EPM Exam Questions
EPM Exam Questions
EPM Exam Questions
Gautam realized that the customer wanted the job completed in less time. After discussions with the functional
managers, Gautam developed the table shown below:
Next we can crash either C or F with same crash cost of $3000. Let's crash
activity C by 1 week. Crash cost is $3000. New project duration is 10
weeks. Critical paths are A-C-E-F, A-D-E-F and A-B-F
- Next we will crash activity F which is common activity among A-C-E-F and A-D-
E-F. Crash activity F by 2 weeks. Crash cost is $3000*2=$6000.
New project duration is 8 weeks.
Critical paths are A-C-E-F, A-D-E-F and A-B-F.
- Next we will crash activity C, D, B by 1 week.
Crash cost is 1000+1500+3000=5500.
New project duration is 7 weeks. Critical paths are A-C-E-F, A-D-E-F and A-B-F
We cannot crash any further.
a. Since minimum project duration is 7 weeks. So there will penalty of $5000.
Total crash cost = 5500+6000+3000+2000+1500 = $18000
Hence, minimum amount of additional funding that Arnie should request =
5000+18000 = $23,00
The baseline (PV) is the sum of the cost accounts, and each cost account is the
sum of the work packages in the cost account. What all costs are included in the
baseline?
Ans :
Planned value is the approved budget you apply to an activity or work breakdown
structure (WBS) (WBS). A management reserve is not included in this budget.
The planned value is distributed over the course of the project in stages. Though
intended value only describes the actual labor you've done at a specific moment
in time.
The budget at completion (BAC), performance measurement baseline (PMB), and
budget at completion (TPV) are additional terms for the overall project value
(BCWS).
The cost baseline is a critical factor, but it can also be used to evaluate cost
performance, cost variance, and planned versus actual effort. Without a baseline,
there is no way to compare your expenditure to and manage costs. When
managing a project, there are few things more critical than cost management.
Estimating the entire project expenses is the first step in developing a cost
baseline. These tasks and the tools required to complete them are included. Task
by task is the simplest approach to accomplish this. Add up all of the costs,
including labour, materials, etc.