CONSTRUCTION COST BREAKDOWN SHEET FOR


A 2 STOREY BUILDING WITH
SIX UNITS OF 2 BEDROOMS FLAT

MATERIAL / LABOUR COSTS

Unit Quantity
Description/Items Total
No price

DECKING SECTION B
1 Cement 4,650 200 bags 930,000.00
/ stone (chippings)
3 "
2 4 350,000 for 25tons 100 tons 1,400,000.00
3 Sharp Sand 38,000 6 trips 228,000.00
4 1 x 1 x 12 board (mid west) 1,650 ??? ???
5 2 x 2 x 12 h/w puline 300 150 pcs. 45,000.00
6 2 x 4 x 12 h/w rafter 950 20 pcs. 19,000.00
7 Bamboo 700 250 175,000.00
8 2" nail 13,500 1 bag 13,500.00
9 3" nail 13,500 2 bags 27,000.00
10 16mm iron rod (deformed) 7,350 86 lengths 632,100.00
11 12mm iron rod (deformed) 4,150 312 lengths 1,294,800.00
12 8mm iron rod (deformed) 2,100 80 lengths 168,000.00
13 Binding wire 800 60 kg 48,000.00
14 Transportation ???
15 Loading & Offloading ???

Total costs for Material N4,980,400.00

Balance N500,000.00

T0TAL SUM N5,480,400.00