The necessity of qualifying an autoclave and validating the sterilization process arises from various laws and
regulations. Although the terms qualification and validation are usually mentioned
The necessity to qualify an autoclave and to validate the sterilization process comes from, among other things,
the Medicines Act, the Medical Devices Act, the Chemicals Act, and the Ordinance on the Protection of
Biological Substances and Genetic Engineering. These laws and regulations sometimes refer to directives,
rulings, or decisions of the commission, guidelines, and standards. By referring legally binding EU regulations
to legally non-binding standards or guidelines such as the EU-GxP guidelines for
A requirement of the principles of good laboratory practice is that equipment, including validated computer-
aided systems used to collect, record, and reproduce data and to control the environmental conditions relevant to
the test, must be of adequate design and performance. If your autoclave is directly involved in studies on the
above-mentioned product groups, its suitability in terms of design and performance must be proven. In detail,
the supervisory authorities will define the requirements for qualification and validation implementation and
documentation in more detail by specifying standards, guidelines, etc. or they may follow standards because the
standardisation also moves within certain limits.
With such importance placed on the autoclave how can the user be certain that it has achieved the
required sterilization?
As an autoclave operator involved in your manufacturing process – or as a laboratory operator – you are
responsible for your manufacturing process or for the results and conclusions of your study. Qualification and
validation is often carried out with the help of an appropriately qualified service provider. Since only you can
define the product-specific requirements for your process, close cooperation between your specialist
departments, the qualifier/validator, and the autoclave manufacturer is necessary.
Although the terms qualification and validation are usually mentioned in one sentence or even used
synonymously, different statements and approaches are hidden behind them. The common denominator of both
concepts is that documents conforming to the guidelines, which contain the definition of the individual tests and
the documentation of the test results, must be prepared. In many cases, the written qualification/validation plan
also includes protocols that are used to document the test results during implementation.
Qualification: In the context of a system qualification, proof must be provided that a system with the
technology used is suitable for the intended task, works perfectly, and delivers results that meet the
requirements. The main focus here is therefore on the system (the autoclaves) and its correct function.
Validation: The objective of process validation is to prove that the process is effective and can deliver a
product (result) that is reproducible and meets the required quality require
ments. The main focus is therefore on the process itself and proof
of compliance with the acceptance criteria that is to be defined by the system operator.
The process qualification is often a process that takes place within a system, which explains the linking of
terms. The qualification and validation process is illustrated in Figure 2.
DQ – DESIGN QUALIFICATION
The first qualification stage of an autoclave starts as soon as you formulate and document your requirements for
the device to be purchased. This means you have already created your User Requirement Specification (URS);
i.e. the requirements that are made of a device and which must be fulfilled. For many manufacturers, autoclaves
can be equipped with options that influence process accuracy or speed, for example. If certain options
depending on the processes to be carried out are not taken into account in the URS, and if they are not upgraded
according to the device, this can make successful qualification and validation considerably more difficult or
even completely impossible later on. Even at this early stage, future operators should therefore specify exactly
what the autoclave is to be used for, what requirements are to be placed on the processes, and which standards
and guidelines must be observed.
Depending on the complexity of the system or the autoclave, the scope of the URS will vary greatly. Autoclave
suppliers will submit an offer on this basis and, in coordination between the operator and manufacturer,
specifications will be drawn up. Checking for conformity is an elementary component of the first qualification
level – the Design Qualification (DQ). After a successful DQ, the device is manufactured by the manufacturer
according to the agreed specifications. At the same time (either internally, with the manufacturer, or with a
separate service provider), preparing the documents required for the subsequent steps IQ, OQ, and PQ
(validation plan) can now be started. These documents form the basis for implementing the IQ, OQ, and PQ and
specify the inspections and tests to be carried out as well as their parameters and acceptance criteria. Detailed
documentation is required to prove that all checks and tests have been successfully completed.
IQ – INSTALLATION QUALIFICATION
After the design qualification has been successfully completed and the device has been successfully delivered,
the next qualification stage of the autoclave can begin on site – the installation qualification (IQ). The suitability
of the installation site, the physical characteristics of the supplied autoclave, as well as the completeness of the
documentation belonging to the device are now checked and documented in the qualification documents.
Documentation generally includes the operating instructions, maintenance, cleaning, and calibration instructions
as well as material certificates and data sheets for individual installed components.
If this qualification level has also been successfully completed, or if any deviations that may have been detected
have been evaluated on the basis of a risk analysis and appropriate measures have been initiated to eliminate
them, the functional qualification (OQ) of the system can be started.
OQ – OPERATIONAL QUALIFICATION
Proof is now provided that the devices, installations, utilities, and systems meet the requirements and
specifications of the operator, which were specified within the scope of the design qualification. Tests are
carried out to prove that the device is working according to plan. This includes calibration as well as simulating
fault, interference, and shutdown conditions of the device. This procedure serves as documented proof that
defects which may be safety-relevant or quality-influencing for the product are correctly detected by the
autoclave.
Implementing sterilization runs of the autoclave without introduced product is also part of the scope of the
functional qualification. Temperature sensors and a pressure sensor are inserted into the autoclave for this,
which use a data logger to measure pressure and temperature independently of the autoclave controller. The
temperature and pressure values determined in this way can thus be checked against the values determined via
the autoclave control. In addition, bioindicators based on Bacillus stearothermophilus are introduced into the
autoclaves to prove the biological effectiveness of the sterilization process. The aim is to provide documented
proof that a system or device is suitable for its intended use without a product.
Minimum loading,
Medium loading,
Worst case loading.
Worst case loading absolutely must be checked with regard to the loading quantity, for example. Other
parameters may need to be considered if they could influence the result of the sterilization process.
As with the OQ, the sterilization process is checked by temperature and pressure sensors which record the
corresponding data independently of the autoclave control by means of a data logger. In addition, the biological
effectiveness of the sterilization process is also demonstrated by reference indicators based on Bacillus
sterothermophilus. In the PQ, unlike in the OQ, the temperature sensors as well as the bioindicators are placed
in the product to be tested (loading pattern) in order to provide proof of the sterilizing effectiveness in the
product. It is important that the temperature sensors as well as the bioindicators are placed in the points of the
product where it is expected that a sterilizing effect is most difficult to achieve. The aim is documented proof
that a process can reproducibly deliver the expected result taking the product into account.
When performing the OQ and PQ, the number of temperature measurement points within the working chamber
should comply with the recommendations of the relevant standards such as EN 556 or the GxP guidelines, as
any deviation from these will probably lead to queries during an inspection. 12 temperature measuring points
should therefore be provided per 1 m3 of sterilization chamber. A bioindicator based on the Bacillus
stearothermophilus is placed at each temperature measuring point.
Re-Validation
If all qualification steps and the process validation(s) have been successfully completed, the operator must
specify an interval for re-validation. It is a good idea to coordinate with the autoclave manufacturer at this point,
as it makes sense to combine the re-validation with the necessary recurring calibration of the instrument
sensors.
Caution is required when changing process parameters. This includes, for example
Since changes can also occur gradually, i.e. barely or even not at all noticeably, re-validation should always be
carried out at fixed intervals. An interval of one year has been proven here. For particularly critical processes,
however, the interval for re-validation can also be defined at shorter intervals.