1.minutes of Kick Off Meeting - 20jul2021 R2
1.minutes of Kick Off Meeting - 20jul2021 R2
1.minutes of Kick Off Meeting - 20jul2021 R2
2. Contents:
Mr. Nguyen Van Thanh, on behalf of PMB2, opened the meeting by welcoming all attendees and thanking them for their time.
For the purpose of effective project execution after the Effective date, the Parties hold this meeting session to detail the following issues
which were informed to all Parties.
ge1.4 List of Manpower for Project Sub-Clause 4.9 EPC shall assign the competent personnel at site As per Attachment 1.4
with CV of Key Personnel - Quality to make decision immediately and to push the
Minutes of Kick Off Meeting - xxAug2021 R1 2
Quang Trach I Thermal Power Plant Project - Contract No. 38/2021/QT1-EVNPMB2-MC-HDEC-CC1 Minutes of Kick-off Meeting
2. Definitions Sub-Clause 1.1 All parties are fully incorporated with the
- Definitions Abbreviation in Transmittals off Contract
Documents as follows:
2.1 Representative & Power of GC1.1.2 PMB2 is the Owner (EVN) representative for
Assignment implementation of Quang Trach I power plant
project.
3. Communication
3.3. Language Sub-Clause 1.4 The contractual language in all Documents and
- Law and Drawings shall be in English.
Language
Monday – Friday;
08:00 AM to 12:00 AM
01:00 PM to 05:00 PM
Tet 5 To be
Holidays informed
Hung 1 To be
vuong informed
holiday
4. Drawing Title Block and Sub-Clause 5.9 The Drawing Title Block and Document Title
Document Title Block - Contractor's Block are agreed as Attachment 4.1 and
Drawings, Attachment 4.2.
Documents, Attachment 4.1: Quang Trach I Drawing Title
Data and Block.
Instructions
Attachment 4.2: Quang Trach I Document Title
Block.
5.1. The correspondence numbering All parties agree to follow the following
correspondence identification code.
lang
Design Review Meeting: QTI-MoM-DRM-
5.9.1 C002-0213
List of
Document for
the Owner's
Review or
Approval
11. Weekly Report and weekly GC 4.21 The Contractor is requested to submitted
meeting weekly report to the A2/C1 on Monday every
Sub-Clause 5.9 week.
- Contractor's Weekly Report will comprise the followings:
Drawings,
summarize current site activities;
Documents,
remark and update the project baseline
Data and schedule;
Instructions
provide site activities looking ahead of two
(02) weeks;
Documents The weekly meeting shall be hold at 2:00PM
and Data every Wednesday at the site.
Besides weekly meetings at site, the Parties
agreed to hold meetings as required for critical
issues in relation to Plant, Manufacture,
Engineering Meetings
12. Sub-Clause 5.9 - Engineering meetings will be held weekly,
- Contractor's by the following days of Weekly meeting, or
Drawings, as required. The meeting shall take place at
Documents, PMB2/ PMC’s site office
Data and - The agenda of the engineering meeting to
Instructions clarify the PMB2/ PMC’s comments will be
informed via email to PMB2/ PMC three
Documents working days before the meeting
and Data
- In cases EPC contractor intend to discuss
new design issues, relevant documents
including hard copies and soft copy (in
electronic file) shall be available for PMB2/
PMC two weeks before the meeting. For
urgent cases, related documents including
hard copies and soft copy (in electronic file)
shall be available for PMB/ PMC one week
before the meeting (in electronic file)
-
Site meetings
14. - Besides, the followings may be held at site
including the Employer’s and the
contractor’s authorized persons.
15. Critical Path Analyze & S-Curves - The critical path analyze & S-curves
Diagram diagram shall be included in the monthly
report and weekly report.
Codes and Standards A2/C1 requested MHC to use the latest version
16. Sub-Clause 5.9
of Standards and Codes to be submitted for
- Contractor's
approval (except those specified in RFP), in
Drawings,
compliance with Article 4 of Circular
Documents,
18/2010/TT-BXD.
Data and
Instructions
In compliance with Article 7 of Circular
19. Work Plan Procedure (Method Sub-clause to MHC must submit his Work Plan
Procedure/Method statements and detailed ITPs
statement) and detailed ITPs Clause 5.9
for all parts of the Works to A2/C1 for approval
3 months before the construction of each item
of the Works
The Contractor is requested to officially submit
20. Plant Designation System (KKS
the full details of KKS system applied for Coal
Fired Power Plant including but not limited to
the detail as follows: KKS Guidelines and Total
Plant Key, Function Key, Equipment Unit Key
and Component Key, and made the presentation
of KKS in principle.
Moreover, the Contractor is asked for providing
the KKS guidelines that they applied in
previous power plant projects for reference
List of
Document for
the Owner's
Review or
Approval
List of
Document for
the Owner's
Review or
Approval
List of
Document for
the Owner's
Review or
Approval
25. Site temporary facilities GC 6.6 Except as otherwise stated in the Owner’s
Facilities for Requirements, the Contractor shall provide and
Staff and maintain all necessary accommodation and
welfare facilities for the Contractor’s Personnel.
Labour
The Contractor shall also provide facilities for
Appendix 4 the Owner’s Personnel as stated in the Owner’s
Requirements.
The Contractor shall not permit any of the
9. General and
Detailed
Drawing and
Documents of
Construction
Area and
Temporary
Facilities
27. Site Environmental Protection Appendix 4 Before the start of works on site, MHC must
Plan submit the Site Environmental Protection
regulation/plan to A2/C1 for approval. The
plan has to cover all aspects of site
Environmental Protection.
MHC shall be responsible for submitting to
List of
A2/C1 an environmental report detailing the
Document for
environmental impact assessment for the
the Owner's
site every month and other environmental
Review or
reports as requirements in the Contract
Approval
document.
MHC is required to comply with EIA
requirements approved by authorities.
Work permits for foreign labors The EPC Contractor is requested to comply
28. Sub-Clause 6.1
with the regulations, as follows:
- Engagement
- To commit them sufficiently implementing the
of Staff and
regulations of Vietnam Law on recruitment and
Labour
management of foreign labors in Vietnam.
- To implement the work permit application at
work permit agency in Quang Binh Province for
foreign labors before working in Quang Trach I
project.
- To carry out registrations and declarations of
temporary residence and absence with the local
police in case there are foreign labors working.
- To promptly contact to Labor and Social
Welfare Service, for instructions of establishing
the plans to use foreign and Vietnamese labors,
then submit to People’s Committee of Quang
Binh Province for approval in order to not affect
the progress of permits for foreign labors before
working in Quang Trach I project.
A3/C3 have provided the EPC Contractor with
some current regulations of Vietnam Law on
recruitment and management of foreign labors
30. Emergency medical care GC 6.7. Health First aid room staffed by a doctor equipped
with ambulance vehicle will be provided on site
and Safety
by MHC during construction working time.
MHC will submit Operations Plan by the end of
August, 2021
Safety
and Safety
Sub-Clause 4.9
- Quality
Assurance
33.2 Power for construction Sub-Clause MHC is required to submit the construction
4.19 - power load demand by the end of August,
Electricity, 2021
Water and Fuel
List of
Document for
the Owner's
Review or
Approval
9. General and
Detailed
Drawing and
Documents of
Construction
Area and
Temporary
Facilities
44.
Contractor’s
working Area
II COMMERCIAL
Schedule of Payment
1. Sub-Clause - To discuss by all parties
14.4 -
Schedule of
Payments
Shipment procedure
3. Sub-Clause - Master List of Imported Permanent
7.10 - Equipment and Materials:
Shipment MHC is requested to contact local Customs to
Minutes of Kick Off Meeting - xxAug2021 R1 34
Quang Trach I Thermal Power Plant Project - Contract No. 38/2021/QT1-EVNPMB2-MC-HDEC-CC1 Minutes of Kick-off Meeting
5.1. Taxes and Duties on imported It is reminded by the Owner that the
Plant and Equipment Contractor shall be responsible for related
the site.
III Others
List of
Document for
the Owner's
Review or
Approval
5 Material Inspection Procedure GC 7. PLANT, - A2/C1 requested and EPC agreed to prepare
MATERIALS a procedure for receiving material at site or
AND local fabrication shop.
WORKMANS
HIP
MATERIALS
AND
WORKMANS
HIP
7 Health, Safety and Environment GC 6.7. EPC is required to submit Health, Safety and
Health and Environment Procedure as Manual Book.
Procedure
Safety
Procedures
49.
Environmental
monitoring
report
Safety
8. Permit to work Sub-Clause 2.1 The EPC contractor & sub-contractors before
- Right of allowing on site must submit a permit to work
Access to the to A2/C1 for approval.
Site For foreign labors, the EPC contractor is
30. Draft required to comply with the following
Permit To regulations:
Work System + To commit them sufficiently to comply with
the regulation of Vietnamese law on recruitment
and management of foreign labors in Vietnam
29. Site
Procedures
14. Interfaces between Power Plant Annex B– - Technical interface: terminal point: water
Project and Others (third parties) Interface intake, discharge, elevation, coordination,
Requirements access roads, etc.
and terminal - Schedule interface
points drawing
- Contractor is requested to provide detail
schedule for advising/working with third
parties
Interface
Requirements
and terminal
points drawing
39. Project
Terminal Point
Schedule
15.1 Water supply for Construction Sub-Clause - The EPC contractor is required to submit the
4.19 - construction water for coordination.
Electricity,
Water and Fuel
15.2 Temporary Power supply for - The EPC contractor is required to submit the
Construction Sub-Clause construction power demands for
4.19 - coordination.
Electricity,
Water and Fuel
15.3 Access Road to Site GC 4.15. The Contractor shall be deemed to have been
Access Route satisfied as to the suitability and availability of
access routes to the Site. The Contractor shall
16. Hand over schedule from EVN - The meeting for handing over schedule from
and EPC and vice versa EVN and EPC shall be held on ….
19. Site organization/management for Sub-Clause 4.4 There are many packages implemented during
Project – Project constructions. So there are many
Subcontractors interfaces and chaos such as: construction areas,
determined
during Kick-
off meeting
Consignee: To Order
Notify: Vietnam
Electricity Power
Projects Management
Board No. 2 for
Quang Trach I
Thermal Power Plant
by the Owner.