the Invalidity
validation failure Acceptance
invalidity and Documentation
acceptance.
Stop
Page 45 of 59
Start
No
No
No
Fully document
the estimation/ Estimation/Editing
editing process Documentation
and data required
to create the edit
data file.
Stop
Page 46 of 59
Start NOTE:
The MPDR (Measurement Point Definition Record)
process for the addition or modification of a
measurement point that is required as the result of
changes to one or more physical metering systems
begins when the AESO authorizes either:
MSP provides the AESO No y the addition of a new transmission system facility
with an MSLD. which can include, but is not necessarily limited
to, any one of the following events:
y the construction of a new transmission to
distribution system substation (POD), or
MSLD y the interconnection of a new generation
acceptable facility to the transmission system (POS), or
? y the construction of a new interconnection
with a nieghboring transmission or
distribution control area (POI), or
y the creation of an ISD that requires new or
Yes modified metering points
y the modification of a transmission system facility
which can include, but is not necessarily limited
AESO (re)drafts an MPDR
to, any one of the following events:
based upon the MSLD and
y the addition/removal of a distribution feeder
any specific technical and/or
in a transmission to distribution substation
commercial terms that may
where feeder metering is being used to
be applicable to, or included
provide metering data for a measurement
as part of, the agreemeent
NOTE: point, or
between the AESO and their
This is a continuous revision y changes to a transmission substation
Customers/Participants.
process that must be No configuration that result from permanent
completed before any end- switching or reconfiguration operations, or
to-end testing can be carried y the installation of new metering points to
out on the measurement AESO provides a copy of the replace those formerly used for
point or underlying metering draft MPDR to the MSP and measurement point calculation purposes
points. MDP associated with the
new/modified measurement
point to which the MPDR
applies.
MPDR
finalized
?
Yes
NOTE:
An MSLD (Metering Single Line Diagram) is a AESO provides a copy of the NOTE:
standard electrical facility single line diagram that final MPDR to the MSP and At this point, the AESO,
indicates, all metering systems included within MDP associated with the MSP and MDP all have a
the scope of the facility, the: new/modified measurement final MPDR and end-to-end
y CT location and polarity point to which the MPDR metering/measurement point
y PT location and polarity applies. testing can commence.
y METER make/model
y CT/PT interconnections with METER and
any non-revenue metering equipment Stop
y RECORDER make/model (if applicable)
y TOTALIZER make/model (if applicable)
y pulse output connections between all
meters, totalizers and recorder (if
applicable)
Page 47 of 59
Start NOTE:
The MPDR (Measurement Point Definition Record)
process for a measurement point that is being added/
modified where such addition/modification is NOT the
result of any physical metering system changes can
only be initiated by the AESO and may include, but
AESO (re)drafts the MPDR not necessarily be limited to, any one of the following
based upon the existing events:
MSLD and any specific y a single POD being split
commercial terms that may y multiple PODs being combined
now be applicable to, or y loss compensation requirements
included as part of, y the consolidation of one or more existing
NOTE: agreements between the measurement points through an Industrial
This is a continuous revision AESO and their Customers/ System Designation application where no new or
process that must be No Participants. modified metering points are required
completed before any end-
to-end testing can be carried
out on the measurement
point. AESO provides a copy of the
draft MPDR to the MSP and
MDP associated with the
new/modified measurement
point to which the MPDR
applies.
MPDR
finalized
?
Yes
NOTE:
An MSLD (Metering Single Line Diagram) is a Stop
standard electrical facility single line diagram that
indicates, for all revenue metering systems
included within the scope of the facility, the:
y CT location and polarity
y PT location and polarity
y METER make/model
y CT/PT interconnections with METER and
any non-revenue metering equipment
y RECORDER make/model (if applicable)
y TOTALIZER make/model (if applicable)
y pulse output connections between all
meters, totalizers and recorder (if
applicable)
Page 48 of 59
Start NOTE:
The MPDR (Measurement Point Definition Record)
process for deleting a measurement point can only be
initiated by the AESO.
Stop
Page 49 of 59
Page 50 of 59
Page 51 of 59
1 Activation date: This date is when the MPDR comes into force, this date is
based on any one of three things:
• The energization of the equipment that the MPDR refers to
• The starting date of the contract that the MPDR has been written to reflect
• The start of a contract that required changing the name or a change in the
metering arrangement that is currently in place.
2 Measurement Point (MP): The Measurement Point refers to two parts of the
MPDR:
MPID: This MPID is the identifier used by the AESO for billing purposes
Name: This is the name of the substation or facility that the MPDR refers to,
usually the name given to a facility or substation by the contract holder.
POD: Point of Delivery. Where the electricity flows out of the Transmission
system to meet load.
4 Contract Holder: This indicates the company or entity that has signed a contract
with the AESO (usually the owner of the facility) to buy and/or sell electricity.
5 LSA: Load Settlement agent. This indicates which company the contract holder
has arranged to settle the financial details of this measurement point.
6 MDP: Meter data provider. Indicates the company that is responsible for collecting
and transporting the data collected from revenue meters to the AESO.
7 Capacity: Indicates the capacity of the contract for either supply or demand that
has been signed with the AESO. This number should be expressed as the MW value of
the contract that has been signed with the AESO
Page 52 of 59
These criteria will be used in the development of AESO functional specifications as well
as the PPS of the TFOs.
(a) Revenue Metering is applied to two types of distribution circuits which can be
classified as Urban and Rural. Urban circuits have lumped metering, i.e. the
revenue metering is located on the secondary of the transformer which in turn feeds
one or more feeders. Rural feeders cover a large geographic area and
consequently require individual circuit metering, i.e. revenue meters are applied to
each circuit.
(b) New 25 kV feeders require Measurement Canada approved revenue class metering
equipment as per the AESO’s current revenue metering standard.
(d) Changes to dispensated equipment (CT’s and PT’s) on existing 25 kV feeders is not
required where the CT’s and PT’s are subject to the Measurements Canada
dispensation obtained by the AESO and the equipment is functioning as designed.
The use of existing dispensated (CT’s and PT’s) equipment is encouraged.
(e) Existing 25 kV feeders will only have metering equipment (CT’s and PT’s) replaced
where the existing metering equipment has failed and will be replaced in kind.
That is, a failed dispensated CT or PT will be replaced by a dispensated CT or PT.
Where this is not possible or practical, the AESO will give consideration to replacing
the failed metering equipment with Measurement Canada approved equipment.
The equipment owner will contact the AESO only for those cases where the
metering equipment can not be replaced with like equipment.
(f) Individual feeder metering shall be installed at all new Rural substations. Individual
feeder metering may be applied to Urban feeders where the TFO requires such
metering. Substation totalized metering will be achieved through the Measurement
Point Definition Record (MPDR) and a virtual metering point.
Page 53 of 59
(g) All metering equipment on new feeders must be revenue class. Metering
equipment must comply with Measurement Canada standards and be maintained
by the TFO in accordance with those standards.
(h) The AESO will review metering replacements as contained in the TFO’s PPS on a
case by case basis.
Page 54 of 59
APPENDIX 11 DEFINITIONS
“accuracy class”: The upper limit of error demonstrated when a meter or instrument
transformer is tested in accordance with this Standard.
“Act”: The Electric Utilities Act (Alberta) as amended from time to time.
(b) any Metering Service Provider who provides metering services that affect,
or have the potential to affect, the measurement data, or
(d) any Data Recipient who uses the measurement data for financial settlement
purposes.
“business day”: A day other than a Saturday, a Sunday, a statutory holiday in the
province of Alberta, or a Monday when a statutory holiday occurs on a Saturday or
Sunday and the following Monday is a day during which financial banking privileges are
suspended.
“check metering”: In relation to a metering point, a metering system provided for that
metering point in accordance with Appendix 6 of this Standard.
“data centre”: All the computer and communications related equipment and systems,
that are not part of either a metering system or a data system, necessary to provide
data centre services.
“Data Centre Provider”: The person who is, by virtue of a data centre services
agreement, accountable for the provision of data centre services.
“data centre services”: All services related to the operation of the data centre
necessary to meet the requirements of this Standard.
“data centre services agreement”: An agreement between the AESO and the Data
Centre Provider that defines the applicable metering points and measurement
Page 55 of 59
points along with the terms and conditions of service related to the provision of the
associated data centre services.
“Data Recipient”: Any person who has a measurement services agreement with the
AESO.
“data system”: All the computer and communications related equipment, that is not part
of either the data centre or any metering system, required to collect and process
metering data from one or more metering systems and transfer the metering data or
the resultant derived measurement data to the data centre.
“Electricity & Gas Inspection Act”: The federal Electricity & Gas Inspections Act and
Regulations.
“daily system measurement file”: An electronic data file, containing metering data
and/or measurement data arranged in a pre-defined format, that is transferred from a
Metering Data Provider to the Data Centre Provider.
“in-situ test”: A test made on equipment that is still installed at the site where it
normally operates.
“interval data”: A data set consisting of one or more records where each such record
contains, as a minimum:
(a) the volumes of one or more energy metrics that have accumulated over a
common specific interval, and
Page 56 of 59
(a) for each metering system there exists one, and only one, related data
system, and
(b) for each data system there exists at least one related metering system.
“meter”: The apparatus which measures active energy or reactive energy or both,
including any internal recorder, remote communications equipment, clock or current
or voltage transformers which are normally tested as a part of the apparatus.
“Metering Data Provider”: A person who is, by virtue of a metering data services
agreement, accountable for the provision of metering data services.
Page 57 of 59
“metering data services”: All services related to the operation of the data systems
necessary to meet the requirements of this Standard.
“metering system”: All the metering equipment required for the measurement and, if
applicable, remote storage of the active energy and reactive energy interval data for
a single metering point.
“metering system services”: All services related to the design, installation, operation
and maintenance of the metering systems necessary to meet the requirements of this
Standard.
“Mountain Standard Time”: The mean time at the 105th meridian of longitude west of
Greenwich, England.
Page 58 of 59
“reactive energy”: The power which performs no useful work, but which periodically
shifts back and forth between the generator and the magnetic or dielectric field.
Expressed in units of varhours (VARh).
“reading”: In relation to a meter, means the record made or quantity displayed by that
meter of active energy or reactive energy transferred in a particular direction at a real
metering point during a particular period of time.
“real metering point”: The physical point of electrical connection of the primary circuit
of a current transformer that forms part of the metering system used to measure the
active energy or reactive energy transferred through that point.
“recorder”: An apparatus that stores interval data records obtained through a direct
internal or external connection to a meter that allows such interval data to be retrieved
at a future point in time.
“time-stamp”: A record of the date and time of an event in a format as defined by this
Standard.
“virtual metering point”: An effective point of measurement, that may or may not be
physically locatable, where active energy or reactive energy deemed to have been
transferred through the point is derived from an algorithmical manipulation of the active
energy and reactive energy data of one or more metering points.
“written notification”: Includes any written notice delivered via letter mail, courier,
facsimile or email.
Page 59 of 59