Dear Sir,
2. We undertake, if our Bid is accepted, to commence the work within Seven (7)
days of receipt of the order to commence, and to complete and deliver the
sections and whole of the works comprised in the Contract within the period
stated in the bid hereto.
3. If our Bid is accepted, we will furnish Performance Security (ies) in the form of a
Bank Guarantee to be jointly and severally bound on us, in accordance with the
Conditions of Contract.
4. We agree to abide by this Bid for the period of One Hundred & Twenty (120)
days from the last date fixed for Bid Submission and it shall remain binding upon
us and may be accepted at any time before the expiry of that period.
We confirm our agreement to treat the Bid documents and other records
connected with the works as secret and confidential documents and shall not
communicate information contained therein to any person other than the person
authorised by the Employer or use such information in any manner prejudicial to
the safety and integrity of the works.
Unless and until an agreement is prepared and executed, this Bid, together with
your written acceptance thereof, shall constitute a binding Contract between us,
but without prejudice to your right to withdraw such acceptance without assigning
any reasons thereof.
We understand that you are not bound to accept the lowest or any bid you may
receive.
Address : _________________________
_________________________
_____________________
9.01 The Bill of quantities shall be read in conjunction with the Instructions to Bidders,
General and Special Conditions of Contract, Scope of Work and Specifications.
9.02 The quantities given in the Bill of quantities are estimated quantities. The basis
of payment will be actual quantities of work indented and carried out and valued at the
rates and prices tendered in the priced Bills of quantities, where applicable and
otherwise at such rates and prices as the Engineer may fix with in the terms of Contract.
9.03 The rates and prices tendered in the priced Bill of Quantities shall include all
equipment, plant, tools, spares, labour, supervision, overheads, consumables, materials,
erection, maintenance, testing of input material delivered, profit, taxes and duties
together with all general risks, liabilities and obligations set out and implied in the
Contract and other incidentals to comply with the requirement of technical specifications.
9.04 The rates and prices shall be quoted entirely in Indian Currency.
9.05 A rate or price shall be entered against each item in the Bill of Quantities whether
the quantities are stated or not. The cost of the items against which the contractor has
failed to enter rate or price shall be deemed to be covered by other rates and prices
entered for the related items of work.
9.06 The whole cost of complying with the provisions of the contract shall be included
in the items provided in the priced Bill of Quantities and where no rates are provided the
cost shall be deemed to be distributed among the rate and prices entered for the related
items of work.
9.07 The contractor shall keep the entire carriageway neat and clean throughout the
contract period. The contractor shall maintain guard rails, railings, crash barriers,
road furniture etc. in good condition by cleaning them frequently as advised /
required by using suitable detergents/chemicals.
• The staff of the contractor shall wear safety jackets, shoes, helmets etc.
while on duty and any violation will attract a fine of Rs. 5,000/- for each
incident.
• Failure to erect safety signage or trying to carry out the works without
proper precautions/safety measures as required will attract a fine of Rs.
5,000/- for each incident.
9.08 The Tendered rate for incident Management shall include all equipment, labour,
material, consumable, tools, spares and other incidentals to comply with the
requirement of the scope of the work and technical specifications.
SECTION: VIII
DRAWINGS
SECTION: IX