Lacerda 2017
Lacerda 2017
Lacerda 2017
Fig. 1. Conventional system topology of a PV plant feeding a dc industrial Fig. 2. Proposed solution of a PV plant directly feeding an industrial process
process. with dc.
efficient in comparison to the commercial option available, The inverter is replaced by a dc/dc converter with higher
consider Fig. 3 (a) where an example of industrial system is efficiency, and the generated power is directly feed into the
shown. The process load demands the equivalent to a 100% dc process. The total demand from grid is 75.8%, which
power, and it is fed by a grid-connected transformer and a means that the total losses in the system are 5.8%. In addition
rectifier. The efficiency of such equipment can vary to a decrease in demand from the grid, there was a reduction
depending on the rated power and the operation conditions, of 35% of total losses in comparison to the typical
but for the sake of this example, it will be considered commercial solution.
respectively 98% and 95%, which are typical values for these Although just illustrative and with arbitrary values, the
devices. Knowing that the PV system is not connected, then example stated shows that the proposed solution can promote
the total power demanded from the grid is 107.4%, which a significant benefit in terms of total system efficiency. It is
means that a total of 7.4% of power is lost due to the worth saying that if the efficiencies considered or the total
transformer and the rectifier (conduction losses neglected). PV system production were different values, then the
Consider now the situation illustrated in Fig. 3 (b), where a reduction of 35% in losses could be a different value.
PV system with instant power generation of equivalent 30% However, the total losses would still be lesser in the proposed
is connected to the grid through a 95% efficiency inverter solution, due to the use of lesser conversion devices.
(typical commercial solution). In this situation, the power Other studies in the literature had suggested similar
generated by the solar plant is fed to the process in ac, solutions for this problem, but in different contexts. Some
reducing the demand from the grid to 78.9%. Given that the articles have mentioned the use of PV energy to feed loads
generated power is 30% and the load consumption is 100%, directly in dc, but as a variation of a particular converter
then there was 8.9% of total losses. Despite the demand from topology or in a microgrid [2], [3], [4], [5], [6]. Others
the grid had largely decreased with the PV generation, the suggested the feeding of dc loads directly from PV systems in
total losses have actually increased, due to the addition of the standalone applications [7], and some even considered small
inverter. scale electrolysis processes [8], [9].
Then Fig. 3 (c) shows the solution proposed in this paper. As per the present paper, what is being proposed is an
alternative use of a well-known converter topology, in a real have large rooftop areas and underused land, such as inactive
industry application, and to feed the process in a mining areas or tailings dams, which can be employed for the
complementary way with the grid - a different approach from purpose of installing the solar panels.
all the papers referenced. The goal is to identify the benefits
and to introduce a concept that is not commercially explored III. PV SYSTEM DESIGN
yet, but have a large potential. A case study will be used to The first step on designing the PV system is the solar panel
develop the solution and to reveal the restrictions involved, selection. For this project, it will be considered a typical
and a conceptual project will be presented as a methodology polycrystalline silicon panel, easily found in the market [10].
to be followed by other large-scale real projects. Table I shows the main characteristics of this type of panel.
This work has the support of Votorantim Metais, a metal The next step consists on determining the total capacity of
company that is investigating the feasibility of such systems the PV plant, therefore, the amount of solar panels that could
in order to apply its concepts in a real electrolysis plant. be installed in the available area. In contrast with rooftop
installations, where almost all the space available is used
II. CASE STUDY directly to install panels, in large areas where the panels must
In order to assess the proposed concept, a case study will be installed on the ground a significant part must be let
be carried out. A fictitious industrial plant will be considered unused. This is due to the need of space for circulation of
and, although it is not real, the parameters were chosen to maintenance personnel and vehicles, and also to guarantee
represent a good approximation of the values found on real that the panel sets will not shade each other depending on the
operating plants. The same decisions and restrictions taken irradiation angle. Only a detailed project that takes care of
care in this case study can be used later on a real these specific restrictions of the site could then determine the
implementation, therefore it can be seen as a project exact proportion of the total area that could be used directly
methodology. for installing panels.
The industrial plant has an electrolysis process and its In order to simplify this analysis, some inferences were
electrical system consists of a grid-connected transformer made over an NREL report regarding land-use requirements
feeding a thyristor rectifier. The output current of the rectifier for solar energy in the United States [11]. The objective was
can be regulated by controlling the gate firing angle, and its to find a typical ratio of the area effectively occupied by
value is determined by the process in order to achieve the panels, over the total PV plant area. Although the report does
best performance of the metal production. Likewise, the not mention this factor directly, after a few assumptions, it
output voltage of the rectifier is determined by the was concluded that it lies in the range from 31% to 58%. For
electrolysis cell voltage, which varies depending on the cell the purpose of this case study, it will be assumed that the
area and the material being produced, although it remains effective PV panels area correspond to 50% of the total area,
approximately stable during regular operation. The rated a ratio that seems reasonable in comparison to the data
output values are then selected as 400 Vdc and 50 kA, available in the report and also with known real PV projects.
summing up to a rated power of 20 MW. The panels presented on Table1 have the dimensions of
It will be considered also that the PV power will be 0.99 m x 1.64 m (1.62 m²). Considering that they will be
injected upstream of the current measuring point, allowing installed with a tilt angle of 20º, an assumed value for the
the rectifier to sense when the solar energy is being produced. fictitious plant latitude, it comes to a total of 16,386 panels,
By doing so, the rectifier can control the current drained from or 4.096 MW of total peak DC power capacity.
grid to reduce its value and equalize the load current in a The next decision to be made concerns on how the panels
fixed value throughout the operating cycle. It should be will be associated in sets of series and parallels. The series
mentioned that in real existing plants, where the connection connection determines the operation voltage levels, which
of a PV system upstream of the measuring point may not be from one point of view must be as high as possible, to
possible due to space restrictions, an alternative solution is to decrease conduction losses on the long cables inherent to
build a data network to inform the rectifier control system of
the solar-generated current value, allowing the rectifier to TABLE I
MAIN ELECTRICAL CHARACTERISTICS OF THE PV PANEL
actuate reducing its drained current as well. There will be no
need of a battery bank since all the power will be instantly Description Symbol Quantity Unit
used in the process. Maximum power Pmax 250 W
Lastly, it is assumed that the industrial plant has an area of Open-circuit voltage Voc 37.6 V
50,000 m² available to be used for the installation of the new Short-circuit current Isc 8.92 A
Voltage at Pmax Vmp 29.8 V
PV system. This assumption is likely to occur in real world Current at Pmax Imp 8.39 A
plants due to the fact that companies that performs Efficiency PCE 15.4 %
electrolysis (generally Mining and Metals companies) often
a single Buck, the process current was also reduced to 1/60 of decreases the current drained from grid when it senses that
the total rated 50 kA (833.33 A). Fig. 6 illustrate the results the total load current is exceeding its maximum value.
obtained, where the temperature was set fixed in 25ºC.
In the upper graphic of Fig. 6 it can be seen that as the V. LOAD CURRENT STABILITY
irradiance varies throughout the day, the power output tends One main aspect regarding the application suggested in
to accommodate in the maximum value possible. In this paper is the stability of the load current. As briefly
particular, when the irradiance is 1,000 W/m² (nominal described before, such processes need the load current to be
condition), then the power output sets in approximately 67.5 as stable and accurate in the target value as possible, since
kW, the expected rated power in dc side. This shows the this will affect the productivity and the quality of the material
implemented MPPT algorithm is working accordingly. It is being produced. Hence, the inherent variance in output
worth to mention that for the simulation the converters and current from the PV plant must be accommodated by the
cables were considered lossless, as the simulation had the regular current control, originally designed for the process (e.
purpose of verifying the solution technically and not to make g. in Fig. 5, the control performed by the thyristor rectifier
an efficiency assessment. together with the current measurement).
As per the lower graphic in Fig. 6, it shows that the load This variation is due to the fact that the MPPT technique
current is keep steady even when the irradiance and the PV forces the PV system output to follow as closely as possible
current raises. This is due to the rectifier current control, that the irradiance, seeking to extract the maximum power of a
given condition. That combined with a windy and cloudy
weather can provoke high di/dt. As an example, Fig. 7 shows
an experimental measurement of a PV array of 8.11 A rated
current during one day of operation (out of a set of hundreds
of days). The highlighted line shows the highest di/dt
registered for that day, a 6.5 A rise during 5 minutes, which
represents about 80% of the rated current. Although this data
only represents a particular event for a single PV plant, it
shows that the PV output can have a substantially high di/dt
in some extreme conditions.
On the other hand, such industrial processes will have a
current control system with a limited di/dt, usually due to the
technology employed in the converter. This must prevent the
PV plant to achieve any power capacity desired, since the
effects of the weather condition cannot overtake the
maximum di/dt tolerated by the process. In order to illustrate
this limitation, Fig. 8 shows the behavior of an example
Fig. 6. Simulation results: (a) Irradiance and PV output and (b) current from electrolysis plant that is commanded to reduce its output
the converter, from the grid and applied to the DC load, during a irradiance current. The control system limits the decay ratio, reaching
variation. its target value after about some time.
ACKNOWLEDGEMENTS
Fig. 8. Example of the real current output on an electrolysis process after a
change in the desired control setpoint by the operator. The authors would like to thank the financial support from
These two limitations must then be used to calculate the the Brazilian federal government agencies CAPES and
CNPq, the Minas Gerais state government agency FAPEMIG
maximum power capacity of a PV plant directly feeding a dc
and the partner research company Votorantim Metais
industrial load. The designer of the system must investigate
(research grant no. 24985).
the process where the solar power will be injected in order to
make sure that the power variations due to weather
REFERENCES
conditions can be met by the current regulator, even if in
some cases this means the PV plant must have its capacity
[1] Kristin Seyboth, F. Sverrisson, F. Appavou, A. Brown, B. Epp, A.
decreased. Leidreiter, C. Lins, E. Musolino, H. E. Murdock, K. Petrichenko, T.
C. Farrell, T. T. Krader, A. Tsakiris, J. L. Sawin, J. Skeen, and B.
VI. CONCLUSION Sovacool, Renewables 2016 Global Status Report. 2016.
[2] H. Elfeqy, M. Shahin, A. Al-Rumaihi, A. Massoud, and A. Gastli, “A
This paper presents an alternative approach in terms of the highly efficient PV power system for DC MicroGrids,” in 2016 IEEE
use of PV systems to contribute in power generation for Symposium on Computer Applications & Industrial Electronics
(ISCAIE), 2016, pp. 183–188.
industrial plants. Particularly, for processes fed in dc, it was [3] N. Zhang, D. Sutanto, and K. M. Muttaqi, “A four-port DC-DC
shown that the proposed technology can promote a converter to integrate energy storage system and solar PV to supply
significant reduction in general losses, making such projects the grid and local load demand,” in 2015 Australasian Universities
Power Engineering Conference (AUPEC), 2015, pp. 1–6.
more economically feasible in comparison to the traditional [4] D. Debnath and K. Chatterjee, “A transformerless grid connected
and commercially available technology. This is especially inverter for solar photovoltaic systems having capability to negotiate
interesting for Metals and Mining companies, since they are DC loads,” in 2015 IEEE International Conference on Industrial
Technology (ICIT), 2015, pp. 2835–2840.
usually the biggest consumers of dc in the industry. [5] Aditya C, Sundararaman K, and Gopalakrishnan M, “Multiple-
The concept proposed was then used in a case study, where integrated converters for grid-connected PV systems with intermediate
its many aspects could be explored. The methodology and DC loads,” in 2016 2nd International Conference on Advances in
Electrical, Electronics, Information, Communication and Bio-
restrictions developed indicates that such projects are Informatics (AEEICB), 2016, pp. 544–548.
technically viable, even though some considerations may be [6] S. N. David, S. P. Santosh, and L. S. Narayanan, “Control Strategy for
different from regular PV plants. Simulation results Power Flow Management in a PV System Supplying DC Loads,” in
demonstrated that the procedure established can be followed 2014 International Conference on Power Signals Control and
Computations (EPSCICON), 2014, vol. 60, no. 8, pp. 1–5.
in real industrial plants. [7] U. Shah, P. Kadam, and G. Lahoti, “Control of standalone solar PV
Finally, one key aspect was addressed in order to system in varying operating conditions for DC loads,” in 2016 IEEE
guarantee the proper operation of the conjugated system: the