Tunneling in Soft Strata
Tunneling in Soft Strata
Tunneling in Soft Strata
475
476 A Textbook of Transportation Engineering
method is particularly suitable for brick lining. This method has the following disadvantages
() The efficient working of the system requires large number of trench jacks which interfare
with the working of the working party.
1. Concrete lining
,(1) 2. Trench jacks
(1)
(2)
3.1. Tunnelling with Needle Beam Method
Fig.
hand making the process tedious and time
(i) The heavy beams have to be pushed by
consuming.
Mechanical method of concrete lining becomes difficult as beams and bracings have to
(i)
used.
The process adopted is as below
the roof of the drifi and this in turm is
() Lagging carried on wooden segments supports cut in the sides of the monkey
two trench jacks which are set in hitches
drift whichbyitself is driven for a short distance of 90 cm on the working face beyond
supported
the day's work.
skidded forward into the monkey drift after the
(i) The 5 m long needle beam is slowly
drift indicated in sequence (i) above is completed.
the stout posts
(ii) The rear end of the needle beam is carried on stout posts which rest on
while the front end rests on planks on
resting on the lining of the floor of the tunnel
the floor of the drift
(iv) Other trench lacks are removed and the drift is widened sideways and supported by
lagging, segments and trench jacks.
For supporting the roof compressed air may be sued for supporting the roof.
(c) Flying Arch Method (see Fig. 3.2)
The liner plates of the arch are supported by trench jacks which rest on the bench. Each
day's work is concreted with half round arch forms.
3.3. SHIELD METHOD OF TUNNELLING (See Fig. 3.2 (a))
This method is particularly suitable for construction of tube railway tunnels in clay. The
machine consists of circular shield of thick steel plates with proper strong stiffeners. 1he
excavation may be carried out by hand (manual layout) or by the help of pneumatically operated
clay spades section. Hydraulic jacks are used for pushing the shield forward.
Parts of the shield are
() Cutting edge. It is provided with stiffeners and cuts into the earth to be excavated.
(i) Hood. It protects the workmen in the forward action.
(iin) Tail. It is normally of heavy cast iron and is the forward extension of the ring.
(iv) Propelling jacks. These jacks push the shield forward cutting the soil.
They permit the muck to flow into the completed portion of the shield port holes are provided
in the diaphragm. The shield is strengthened by circular box girder which carries the skin and
there are horizontal and vertical box girders for strengthening the ring beam.
477
Methods of Tunnelling in Soft Strata
These shields have been used in the European countries for tube railways and for tunnelling
work under rivers.
1. Shield plate
Holes for jacks
.00 /m K-
8m T 1. Skin plate
2. Cutting edge
(1) . Port
4. Vertical frame (2 3. Hood
4. Plateform for
5. Horizontal frame
6. Diaphragm miner
5. Face jack
a: Cross-section
(3 (6) 6. Propelling Jack
8) (4) 7. Cutting edge
8. Ring girder
(5)
(4 3.5m
(2) (7
(b) Longitudinal section
(a) Cross-section
increases production.
air and is
Plenum compressed air method. This method uses the compressed
() or
soft strata or water bearing grond. The equipment
associated
Specially useful for tunnelling over
(i) English
(iv) Belgian
Tunnelling in soft strata involves the following;
(a) Explosives are not required.
(6) Slow progress of work as wörk has to be carried out cautiously.
(c) Work by manual labour is adequate.
(d) Timbering for supporting the section is required.
below
Brief description of standard methods states above is given
() Forepoling method. (See Fig. 3.3)
shown in Fig. 3.3.
The ground ahead is supported by boards driven as
of breasting the forepoles act as
These ribs are known as 'Spiles'. Beyond the point
their forwardness are supported by steel ribs.
cantilever. They carry the weight of the ground till
(1)
(2) (2)
1. Cap
(1) 2. Shoulder timber
3. Wall plate
4. Strut
(2) 5. Post
6. Sill
3)
4. Cut to point
(3) R
(a) Excavating trench PORS. Cutting pockets in the trench sides to insert shores to underpin
the arch.
(e) Clearing alternating spaces between the shores and building supporting side masonry.
The important advantage of the method is that lighter sections are required.
3.5. TIMBERING
Timbering plays a very important role in the construction of tunnels. Particular method of
timbering is govermed by the design of the tunnel, characteristics of the soil, and size of the
tunnel, the design of timbering is as important as the design of the tunnel itself. Whatever be the
design following principles should serve 2s guide lines for the design of tinmbering
(a) Avoid having bending members as timber components.
(6) Keep length of the timber within reasonable limits from the point of view of the
availability of the section transportation in addition to handling during the erection.
(c)The timber design should be complete in itself. The top floor and sides shculd receive
pressure which would ensure compression on the timber sections
d)The joints should be sinmple and abutting surfaces should be as simple as possible.
During construction it should be ensured that the timber sections are not subjected to any
tensile stresses and the compression should be within the permissible limits.
If suitable precautions are taken during selection of timber and in the process of design
along with the protection against deformation and decay it would be possible for the shuttering
to be used a number of times there by saving the cost of construction.
3.6. TUNNELLING ON FIRM GROUND
Tunnelling on firm ground may be classified as under
(a) Traditional method involving drilling and blasting.
(b) Excavation by tunnelling methods (Refer article 3.4)
(a) Traditional method of drilling and blasting:
Methods of tunnelling under this system are
() Full Face method
(i) Top heading and benching
(iii) Drift method
drift method.
(iv) Multiple
The above methods are briefly described below
()Full face method. (See Fig. 3.7). The method is suitable for comparatively fim soils
where the excavation portion can hold itself for some time to allow removal of muck collected
(1)
I
2)
(3) 1. Drill hols
2. Heading
3. Benching
(4) 4. Hooked
II
Fig. 3.7. Full Face Method Fig. 3.8. Top heading and Benching
482 A Textbook of Transportation Engineering
during excavation. The excavation is divided into top, middle bottom sections shown as I,
and III in Fig. 3.8.
The top section is excavated and removed. It is followed by excavation of the second section
which is excavated and the muck removed. The bottom is then excavated and the muck removed
The method is suitable for small size tunnels.
(i) Top heading and benching (See Fig. 3.8). This method is suitable for tunnelling in
soils which can not hold itself by the time mucking operations are carried out. The heading is
excavated and supported to the full length or part of the length of the tunnel before starting the
benching. The heading is always ahead of the benching depending upon the nature of the soil
and progress of the work. The principle is illustrated in Fig. 3.8.
(i) Drift method. (See Fig. 3.9). The 'Drift' indicates a pilot tunnel
(miniature) made inside or along the centre of the tunnel. This drift in the
second stage widened by drilling holes on its face as illustrated in Fig. 3.9.
Depending upon the position of the drift method is further classified as ()
Wall place Drift, (b) Side Drift, and (c) Multiple Drift.
(a) Wall plate drift. Sometimes the top heading methods have to be
supplemented by introduction of drifts on each side of the spring line. They
have to be driven when the rock under consideration is so bad that the
procedure of 'heading in' only a very short advance per pull in the heading. Fig. 3.9. Drift
The top ribs is such cases are supported by wall plates of suitable lengths. Method.
(b) Side drift. In large size tunnels the excavation is required to be
supported before mucking. In such cases the rib, wall plate and post type of support is resorted
to. On each side on the sub-grade drift is driven ahead. If the situation so. demands full face
operation is carried out followed by quick erection of roof ribs.
In situations where ground conditions do not permit full operation multiple drift is resorted
to.
(c) Multiple drift method. The method is resorted to frequently to get through crushed
rock in fault areas where the crushed rock behaves like earth even if the rock may have hardened
enough to require blasting. The following two methods are adopted in such a situation
Method No. 1
The work involves the following stages
() Construction of crown drift.
i) Supporting the drift by two vertical posts to be subsequently removed and segment of
steel ribs is provided forming part of the ultimate steel rib.
(ii) Constructing drift on either side of the central drift.
(iv) Supporting the rib segments resulting in the formation of a complete semi-circle above
the springing.
(v)The above operations are followed by benching.
Method No. 2
The following stages are involved
() Driving a side drift through sub-grade on either side.
(i) Constructing a side support in steel or concrete in each drift along with suitable arrangement
for drainage.
(ii) Constructing concrete wall in a single lift in case the height of side walls is too great.
(iv) Driving side drift immediately above the concrete side wall carried upto spring line.