Technical Minimum - R20191031
Technical Minimum - R20191031
Technical Minimum - R20191031
Notification
PART - I PRELIMINARY
1.2 These Regulations shall come into force with effect from 1st April, 2020 and
shall, unless otherwise directed by the Commission, remain in force up to
31st March, 2025 for the duration of second control period.
1.3 These Regulations shall extend to the whole of the State of Haryana.
2. SCOPE OF APPLICATION
2.1 These Regulations shall be applicable to all existing and future Generating
Companies, Transmission Licensees / SLDC and Distribution Licensees and
their successors/assignees, if any, and shall apply where the Commission
determines: -
iii) State Load Dispatch Centre (SLDC) fees and charges under section
32(3) of the Act;
v) tariff in all other cases where the Commission has the jurisdiction for
tariff determination; and
Page 1 of 128
under the first proviso to sub-section (2) of section 42 of the Act, in
accordance with the Open Access Regulations.
2.2 In case the tariff has been determined through transparent process of tariff
based competitive bidding in accordance with the guidelines issued by the
Central Government as per Section 63 of the Electricity Act, 2003, the
Commission shall adopt such tariff in accordance with the provisions of the
Act;
2.3 These Regulations shall not apply for tariff determination of renewable energy
generation projects. The tariff for such generation projects shall be
determined as per Haryana Electricity Regulatory Commission (Terms &
Conditions for determination of Tariff from Renewable Energy Sources,
Renewable Purchase Obligation and Renewable Energy Certificate)
Regulations, 2017 as amended from time to time.
3.1 “Act” means the Electricity Act, 2003 (36 of 2003) as amended from time to
time;
3.2 “Accounting Statement” for the purpose of these Regulations, shall include: -
ii) Cash flow / fund flow statement in line with the relevant Accounting
Standards of the Institute of Chartered Accountants of India;
Page 2 of 128
company or a transmission licensee or a distribution licensee or SLDC whose
tariff / charges the subject of review by the Commission;3.4 “ARR” means
Aggregate Revenue Requirement comprising of allowable Operating Expenses
(OPEX), Capital Expenditure (CAPEX) and Return on Equity (RoE) for
generation, transmission & SLDC and Wheeling& Retail supply of electricity by
a distribution licensee;
Page 3 of 128
losses within the generating unit / plant, expressed as a percentage of the
sum of gross energy generated at the generator terminals of the generating
unit / all the units of the generating plant;
Provided that AUX shall not include energy consumed for supply of power to
housing colony and other facilities at the generating station and the power
consumed for construction works at the generating station;
3.8 “availability”
ii) in relation to a generating station, for a given period, it shall mean the
average of the daily declared capacities as certified by the State Load
Despatch Centre (SLDC) for all the days during the period expressed as
a percentage of the installed capacity minus normative AUXc as provided
in these Regulations. The formula specified for the purpose shall be as
under: -
10000 DC i
Availability (%) =
N IC (100 − AUX n )
Where:
∑ = Summation from i = 1 to N;
3.9 “bank rate” shall mean the State Bank of India Marginal Cost of Funds based
Lending Rate (MCLR) of one-year tenor, prevalent at the beginning of the
relevant financial year.
3.10 “base year “means the financial year immediately preceding the first year of
the Control Period and used for the purposes of these Regulations;
ii) “transmission system” means the person who has availed of the
transmission system on payment of transmission charges determined
under these Regulations. This includes a distribution licensee, a
transmission licensee, a person who has setup a captive power plant or a
generating company including merchant power plant or a consumer
availing long-term or medium-term open access utilizing such transmission
system. Short-term open access consumers will not be treated as
beneficiaries;
iii) “SLDC” means the person who uses the services of SLDC and shall
include distribution licensee, transmission licensee, a person who has set
up captive power plant or a generating company including merchant
power plant or a consumer availing long-term or medium-term open
access.
3.14 “collection efficiency” means the ratio of total revenue realised to the total
revenue billed during the same financial year. The revenue realisation from
arrears pertaining to the same financial year shall be included but revenue
realisation from late payment surcharge and arrears pertaining to the previous
years shall not be included for computation of collection efficiency;
3.17 “control Period” means a multi-year tariff period fixed by the Commission from
time to time. The control period, under these Regulations, shall be of five
years i.e. from 1st April 2020 to 31st March 2025.
3.18 “core business” for the purpose of these Regulations, means the regulated
activities of the generating company or the transmission licensee or the
distribution licensee, as the case may be, and does not include any other
business;
3.19 “cut-off date” means 31st March of the year closing after two years of the
year of commercial operation of the project, and in case the project is
Page 5 of 128
declared under commercial operation in the last quarter of a year, the cut-off
date shall be 31st March of the year closing after three years of the year of
commercial operation;
(a) enactment, bringing into effect or promulgation of any new Indian law; or
(b) In relation to Hydro Power Plants including PSP, CoD shall be the date
declared by the Generating Company after demonstrating peaking
capacity corresponding to the installed capacity of the generating station
through successful trail run after seven days’ notice to the beneficiaries
Page 6 of 128
and scheduling shall commence from 00.00 Hrs of the day following the
day of successful completion of trial run. Additionally, the Generator shall
certify that the said generation unit fully comply with the applicable
provisions and technical standards of the Central Electricity Authority
(Technical Standards for Construction of Electrical Plants an Electric
Lines) Regulations, 2010 and Haryana Electricity Regulatory Commission
(Grid Code) Regulations, as amended and / or re-enacted.
(c) in relation of transmission system, the date from 00.00 Hrs of charging
the transmission system or part thereof to its rated voltage level or
seven days after the date on which it is declared ready for charging by
the transmission licensee, but is not able to charge for reasons not
attributable to the transmission licensee, its suppliers or contractors.
3.22 “declared capacity” or ‘DC’ means the capability of generating plant to deliver
ex-bus electricity in MW declared by such generating plant in relation to any
time-block of the day or whole of the day, duly considering the availability of
fuel or water;
Page 7 of 128
3.23 “De-capitalization” means reduction in Gross Fixed Assets (GFA) and reflected
in the Fixed Assets Register subsequent to removal of the assets as admitted
by the Commission;
3.24 “Design Energy” in relation to hydro power plant means the quantum of
energy that could be generated in a 90 percent dependable year with 95
percent installed capacity of the generating station;
3.27 “existing generating plant” means generating plants declared under commercial
operation on or a date prior to 31st March 2020;
3.28 “existing transmission system” means the transmission system declared under
commercial operation on or a date prior to 31st March 2020;
3.29 “Force Majeure’ for the purpose of these regulations shall mean the events or
circumstances or combination of events and circumstances including those
stated below which partly or fully prevents the generating company or
transmission licensee or distribution licensee to complete the project within the
specified timeline in the investment approval, and only if such events or
circumstances are not within the control of the generating company or
transmission licensee or distribution licensee and could not have been
avoided, had they taken reasonable care or complied with the prudent
practices :
b) Any act of war, invasion, armed conflict or act of foreign enemy, blockade,
embargo, revolts, riot, insurgency, terrorist or military action; or
d) Delay in obtaining statutory approval for the project except where the delay
is attributable to the project developer(s);
Page 8 of 128
3.31 “station heat rate” or ‘SHR’ means the heat energy input in kCal required to
generate one kWh of electrical energy at generator terminals;
3.32 “infirm power” means electricity injected into the grid prior to the Scheduled
COD or the date of commercial operation of a unit or block of a generating
plant whichever is earlier;
3.33 “installed capacity” or 'IC’ means the summation of the name plate capacities
of all the units of the generating plant or the capacity of the generating plant
(reckoned at the generator terminals) approved by the Commission from time
to time;
3.34 “licensee” means any person or persons granted license under Section 14 or
exempted under Section 13 of the Act including deemed licensee
3.35 “licensed business” means the functions and activities, which the licensee(s)
is required to undertake in terms of the licence granted by the Commission or
as a deemed Licensee(s) under the Act;
Page 9 of 128
3.39 “medium term transmission consumer” means a person having a medium-
term lien for a period as defined in the open access Regulations notified by
the Commission from time to time over an intra-State transmission system by
paying all applicable charges;
3.40 (a) “new generating plants” means generating plants declared under
commercial operation on a date after 31st March 2020;
10000 G i
PLF (%) =
N IC (100 − AUX n )
Where:
3.43 “project”
Page 10 of 128
water conductor system, power generating station, as apportioned to power
generation;
(d)In relation to State Load Despatch Centre means any project associated
with integrated operation of power system in the State; and
3.45 “rated voltage” means the manufacturer’s design voltage at which the
transmission/distribution system is designed to operate or such lower voltage
at which the line is charged, for the time being, in consultation with supplier
and receiver of electricity
3.47 “revenue” means the amount billed or assessed to be billed at the applicable
tariff including any fuel price adjustments in the case of a Generating
Company and in the case of distribution licensees shall be inclusive of MMC,
FSA or any other charges i.e. power factor surcharge, load / demand
surcharge etc. for sale of power.
3.48 ‘Scheduled Energy’ means the quantum of energy scheduled by the State
Load Dispatch Centre to be injected into the grid by a generating station for a
given time period;
3.49 “Scheduled generation” for any given time or time block means the quantum
of ex-bus energy scheduled by the State Load Dispatch Centre to be injected
into the grid by a generating plant.
Page 11 of 128
3.51 “State” means State of Haryana;
3.52 “State Load Dispatch Centre” or ‘SLDC’ means the centre established by the
State Government under section 31 of the Act for purposes of exercising the
powers and discharging the functions under Section 32 of the Act;
3.54 “tariff” means the schedule of charges for generation, transmission and
distribution & retail supply of electricity with terms and conditions applicable
thereto;
3.57 Trial Run or Trial Operation: Trial Run or Trial Operation in relation to a
thermal Generating Station or a unit thereof shall mean successful running of
the generating station or unit thereof on designated fuel at Maximum
Continuous Rating or Installed Capacity for a continuous period of 72 hours
and in case of a hydro Generating Station or a unit thereof for a continuous
period of 12 hours:
Provided that:
(ii) The partial loading may be allowed with the condition that average load
during the duration of the trial run shall not be less than Maximum
Page 12 of 128
Continuous Rating, or the Installed Capacity excluding period of interruption
and partial loading but including the corresponding extended period.
(iii) Units of thermal and hydro Generating Stations shall also demonstrate
capability to raise load upto 105% or 110% of this Maximum Continues Rating
or Installed Capacity, as the case may be.
3.58 “unit” unit’ in relation to a thermal power generating plant means steam
generator, turbine-generator and auxiliaries, or in relation to a combined cycle
gas based thermal power generating plant, means turbine-generator, waste
heat recovery plant and auxiliaries‘and in relation to a hydro generating station
means turbine-generator and its auxiliaries’;
3.60 “wheeling” means the operation whereby the distribution system and
associated facilities of a transmission licensee or distribution licensee, as the
case may be, are used by another person for the conveyance of electricity on
payment of charges to be determined under section 62 of the Act;
3.62 “Year” means the financial year i.e. a period commencing on 1st April of a
calendar year and ending on 31st March of the subsequent calendar year;
(a) “Current Year” means a year in which the petition for aggregate
revenue requirement or determination of tariff is to be filed;
(b) “Ensuing Year” means the year immediately following the current year;
and
(c) “Previous Year” means the year immediately preceding the current year
3.63 “Technical Minimum Schedule” in respect of State Generating Stations shall
have the same meaning as provided in Regulation 34 of these Regulations.
Words appearing in these Regulations and not defined shall bear the same
meaning as in the Act. All other expressions used herein but not specifically
defined herein but defined in the Act shall have the meaning assigned to
them in the Act. The expressions used herein but not specifically defined in
the Regulations or in the Act but defined under Haryana Electricity Reform
Act, 1997 (Act 10 of 1998) shall have the meaning assigned to them under
the said Act, provided that such definitions in the Haryana Electricity Reform
Act, 1997 are not inconsistent with the provisions of the Electricity Act, 2003.
Page 13 of 128
PART II - MULTI YEAR TARIFF FINANCIAL PRINCIPLES
4. GENERAL
4.2 The Commission shall adopt Multi Year Tariff (MYT) framework for
determination of ARR/tariff for each year of the Control Period from the
FY 2020-21 i.e. 1.04.2020.
(a)The capital investment plan and the business plan for a period not less than
the control period to be submitted by the utilities for their respective
businesses along with the MYT Petition;
Provided that to begin with, the generating companies and the licensees
may file their business plan by the end of January 2020 and the first-year
investment plan with the respective MYT Petition for the second control
period under these Regulations.
(b) The forecast for each year of the control period of the various financial and
operational parameters of ARR, based on reasonable assumptions, to be
filed by the utilities for their respective businesses;
(d) The mid-year performance review vis-a-vis the approved forecast and
variations in performance of controllable and uncontrollable items;
Provided that the Generating Company and the Licensees shall submit their
Accounting Statements / Segmented Accounts / Allocation Statement to
support their claims / assessment including reasons of variations in various
expenses, at the time of performance review / Truing-up.
(f) The mechanism for pass through of approved gains or losses on account
of uncontrollable items.
Page 14 of 128
Provided that the Commission shall apply prudence check with regard to
the following: -
vii) Merit Order scheduling of power in line with requirement and additional
revenue earned over and above the average power purchase cost on
trading of surplus power;
4.4 Tariff during the control period: The Commission shall determine the ARR for
each year of the control period and tariff for the first year of the control period
separately for Generation Company (ies), transmission licensee(s) / SLDC and
distribution licensee(s).
Page 15 of 128
4.5 The tariff applicable to each business in each of the remaining years of the
control period shall be notified by the Commission through a separate order
after taking into consideration the following: -
4.7 The tariff determined by the Commission and the directions given in the MYT
order shall be quid pro quo and mutually inclusive. The tariff determined shall,
within the time period specified in the order, be subject to the compliance of
the directions by the generating company and the licensees to the satisfaction
of the Commission. Non-compliance of the directions shall lead to such
amendment, revocation, variations and alterations in the tariff, as may be
ordered by the Commission. Further non-compliance of directions given in the
tariff order may also lead to invocation of the provisions of section 142 and
146 of the Electricity Act, 2003.
Provided the Generation Company and / or the Licensee may seek extension
in time for compliance of the directives with appropriate justification to the
satisfaction of the Commission.
4.8 The tariff determined by the Commission shall continue to be applicable till it is
modified / amended or revised by the Commission.
4.9 The norms specified under these Regulations are the ceiling norms and this
shall not preclude the generating company and/or licensee or any other person,
as the case may be, from agreeing to improved norms of operation. In case
the improved norms are agreed to, such norms shall be applicable for
determination of tariff.
5.1 The tariff for the generating company shall be determined plant-wise. Following
shall be the categorization for the existing thermal plants of State Generator
i.e. HPGCL: -
Page 16 of 128
Unit-5: 210
Unit-6: 210
2 Panipat TPS Unit 7 and 8
Unit-7: 250
Unit-8: 250
3 DCR TPS Yamunanagar
Unit-1: 300
Unit-2: 300
4 Rajiv Gandhi TPS Khedar (Hisar)
Unit-1:
600
Unit-2:
600
5.2 The generating company shall prepare its annual accounts in a manner such
that all individual plants / units are treated as separate business entity
including any new plant that may be commissioned during the control period.
5.3 The operational norms for each generating plant shall be specified unit-wise.
Therefore, the statement of account should also include the unit-wise
performance parameters for each plant.
5.4 The generating company shall file the tariff petition as per the above
categorization. All plants indicated above and the plants which may be
commissioned during the control period shall have separate interface metering
with the transmission licensee(s) as per CEA (Installation and Operation of
Meters) Regulations, 2006 as amended from time to time and, as and when
intra state ABT is implemented, different power plant, as categorised above,
shall be scheduled separately as per the intra State ABT Regulations as may
be notified by the Commission from time to time.
5.5 For the plants, if any, not covered under ABT the Commission may determine,
single part tariff based on a normative PLF.
Provided the Commission may determine tariff for hydro power projects up to
25 MW separately as per the norms specified in the HERC RE Tariff
Regulations in vogue.
5.6 ‘target / normative availability’ and ‘target / normative PLF’ shall be construed as
normative availability and normative PLF till such the time power plants are
brought under intra-State ABT framework.
Page 17 of 128
6. ARR / Tariff OF TRANSMISSION BUSINESS AND SLDC
6.1 The transmission licensee i.e. Haryana Vidyut Prasaran Nigam (HVPN) has
been notified as the State Transmission Utility by the Haryana Government as
per Section 39(1) of the Act and has also been entrusted with the operation of
SLDC. Accordingly, HVPN shall submit separate ARR for its transmission
business and SLDC business, as long as it remains under its control, as per
provisions of these Regulations.
6.2 The HVPN shall maintain separate accounts for SLDC and transmission
business. Till accounts are segregated, STU shall prepare an Allocation
Statement to apportion costs and revenues to respective businesses. The
Allocation Statement shall be considered by the Commission only if it is
certified by the Statutory Auditor/Cost Auditor and approved by the Board of
Directors of the STU, and it shall be accompanied with an explanation of the
methodology which shall be consistent over the Control Period.
6.5 The transmission tariff determined by the Commission shall comprise all or any
of the following: -
Provided that Non-Tariff Income shall include, but not limited, to Income from
rent of land/building, sale of scrap, investments/advances, rentals, supervision
charges for capital works, sale of tender/documents/advertisements etc.
Provided the existing transmission licensee / STU are able to collect and
collate sufficient data / underlying assumptions including voltage wise
transmission loss allocation factor w.r.t. distance sensitive cost of transmission
after undertaking a detailed study relating the hybrid method (PoC methodology
of CERC bringing together the marginal and average participation approach)
and load flow study including its likely impact on the beneficiaries of
transmission services along with the timelines for implementing the same.
6.7 The aggregate revenue requirement, net of deductions and other income, for
transmission business as approved by the Commission for the control period
shall be the total cost of the transmission system (ATC). The ATC shall be
recovered from all the users of the Transmission System for the respective
year(s) of the control period as per the formula specified herein.
Provided that the ATC, as determined by applying the ibid formula shall
be either:-
Or
Provided also that the base transmission tariff for short term users
including Open Access Consumers shall be determined in accordance
with the following formula:-
Where:
Page 20 of 128
6.8 Provisional Transmission Tariff
6.10 The petition for determination of provisional transmission tariff shall inter alia
include the following: -
Provided in the case the CoD is delayed beyond six months from the
date of Commission’s Order determining / approving provisional
transmission tariff, the said Order shall cease to be applicable and the
Petitioner shall be required to file a tariff petition afresh after the date of
CoD.
iv) The transmission licensee shall file a petition for determination of final
tariff transmission tariff within six months from the date of CoD based on
the audited capital expenditure and capitalisation as o the date of CoD of
the transmission project.
Page 21 of 128
7. WHEELING (PURE WIRES) AND RETAIL SUPPLY BUSINESS
7.1 The distribution licensee shall segregate the accounts of the licensed business
into Wheeling Business and Retail Supply Business and submit separate ARRs
for the respective businesses. The ARR, approved by the Commission, for
Wheeling Business, shall be an input to determine wheeling charges
recoverable from Open Access consumers and the ARR for Retail Supply
Business, as approved by the Commission, shall be considered to determine
Retail Supply tariff for sale of electricity to different categories of consumers of
the distribution licensee which will be inclusive of wheeling charges.
Provided that till such time the accounts are segregated, as per provisions of
these Regulations, the distribution licensee shall prepare an allocation
statement to apportion costs and revenues to respective business. The
allocation statement shall be approved by the Board of Directors of the
distribution licensee and accompanied with an explanation of the methodology
which should be consistent over the control period under these Regulations.
8. MYT APPROACH
8.1 Base Line values- The Commission shall determine baseline values for
various financial and operational parameters of ARR for the control period
taking into consideration such parameters approved by the Commission in the
past, actual average figures of last three years, audited accounts, estimate of
the figures for the relevant year, Industry benchmarks/norms and other factors
as may be considered appropriate by the Commission;
8.2 Control Period – The second control period under Multi-Year Tariff framework
shall be a period of five (5) years commencing from 1st April 2020.
iv) Depreciation
vi) Return on average (opening + closing) Equity for the relevant year
vii) Provision for bad and doubtful debts as may be admitted by the
Commissions subject to the ceiling of 0.5% of the account receivable as per
the audited accounts of the relevant year.
Page 22 of 128
Provided that the wheeling charges shall be net of i) Non-Tariff Income, ii)
Income from Other Business (ARR – (Non-Tariff Income + Income from Other
Business).Non-Tariff Income shall include rent from land / building, sale of
scrap, investment income, interest earned on advances to suppliers /
contractors, rental income from staff quarter / guest houses, income from
schedule of charges, income from supervision charges for capital works,
income from sale of tender documents, income from advertisements etc.
8.3.1 The method of recovery of the Distribution charges (wires business) shall
either be on the basis of energy wheeled basis (Rs. kWh / kVAh) or on the
basis of contracted capacity (Rs/kW/kVA/month) as considered appropriate by
the Commission.
8.3.2 Distribution Loss (%) / Aggregate Technical & Commercial loss (%) shall be
as determined by the Commission in the Order in the MYT petition filed by
the power utilities.
Provided that for wheeling transactions, the voltage wise wheeling loss shall
be determined by the Commission in the MYT petition filed by the power
utilities.
Provided for the above, the voltage wise technical losses shall be projected
by the power utilities based on system configuration and capital investment
plan.
8.3.3 O&M Expenses (Wires Business) shall comprise of Employees Cost, Repair
& Maintenance Expenses (R&M), Administrative & General Expenses (A&G).
Provided that between Distribution (Wires) and Retail Supply Business, the
individual components of O&M Expenses shall be allocated, based on the
segregated accounts/ allocation statement submitted by the Licensee
Provided that the ARR computed as per above shall be net of Non-Tariff
Income, income from Other Business, receipts from cross – subsidy
surcharge and additional surcharge etc.
Provided further that the prior period expenses shall be considered at the
time of truing – up on a case to case basis subject to prudence check.
However, all penalties payable by the distribution licensee arising from
Commission’s order, courts / tribunal, CGRF / Ombudsman shall not be
allowed to be recovered through ARR.
Provided that the Commission shall determine the distribution / AT&C loss
trajectory in the annual tariff Order after reviewing the actual losses
including feeder wise loss levels in the FY 2019-20 and beyond.
8.3.5 Power Procurement: The distribution licensee shall procure power from the
sources for which Power Purchase Agreement has been approved by the
Commission. The power procurement plan shall be prepared incorporating
aspects of peak support / peak shifting, ramping requirements, ancillary
services, grid security and deviation management. This shall be done by way
of including provision for Energy Storage Systems in the power procurement
plan
Provided that for any procurement from medium to short term contracts that
may be required, the distribution licensee(s) shall obtain prior approval of the
Commission with supporting data / details along with proper justification.
Provided that the power procurement plan submitted for the control period
shall comprise of quantitative forecast of quantum and cost of the unrestricted
base load and peak load demand in its licensed area. An estimate of month
wise availability of power to meet base load and peak load demand both in
terms of megawatt (MW) and Million Units (kWh). The procurement plan shall
inter-alia include action plan regarding energy conservation, energy efficiency
and demand side management.
Provided further that the power procurement plan shall also include
procurement of renewable energy or renewable energy certificate in case the
available RE Sources are not sufficient to meet with the RPO trajectory as
specified by the Commission including backlog, if any, allowed by the
Commission during the previous year(s).
Page 24 of 128
Provided that the Distribution licensee(s) shall share its power procurement
plan with the State Transmission Utility in order to maintain consistency in
the intra-state transmission system planning.
8.3.6 Power Purchase Agreement (PPA) – The Commission shall consider approval
of PPA in the light of the approved power procurement plan either u/s
section 86(1)(b) or 63 of the Act.
Provided that all such PPAs shall be submitted in the Commission with
complete documentations and adherence to the relevant guidelines and
policy. Further, no PPA / Supplementary Agreement shall be executed without
the prior approval of the Commission.
Provided that the Commission shall approve the PPA as such or with
appropriate modifications or reject the same after holding public /
Stakeholders consultation on the same and if the same is not in conformity
to the level of transparency required including competitiveness of the project
or is found to be in violation of relevant statute / guidelines, the same shall
not be admitted and rejected outrightly.
8.3.7 The O&M norms for the retail supply business shall be same as in the case
of Distribution (Wires) business.
(a) For the purpose of this Regulation, the items of ARR shall be identified
as 'controllable' or 'uncontrollable'. The variation on account of
uncontrollable items shall be treated as a pass-through subject to
prudence check/validation and approval of the Commission;
Availability Controllable
Page 25 of 128
ARR Element Controllable/ Uncontrollable
Depreciation Controllable
Page 26 of 128
ARR Element Controllable/ Uncontrollable
8.4 Norms: Commission shall determine norms for ‘controllable’ items and where the
performance of the utilities for their respective businesses is sought to be
improved upon through incentive and penalty framework, trajectory for specific
variables may be stipulated. The variations in the controllable items over and
above the specified norms will be governed by incentive and penalty framework
specified in these Regulations.
8.5 Forecast of expected revenue from tariff: The applicant shall develop
forecasting mechanism of expected revenue from tariff and charges and submit
the same along with complete supporting details, including but not limited to the
details of past performance, proposed initiatives for achieving efficiency or
productivity gains, technical studies or secondary research and contractual
arrangements, to enable the Commission to assess the reasonableness of the
forecast.
Page 28 of 128
9.3 The capital investment plan, in case of a generation company, will be
commensurate with generation capacity growth, renovation &
modernization requirements etc.
9.6 The generation company and licensee shall submit all information / data
required by the Commission for approval of the capital investment plan.
9.7 In the normal course, the Commission shall not revisit the approved
capital investment plan during the control period. However, during the
mid-year performance review and true-up, the Commission shall monitor
the year wise progress of the actual capital expenditure incurred by the
generating company or the licensee vis-à-vis the approved capital
expenditure and in case of significant difference between the actual
expenditure viz-a-viz the approved expenditure, the Commission may
true up the capital expenditure, subject to prudence check, as a part of
annual true up exercise on or without an application to this effect by the
generation company/licensee. The generating company and the licensee
shall submit the scheme-wise actual capital expenditure incurred along
with the mid-year performance review and true-up filing.
Page 29 of 128
9.8 In case during the mid-year performance review, the actual cumulative
capital expenditure incurred up to the current year starting from first
year of the control period, is less by more than 10% of the approved
cumulative capital expenditure, the Commission shall true-up the costs
incidental to the actual capital expenditure in the current year and
remaining years of the control period.
Provided that the actual capital expenditure incurred shall be only for
the schemes as per the approved capital investment plan.
Provided that if the actual capital expenditure incurred is more than the
approved capital expenditure, the Commission shall not allow any true-
up of the cost incidental to such variations.
9.9 In case the capital expenditure is required due to Force Majeure events
for works which have not been approved in the capital investment plan
or for works that may have to be taken up to implement new schemes
approved by the State/Central Govt., the generating company or the
licensee shall submit an application containing all relevant information
along with reasons justifying emergency nature of the proposed work
seeking approval by the Commission. In the case of works or schemes,
other than those required on account of Force Majeure events, the
Commission shall consider to give approval only in those cases where
the works / schemes are wholly / substantially financed by the State /
Central Government or, in view of the Commission, shall benefit a large
mass of consumers of the State. The generating company or the
licensee may take up the work prior to the approval of the Commission
only in case the delay in approval will cause undue loss and such
emergency nature of the scheme has been certified by the Board of the
Directors and intimated to the Commission:
Provided that the generating company or the licensee shall submit the
requisite details, as required as per Regulation 9.1 above, within 10
days of the submission of the application for approval of emergency
work;
Provided further that for the purpose of Regulation 9.7 and 9.8, such
approved capital expenditure shall be treated as a part of actual capital
expenditure incurred by the licensee as well as the capital expenditure
approved by the Commission.
9.10 In case the capital expenditure incurred for approved schemes exceeds
the amount as approved in the capital expenditure plan, the generating
company or the transmission or the distribution licensee, as the case
Page 30 of 128
may be, shall file an application with the Commission at the end of
control period for truing up the expenditure incurred over and above the
approved amount. After prudence check, the Commission shall pass an
appropriate order on case to case basis. The true-up application shall
contain all the requisite information and supporting documents.
9.13 The Commission shall approve the capital investment plan within a
period of 45 days from the date of its filing or submission of complete
information, whichever is later.
9.14 For the purpose of second control period, the timeline for submission of
business plan by the generating company and the licensees shall be as
specified in Regulation 75 of these Regulations.
Page 31 of 128
done and submit the same along with ARR / Tariff petition. No RoE,
depreciation interest cost etc. shall be allowable on the same.
9.15 To enable faster adoption of Electric vehicles in the State, the Utilities
i.e., HPGCL, HVPNL, DHBVN and UHBVNL shall endeavour to set up
Public Charging Station (PCS) for charging Electric Vehicles near to
their Sub-Stations or any other appropriate place.
10.1 The generating company and the licensee, in respect of their respective
businesses, shall file for approval of the Commission a business plan for a
period covering the entire control period along with the MYT petition. The
business plan shall provide the details for each year of the control period.
10.2 The business plan for a generating company shall be based on planned
generation capacity growth and shall contain among other things the following
(i) generation forecasts; (ii) future performance targets; (iii) proposed efficiency
improvement measures; (iv) saving in operating costs; (v) Plan for reduction
in per unit/per MW cost of generation (vi) financial statements (which include
balance sheet, profit and loss statement and cash flow statement) - current
and projected (at least for the control period duration) along with basis of
projections; (vii) any other new measure to be initiated by the Generating
Company e.g. IT initiatives, third party energy audit etc.
10.3 The business plan for transmission licensee shall be based on proposed
generation capacity addition and future load forecasts of the state and should
contain among other things the following: (i) future plans/ performance targets
of the company including efficiency improvement measures proposed to be
introduced (ii) plans for meeting reactive power requirements; (iii) plan for
reduction in transmission losses; (iv) plan for improvement in quality of
transmission service and reliability; (v) metering arrangements; (vi) Plan for
reduction in per MW transmission cost, (vii) financial statements (which
include balance sheet, profit and loss statement and cash flow statement)-
current and projected (at least for the period of control period duration) along
with basis of projections; (viii) any other new measure to be initiated by the
Licensee e.g. IT initiatives etc.
10.4 The business plan for distribution licensee shall be based on sales forecast
(MUs)/load growth and should contain among other things the following: (i)
future plans/ performance targets of the company including efficiency
improvement measures proposed to be introduced (ii) plan for reduction in
distribution and non-technical losses;(iii) plan for improvement in quality of
supply and reliability; (iv) metering arrangements; (v) plan for improvement in
Page 32 of 128
collection efficiency (vi) plan for improvement in consumer services/new
consumer services (vii) Plan for reduction in O & M cost per MU of energy
sales (viii) MIS; (ix) scheme for third party energy audit (x) plan for
improvement in metering and billing; (xi) financial statements (which include
balance sheet, profit and loss statement and cash flow statement)- current
and projected (at least for the period of control period duration) along with
basis of projections; (xii) any other new measure to be initiated by the
Licensee(s) e.g. IT initiatives, development of distribution franchisee, periodical
business satisfaction surveys etc.
10.6 The generation company and the licensee shall submit all information / data
as required by the Commission for necessary approval of the business plan.
The Commission shall scrutinize the business plan taking into consideration
the additional information provided by the applicant, if any.
10.7 The Commission shall approve the business plan within a period of 45 days
from the date of its filing or submission of complete information, whichever is
later.
10.8 For the purpose of second control period, the timeline for submission of
business plan by the generating company and the licensees shall be as
specified in Regulation 75 of these Regulations.
11.1 The generating company and the licensee shall file an application for mid-
year performance review, true-up of previous year and tariff for the ensuing
year not less than 120 days before the close of each year of the control
period, complete in all respects including the information in the existing
formats as per present practice, till such time new formats are finalised by
the Commission.
11.2 The generating company and the licensees, within 7 (seven) days of filing of
the application for mid-year performance review and true-up, shall publish for
information of the public, the contents of the application filed with the
Commission for mid-year performance review, true up of previous year and
approval of tariff for the ensuing year in an abridged form in such manner as
the Commission may direct and shall provide copies of the application and
Page 33 of 128
other documents filed with the Commission at a price not exceeding normal
photocopying charges. The generating company and the licensees shall also
host the application and other documents at their official websites.
11.3 The generating company and the licensee shall provide with the application
for mid-year performance review the details of actual capital expenditure and
details of any statutory levies and actual operational and cost data to enable
the Commission to monitor the implementation of its order including
comparison of actual performance with the approved forecasts (and reasons
for deviations). In addition the generating company and the licensees shall
also submit Annual Statement of Performance and Accounts of their
respective businesses (indicating the plant-wise cost data, and unit-wise
performance parameters in case of a generation company), a copy of latest
audited accounts, analysis of detailed reasons for losses, if any, and any
other information which the Commission may require to assess the reasons
and extent of any variation in the performance from the approved forecast
and the need for tariff resetting.
11.4 In their application for performance review, true-up and tariff for ensuing year,
the generating company and the licensee shall submit information for the
purpose of calculating expected expenditure and tariff along with information
on financial and operational performance for the previous year(s). The
information for the previous year should be based on audited accounts copies
of which shall be supplied along with the application. In case audited
accounts for the previous year are not available, audited accounts for the
latest previous year should be filed along with unaudited accounts or
provisional accounts for all the succeeding years. The application should also
include the proposal for tariff revision, if any.
11.5 The scope of the mid-year performance review shall be a comparison of the
performance of the generation company and the licensees for the relevant
financial year with the approved forecast of ARR for their respective
businesses and the performance targets specified by the Commission. Upon
completion of the mid-year performance review and truing up as per
Regulation 13, the Commission shall pass an order recording:
(a) The revised approved ARR for such financial year including approved
modifications, if any;
(b) The approved aggregate gain or loss on account of controllable items and
sharing of such gains or losses;
Page 34 of 128
(d) Pass through of variations in controllable items due to force majeure events,
if any.
11.6 “The Commission shall review/consider, during the control period, the
application made under this Regulation as also the application for truing up
of the ARR of the previous year, as per provision of the Regulation 13, on
the same principles as approved in the MYT order on the original application
for determination of ARR and tariff. The review / true–up for FY 2018-19 and
FY 2019-20 shall, however, be done on the same principles as approved in
the tariff order for FY 2018-19 and for FY 2019-20. Upon completion of such
review/truing up, either approve the proposed modification with such changes
as it deems appropriate, or reject the application for the reasons to be
recorded in writing. The Commission shall afford opportunity of being heard
to the affected party in case it considers rejecting the application.”
12.1 Various elements of the ARR of the generating company and the licensee
will be subject to incentive and penalty framework as per the terms
specified in this Regulation. The overall aim is to incentivize better
performance and penalize poor performance, with the base level as per
the norms / benchmarks specified by the Commission.
(ii) Interest on new long-term loans- Applicable when interest rate falls below
or exceeds the level specified by the Commission.
(iv) Interest on working capital- Applicable when interest rate falls below or
exceeds the level specified by the Commission
Page 35 of 128
(i) Plant Availability Factor (PAF)- Applicable when actual PAF falls below
or exceeds the level specified by the Commission
(ii) Station heat rate (SHR)- Applicable when actual SHR falls below or
exceeds the level specified by the Commission
(iii) Auxiliary Energy Consumption (AUX)- Applicable when actual AUX falls
below or exceeds the level specified by the Commission
(iv) Specific Fuel Oil Consumption (SFC)- Applicable when actual SFC falls
below or exceeds the level specified by the Commission
(v) Transit loss of coal- Applicable when actual transit loss falls below or
exceeds the level specified by the Commission
(i) Availability- Applicable when actual availability falls below or exceeds the
level specified by the Commission. The incentive for actual availability
above target availability shall be worked out as per the following formula:
Where
I = Incentive
Note 2: For all purposes the ‘normative target availability factor’ shall be
considered for recovery of fixed charges. Any fall in the actual availability from
Page 36 of 128
the normative target availability shall result in pro-rata reduction of fixed
charges.
12.3 The gains / losses shall be computed item wise separately for each
business. The computations shall be based on the data submitted by
the generating company and the licensees in the application for mid-
year performance review / true – up and audited annual accounts
corresponding to the financial year.
The item wise gain shall be shared between the generating company
or the licensee, as the case may be, and their respective beneficiaries
in the ratio of 50:50. However, the sharing ratio of 50:50 may be
revised to a maximum of 60:40 at the time of true-up during mid-year
performance review / true-up. The manner of utilization of the additional
10% gain shall be specified by the Commission from time to time.
(b) The item wise losses on account of other controllable factors, unless
otherwise specifically provided by the Commission, shall be borne
by the distribution licensee.
Page 37 of 128
12.5.2 The item wise losses on account of controllable factors in case of a
generation company/transmission licensee, unless otherwise specifically
provided by the Commission, shall be borne by the generation
company/ transmission licensee.
13. TRUING-UP
13.1 Truing-up of the ARR of the previous year shall be carried out along
with mid-year performance review of each year of the control period
only when the audited accounts in respect of the year(s) under
consideration is submitted along with the application. In case audited
accounts pertaining to the year, of which truing-up is to be undertaken,
are not available, the generating company or the licensee as the case
may be, shall submit the provisional account duly approved by the
Board of Directors of the company/licensee.
13.2 Truing-up of uncontrollable items shall be carried out at the end of each
year of the control period through tariff resetting for the ensuing year
and for controllable items shall be done only on account of force
majeure conditions and for variations attributable to uncontrollable
factors.
13.3 The Commission shall allow carrying costs for the trued–up amount
(positive or negative) at the interest rates specified in these Regulations by
adjusting the interest allowed on the working capital requirement for the
relevant year of the control period.
(b)Holding cost for under/over recovered amount from the close of the
relevant year and upto the middle of the ensuing year of the control
period whereupon the trued-up amount has been adjusted by appropriate
resetting of tariff in accordance with regulation 13.4, calculated as
additional borrowing for working capital for that period.
Page 38 of 128
in the one control period shall be adjusted in the subsequent control
period.
14.1 At the end of the second control period, the Commission shall review
the achievement of objectives and implementation of the principles of
MYT laid down in these Regulations.
14.2 To meet the objectives of the Act, the National Electricity Policy and
National Tariff Policy, the Commission may revise the principles of MYT
for the third and subsequent control periods.
14.3 The end of the second control period shall be the beginning of the third
control period. The generating company and the licensee shall follow the
same procedure unless specified otherwise by the Commission. The
Commission shall analyse the performance with respect to the targets
set out at the beginning of the control period and shall determine the
base values for the next control period on the basis of actual
performance achieved, expected improvement and other relevant factors.
Page 39 of 128
PART III - COMPONENTS OF ARR AND TARIFF FOR GENERATION,
TRANSMISSION AND DISTRIBUTION BUSINESS
15.1 The tariff for sale of electricity from a thermal generating plant shall
comprise of two parts, namely,
15.2 Both the components will be worked out in the manner provided in these
Regulations.
15.3 The fixed cost of generating plant (thermal or hydro) shall include the
following elements:
a) Return on equity
b) Interest and financing charges on loan capital
c) Interest on working capital
d) Depreciation
e) Operation and maintenance expenses
f) Foreign exchange rate variation, if any
g) All statutory levies and taxes, if any, excluding taxes on income,
15.4 The Energy Charges (or variable charges) for a generating plant
(thermal) shall comprise of primary and secondary fuel cost.
15.5 For the hydro plants i.e. Western Yamuna Canal Hydro project,
Bhudkalan and Kakroi Hydro Plants, however, a single part tariff, based
on a normative PLF and fixed cost worked out as per Regulation 34
hereinafter, may be determined by the Commission. Unless otherwise the
Commission considers it appropriate to determine the same under HERC
RE Regulations in vogue.
16.1 The following charges shall be recovered for the use of intra-state
transmission system:
Page 40 of 128
Requirement of the transmission licensee approved by the Commission for
each year of the control period;
(c) Short-term open access consumers shall pay the charges for usage of
Transmission system in terms Rs per kWh as specified in third proviso of
regulation 50 (b).
16.2 SLDC charges, to reflect the cost of operating the State Load Dispatch
Centre (SLDC) including the cost of owning & maintaining it. These shall
be levied as SLDC charges to the beneficiariesof the services of SLDC
in accordance with the provisions of theseRegulations
16.3 The ARR’s for the transmission business and SLDC business comprise
of only fixed costs which shall have the following components:
17.1 For distribution licensees, the commission shall determine (i) retail supply
tariff for their retail supply business i.e. sale of electricity to the
Page 41 of 128
consumers in their respective licensed areas which will be inclusive of
wheeling charges and (ii) wheeling tariff for their wheeling business which
shall be for the purpose of recovering wheeling charges from open
access consumers falling in their respective licensed areas.
17.2 The ARRs of the distribution licensee for retail supply business and
wheeling business will comprise the following elements:
A - Expenses A - Expenses
d) Depreciation d) Depreciation
Total expenses – A
Total expenses – A
B - Income / receipts:
B - Income / receipts:
a) Non – tariff income including revenue from
a) Non – tariff income
various surcharges
b) Income from other business, to
b) Income from other business in
the extent specified for wheeling tariff
accordance with HERC Regulations, 2007 as
amended from time to time. Total Income / receipts – B
(A – B)
(A – B)
Page 43 of 128
PART IV- GENERAL PRINCIPLES FOR DETERMINATION OF COMMON
COMPONENTS OF ARR AND TARIFF FOR GENERATION,
(1) The Capital cost as admitted by the Commission after prudence check and
subject to debt-equity ratio as per provisions of these Regulations, shall
form the basis of determination of tariff for new power projects.
Provided that where the power purchase agreement entered into between
the generating Company and the beneficiaries or transmission service
agreement entered into between transmission licensee and the long-term
transmission consumer, as the case may be, provides for a ceiling of
actual expenditure, the capital expenditure shall not exceed such ceiling
for determination of tariff;
Provided also that where the Commission has given ‘in principle’
acceptance to the estimates of project capital cost and financing plan,
the same shall be the guiding factor for applying prudence check on the
actual capital expenditure;
(2) The Capital Cost of a new project shall include the following:
(b) Interest during construction and financing charges, on the loans (i)
being equal to 70% of the funds deployed, in the event of the actual
equity in excess of 30% of the funds deployed, by treating the excess
equity as normative loan, or (ii) being equal to the actual amount of loan
in the event of the actual equity less than 30% of the funds deployed;
Page 44 of 128
(d) Interest during construction and incidental expenditure during
construction as computed in accordance with these Regulation.
Provided that:
(i) where the generating station has any transmission equipment forming part
of the generation project, the ceiling norms for initial spares for such
equipment shall be as per the ceiling norms specified for transmission system
under these Regulations:
(ii) once the transmission project is commissioned, the cost of initial spares
shall be restricted on the basis of plant and machinery cost corresponding to
the transmission project at the time of truing up:
(iii) for the purpose of computing the cost of initial spares, plant and
machinery cost shall be considered as on cut-off date excluding IDC, IEDC,
Land Cost and cost of civil works. The generator/licensee shall submit the
breakup of head wise IDC & IEDC in its tariff application.
(h) adjustment of revenue due to sale of infirm power in excess of fuel cost
prior to the COD as specified under these Regulations; and
Page 45 of 128
(i) adjustment of any revenue earned by using the assets before COD.
(3) The capital cost in case of a new hydro generating station shall also include:
(a) cost of approved rehabilitation and resettlement (R&R) plan of the project
in conformity with National R&R Policy and R&R package as approved; and
(b) cost of the developer’s 10% contribution towards Rajiv Gandhi Grameen
Vidyutikaran Yojana (RGGVY) project in the affected area.
(4) The capital cost with respect to thermal generating station, incurred or
projected to be incurred on account of the Perform, Achieve and Trade (PAT)
scheme or to achieve Environmental Norms / Statutory Norms of Government
of India will be considered by the Commission on case to case basis and
shall include:
(5) The following shall be excluded or removed from the capital cost of the
existing and new project:
(a) The assets forming part of the project, but not in use;
(d) the proportionate cost of land which is being used for generating power
from generating station based on renewable energy:
Provided that any grant received from the Central or State Government or any
statutory body or authority for the execution of the project which does not
carry any liability of repayment shall be excluded from the Capital Cost for the
purpose of computation of interest on loan, return on equity and depreciation;
(6) Capital cost to be allowed by the Commission for the purpose of determination
of tariff for respective businesses will be based on the capital investment plan
prepared by the generating company or the licensee, as the case may be, and
approved by the Commission prior to the filing of application for multiyear tariff
by the generating company/licensees.
(7) Restructuring of capital cost in terms of relative share of equity and loan
component, subject to provisions of Regulation 19, shall be permitted during the
tariff period provided it does not affect tariff adversely. Any benefit from such
Page 46 of 128
restructuring shall be subjected to incentive / penalty framework as per
Regulation 12.
(8) The amount of any contribution made by the consumers, open access
consumers and Government subsidy towards works for connection to the
distribution system or transmission system of the distribution /transmission
licensee, shall be deducted from the original cost of the project for the purpose
of calculating the amount under debt and equity under these Regulations.
Where the capital cost considered in tariff by the Commission on the basis of
projected additional capital expenditure exceeds the actual additional capital
expenditure incurred on year to year basis by more than 10%, the generating
company or the transmission licensee shall refund to the beneficiaries or the
long term transmission customers as the case may be, the tariff recovered
corresponding to the additional capital expenditure not incurred, as approved
by the Commission, along with interest at 1.20 times of the bank rate as
prevalent on 1st April of the respective year.
Where the capital cost considered in tariff by the Commission on the basis of
projected additional capital expenditure falls short of the actual additional
capital expenditure incurred by more than 10% on year to year basis, the
generating company or the transmission licensee shall recover from the
beneficiaries or the long term customers as the case may be, the shortfall in
tariff corresponding to difference in additional capital expenditure, as approved
by the Commission, along with interest at the bank rate as prevalent on 1 st
April of the respective year.
B. Distribution Licensee
Page 47 of 128
Any shortfall in tariff recovered on account of variation in projected
capitalization in the tariff order vis-a-vis trued up capitalization by more than
10% during the year, shall be adjusted in the Revenue Gap/Surplus of the
relevant year along with interest rate at 0.80 times of the bank rate prevalent
on 1st April of respective year.
The following principles shall be adopted for prudence check of capital cost of the
existing or new projects:
(1) In case of the thermal generating station and the transmission system,
prudence check of capital cost may be carried out taking into consideration
the benchmark norms specified/to be specified by the Commission from time
to time:
Provided that in cases where benchmark norms have not been specified,
prudence check may include scrutiny of the capital expenditure, financing plan,
interest during construction, incidental expenditure during construction for its
reasonableness, use of efficient technology, cost over-run and time over-run,
competitive bidding for procurement and such other matters as may be
considered appropriate by the Commission for determination of tariff:
Provided further that in cases where benchmark norms have been specified,
the generating company shall submit the reasons for exceeding the capital
cost from benchmark norms to the satisfaction of the Commission for allowing
cost above benchmark norms.
(2) The Commission may issue new guidelines or at its discretion, get the
capital cost of any project, vetted by an independent agency or an external
expert. However, the same shall be considered as guiding factor only and not
binding on the Commission as such.
(3) The Commission may issue new guidelines or revise the existing
guidelines for scrutiny and approval of commissioning schedule of the hydro-
electric projects in accordance with the tariff policy issued by the Central
Government under section 3 of the Act from time to time which shall be
considered for prudence check.
(4) Where the power purchase agreement entered into between the generating
company and the beneficiaries provides for ceiling of actual capital
expenditure, the Commission shall take into consideration such ceiling for
determination of tariff for prudence check of capital cost.
Page 48 of 128
C. Interest during construction (IDC), Incidental Expenditure during Construction
(IEDC)
Provided that if the delay is not attributable to the generating company or the
licensee as the case may be, and is due to uncontrollable factors as specified
in these Regulations, IDC may be allowed after due prudence check:
Provided further that only IDC on actual loan may be allowed beyond the
SCOD to the extent, the delay is found beyond the control of generating
company , after due prudence and considering prudent phasing of funds.
(1) Incidental expenditure during construction shall be computed from the zero
date and after considering pre-operative expenses upto SCOD:
Provided that if the delay is not attributable to the generating company or the
transmission licensee, as the case may be, and is due to uncontrollable
factors, IEDC may be allowed after due prudence check:
Page 49 of 128
(3) In case the time over-run beyond SCOD is not admissible after due
prudence, the increase of capital cost on account of cost variation
corresponding to the period of time over run may be excluded from
capitalization irrespective of price variation provisions in the contracts with
supplier or contractor of the generating company.
(1) The “controllable factors” shall include but shall not be limited to the
following:
(2) The “uncontrollable factors” shall include but shall not be limited to the
following:
Page 50 of 128
18.2 Additional capitalization
18.2.1 The Commission may consider allowing, subject to prudence check, any
additional capital expenditure incurred or projected to be incurred, after the
commercial operation date of a project and up to the cut-off date, on the
following provided the same was part of the original scope of work of the
project:
18.2.2 The Commission may consider admitting, after prudence check, the capital
expenditure of the following nature actually incurred after the cut-off
date:
(e) Any additional works / services which have become necessary for
efficient and successful operation of the project, but not included in
the original project cost;
Page 51 of 128
18.2.3 Impact of additional capitalization in tariff revision within the approved
project cost shall be considered by the Commission once during a
particular financial year of the control period.
18.2.5 Provided also that if any expenditure has been claimed under Renovation
and Modernization (R&M), repairs and maintenance under O&M
expenses and Compensation Allowance, same expenditure cannot be
claimed under this Regulation.
18.2.7 The scrutiny of the project cost estimates by the Commission shall
include the reasonableness of the capital cost, financing plan, interest
during construction, use of efficient technology and such other matters
for the purposes of determination of tariff.
(1) The generating company or the transmission licensee, as the case may be, for
meeting the expenditure on renovation and modernization (R&M) for the purpose of
extension of life beyond the originally recognized useful life for the purpose of tariff
of the generating station or a unit thereof or the transmission system or an element
thereof, shall make an application before the Commission for approval of the
proposal with a Detailed Project Report giving complete scope, justification, cost-
benefit analysis, estimated life extension from a reference date, financial package,
phasing of expenditure, schedule of completion, reference price level, estimated
completion cost including foreign exchange component, if any, and any other
information considered to be relevant by the generating company or the
transmission licensee.
(2) Where the generating company or the transmission licensee, as the case may
be, makes an application for approval of its proposal for renovation and
modernization, the approval shall be granted after due consideration of
reasonableness of the cost estimates, financing plan, schedule of completion,
interest during construction, use of efficient technology, cost-benefit analysis, and
such other factors as may be considered relevant by the Commission.
(3) In case of gas/ liquid fuel based open/ combined cycle thermal generating
station, any expenditure which has become necessary for renovation of gas
turbines/steam turbine after 25 years of operation from its COD and an expenditure
necessary due to obsolescence or non-availability of spares for efficient operation of
the stations shall be allowed:
Provided that any expenditure included in the R&M on consumables and cost of
components and spares which is generally covered in the O&M expenses during the
major overhaul of gas turbine shall be suitably deducted after due prudence from
the R&M expenditure to be allowed.
(b) In case the actual equity employed is in excess of 30%, the amount of
equity for the purpose of tariff determination shall be limited to 30%, and
the balance amount shall be considered as normative loan;
(c) In case the actual equity employed is less than 30%, then the actual
debt-equity ratioshall be considered;
(d) The premium, if any, raised by the generating company or the licensee
while issuing share capital and investment of internal accruals created
out of free reserve, shall also be reckoned as paid up capital for the
purpose of computing return on equity subject to the normative debt
equity ratio of 70:30, provided such premium amount and internal
accruals are actually utilized for meeting capital expenditure and form
part of the approved financial package. For the purposes of computation
of return, the portion of free reserves utilized for meeting the capital
expenditure shall be considered from the date the asset created is
productively deployed in the business.
Provided that:
20.1 The rate of return on equity shall be decided by the Commission keeping
in view the incentives and penalties and on the basis of overall
performance subject to a ceiling of 14% provided that the ROE shall not
be less than the net amount of incentive and penalty.
II. 50% of equity capital portion of the allowable capital cost for the assets
put to use during the year.
Provided that for the purpose of truing up, return on equity shall be
allowed from the COD on pro-rata basis based on documentary evidence
provided for the assets put to commercial operation during the year.
20.3 Return on equity invested in work in progress shall be allowed from the
actual date of commercial operation of the assets.
20.4 There shall be no Return on Equity for the equity component above
30%.
Page 55 of 128
21. INTEREST ON LOAN CAPITAL
(i) Interest on loan capital shall be computed loan-wise for existing loans
arrived in a manner specified in Regulation 19 and shall be as per the
rates approved by the Commission.
(ii) The loan outstanding as on 1st April of each financial year shall be
worked out as the gross loan in accordance with Regulation 19 by
deducting the cumulative repayment as admitted by the Commission up
to 31st March of previous financial year from the gross normative loan;
(iii) The rate of interest shall be the weighted average rate of interest on
institutional loans calculated on the basis of the actual loan portfolio at
the beginning of each year applicable to the project. In case the
weighted average rate is not available, the interest rate approved by the
Commission in its earlier tariff order shall be allowed.
Provided that if there is no actual loan for a particular year but normative
loan is still outstanding, the last available weighted average rate of
interest shall be considered;
Provided further that if the generating plant/project does not have actual
loan, then the weighted average rate of interest of the generating
company/licensee as a whole shall be considered.
(iv) The interest on loan shall be calculated on the normative average loan
of the year by applying the weighted average rate of interest;
(v) The generating company and the licensee shall from time to time review
their capital structure i.e. debt and equity and make every effort to
restructure the loan portfolio as long as it results in net savings on
interest. The costs associated with such re-financing shall be borne by
the beneficiaries and the net savings (after deducting the cost of re-
financing) shall be subjected to incentive / penalty framework as
mentioned in the Regulation 12 which shall be dealt with at the time of
mid-year performance review/true-up.
(vi) The changes to the loan terms and conditions shall be reflected from
the date of such re-financing and benefit passed on to the beneficiaries;
(vii) In case of any dispute relating to re-financing of loan, any of the parties
may approach the Commission with proper application along with all the
relevant details. During the pendency of any dispute, the beneficiaries
shall not withhold any payment on account of orders issued by the
Commission.
Page 56 of 128
(viii) In case any moratorium period on repayment of loan is availed of by the
generating company or the licensee, depreciation provided for in the tariff
during the years of moratorium shall be treated as repayment during
those years and interest on loan capital shall be calculated accordingly.
Provided that the repayment for each year of the control period shall be
deemed to be equal to the depreciation allowed for the corresponding
year.
(i) Rate of interest on new loans i.e. on or after 01.04.2020 shall be equal
to the marginal cost of funds-based lending rate (MCLR) of the SBI plus
a maximum of 150 basis points w.r.t.1st April of the relevant financial
year. They shall however, be required to submit due justification to the
Commission for the terms and conditions of the loans raised by them
including the loan sanction letter from the banks/ lending institutions,
indicating the applicable rate of interest.
Provided further that neither penal interest nor overdue interest shall be
allowed for computation of Tariff
(ii) Any variation above or below the allowed interest rate shall be subject to
the incentive and penalty framework specified in Regulation 12. The
incentives on refinancing should be net of costs.
21.3 The interest computation shall exclude interest on loan amount, normative
or otherwise, to the extent of capital cost funded by Consumer
Contributions, Grants or Deposit Works carried out by Transmission
Licensee or Distribution Licensee or Generating Company, as the case
may be.
21.4 Interest shall be allowed on the amount held as security deposit held in
cash from Transmission System Users, Distribution System Users and
Retail consumers, at the Bank Rate as on 1st April of the financial year
Page 57 of 128
in which the petition is filed provided it is payable by the
transmission/distribution licensee.
Generating company
Page 58 of 128
expenses;
Transmission licensee
Provided that at the time of truing up for any year, the working capital
requirement shall be re-calculated on the basis of the values of
components of working capital approved by the Commission in the truing
up
Distribution licensee
I. Wheeling of electricity:
less
Provided further that for the purpose of Truing-up for any year, the
working capital requirement shall be re-computed on the basis of the
values of components of working capital approved by the Commission
in the Truing-up before sharing of gains and losses
a) Normative O&M expenses for retail supply business for 1 (one) month;
Page 59 of 128
security / advance consumption deposit.
Provided that for the purpose of Truing-up for any year, the working
capital requirement shall be re-computed on the basis of the values of
components of working capital approved by the Commission in the
Truing-up before sharing of gains and losses;
Rate of interest on working capital shall be equal to the MCLR of the relevant
financial year plus a maximum of 150 basis points. However, while claiming
any spread, the generator and the licensees shall submit loan sanction letter
from the banks/ lending institutions, indicating the applicable rate of interest.
For the purpose of truing up, the actual weighted average Rate of Interest will
be considered on the normative working capital by the Commission, subject to
the ceiling margin as indicated above.
23. DEPRECIATION
(a) The value base of asset shall be the historical capital cost of the asset
as admitted by the Commission. The historical capital cost shall include
additional capitalization including foreign exchange rate variation, if any
already allowed by the Commission up to 31st March of the relevant
year.
(b) The residual value of the asset shall be considered as 10% and
depreciation shall be allowed up to maximum of 90% of historical capital
cost of the asset;
Provided that the salvage value for IT equipment and software shall be
considered as NIL and 100% value of the assets shall be considered
depreciable.
(c) Depreciation shall be calculated annually over the useful life of the asset
at the rates specified in Appendix II up to 31st March of the 12th year
from the date of commercial operation of the asset. From 1st April of
13th year from the commercial date of operation of the asset, the
remaining depreciable value if any out of the 90% of the capital cost of
the asset shall be equally spread over the balance useful life of the
asset.
Page 60 of 128
The deprecation rates given in Appendix-II will be applicable w.e.f.
1.04.2020 only. The depreciation, in case of existing assets, up to
31.03.2020 shall be considered as already allowed and shall not be re–
visited. The deprecation rates as per Appendix-II for such assets shall be
applicable w.e.f 1.04.2020 up to 12th year from the date of COD.
Provided that the rate provided in Appendix II, are the upper ceiling of
the rate of depreciation to be provided up to 12th year from the date of
COD and the developer shall have the option of indicating, while seeking
approval for tariff, lower rate of depreciation, subject to the aforesaid
ceiling.
(d) Land shall not be considered as a depreciable asset and cost shall be
excluded from the capital cost while computing depreciable value of
asset.
(f) Depreciation shall not be allowed on assets (or part of assets) funded by
consumer contribution (i.e., any receipts from consumers that are not
treated as revenue) and capital subsidies / grants. Provision for
replacement of such assets shall be made in the capital investment plan.
24.1 The generating company or the licensee, as the case may be, may
hedge foreign exchange exposure in respect of the interest on foreign
currency loan and repayment of foreign loan acquired for the project in
part or full at their discretion to safeguard their interest against
extraordinary variations in the foreign exchange rates.
24.2 The generating company or the licensee shall recover the cost of
hedging of foreign exchange rate variation corresponding to the normative
foreign debt, in the relevant year on year-to-year basis as expense in the
period in which it arises and no extra rupee liability corresponding to
such foreign exchange rate variation shall be allowed against the hedged
foreign currency debt;
24.3 To the extent the generating company or the licensee is not able to
hedge the foreign exchange exposure, then to that extent, the extra
rupee liability towards interest payment and loan repayment
corresponding to the normative foreign currency loan in the relevant year
Page 61 of 128
shall be permissible provided it is not attributable to the generating
company/licensees or their contractors.
24.4 The generating company/the licensee shall recover the cost of hedging
and foreign exchange rate variations on year to year basis as income or
expense in the period in which it arises
24.5 Any gain or loss on account of foreign exchange rate variation pertaining
to the loan amount availed during the construction period shall form part
of the capital cost.
Income tax, if any, on the income stream of the generating company or the
licensee shall not be treated as an expense or a pass-through component in the
tariff and shall be payable by the generating company or the licensees on their
own.
The generation company and the licensees may engage in any other business for
optimum utilization of their assets with prior intimation to the Commission. Such
instances and transactions shall be governed in accordance with the Treatment of
Income of Other Businesses of Transmission Licensee(s) and Distribution
Licensee(s), Regulations, 2007 notified by the Commission, as amended from time
to time.
Provided that the licensee shall follow a reasonable basis for allocation of all joint
and common costs between the core/licensed business and the other business and
shall submit the allocation statement as approved by the Board of Directors to the
Commission along with his application for determination of tariff;
Provided further that where the sum total of the direct and indirect costs of such
other business exceed the revenues from such other business or for any other
reason, no amount shall be allowed to be added to the aggregate revenue
requirement of the generation company or the licensees, as the case may be, on
account of such other business.
27.1 The utility may submit to the Commission the prior period expenses as a
part of the filing for truing up;
27.2 The Commission may allow prior period expenses for uncontrollable cost
items only as per the audited accounts during truing up.
Page 62 of 128
PART V- PRINCIPLES FOR DETERMINATION OF TARIFF AND NORMS OF
OPERATION FOR GENERATION BUSINESS
MYT Period
Plant Name (Units) 2020-21 2021-22 2022-23 2023-24 2024-25
(%) (%) (%) (%) (%)
Panipat TPS (Unit 5) 85
Panipat TPS (Unit 6) 85 85 85 85 85
Panipat TPS (Unit 7) 85 85 85 85 85
Panipat TPS(Unit 8) 85 85 85 85 85
DCR TPS, Yamuna Nagar (Unit 85 85 85 85 85
1)
DCR TPS, Yamuna Nagar (Unit 85 85 85 85 85
2)
Rajiv Gandhi TPS, Khedar (Hisar) 85 85 85 85 85
(Unit 1)
Rajiv Gandhi TPS, Khedar (Hisar) 85 85 85 85 85
(Unit 2)
Description
(a)Existing Plants
MYT Period
Page 63 of 128
(b) New Plants Commissioned on or after 1st April 2020
For Coal-based generating stations with induced draft cooling towers, the
norms shall be further increased by 0.5%.
MYT Period
Plant Name 2020-21 2021-22 2022-23 2023-24 2024-25
(Units) (kCal/kWh) (kCal/kWh (kCal/kWh (kCal/kWh) (kCal/kWh)
Panipat TPS 2550 2550 2550 2550 2550
(Units 5&6)
Panipat 2500 2500 2500 2500 2500
TPS(Units 7 &
8)
DCR TPS, 2344 2344 2344 2344 2344
Yamuna Nagar
(Units 1&2)
Rajiv Gandhi 2387 2387 2387 2387 2387
TPS, Khedar
(Hisar) (Unit
1&2)
Note: Station heat rate norms for DeenBandhuChhottu Ram TPS (Unit 1 and
2) and Rajiv Gandhi TPS (Unit 1 and 2) have been determined considering
their design heat rate as 2201 kCal/kWh and 2241 kCal/kWh respectively and
multiplying the same with a factor of 1.065.
Page 64 of 128
(b) New Plants Commissioned on or after 1st April 2020
Generating Plants
Where the Design Heat Rate of a unit means the unit heat rate guaranteed by the
supplier at conditions of 100% MCR, zero percent make up, design coal and design
cooling water temperature/back pressure:
Provided that the design heat rate shall not exceed the following maximum design
unit heat rates depending upon the pressure and temperature ratings of the units:
Minimum Boiler
Efficiency
Provided further that in case pressure and temperature parameters of a unit are
different from above ratings, the maximum design unit heat rate of the nearest class
shall be taken;
Page 65 of 128
Provided also that where unit heat rate has not been guaranteed but turbine cycle
heat rate and boiler efficiency are guaranteed separately by the same supplier or
different suppliers, the unit design heat rate shall be arrived at by using guaranteed
turbine cycle heat rate and boiler efficiency.
Note: In respect of units where the boiler feed pumps are electrically operated, the
maximum design unit heat rate shall be 40 kCal/kWh lower than the maximum
design unit heat rate specified above with turbine driven Boiler Feed Pump.
= 1.05 X Design Heat Rate of the unit/block for natural gas and
= 1.071 X Design Heat Rate of the unit/block for liquid fuel (kCal/kWh)
Where the Design Heat Rate of a unit/block shall mean the guaranteed heat
rate for a unit/block at 100% MCR and at site ambient conditions, zero
percent make up, design fuel and design cooling water temperature/back
pressure.
MYT Period
Type Norms
Page 66 of 128
(5) Operation and maintenance expenses:
The norms for O & M expenses (in Rs. Lac per MW) for the existing plants and
the plants Commissioned on orafter 1st April 2020 shall accordingly be as under:-
Provided that the above norms shall be multiplied by the following factors for
additional units in respective unit sizes for the units whose COD occurs on or after
1st April 2020 in the same plant:
(6) The norms for thermal power plants other than the existing plants listed
above, whose tariff determination falls under the jurisdiction of the Commission, shall
be same as for the new plants given in the sub clause (1) to (5) above
corresponding to the capacity/type of the plant.
(7) For the generating unitsthat undergo renovation and modernization: the
Commission shall specify a separate set of norms of operation to be adopted
during the renovation and modernization period and for the subsequent
period. These norms shall be specified by the Commission on case to case
basis as part of the renovation and modernization capital investment approval
and shall prevail over the norms specified in these Regulations. The
generation tariff shall be determined accordingly by the Commission for such
generating units.
(a) Expenses on secondary fuel oil (in Rs.) shall be computed corresponding to
normative secondary fuel oil consumption (SFC) specified in this Regulation,
in accordance with the following formula:
Where,
Page 68 of 128
(b) Initially, the landed cost of secondary fuel oil shall be considered based on
the weighted average price of secondary fuel oil during the three preceding
months and in the absence of landed costs for the three preceding months,
latest procurement price for the generating plant, before the start of the
year shall be considered
(c) The secondary fuel oil expenses shall be subject to fuel price adjustment at
the end of each year of tariff period as per following formula:
Where,
LPSFy = Weighted average landed price of secondary fuel oil for the
Year in Rs./ml.
(b) A generating plant shall recover full capacity charge at the normative
annual plant availability factor specified by the Commission. Recovery of
capacity charge below the level of target availability shall be on pro-rata
basis. No capacity charge shall be payable at zero availability. Total
recovered fixed charges for a Unit up to the end of a month shall not be
more than the admissible approved fixed charges for that Unit as worked
out corresponding to the cumulative PLF (after including deemed
generation) up to the end of that month. For example, at the end of 3rd
month, if the deemed PLF is 80% and the normative PLF is 85%, the
admissible approved fixed charges would be AFC/4 (0.80/ 0.85) where
AFC are the approved annual fixed charges. In case cumulative PLF at
the end of 3rd month is more than the normative PLF, the admissible
approved fixed charges will be AFC/4;
(c) The capacity charge payable to a thermal generating plant (in Rs.) for a
calendar month shall be calculated in accordance with the following
formula: -
CC1= (AFC/12)( PAF1 / NAPAF ) subject to ceiling of (AFC/12)
CC2 =((AFC/6)( PAF2 / NAPAF ) subject to ceiling of (AFC/6)) – CC1
Page 69 of 128
CC3 =((AFC/4) ( PAF3 / NAPAF ) subject to ceiling of (AFC/4)) – (CC1+CC2)
CC4 =((AFC/3) ( PAF4 / NAPAF ) subject to ceiling of (AFC/3)) – (CC1+CC2+CC3)
CC5 = ((AFC x 5/12) ( PAF5 / NAPAF ) subject to ceiling of (AFC x 5/12)) – (CC1+CC2 +CC3+CC4)
CC6 = ((AFC/2) ( PAF6 / NAPAF ) subject to ceiling of (AFC/2)) – (CC1+CC2+CC3+CC4 + CC5)
CC7= ((AFC x 7/12) ( PAF7 / NAPAF ) subject to ceiling of (AFC x 7/12)) – (CC1+CC2 +CC3 +CC4 + CC5 + CC6)
CC8 = ((AFC x 2/3) ( PAF8 / NAPAF ) subject to ceiling of (AFC x 2/3)) – (CC1+CC2 +CC3 +CC4 + CC5 + CC6 + CC7)
CC9 = ((AFC x 3/4) ( PAF9 / NAPAF ) subject to ceiling of (AFC x 3/4)) – (CC1+CC2 +CC3 +CC4 + CC5 + CC6 + CC7+
CC8)
CC10=((AFC x 5/6) ( PAF10 / NAPAF ) subject to ceiling of (AFC x 5/6)) – (CC1+CC2 +CC3 +CC4 + CC5 + CC6 + CC7
+ CC8 + CC9)
CC11 = ((AFC x 11/12) ( PAF11 / NAPAF ) subject to ceiling of (AFC x 11/12)) – (CC1+CC2+CC3 +CC4 + CC5 + CC6 +
CC7 + CC8 + CC9 + CC10)
CC12 = ((AFC) ( PAFY / NAPAF ) subject to ceiling of (AFC)) – (CC1+CC2+CC3+CC4 + CC5 + CC6 + CC7 + CC8 +
CC9 + CC10 + CC11)
Provided that in case of generating station or unit thereof is under shutdown due to
Renovation and Modernization, the generating company shall be allowed to recover O&M
expenses and interest on loan only.
Where,
AFC = Annual fixed cost specified for the year, in Rupees.
NAPAF = Normative annual plant availability factor in percentage.
PAFn = Percent Plant availability factor achieved upto the end of the nth month.
CC1, CC2, CC3, CC4, CC5, CC6, CC7, CC8, CC9, CC10, CC11 and CC12 are the
Capacity Charges of 1st, 2nd, 3rd, 4th, 5th, 6th, 7th, 8th, 9th, 10th, 11th and 12th months
respectively.”
Note: Till Intra – State ABT is implemented, Plant Availability Factor (PAF),
wherever mentioned, shall mean Plant Load Factor (PLF). For working out
annual PLF for the purpose of recovery of annual fixed charges, deemed
generation on account of backing down on the instructions of SLDC or on
the request of Discoms shall be included.
The fixed cost of a thermal generating station shall be computed on annual basis
based on the norms specified under these regulations and recovered on monthly
basis under capacity charge. The total capacity charge payable for a generating
station shall be shared by its beneficiaries as per their respective percentage share
or allocation in the capacity of the generating station. The capacity charge shall be
recovered under two segments of the year, i.e. High Demand Season (period of
three months) and Low Demand Season (period of remaining nine months), and
within each season in two parts viz., Capacity Charge for Peak Hours of the month
and Capacity Charge for Off-Peak Hours of the month as follows:
Page 70 of 128
Capacity Charge for the Year (CCy) =Sum of Capacity Charge for three
months of High Demand Season +Sum of Capacity Charge for nine
months of Low Demand Season
Capacity Charge for the Month (CCm) =Capacity Charge for Peak Hours
of the Month (CCp) +Capacity Charge for Off-Peak Hours of the Month
(CCop)
Page 71 of 128
Provided that in case of generating station or unit thereof under shutdown
due to Renovation and Modernisation, the generating company shall be
allowed to recover O&M expenses and interest on loan only.
Where,
PAFMpn = Plant Availability Factor achieved during Peak Hours upto the
end of nth Month in a Season;
(3) Normative Plant Availability Factor for “Peak” and “Off-Peak” Hours in
a month shall be equivalent to the NAPAF specified in these Regulations.
The number of hours of “Peak” and “Off-Peak” periods during aday shall
be four and twenty respectively. The hours of Peak and Off-Peak periods
during a day shall be declared by the SLDC at least a week in advance.
The High Demand Season (period of three months, consecutive or
otherwise) and Low Demand Season (period of remaining nine months,
consecutive or otherwise) in a region shall be declared by the SLDC, at
least six months in advance:
Page 73 of 128
Charge for cumulative Peak Hours derived based on NAPAF, shall not be
allowed to be off-set by over-achievement of PAF, if any, and consequent
notional over-recovery of Capacity Charge for cumulative Off-Peak Hours
in that Season.
(5) The Plant Availability Factor achieved for a Month (PAFM) shall be
computed in accordance with the following formula:
Where,
DCi = Average declared capacity (in ex-bus MW), for the ith day of the
period i.e. the month or the year as the case may be, as certified by the
State load dispatch centre after the day is over.
Note: DCi and IC shall exclude the capacity of generating units not
declared under commercial operation. In case of a change in IC during
the concerned period, its average value shall be taken.
Provided further that in case HPGCL’s power stations are backed down
on the instructions of the DISCOMs and at the same time the Discoms
are drawing power at a lower rate from some other sources i.e.
generators, traders etc. or resorting to drawls under UI mechanism, the
Discoms shall compensate HPGCL to the extent of fixed cost
corresponding to loss of generation due to backing down. In such cases
HPGCL shall have the right to sell power not scheduled by the Discoms
Page 74 of 128
to a third party provided any revenue earned on this account shall first be
adjusted against the fixed cost to be recovered from the Discoms.
(a) The Energy charges or variable charges shall cover the main fuel cost &
secondary fuel oil and shall be payable for the total energy scheduled to
be supplied to a beneficiary during the calendar month on ex-power plant
basis, at the specified variable charge rate, with fuel price adjustment.
(b) The Energy charge for the month shall be worked out on the basis of ex-
bus energy scheduled to be sent out from the generating plant in
accordance with the following formula:
= Energy Charge Rate (Rs. / kWh) x Scheduled Energy (ex-bus) for the
month (kWh)
Note: Till the time intra state ABT is implemented, ‘scheduled energy’ may
be read as ‘actual energy sent’.
(c) Energy charge rate (ECR) in Rs. per kWh on ex-power plant basis shall
be determined to three decimal places in accordance with the following
formula:
[[{SHR-(SFCXCVSF) X LPPF}/CVPF]+(SFCXLPSF)]x{100/(100-Aux)}
(ii) In case secondary fuel Oil cost is not the part of ECR
[{SHR-(SFCXCVSF) X LPPF}/CVPF]x{100/(100-Aux)}
Where
Page 75 of 128
LPPF =Weighted average landed price of primary fuel in Rs./kg.
The landed cost of fuel for the month shall include price of fuel
corresponding to the grade and quality of fuel inclusive of royalty, taxes and
duties as applicable, transportation cost by rail/road or any other means, for
the purpose of computation of energy charge and in case of coal, shall be
arrived at after considering normative transit/moisture and handling losses as
percentage of the quantity of coal dispatched by the coal supply company
during the month as follows:
HPGCL shall claim FPA as per the details provided here under: -
Initially gross calorific value of coal shall be taken as per actual in the
preceding financial year for which data is available. Any deviation shall be
adjusted based on the gross calorific value of coal received and burnt and
landed cost incurred by the generating company for procurement of coal on
month to month basis. No separate petition shall be required to be filed with
the Commission for fuel price adjustment. In case of any dispute related to
primary fuel price adjustment, an appropriate application in accordance with
Haryana Electricity Regulatory Commission (Conduct of Business) Regulations,
2004, as amended from time to time or any statutory re-enactment thereof,
shall be made by the affected party before the Commission. For determining
fuel price adjustment (FPA) amount the following formula shall be adopted:-
Page 76 of 128
Where,
Provided that the above provision in the Regulation shall continue as an option
available to the Commission and shall be implemented as and when considered
feasible by the Commission except for the HPGCL’s power plants of old vintage at
Panipat.
Page 77 of 128
2. The intra-State Generator may be directed by SLDC concerned to operate its
unit(s) at or above the technical minimum but below the normative plant availability
factor on account of grid security or due to the fewer schedules given by the
beneficiaries.
Provided that:
(i) In case of coal / lignite based generating stations, following station heat rate
degradation or actual heat rate, whichever is lower, shall be considered for the
purpose of compensation: -
3 65 - 74.99 2 4
4 55 - 64.99 3 6
(ii) In case of coal / lignite based generating stations, the following Auxiliary Energy
Consumption degradation or actual, whichever is lower, shall be considered for the
purpose of compensation:
1 85 – 100 NIL
2 75 – 84.99 0.35
3 65 – 74.99 0.65
4 55 - 64.99 1.0
Page 78 of 128
(iii) Where the scheduled generation falls below the technical minimum schedule, the
SLDC concerned shall have the option to go for reserve shut down and in such
cases, start-up fuel cost over and above seven (7) start / stop in a year shall be
considered as additional compensation based on following norms or actual,
whichever is lower:
200/210/250 MW 20 30 50
500 MW 30 50 90
660 MW 40 60 110
(v) Compensation for the Station Heat Rate and Auxiliary Energy Consumption shall
be worked out in terms of energy charges.
(vi) The compensation so computed shall be borne by the entity who has caused
the plant to be operated at schedule lower than corresponding to Normative Plant
Availability Factor up to technical minimum based on the compensation mechanism
finalized by the SLDC.
(vii) No compensation for Heat Rate degradation and Auxiliary Energy Consumption
shall be admissible if the actual Heat Rate and / or actual Auxiliary Energy
Consumption are lower than the normative Station Heat Rate and / or normative
Auxiliary Energy Consumption applicable to the unit or the generating station.
(viii) There shall be reconciliation of the compensation at the end of the financial
year in due consideration of actual weighted average operational parameters of
station heat rate, auxiliary energy consumption and secondary oil consumption.
(ix) No compensation for Heat Rate degradation and Auxiliary Energy Consumption
shall be admissible if the actual Heat Rate and / or actual Auxiliary Energy
Consumption are lower than the normative station Heat Rate and/or normative
Auxiliary Energy Consumption applicable to the unit or the generating station in a
month or after annual reconciliation at the end of the year.
Page 79 of 128
above provisions in the PPAs entered into by it for sale of power in order to claim
compensations for operating at the technical minimum schedule.
5. The generating company shall keep the record of the emission levels from the
plant due to part load operation and submit a report for each year to the
Commission by 31st May of the year.
7. The SLDC shall work out a mechanism for compensation for station heat rate
and auxiliary energy consumption for low unit loading on monthly basis in terms of
energy charges and compensation for secondary fuel oil consumption over and
above the norm of 0.5 ml/kWh for additional start-ups in excess of 7 start-ups, in
consultation with generators and beneficiaries including its sharing by the
beneficiaries.
Norms of operation and determination of tariff for hydro power plants other than
those covered under renewable energy sources, shall be as under:-
34.1 The tariff for sale of electricity from a Hydro Generating Station shall comprise
of two parts, namely, the Capacity Charge and Energy Charge.
(a) Depreciation;
Page 80 of 128
Provided that Depreciation, interest and finance charges on Loan Capital, Interest on
Working Capital and Return on Equity for Hydro Generating Stations shall be
allowed in accordance with the provisions specified in these Regulations:
34.3 The norms of operation for existing hydro generating stations for recovery of
Annual Fixed Charges shall be as under:-
80% 1
80% 1
The following Normative Annual Plant Availability Factor CNAPAF) shall apply to
other hydro generating stations for recovery of Annual Fixed Charges:
a) Storage and Pondage type plants with head variation between Full Reservoir
Level (FRL) and Minimum Draw Down Level (MDDL) of up to 80%, and where
plant availability is not affected by silt: 90%
b) In case of storage and pondage type plants with head variation between full
reservoir level and minimum draw down level is more than 8% and when plant
availability is not affected by silt, the month wise peaking capability as provided by
the project authorities in the DPR (approved by CEA or the State Government) shall
form basis of fixation of NAPAF.
c) Pondage type plants where plant availability is significantly affected by silt: 85%.
The following Auxiliary Energy Consumption shall apply to other Hydro Stations
(2) The O&M expenses for each subsequent year will be determined by
escalating the base expenses determined above, at the escalation factor of 4%.
Where;
i= 1
2. The Energy Charge shall be payable by every beneficiary for the total energy
supplied to the beneficiary, excluding free energy for home state (FEHS), if
any, during the calendar month on ex-power plant basis, at the computed
Energy Charge rate.
Total Energy Charge payable to the Generating Company for a month shall
be:
(Energy Charge Rate in Rs./kwh) x {Energy (ex-bus)} for the month in kWh x
(100-FEHS)/100 .
3. Energy Charge Rate (ECR) in Rupees per kWh on ex-power plant basis, for
a Hydro Generating Station, shall be determined up to three decimal places
based on the following formula:
Where;
(i) in case the energy shortfall occurs within ten years from the date of
commercial operation of a generating station, the ECR for the year following
the year of energy shortfall shall be computed based on the formula specified
in these Regulations with the modification that the DE for the year shall be
considered as equal to the actual energy generated during the year of the
shortfall, till the Energy Charge shortfall of the previous year has been made
up, after which normal ECR shall be applicable;
(ii) in case the energy shortfall occurs after ten years from the date of
commercial operation of a generating station, the following shall apply:-
Suppose the specified annual Design Energy (DE) for the station is DE
MWh, and the actual energy generated during the relevant (first) and the
Page 83 of 128
following (second) financial years are Al and A2MWh, respectively, Al being
less than DE, then the Design Energy to be considered in the formula in
these Regulations for calculating the ECR for the third financial year shall be
moderated as (A1 + A2 - DE) MWh, subject to a maximum of DE MWh and
a minimum of Al MWh;
ln case the Energy Charge Rate (ECR) for a hydro generating station, as
computed in Regulation above exceeds ninety paise per kWh, and the actual
saleable energy] in a year exceeds {DE x (100 - AUX) x (100-FEHS)/
10000) MWh, the Energy Charge for the energy in excess of the above
shall be billed at ninety paise per kWh only:
Provided that in a year following a year in which the total energy generated
was less than the design energy for reasons beyond the control of the
Generating Company, the Energy- Charge Rate shall be reduced to ninety
paise per kWh after the energy charge shortfall of the previous year has
been made up.
The State Load Dispatch Centre shall finalize the schedules for the hydro
generating stations, in consultation with the beneficiaries, for optimal
utilization of all the energy declared to be available, which shall be
scheduled for all beneficiaries in proportion to their respective allocations in
the generating station.
For the purpose of determination of tariff, the capital cost and additional
capitalisation for Hydro Power Plants shall be allowed/approved in accordance
with the provisions outlined under Regulation 18.
(a) As and when intra state ABT is implemented, all variations between actual
net injection and scheduled net injection for generating plant, and all
variations between actual net drawl and schedule net drawl for beneficiaries
shall be treated as their respective unscheduled interchanges (UI) and will
be dealt with as per the intra-State ABT Regulations to be notified by the
Commission.
(b) The profit and loss on account of unscheduled interchange shall be to the
account of the generating company.
Page 84 of 128
36 SCHEDULING
The methodology for scheduling and dispatch for the generating plant shall
be as specified in the Haryana Grid Code/IEGC and the intra state ABT
Regulations to be notified by the Commission as amended from time to time.
Until the intra-State ABT Regulations are notified by the Commission CERC
ABT Regulations would be applicable.
(b) SLDC and transmission charges paid for energy sold outside the state, if
any, shall not be considered as expenses for determining generation tariff.
38 REACTIVE ENERGY
A generating station shall inject/absorb the reactive energy into the grid as
per the directions of State Load Despatch Centre. Such injection/absorption
may be undertaken on the basis of machine capability and in accordance
with the directions issued by SLDC as per the provisions of Haryana Grid
Code as amended from time to time.
(ii) The operating log books of the generating plant shall be available for
review by the State Load Dispatch Centre. These books shall contain
record of machine operation and maintenance.
(iii) The SLDC shall provide to the Commission any data/information in the
context of demonstration of declared capacity by a generating company
Page 85 of 128
or in the context of any other issue concerning system operation/security
as may be asked for by the Commission.
(ii) Processed data of the meters along with data relating to declared
capacities and schedules etc shall be supplied by State Load Dispatch
Centre to the State Transmission Utility;
(iii) For all purpose, the Standards for Metering and Accounting specified in
the Haryana Grid Code Regulations 2009, intra-State ABT Regulations
to be notified by the Commission and the Central Electricity Authority
(Installation and Operation of Meters) Regulations 2006 notified by the
CEA, shall be adopted and followed. Until the intra-State ABT
Regulations are notified by the Commission, CERC ABT Regulations
would be applicable.
(i) Bills shall be raised for capacity charges, and energy charges on
monthly basis by the generating company in accordance with these
Regulations, and applicable payments shall be made by the beneficiaries
directly to the generating company.
(ii) Payment of the capacity charges for a thermal generating plant shall be
shared by the beneficiaries of the generating plant as per their
percentage allocated share for the month (inclusive of any allocation out
of the unallocated capacity) in the installed capacity of the generating
plant.
0-7 2.0
8-14 1.0
15-21 0.5
Page 86 of 128
22-30 0.25
In case the payment of any bill for charges payable under these Regulations
is delayed by the beneficiary beyond a period of 30 days from the date of
receipt of bill, a late payment surcharge at the rate of 0.04% per day shall
be levied by the generating company and shall be payable by the
beneficiaries.
(b) Any revenue earned by the generating company from sale of infirm
power after accounting for the fuel expenses shall be applied for reduction in
capital cost. Any loss on this account shall not be taken into consideration.
45 NON-TARIFF INCOME
(a) All incomes being incidental to electricity business and derived by the
generating company from sources, including but not limited to profit derived
from disposal of assets, rents, miscellaneous receipts from the beneficiaries,
etc. shall constitute non-tariff Income of the generating company;
Provided that the generating companyshall submit full details of his forecast
of non-tariff income to the Commission in such form as may be stipulated by
the Commission from time to time;
Provided that Late Payment Surcharge and Interest on Late Payment earned
by the Generating Company shall not be considered under Non-tariff Income;
(c) The “non-tariff income” shall include but shall not be limited to the
following:
Page 87 of 128
vi. Interest on advances to suppliers/contractors;
xiii. Interest on investments, fixed and call deposits and bank balances;
Page 88 of 128
PART VI - PRINCIPLES FOR DETERMINATION OF TARIFF AND NORMS OF
OPERATION FOR TRANSMISSION BUSINESS
Provided also that for AC system, two trippings per year shall be allowed, and
after two trippings in a year, additional 12 hours outage shall be considered in
addition to the actual outage:
The actual audited Employee cost (excluding terminal liabilities) and A&G
expenses for the financial year preceding the base year, subject to
prudence check, shall be escalated at the escalation factor of 4% to
arrive at the Employee cost (excluding terminal liabilities) and A&G
expenses for the base year of the control period. The O&M expenses for
the nth year of the control period shall be approved based on the formula
given below:
Where,
▪ EMPn – Employee costs of the transmission licensee for the nth year
excluding terminal liabilities;
Page 89 of 128
▪ A&Gn – Administrative and general costs of the transmission licensee
for the nth year;
Where,
▪ GFA is the average value of gross fixed assets for the nth year;
▪ INDXnmeans the inflation factor for the nth year as defined herein
after:
Where,
Note: As and when any material price index specific to power sector or a
more relevant Index becomes available, the same shall replace the Index
used for working out R&M cost.
Consumer Price Index for Industrial Workers (all India) as per Labour
Bureau, Government of India in the previous year
Page 90 of 128
Note 1: For the purpose of estimation, the same INDXn value shall be
used for all years of the control period. However, the Commission will
consider the actual values in the INDX n at the end of each year during
the mid-year performance review and true-up exercise and true-up the
employee cost and A&G expenses on account of this variation.
(a) The trajectory for, intra-state transmission loss, during the control period
shall be as under:
(b) The losses shall be borne by the beneficiaries in kind. The SLDC shall
reduce the demand scheduled by the beneficiaries during each time
block by the 12 months rolling transmission losses (the said period will
be the 12 months period proceeding the relevant month by 3 months).
The SLDC shall post the rolling 12 months losses regularly on its
website. The SLDC, however, shall develop necessary software for
working out rolling 52-week losses and reduce the scheduled demand
accordingly thereafter.
(c) If the actual annual transmission losses (%) exceed the benchmark
value (%) approved by the Commission, the licensee(s) shall be
penalized in the following manner:
Page 91 of 128
Percentage increase Penalty
above the Loss level
specified by the
Commission
Upto 5% No Penalty
46 NON-TARIFF INCOME
(a) All incomes being incidental to electricity business and derived by the
licensee from sources, including but not limited to profit derived from disposal
of assets, rents, miscellaneous receipts from the beneficiaries, etc. shall
constitute non-tariff Income of the licensee;
Provided that the transmission licensee shall submit full details of his forecast
of non-tariff income to the Commission in such form as may be stipulated by
the Commission from time to time;
Provided that Late Payment Surcharge and Interest on Late Payment earned
by the the Licensee shall not be considered under Non-tariff Income;
Page 92 of 128
(c) The “non-tariff income” shall include but shall not be limited to the
following:
xii. Deferred Income from grant, subsidy, etc., as per Annual Accounts;
xiv. Interest on investments, fixed and call deposits and bank balances;
(a) The charges payable by the short-term open access consumers shall
be as specified in the intra-State open access Regulations notified by the
Commission and as amended from time to time;
‘(b) Intra State Transmission Charges and SLDC charges applicable to short
term open access consumers shall not be applicable on short term power
purchase/sale by the long-term and medium-term beneficiaries of the
transmission licensee
(c) 25% of the charges collected from the short-term open access consumers
on account of application money and transmission charges shall be retained
by the transmission licensee and the balance 75% shall be considered as
non-tariff income and adjusted towards reduction in the transmission charges
payable by the long term and medium-term users.
(a) The reactive energy charges shall be as provided in the Haryana Grid
Code as amended from time to time.
Page 93 of 128
(b) Reactive energy charge shall be payable and shared as per Regulation
5.5.1 of Haryana Grid Code (HGC) Regulation, 2009 as amended from
time to time;
(c) Reactive energy account shall be maintained and operated as per the
intra-State ABT Regulations to be notified by the Commission and as
amended from time to time. Until the intra-State ABT Regulations are
notified by the Commission, CERC ABT Regulations shall be applicable;
(d) The reactive energy charges from embedded open access consumers
shall be recovered by the distribution licensee by apportioning the total
reactive energy drawn during the month in the ratio of energy drawn
through open access and the energy drawn from the distribution
licensee. The reactive energy charges shall be recovered for the
apportioned reactive energy corresponding to energy drawn through
open access at the applicable rate.
Page 94 of 128
transmission charges leviable on each beneficiary shall be
computed as per the following formula.
ATC CA
12 CS
Where,
Provided further that the Long Term and Medium-Term beneficiaries of the
Transmission System shall pay no other charges for the use of
Transmission Network of STU.
Provided also that the transmission charges shall be payable by the short-
term open access consumers for the scheduled energy drawl at per kWh
rate as worked out by dividing the annual transmission charges by the
total volume of energy transmitted by the transmission licensee during the
previous year. Provided further that Intra-State charges payable by the
Open Access Consumers shall not be applicable on short term Open
Access power purchase / sales by the Distribution Licensee.
Page 95 of 128
51.1.1The aggregate of the yearly revenue requirement for all Transmission
Licensees, less the deductions, as approved by the Commission for
a financial year, shall form the “Total Transmission Cost” (TTC) of
the Intra State transmission system, to be recovered from the
Long-term and Medium term Transmission System Users (TSUs) for
that financial year, in accordance with the following formula:
n
TTC= ∑ (ARRi- NTi- Oi) – STR
i=1
Where,
STR = Revenue from short-term open access charges recovered and not
allowed to be retained during previous financial year.
Page 96 of 128
same manner as provided for in Regulation 50 for sharing of
annual transmission charges.
“The annual charges of SLDC determined as per Regulations 6 and 16, shall be
recovered as a single composite charge from the beneficiaries as under:
(i) The SLDC charges shall be levied by the Transmission licensees / STU, also
designated as the SLDC, on the basis of weighted average of the lines (Ckt. km)
owned by the Intra State Transmission Licensee(s) as on the last day of the month
prior to billing of the month.
_________
Total __XXX___
(ii) The SLDC charges from the generating companies and sellers (which Exclude
short term open access consumers) shall be collected in proportion to their installed
capacity /contracted capacity as on the last day of the month prior to billing of the
month.
(iii) The SLDC charges from distribution licensees and buyers (which exclude short
term open access consumers) shall be collected in proportion to the sum of their
allocated transmission capacity in MVA as on the last day of the month prior to
billing of the month.
Page 97 of 128
(v)Any deviation in the value of annual SLDC charges determined and collected
from the beneficiaries shall be trued up during the mid-year performance review and
true-up.
(vi) For the purpose of recovery of SLDC charges from the entity which has entered
into a long term open access / Medium Term open access agreement with STU,
shall be considered under the category in wunhich it has applied/signed the Long
Term/Medium Term Open Access agreement i.e. generator/supplier or distribution
licensee/buyer”.
The short-term open access consumers shall pay composite SLDC charges as
provided in HERC (Terms and conditions for grant of connectivity and open access
for intra–State transmission and distribution system), Regulations, 2012 as amended
from time to time. The total receipt of SLDC charges from short term open access
consumers shall be utilised to reduce the SLDC charges payable by the
beneficiaries.
54.1 The State Transmission Utility shall raise bills for SLDC and
transmission charges payable by the beneficiaries on a monthly basis.
The STU shall raise bills for UI charges on weekly basis as and when
intra state ABT is implemented. UI accounting procedures shall be
governed by intra-state ABT Regulations to be notified by the
Commission as amended from time to time.
0-7 2
8-14 1
15-21 0.5
22-30 0.25
Page 98 of 128
receipt of bill, a late payment surcharge of 0.04% per day shall be
payable by the beneficiary.
c) System Reliability
The Transmission Licensee in its Business Plan filings shall submit and
propose the trajectory for the achievement of quality targets including
reduction in the frequency of interruptions. The Commission shall specify the
targets for each parameter. The Transmission Licensee shall submit its
performance on each parameter in the form and manner specified by the
Commission. In the case of frequency of interruptions being high the same
will have bearing on the level of incentive allowed for availability.
Page 99 of 128
PART VII - PRINCIPLES FOR DETERMINATION OF TARIFF AND NORMS OF
OPERATION FOR DISTRIBUTION BUSINESS
(a) The distribution loss shall be equal to the difference between the energy
injected into the distribution system (X) and the sum of energy sold to all
its consumers (Y);
(b) Energy sold shall be the sum of metered sales and assessed unmetered
sales, if any, based on approved methodology/ norms. The percentage
distribution loss shall be as follows:
(c) The distribution licensee shall file the loss trajectory in the business plan
commensurate with the capital investment plan. The Commission after
verification and evaluation of the same shall approve the loss trajectory
for each year of the control period;
(d) The distribution loss level will be linked to a normative load factor for
unmetered agriculture consumers. The distribution licensee shall establish
consumption of unmetered agriculture consumers through a representative
and reliable energy audit/sample tube well metering/sample DT metering/
meter readings of the 11 kV segregated AP feeders and submit requisite
data for consideration of the Commission.
Provided that the Distribution loss trajectory for the control period shall be
decided by the Commission in the MYT Order, considering the past
performance data, estimate of distribution losses for each year of the
control period submitted by the Distribution Licensees in their MYT Petition,
industry bench marks/norms and after consideration of other relevant
factors considered appropriate by the Commission. The distribution licensee
shall submit appropriate feeder wise losses data along with its plans to
bring the same within the industry benchmark and accordingly calculate
and submit the loss reduction trajectory along with the MYT petition for the
first year of the second control period.
(e) In the absence of requisite data in respect of such energy audit / sample
surveys / sample DT metering/ meter readings of segregated 11kV AP
feeders, the Commission shall not accept the claim of the distribution
where,
The norms for Collection Efficiency for the distribution licensee(s) shall be
99.50% for every year of this Control Period.
Besides the Collection Efficiency, the Commission shall also monitor the
recovery of arrears of previous years for which the Commission shall
prescribe the targets and shall accordingly assess the performance of the
licensee with regard to recovery of arrears.
The Distribution Licensee shall file AT&C Loss trajectory for monitoring
AT&C Losses.
% AT&C losses=100-CEx(1-DL/100)
The actual audited expenses for the financial year preceding the base year,
subject to prudence check, shall be escalated at the escalation factor of 4%
to arrive at the Employee Costs and Administrative and General Costs for
the base year of the control period. The O&M expenses for the nth year of
the control period shall be approved based on the formula given below.
Where,
Where,
▪ ‘GFA’is the average value of the gross fixed asset of the nth year.
▪ ‘INDXn’means the inflation factor for the nth year as defined herein
after.
Where,
Note 1: For the purpose of estimation, the same INDXn value shall be
used for all years of the control period. However, the Commission
shall consider the actual values of the INDXn at the end of each year
during the annual performance review exercise and true-up the
employee cost and A&G expenses on account of this variation.
Note 3: As and when any material price index specific to power sector
or a more relevant Index becomes available, the same shall replace
the Index used for working out R&M cost.
Consumer Price Index for Industrial Workers (all India) as per Labour
Bureau, Government of India in the previous year
58.1 The distribution licensee shall forecast monthly sales for each
customer category and sub-categories for all years of the control
period in their business plan and ARR filings, for review and approval
by the Commission.
58.2 So long as there are any un-metered agriculture consumers, the sales
forecast for unmetered agriculture consumer shall be validated with
norms approved by the Commission on the basis of a proper study
carried out by the distribution licensee.
58.3 The Commission shall examine the forecasts for their reasonableness
based on growth in the number of consumers, pattern of consumption,
losses and demand of electricity in previous years and anticipated
growth in the subsequent years and any other factor, which the
Commission may consider relevant and approve the sales forecast with
such modifications as deemed fit;
58.6 Based on the above, the distribution licensee shall project month- wise
and source-wise power purchase requirement for each year of the
control period.
58.7 The Commission shall scrutinize and approve the requirement for
purchase of power with such modifications as deemed fit, for each
year of the control period;
58.8 Any power purchased by the distribution licensee over and above the
requirement of power approved by the Commission or variation in the
mix of power purchased in any year shall be considered by the
Commission if it is for reasons beyond the control of the distribution
licensee(s). The Commission shall, however, estimate the revenue from
Page 104 of 128
such sales and allowable quantum of power purchase based on target
losses as per the FSA mechanism approved by the Commission. The
resultant cost and revenue shall be adjusted during true-up exercise
for the said financial year in the next year’s tariff;
59.1 The distribution licensee shall be allowed to recover the cost of power
it procures from all approved sources including the power procured
from the State-owned generating stations, independent power
producers, Central generating stations, renewable energy sources and
others, for supply of power to consumers, based on the sales forecast
and losses for the distribution licensee approved by the Commission
for each year of the control period;
59.3 While approving the cost of power purchase, the Commission shall
determine the quantum of power to be purchased from various sources
in accordance with the principles of merit order schedule and despatch
based on a ranking of all approved sources of supply in the order of
their variable cost of power. All power purchase costs will be
considered legitimate unless the Commission concludes that the merit
order principle has been violated or power has been purchased at
unreasonable rates except for marginal purchases of transient nature
beyond the control of the licensee subject, however, to Regulation
59.2;
59.7 Any loss on account of increase in power purchase cost, not covered
above, shall be borne by the distribution licensee subject to regulations
12 regarding sharing of gains and losses.
60.1 The distribution licensee shall submit a rolling quarterly forecast of the
quantum of short-term power to be purchased for the year for the
Commission’s approval. The forecast shall be based on monthly sales
forecast, the power available from approved long-term sources of
power, merit order dispatch of available sources, banking with other
distribution utilities, load curtailment, time of its requirement, availability
of short-term power and the expected price. The distribution licensee
shall provide the basis for forecast of short-term power procurement
price including the criteria for evaluation of alternative options;
Provided that the cost of the additional power shall be allowed at the
ceiling price for short term power determined by the Commission in
accordance with Regulation60.2.
60.4 The variation in actual quantum and price of short-term power vis-a-vis
the quantum and price of short-term power approved by the
Commission shall be subjected to prudence check by the Commission
and shall be adjusted on yearly basis along with the annual
performance review based on the price and quantum cap determined
by the Commission for each quarter as mentioned in the above
Regulation.
62.1 The consumers availing wheeling services for ‘open access’, will be
charged a wheeling tariff as determined under these Regulations;
63.3 The distribution licensee shall also submit along with ARR, requisite
calculation for determination of cross subsidy surcharge and additional
surcharge for consideration of the Commission. The cross-subsidy
surcharge and additional surcharge shall be payable as determined by
the commission from time to time.
Bad and doubtful debts shall be allowed to the extent the distribution
licensee has actually written off bad debts subject to a maximum of
0.5% of sales revenue. However, this shall be allowed only if the
distribution licensee submits all relevant data and information to the
satisfaction of the Commission. In case there is any recovery of bad
debts already written off, the recovered bad debts will be treated as
other income.
The Commission shall introduce various policies like Time of Day (ToD)
Tariff pertaining to Demand Side Management in order to flatten the Load
Curve of the State and optimise the Power Purchase Cost.
(i) The commission shall specify the norms for maximum permissible
distribution transformers’ failure rate separately for urban and rural
areas in the MYT order;
0 0
>0≤5 % 1%
>5≤10 % 2%
>10≤15% 3%
>15≤20% 5%
0 0
>0≤2.5% 1%
>2.5≤5% 2%
>5≤7.5% 3%
(i) The distribution licensee shall provide requisite report on the progress
of compliance of the performance parameters as specified in the
HERC (Standards of Performance for the Distribution licensee)
Regulations, 2004 as amended from time to time;
(ii) The transmission licensee shall also provide requisite report on the
progress of compliance of the performance parameters as may be
specified by the Commission in the “Standards of Performance for the
Transmission Licensee Regulations” to be notified by the Commission
and as amended from time to time.
(iv) The distribution licensee shall submit and upload on their website
circle-wise quarterly report containing the following for their respective
circle: -
(b) Distribution loss along with the reason for loss above 15%
(d) Sale of power and billing done in the previous quarter along with
the status of recovery.
The Distribution Licensees shall submit the following Audited Information for the
relevant Financial Year along-with their True-up Petitions:
o Fixed Charges,
o Energy Charges,
66.3 For the purpose of recovery of FSA, power purchase cost shall include
all invoices raised by the approved suppliers of power and credits
received by the distribution licensees during the quarter irrespective of
the period to which these pertain for any change in cost in accordance
66.4 In case of negative FSA, the credit shall be given to the consumers by
setting off the minus figure against the positive figure of FSA being
charged from the consumers. In other words, credit of FSA shall be
given only against FSA being charged so that the base tariff determined
by the Commission remains unchanged.
66.5 Only the allowed percentage of transmission and distribution losses for
the relevant year as per the approved ARR shall be considered for
working out FSA.
66.7 For moderation purposes, the recovery of per unit FSA shall be limited
to 15% of the approved per unit ‘average power purchase cost’ or such
other ceiling as may be stipulated by the Commission from time to time.
For calculating FSA, variations in quarterly purchase volume from an
approved source are allowed subject to an overall ceiling of annual
approved volume from that source. In case a portion of the FSA for any
quarter is not recovered due to the ceiling of 15%, the under recovered
amount shall be added to the FSA for the next quarter.
66.8 Per unit rate of FSA (paisa/kWh) shall be worked out after rounding off
to the nearest paisa;
66.9 The distribution licensee shall submit details relating to FSA recovery to
the Commission for each quarter in the following format by the end of
the following quarter.
(v) Actual cost of power purchase from all sources except (iv) (Rs.
million)
(vii) Total FSA estimated to be recovered for the quarter (Rs. million)
(viii) FSA per unit (Rs/kWh) being recovered during the following
quarter
(xi) Approved sales (Consumer category wise / month wise) for the
quarter (MU)
(xii) Actual sales (Consumer category wise / month wise) for the
quarter (MU)
(xiii) Estimated sales, consumer category wise, for the following quarter
(MU)
Note:
66.10 FSA (Rs/kWh) shall be worked out as per the following formula:
• Actual average power purchase cost (Rs. /KWh) = (total cost of power
purchased during the quarter from approved sources and UI as per
Regulation 66.2in Rs million) / (total volume of power purchased in the
quarter from approved sources and UI in MU) as per Regulation 66.2)
66.11 The licensee shall ensure that the Actual/ estimated FSA arising in a
quarter is recovered in the following quarter. In case the licensee does
not ensure levy of FSA based on the methodology given herein, the
licensee shall have no claim to recover the FSA from the consumers in
any manner in any subsequent period except in accordance with
Regulation 66(3) and 66(7). The unrecovered FSA for the previous
financial year, details of which are supplied to the Commission by the
distribution licensee, may either form part of power purchase cost for
the next financial year or may be allowed to be recovered as annual
adjustment amount in the quarterly recovery of FSA in the next financial
year as the Commission may decide.
67.1 All incomes being incidental to electricity business and derived by the
licensee from sources, including but not limited to profit derived from
disposal of assets, rents, meter rent, income from investments other
than contingency reserves, miscellaneous receipts from the consumers,
etc shall constitute non-tariff income of the licensee;
Provided that the distribution licensee shall submit full details of his
forecast of non-tariff income to the Commission in such form as may be
stipulated by the Commission from time to time.
67.3 The “non-tariff income” shall include but shall not be limited to the
following:
k. Miscellaneous receipts;
68. SUBSIDY
68.1 Pursuant to Section 65 of the Electricity Act, 2003 in case the State
Government requires grant of any subsidy to any consumer or class of
consumers in the tariff determined under Section 62, the distribution
licensee should ensure that the State Government shall, notwithstanding
any direction which may be given under Section 108, pay in advance
the requisite amount as determined by the Commission to compensate
the distribution licensee affected by the grant of subsidy.
69.1 The distribution licensee’s tariff proposal should reflect the reasonable
cost of providing service to each consumer class. In case where tariffs
are historically distorted with significant level of cross-subsidy, the aim
should be to gradually move to non-cross subsidized tariffs.
69.2 In the annual performance review and tariff application, the distribution
licensee shall include a report on how far they have implemented the
The distribution licensee shall file by 1st June and the generating company and the
transmission licensee by 1st August of the first year of the control period or any
other date as may be directed by the Commission, an application containing the
following elements for the approval of the Commission, along with requisite fee in
accordance with the provision of HERC (Fee) Regulation, 2005:
71.2 Tariff filing for the control period under MYT framework
71.2.1 The generating company and the licensees shall file an application for
approval of ARR for their respective businesses for each year of the
control period and tariff for the first year of the control period consistent
with the business plan and the capital investment plan approved by the
Commission. The ARR and tariff filing shall be filed by 30 th November
of the year preceding the 1st year of the control period along with
requisite fee in accordance with the provisions of Haryana Electricity
Regulatory Commission (Fee) Regulations amended from time to time.
The application shall contain all the components of the ARR and tariff
as provided in these Regulations;
71.2.2 The generation company and the licensees shall provide in the
application forecast for each year of the control period of the various
financial and operational parameters of ARR & various other
components of the ARR and tariff relating to their respective businesses
as mentioned in these Regulations. The application, in case of a
distribution licensee and a transmission licensee shall also include:
(a) Sales / demand forecast for each consumer category and sub-
categories for each year of the control period and the methodology and
rationale used;
(b) Power procurement plan based on the sales forecast and distribution
loss trajectory for each year of the control period. The power
(d) Expected revenue from the licensed business, non-tariff income and
income from other business for the base year and first year of the
control period and other matters considered appropriate by the
distribution licensee(s);
Voltage wise estimates losses and cost of supply for various consumer
categories per kW and per kWh / kVh
(f) The ARR for different years of the control period, the revenue gap
and tariff proposal for meeting the revenue gap for first year of the
control period. The tariff proposal should be based on the cost of supply
for various consumer categories and the cross-subsidy reduction road
map.
(g) Proposal for meeting the projected cumulative revenue gap for
first year of the control period which shall include mechanism for
meeting the proposed revenue gap, tariff revision for various consumer
categories etc. In the absence of tariff proposal, the application/petition
shall be considered as incomplete and shall be liable for rejection.
(a) The Transmission system or network usage forecast for each year of
the Control Period, consistent with the Business Plan;
(b) Proposal for transmission tariff design for each year of the
Control Period, including the losses to be charged and the procedure
thereof;
(c) Proposal for transmission tariff for each year of the Control Period
supported by the adequate justification;
(f) Proposal for SLDC charges (in case SLDC is controlled by the
transmission licensee);
71.3 The generating company and the licensee shall also provide a copy of
their respective ARR/tariff filing to each other and also host the same on
their respective websites;
71.4 The generating company and the licensees, within 7 (seven) days of
filing of the application for approval of ARR/Tariff, shall publish in Hindi
and English in daily newspapers having circulation in the area of licensees
/generation company, the contents of the application filed for approval of
ARR/Tariff in an abridged form in such manner as the Commission may
direct for information of the public and shall provide copies of the
application and other documents filed with the Commission at a price not
exceeding normal photocopying charges. The generating company and the
licensees shall also host the application and other documents on their
official websites.
71.5 The distribution licensee shall undertake a separate study to estimate the
cost of supply for various consumer categories and submit the same to the
Commission for its approval along with the MYT filing;
71.6 The distribution licensee shall also undertake a study for preparation of
road map for reduction of cross-subsidy and submit the same to the
Commission for its approval along with the MYT filing;
A Generating Company may also file a petition, not more than six
months prior to the anticipated Date of Commercial Operation (COD), for
determination of provisional tariff of the Unit or Stage or Generating
Station as a whole, as the case may be, based on the capital
expenditure actually incurred up to the date of making the petition or a
date prior to making of the petition, duly audited and certified by the
statutory auditors and the provisional tariff shall be charged from the date
of commercial operation of such Unit or Stage or Generating Station, as
the case may be.
Provided further that any difference in provisional tariff and the final tariff
determined by the Commission and not attributable to the Generating
Company may be adjusted at the time of determination of final tariff for
the following year as directed by the Commission.
The generating company and the licensees shall file their application for
mid-year performance review of the current year, true-up of the previous
year and tariff for the ensuing year along with requisite fee by 30 th
November of each year of the control period as per the details
mentioned in the Regulation 11 & 13 for the Commission’s review, true-
up of uncontrollable/controllable items in accordance with Regulation 8.3
and approval of tariff for the ensuing year.
72.1 The Commission shall, within one hundred and twenty (120) days from
the receipt of complete application and after considering all suggestions
and objections received from the public/other stakeholders:
72.2 The tariff so determined by the Commission shall be in force from the
date specified in the said order and shall, unless amended or
revoked, continue to be in force for such period as may be stipulated
therein.
The generating company and the licensees, as the case may be, shall publish
the tariff approved by the Commission in Hindi and English in daily newspapers
having wide circulation in Haryana and shall put up the complete tariff petition,
including annexure, and approved tariff / tariff schedule on its website and make
available for sale, a booklet containing such tariff or tariffs, as the case may be,
to any person upon payment of reasonable reproduction charges.
74.2 The generating company and the licensee shall submit information as part
of annual review on actual performance to assess the performance vis-à-
vis the targets approved by the Commission at the beginning of the
control period. This shall include annual statements of its performance
and accounts including latest available audited / actual accounts and the
tariff worked out in accordance with these Regulations.
74.3 The Commission may approve any modifications to the forecast of the
generating company or the licensee for the remainder of the control
period, with detailed reasons for the same.
Generating company and the licensee shall adhere to the following schedule
for various activities for the first control period:
Time Schedule for various activities for the 2nd Control Period
76. HEARING
76.1 The Commission may hold hearing(s) on the ARR/tariff filing and hear such
persons as the Commission may consider appropriate to decide on such
ARR/tariff filing.
76.2 The procedure of hearing on the ARR/Tariff filing shall be as per the
provisions of the HERC (Conduct of Business) Regulations, in vogue or in
the manner as the Commission may decide from time to time.
Subject to the provision of the Act and these Regulations, the Commission may,
from time to time, issue orders and directions in regard to the implementation of
these Regulations and procedure to be followed on various matters.
If any difficulty arises in giving effect to any of the provisions of these Regulations,
the Commission may, by a general or special order, not being inconsistent with the
provisions of these Regulations or the Act, do or undertake to do things or direct
the generating company or the licensee to do or undertake such things which
appear to be necessary or expedient for the purpose of removing the difficulties.
The Commission may in public interest and for reasons to be recorded in writing,
relax any of the provision of these Regulations.
80. INTERPRETATION
81.1 Nothing in these Regulations shall be deemed to limit or otherwise affect the
inherent power of the Commission to make such orders as may be necessary for
ends of justice or to protect consumers’ interest or to prevent the abuse of the
process of the Commission.
All enquiries, investigations and adjudications under these Regulations shall be done
by the Commission through the proceedings in accordance with the provisions of
the Conduct of Business Regulations, 2004 as amended from time to time.
The Commission, for reasons to be recorded in writing, may at any time vary, alter
or modify any of the provision of these Regulations after following the due process.
84. REPEAL
Appendix II
Depreciation Schedule
G Lightning arrestors:
H Batteries 5 5.28%
L Meters 15 5.28%
O Office equipments
Q Communication equipment
R IT equipment 6 15.00%