DAS ISLAND DEVELOPMENT – PHASE III

LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.


PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 1 of 14

ABU DHABI NATIONAL OIL COMPANY


(ADNOC)

DAS ISLAND DEVELOPMENT – PHASE III


LAND RECLAMATION AND SHORE PROTECTION

PROJECT No. 5975

INSPECTION AND TEST PLAN


SOIL IMPROVEMENT

MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 3 of 14

ACTIVITY: Soil Improvement

AREA: Das Island

LEVEL: complete fill

No. Activity / description Specification / criteria Frequency Record Inspection and Acceptance Remarks / report
CON ITL COM no.
1. Pre-PCPT BS 1377 1 PCPT in every control box (25 PDF-
x 25 m) over the entire fill progress Report conform
H H W
thickness and at least 2 meters report Attachment 1
below seabed.
2. Post - PCPT BS 1377 2 PCPT (VC: centroid and third PDF-
point / RIC: off the point and on progress
Report conform
the point) in every control box report H H W
Attachment 1**
(25 x 25 m) over the entire fill
thickness*.
3. Re-post PCPT BS 1377 1 PCPT for every failed PCPT PDF-
Report conform
(misreading, inclination, refusal) progress H H W
Attachment 1**
over the entire fill thickness*. report
4. Additional post PCPT BS 1377 2 PCPT (VC: centroid and third PDF-
point / RIC: off the point and on progress
Report conform
the point) in every control box report H H W
Attachment 1**
(25 x 25 m) over the entire fill
thickness*.
* For PCPT’s done after re-compaction of VC boxes by means of RIC for the layer above +1.6mDID, PCPT’s will only be executed to a level of +1.6mDID
** For PCPT’s done after re-compaction of VC boxes by means of RIC for the layer above +1.6mDID, additional reports shall be submitted of all full depth PCPT’s
including those showing conformance below +1.6mDID
MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 4 of 14

ACTIVITY: Soil Improvement

AREA: Das Island

LEVEL: complete fill

No. Activity / description Specification / criteria Frequency Record Inspection and Acceptance Remarks / report
CON ITL COM no.
5. Re-extra post PCPT BS 1377 1 PCPT for every failed PCPT PDF-
(misreading, inclination, progress Report conform
H H W
refusal) over the entire fill report Attachment 1**
thickness*.
6. Second chance PCPT BS 1377 4 PCPT (VC: 2 centroids and 2 PDF-
third points / RIC: 2 off the progress
Report conform
point and 2 on the point) in report W H S/R
Attachment 1**
every control box (25 x 25 m)
over the entire fill thickness*.
7. Re second chance PCPT BS 1377 1 PCPT for every failed PCPT PDF-
(misreading, inclination, progress Report conform
H H S/R
refusal) over the entire fill report Attachment 1**
thickness*.
8. 4 day soaked CBR at 100% BS1377-4, sample 1 test for every 4 control boxes
PDF-third
MDD or 95% MDD or at 90% preparation according (50 x 50 m) for the runwayparty
W H S/R Form # 17
MDD to method 4 area. inspection
report
* For PCPT’s done after re-compaction of VC boxes by means of RIC for the layer above +1.6mDID, PCPT’s will only be executed to a level of +1.6mDID
** For PCPT’s done after re-compaction of VC boxes by means of RIC for the layer above +1.6mDID, additional reports shall be submitted of all full depth PCPT’s
including those showing conformance below +1.6mDID
MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 5 of 14

ACTIVITY: Soil Improvement

AREA: Das Island

LEVEL: complete fill

No. Activity / description Specification / criteria Frequency Record Inspection and Acceptance Remarks / report
CON ITL COM no.
9. 4 day soaked CBR at 100% BS1377-4, sample 1 test for every 16 control PDF-third
MDD or 95% MDD or at 90% preparation according boxes (100 x 100 m) for all of party
W H S/R Form # 17
MDD to method 4 the reclamation area except inspection
the runway. report
10. In situ field density tests BS 1377-9:1990 1 test for every control box (25 PDF-third
x 25 m) for the runway. party
H H W Form # 15
inspection
report
11. In situ field density tests BS 1377-9:1990 1 test for every control box (25 PDF-third
x 25 m) for all of the party
H H W Form # 15
reclamation area except the inspection
runway. report
12. Maximum & minimum dry ASTM D-4253 and 10 reclamation samples (5 out PDF-third
density tests ASTM D-4254 every borrow area) before start party
W W S/R Form # 119
of compaction works. inspection
report
13. Maximum dry density tests and As per TNO-5975-025: 1 test for every control box (25 PDF-third
optimum moisture content tests BS1377-4, clause 3.7 x 25 m) for the runway area. party
W H S/R Form # 119
inspection
report
MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 6 of 14

ACTIVITY: Soil Improvement

AREA: Das Island

LEVEL: complete fill

No. Activity / description Specification / criteria Frequency Record Inspection and Acceptance Remarks / report
CON ITL COM no.
14. Maximum dry density tests and As per TNO-5975-025: 1 test for every 16 control box PDF-third
optimum moisture content tests BS1377-4, clause 3.7 (100 x 100 m) for all of the party
reclamation area except the inspection W H S/R Form # 119
runway. report

15. Particle Size Distribution BS1377-2 1 test every 4 control boxes PDF-third
(50 x 50 m) for the runway party
area. inspection W H S/R Form # 22
report

16. Particle Size Distribution BS1377-2 1 test for every 16 control PDF-third
boxes (100 x 100 m) for all of party
the reclamation area except inspection W H S/R Form # 22
the runway. report

17. Liquid Limit, Plastic Limit and BS1377-2 On samples with PSD PDF-third
Plasticity Index (Atterberg indicating more than 15% fine party
Limits) material (<63μm). inspection W H S/R Form # 18
report

MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 7 of 14

ACTIVITY: Soil Improvement

AREA: Das Island

LEVEL: complete fill

No. Activity / description Specification / criteria Frequency Record Inspection and Acceptance Remarks / report
CON ITL COM no.
18. Settlement monitoring including -Settlement plates, as  Settlement plates: 1 for PDF –
 Settlement plates per TNO-5975-017 every 100 x 100 m fill. settlement
PDF – settlement
 Magnetic probe - Magnetic  Magnetic probe report W H S/R
report
extensometers extensometer, as per extensometer: derived from
TNO-5975-027 drawing 306-REC-C-381
19. Plate Loading Test for CBR HD 25/94 and BS As requested by the PDF –
PDF – settlement
1377-9 COMPANY. settlement W H S/R
report
report
LEGEND: (Inspection and Acceptance)
CON = CONTRACTOR ITL = INDEPENDENT TESTING LABORATORY COM = COMPANY
H = HOLD FOR INSPECTION W = WITNESS INSPECTION S = SURVEILLANCE INSPECTION R = REVIEW

MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 8 of 14

Coding for Inspection and/or Test Requests (ITR)

Inspection and/or Test Requests (ITR’s) are coded in such a way that ITR’s can be conveniently compiled and it is clear which tests are involved. Requests are
made therefore and coded separately for each type of test. Some tests with same frequency and which are executed or for which samples are taken at the same
time are requested under the same ITR code. This is the case for the CBR, PSD and MDD testing where the required in situ samples are taken at the same time
and at the same location. Above results in the following ITR coding:

 For CBR, PSD, MDD the coding will be ITR-5975-CB-001 and further
 For FDT the coding will be ITR-5975-FD-001 and further
 For PCPT the coding will be ITR-5975-SI-001 and further

A special case is the runway area where the frequency of MDD sampling is somewhat higher than PSD and CBR samples, therefore the additional MDD sampling
ITR’s will be requested under: ITR-5975-MD-001 and further.

Form numbering

All the laboratory test reports have Form numbers (refer last column of the table above) as an ID. The form numbers can be found in the bottom left lines for each
test template provided in the attachments.

In addition all test reports will contain the Control Box ID of the sampling location and the code of the relevant ITR.

MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 9 of 14

Attachments

Attachment 1: PCPT Templates

A1.1 Raw PCPT data plot

A1.2 Evaluated average PCPT plot

A1.3 Evaluated centroid PCPT plot

A1.4 Evaluated third point PCPT plot

A1.5 Example of an evaluated PCPT Plot passing below +1.6mDID

MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


Cone resistance (qc) in MPa Sleeve f riction (f s) in MPa Dynamic pore pressure (u2) in MPa Friction ratio (Rf ) in %

0 5 10 15 20 25 30 0 0.1 0.2 0.3 0.4 0.5 0.6 -0.04 0 0.04 0.08 0.12 0.16 0.2 0 0.7 1.4 2.1 2.8 3.5 4.2
+6

+5

+4

+3
<- Depth in m to reference level

+2

+1

-1

-2

-3

-4

-5

-6

-7

-8

u2
Test according to BS 1377: Part 9: 1990 Predrill : 0
225 cm²
15 cm² G.L. 5.68 DID W.L.: 0 Date: 07-Sep-2011
CPTask V1.31

Project: DAS Island Phase III Cone no.: S15CFIIP.S10192


Location: DAS Island Project no.: ITR-5975-SI-0421
Position: 689254.62, 2780971.67 [E-N] CPT no.: TMMQ30PO 1/1
DAS ISLAND DEVELOPMENT − PHASE III
LAND RECLAMATION AND SHORE PROTECTION
PROJECT NO. 5975
SOIL IMPROVEMENT EVALUATIONS

BOX ID: KQW


Date: 25−Jul−2011 Test post average 1/1

Factor of safety
Cone resistance (MPa) Friction ratio (%) against liquefaction (−)

6.5

6.0

5.5

5.0 Ground level (DID +4.92m)

4.5

4.0

3.5

3.0

2.5
Elevetion DID (m)

2.0
Water table (DID +1.60m)
1.5

1.0

0.5

0.0

−0.5

−1.0

−1.5

−2.0

−2.5
Seabed level (DID −2.87m)
−3.0

0 5 10 15 20 0 1 2 3 4 0 2 4

cohesive material near cohesive material first meter

Performance line
Threshold for cohesive soil
Averaged cone resistance of Minimum FoS
TKQW10PO
TKQW10PO, TKQW30PO Calculated FoS
TKQW30PO
TKQW01PR

Test result: References:


Pass, specifications met; 100.0% of analyzed [1]. Box location drawing: 5975−VOM−VOM−GLT−076
CPT(s) meet the performance criteria [2]. Compaction requirements overview: 5975−VOM−VOM−GLT−015
[3]. Verification procedure: TNO−5975−009
Comment:
DAS ISLAND DEVELOPMENT − PHASE III
LAND RECLAMATION AND SHORE PROTECTION
PROJECT NO. 5975
SOIL IMPROVEMENT EVALUATIONS

BOX ID: KQW


Date: 25−Jul−2011 Test post individual 1/2

Factor of safety
Cone resistance (MPa) Friction ratio (%) against liquefaction (−)

6.5

6.0

5.5

5.0 Ground level (DID +4.92m)

4.5

4.0

3.5

3.0

2.5
Elevetion DID (m)

2.0
Water table (DID +1.60m)
1.5

1.0

0.5

0.0

−0.5

−1.0

−1.5

−2.0

−2.5
Seabed level (DID −2.87m)
−3.0

0 5 10 15 20 0 1 2 3 4 0 2 4

cohesive material near cohesive material first meter

Performance line
Cone resistance of Threshold for cohesive soil Minimum FoS
TKQW10PO TKQW10PO Calculated FoS
TKQW01PR

Test result: References:


Pass, specifications met; 100.0% of analyzed [1]. Box location drawing: 5975−VOM−VOM−GLT−076
CPT(s) meet the performance criteria [2]. Compaction requirements overview: 5975−VOM−VOM−GLT−015
[3]. Verification procedure: TNO−5975−009
Comment:
DAS ISLAND DEVELOPMENT − PHASE III
LAND RECLAMATION AND SHORE PROTECTION
PROJECT NO. 5975
SOIL IMPROVEMENT EVALUATIONS

BOX ID: KQW


Date: 25−Jul−2011 Test post individual 2/2

Factor of safety
Cone resistance (MPa) Friction ratio (%) against liquefaction (−)

6.5

6.0

5.5

5.0 Ground level (DID +4.92m)

4.5

4.0

3.5

3.0

2.5
Elevetion DID (m)

2.0
Water table (DID +1.60m)
1.5

1.0

0.5

0.0

−0.5

−1.0

−1.5

−2.0

−2.5
Seabed level (DID −2.87m)
−3.0

0 5 10 15 20 0 1 2 3 4 0 2 4

cohesive material near cohesive material first meter

Performance line
Cone resistance of Threshold for cohesive soil Minimum FoS
TKQW30PO TKQW30PO Calculated FoS
TKQW01PR

Test result: References:


Pass, specifications met; 100.0% of analyzed [1]. Box location drawing: 5975−VOM−VOM−GLT−076
CPT(s) meet the performance criteria [2]. Compaction requirements overview: 5975−VOM−VOM−GLT−015
[3]. Verification procedure: TNO−5975−009
Comment:
DAS ISLAND DEVELOPMENT − PHASE III
LAND RECLAMATION AND SHORE PROTECTION
PROJECT NO. 5975
SOIL IMPROVEMENT EVALUATIONS

BOX ID: MOB


Date: 29−Nov−2011 Test 2nd chance average 1/1

Factor of safety
Cone resistance (MPa) Friction ratio (%) against liquefaction (−)

7.5

7.0

6.5

6.0 Ground level (DID +5.80m)

5.5

5.0

4.5

4.0

3.5

3.0

2.5

2.0
Elevetion DID (m)

Water table (DID +1.60m)


1.5

1.0

0.5

0.0

−0.5

−1.0

−1.5

−2.0

−2.5

−3.0

−3.5 Seabed level (DID −3.67m)

−4.0

−4.5

−5.0

−5.5
0 5 10 15 20 0 1 2 3 4 0 2 4

cohesive material near cohesive material first meter

Threshold for cohesive soil


Performance line
TMOB12PO
Averaged cone resistance of Minimum FoS
TMOB13PO
TMOB12PO, TMOB13PO, TMOB32PO, TMOB33PO Calculated FoS
TMOB32PO
TMOB01PR
TMOB33PO

Test result: References:


Specifications not met; 86% of analyzed CPT(s) [1]. Box location drawing: 5975−VOM−VOM−GLT−076
meet the performance criteria [2]. Compaction requirements overview: 5975−VOM−VOM−GLT−015
[3]. Verification procedure: TNO−5975−009
Comment:
Below +1.6 mDID Pass, 100% of analyzed CPT(s)
meet the performance criteria
DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 10 of 14

Attachment 2: CBR Test Template

MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


REPORT ON CALIFORNIA BEARING RATIO TEST
Contractor : Client Ref. No :
Address : Sample certificate :
Client : Date of Sampling :
Consultant : Sampled by :
Project : Sample brought in by :
Referecne No : Date sample received :
Source : Date test Started :
Location : Date test completed :
Sampling method : Maximum dry density (Mg/m3) :
Sample size (kg) : Optimum moisture content (%) :
Lot size (m3) : Report Ref for MDD/OMC :
Lot no. :

Sample Description : Report No. :


% Retained on 20mm sieve : Report Date :
Initial Moisture content(%) : Lab Project No. :
Initial Bulk density (Mg/m3) : Lab Sample No. :
Initial Dry density (Mg/m3) : Surcharge (Kg) :
Final Bulk density (Mg/m3) : Soaking period (Hours) :
Degree of compaction (%) : Swelling (%) :
Tested by :

6
Force (kN)

Top of Sample
5

4
Bottom of sample
3

0
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
Penetration (mm)

% CBR @ 2.5 mm penetration % CBR @ 5 mm penetration Final moisture content %


Top of Specimen
Base of Specimen

Test method used : #REF!


Initial Preparation Method : #REF!
Moulding Procedure : #REF!
Test method variation : None
Remarks : None

Authorized Signatory

Form # 17 Rev 01 Rev on Jan 2009

Results relate only to the item tested.


This report shall not be reproduced except in full, without the written approval of the laboratory.
DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 11 of 14

Attachment 3: In-situ Density Test Template

MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


REPORT ON IN-SITU DENSITY TEST
Page No. 01 of 01

Contractor
Address
Client
Consultant
Project name
Project No.
Location

Ground Water Level Report No :


Weather Conditions Lab Project No :
Test Spot located by Date Test Started :
Material Description Date Test Completed :
Tested By Report Date :
Test Results
Lab Sample No
Sender's Test No.
Sender's Reference No.
Test chainage / Spot of test
Total chainage

Road No. / Location


Source of Material
Layer Ref.
Layer Thickness (mm)
Test Level (m)
Off set
Bulk Density "p" (Mg/m 3)
Moisture content "M" (%)
Dry Density "Pd"=100xP/100+M
Max. Dry Density (Mg/m3)
Optimum Moisture Content (%)
Degree of compaction (%)

Test Method : BS 1377: Part 9: 1990: Clause 2.2: Amd. 8264: 1995.
Test Method Variation : The pouring cylinder was kept on the template for pouring the sand in the hole.
Remarks : Moisture content of material determined as per BS 1377: Part 2: 1990: Clause 3.2: Amd. 9027: 1996
MDD and OMC#Provided by the Contractor
Degree of compaction calculated based on the max. dry density of material and is reported to
the nearest whole no.
Note : This test is Accredited by Dubai Accreditation Center

Authorized Signatory
Form # 15 Rev 03 Rev on April 2009

Results relate only to the items tested.


This report shall only be reproduced in full.
Any partial reproduction must be approved by the Laboratory
DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 12 of 14

Attachment 4: Plastic and Liquid limit Test Template

MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


REPORT ON DETERMINATION OF PLASTIC & LIQUID LIMIT
Page 1 of 1

Contractor : Report No :

Address : Lab project ref. :

Client : Lab Sample no. :

Consultant : Sampling certificate :

Project Name : Sampled by :

Project Location : Sample brought in by :

Source of sample : Date of Sampling :

Sampling Location : Date sample received :

Sampling method : Date test Started

Sample size (kg) : Date test completed :

Lot size (m3) : Date Reported :

Sender's No. : Tested By :

History of Material : Type of Sample :

Sample Description : Ret.on 425 um Sieve :

TEST RESULTS

Liquid Limit (%) (Clause 4.3)


Plastic Limit (%) (Clause 5.3)
Plasticity Index (%) (Clause 5.4)

Test Method : BS 1377 : Part 2 : 1990: Amd. 9027: 1996 ( Cone penetrometer )

Sample Prep Method : BS 1377 : Part 2 : 1990: Clause 4.2: Amd. 9027: 1996

Method Variation : None

Remarks : None

Form # 18 Rev 02 Rev on July 2009

Authorized Signatory

This report may not be reproduced other than in full except with the prior written approval of the laboratory.
Any amendments made to this document in any way will invalidate the report.
DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 13 of 14

Attachment 5: Maximum and Minimum Test Template

MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


REPORT ON MAXIMUM / MINIMUM DENSITY
Page : 1 of 1

Contractor :
Address : Report No. :
Consultant : Lab. Sample No :
Client name : Lab. Project No :
Project name : Sample Size ( Kg ) :
Project No. : Coordinate :
Project Location : Date received :
Sample Description : Date test Started :
Source : Date test Completed :
Sampling Method : Report Date :
Sampled by : Tested By :
Sample brought by :
Sample No : 05

Test Data

Item

No. Test Name Test Standard Test Result

1 Maximum Density ASTM D 4253 AND 4254

1 Minimum Density ASTM D 4253 AND 4254

Test method variation : None


Remarks :

Form # 119 Rev 00 Issue on November

Authorized Signatory

Results relate only to the items tested.


This report shall only be reproduced in full. Any partial reproduction must be approved by the Laboratory
DAS ISLAND DEVELOPMENT – PHASE III
LAND RECLAMATION AND SHORE PROTECTION AGREEMENT No.
PROJECT NO. 5975 115975C1
TITLE Ref. No.: ITP-5975-350
INSPECTION AND TEST PLAN REV. No. 7
Soil Improvement Date: 27 Nov 2011
Page: 14 of 14

Attachement 6: Particle Size Distribution Template

MAIN CONTRACTOR

VAN OORD MIDDLE EAST LTD – ABU DHABI


REPORT ON PARTICLE SIZE DISTRIBUTION OF SOIL
Page : 1 of 1
Contractor :
Address : Report No. :
Consultant : Lab. Sample No :
Client name : Lab. Project No :
Project : :
Project No. : Sample Size ( Kg ) :
Project Location : Lot No. :
Sample Description : Lot Size :
Source : Sample brought by :
Sender's Ref. : Date received :
Sampling Method : Date test Started :
Location : :
Sampled by : Report Date :
Project Name :

Test Data

Particle Size Distribution Test


BS 1377: Part 2: 1990 Amd 9027. 1996. CL 9.2 (Wet Sieving)

Sieve Size (mm) Passing percentage


14.000
10.000
6.300
5.000
3.350
2.000
1.180
0.600
0.425
0.300
0.212
0.150
0.075

Preparation method : BS 1377: Part 2. CL 9.2.3. Amd 9027.1996


Test method variation : None
Remarks : None
Note : This test is Accredited by Dubai Accreditation Center

Form # 22 Rev 02 Rev on April 2009

Authorized Signatory

Results relate only to the items tested.


This report shall only be reproduced in full.
Any partial reproduction must be approved by the Laboratory

You might also like