Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Cisg 925

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

CISG-online 925

Jurisdiction U.S.A.

Tribunal U.S. District Court for the Northern District of Illinois

Date of the decision 06 July 2004

Case no./docket no. 1:03-cv-01154

Case name Raw Materials Inc. v. Manfred Forberich GmbH & Co. KG

Memorandum Opinion and Order


Denying Plaintiff Raw Material Inc.’s Motion for Summary Judgment

Plaintiff Raw Materials, Inc. («RMI» or «Plaintiff»), an Illinois corporation that deals in used 1
railroad rail, has brought suit against Defendant Manfred Forberich GmbH & Co. KG
(«Forberich» or «Defendant»), a German limited partnership that sells such rail, alleging
breach of contract and fraud relating to Defendant’s undisputed failure to meet its contractual
obligation to deliver 15,000–18,000 metric tons of used railroad rail to Plaintiff. Plaintiff has
moved for summary judgment on its breach of contract claim. Defendant has defended on
force majeure grounds. For the reasons stated below, Plaintiffs motion is denied.

Relevant Facts

RMI is located in Chicago Heights, Illinois. Its primary business is purchasing, processing, and 2
selling used railroad rail which is eventually reheated and rerolled into new products, such as
fence posts or sign posts. (D.E. 21 at 1–2.) Forberich is located in Germany and is in the busi-
ness of selling used railroad rail. Forberich generally obtains its rail from the former Soviet
Union. (D.E. 23 at 1.)

On February 7, 2002, RMI entered into a written contract with Forberich in which Forberich 3
agreed to supply RMI with 15,000–18,000 metric tons of used Russian rail. (D.E. 21 at 3.) The
rail was to be shipped from the port in St. Petersburg, Russia.1 It takes approximately three to
four weeks for ships loaded with rail to travel from St. Petersburg, Russia to the United States.
(D.E. 21 at 14.) The contract provides for «Delivery by: 6-30-2002,» «F.O.B. Delivered Our
Plant, Chicago Heights, IL,» and «Shipping Instructions: RMI, INC. c/c Chicago Heights Steel,
Chicago Heights, IL 60411.» (D.E. 19, Ex. 7, at MF0027.)

The parties agree that in June 2002, Forberich sought an extension of its time for performance 4
under the contract. (D.E. 23 at 4.) However, the circumstances surrounding the extension re-
quest are disputed. Forberich maintains that, pursuant to its normal practice, it had «ear-
marked» a particular supplier, Imperio Trading («Imperio»), to provide it with rails that it

1
The parties do not expressly state in their Rule 56.1 Statements that the rail was to be shipped from St. Peters-
burg, but both parties appear to assume that this is true. (See D.E. 22 at 7 (plaintiff stating that «Forberich was
obligated to ship the rails from St. Petersburg»); see also D.E. 20 at 4–5.)
CISG-online 925

would use to fulfill its contract with RMI. (D.E. 23 at 2–3). In late June 2002, Imperio defaulted
on its contractual obligation to provide rail to Forberich. (D.E. 23 at 4.) Forberich claims that
it requested an extension from RMI because of this breach. (Id.) RMI disputes that Forberich
intended to use rail from Imperio to fulfill Forberich’s contract with RMI. (Id). RMI also asserts,
without citing any record evidence, that Forberich’s request for an extension was based on a
false representation that Forberich was unable to obtain a supply of rail from any source suf-
ficient to meet its obligations to RMI by June 30, 2002.2 (D.E. 18 at 7, 9.)

Whatever the reasons Forberich may have given in seeking its extension, the parties do not 5
dispute that RMI agreed (apparently in a telephone conversation between Mr. Forberich and
RMI Vice President Ron Owczarzak, (D.E. 21, Ex. 0)),3 to extend in some manner the time for
Forberich to perform the contract. (D.E. 23 at 4.) However, the parties dispute the terms of
the extension. RMI contends that it agreed to extend the delivery date (meaning delivery at
RMI’s place of business) to a date «later in the calendar year,» but that the delivery date was
never fixed due to Forberich’s failure to attend a planned meeting in Chicago to discuss the
extension. (D.E. 23 at 4; D.E. 21, Ex. 0; D.E. 19, Ex. 3, at 55.) For purposes of its motion for
summary judgment, «RMI has assumed that had Forberich delivered the contracted goods to
RMI’s plant by December 31, 2002, the Contract would have been satisfied.» (D.E. 22 at 4 n. 1.)
Mr. Owczarzak testified that he «would have been satisfied had the 15,000 to 18,000 tons,
metric tons of rail, been delivered to a port in the United States as of December 31 st, 2002,»
and that he conveyed this to Mr. Forberich, though he did not specify when or how (orally or
by letter).4 (D.E. 19, Ex. 3 at 55.) Mr. Forberich’s declaration states that he understood that
Forberich «had until December 31, 2002 to load the rails and execute the bill of lading to be
in compliance with the contract.» (D.E. 21, Ex. C, ¶ 11.)

Although it is undisputed that Forberich «has never delivered the contracted goods to RMI,» 6
(D.E. 21 at 5), the question of whether Forberich was required to deliver the rails to RMI’s
place of business by December 31, 2002 or merely was obligated to load the rails on a ship by
that date is nevertheless significant because it bears on the viability of Forberich’s contention
that its failure to perform should be excused. Forberich asserts that its failure to perform
should be excused because it was prevented from shipping the rail by the fact that the St. Pe-
tersburg port unexpectedly froze over on approximately December 1, 2002. (D.E. 22 at 4–5.)

2
RMI does not identify any record evidence which supports its contention that, in seeking the extension,
Forberich falsely represented that it was unable to obtain a supply of rail from any source by June 30, 2002. RMI
cites only to paragraph 14 of its 56.1 Statement, (D.E. 18 at 7), which states «Forberich subsequently sought an
extension of the delivery date until December 31, 2002.» (D.E. 19, ¶ 14.) At a minimum, it appears, based on the
material cited to the Court, that a jury could reject Plaintiffs assertion about the circumstances surrounding the
extension.
3
The material portion of the letter Mr. Owczarzak sent to Mr. Forberich on June 27, 2002, regarding their initial
conversation about the extension states as follows: «[w]ith reference to our telephone conversation of Wednes-
day, [sic] Jun 26, 2002, RAW MATERIALS, INC. has agreed to extend the delivery date from June 30, 2002 until a
later date during this calendar year on CONTRACT FORB 3464/02. This later date will be confirmed sometime
during your visit to Chicago in July of this year.» (D.E. 21, Ex. O.) Mr. Owczarzak testified that he and Mr. Forberich
had further discussions but he did not testify to the content of these discussions in detail. (D.E. 19, Ex. 3, at 55.)
4
Perhaps because of Mr. Owczarzak’s testimony that he would have been satisfied if Forberich had shipped the
rail to a U.S. port by December 31, 2002, neither party has offered any evidence regarding how long it would
take to transport 15,000 to 18,000 metric tons of rail from a U.S. port to RMI’s plant in Chicago Heights.
2
CISG-online 925

According to RMI, on the other hand, the port did not freeze over until mid-December 2002,
and, since it takes 3–4 weeks for a ship carrying rail to travel from St. Petersburg to the United
States, Forberich would have had to have shipped out the rail before the port froze in order
for the shipment to arrive by the December 31, 2002 deadline. (D.E. 22 at 7–8.) Thus, RMI
contends that Forberich’s failure to perform under the contract could not have been due to
the freezing of the port.5 (Id.) In other words, according to RMI, regardless of whether the port
froze in mid-December 2002, Forberich would have breached the contract in any event be-
cause it did not load its ships early enough so that they would arrive by the December 31,
2002 deadline. If, however, Forberich was merely required to load the rail by December 31,
2002, then the freezing over of the port could have prevented Forberich from shipping the rail
regardless of whether the port froze on December 1 or in mid-December.

The parties do not dispute that, in a typical winter, the St. Petersburg port does not freeze 7
over until late January, and such freezing does not prevent the vessels from entering and ex-
iting the port. (D.E. 23 at 6.) Mr. Forberich testified that ice breakers are normally used to
allow for shipping. (D.E. 21, Ex. F, at 106.) He further testified that the winter of 2002 was the
worst winter in St. Petersburg in almost sixty years and that ice interfered with shipping at the
end of November and that even the icebreakers were stuck in the ice. (Id.) He also testified
that these were «unexpected weather conditions.» (Id. at 77.) In relation to issues concerning
the freezing of the port, Forberich also submitted the declaration of Mikahil Nikolaev, who
works at the St. Petersburg port. (D.E. 21, Ex. P.) Mr. Nikolaev’s declaration essentially states
the same facts that Mr. Forberich testified to regarding the freezing of the port, except that
the declaration states that the port was frozen over on December 1, 2002, that such early
freezing had not occurred since 1955, and contains the conclusion that no one could have
predicted the early freezing of the port.6 (Id., ¶¶ 7, 10.) Without citation to the record, RMI’s
counsel states in RMI’s brief in support of summary judgment that «it hardly could come as a
surprise to any experienced shipping merchant (or any grammar school geography student)
that the port in St. Petersburg might become icy and frozen in the Russian winter months.»
(D.E. 18 at 12.) One of Forberich’s ships left the St. Petersburg port on approximately Novem-
ber 20, 2002. (D.E. 22 at 7–8, citing (D.E. 21 at 13.)) No evidence has been presented that any
ships left the St. Petersburg port until months after November 20, 2002.7 On January 10, 2003,

5
RMI asserts that Forberich chose not to ship the rail to RMI so that Forberich could, by subsequently entering
into more lucrative contracts with other purchasers, take advantage of a rise in rail prices that occurred after
RMI and Forberich entered their contract (D.E. 18 at 9.)
6
RMI argues that Mr. Nikolaev’s declaration should be stricken on grounds that it lacks support, is based on
speculation, and because Mr. Nikolaev was not disclosed as a witness. (D.E. 22 at 7–8 n. 2.) The Court need not
reach this issue because, as shown below, the Court did not need to rely on Mr. Nikolaev’s declaration in reaching
its decision.
7
Forberich admitted that one of its customers received shipments of rail from approximately January 20, 2003
through March 14, 2003, (D.E. 21 at 12), but no evidence has been presented regarding when the shipment(s)
left St. Petersburg or whether the relevant delivery ship used multi-destination or other indirect delivery route(s).
In fact, the record material cited by Plaintiff invites questions about how the deliveries occurred, as there appears
to have only been one ship involved (the M/V Rosina Topic) and yet the customer received «several shipments
of rail» from Defendant from January 20, 2003 through March 14, 2003. (D.E. 19, Ex. 16 at 2.) Presumably, this
vessel could not (even putting aside the ice question) have made «several» trips between the U.S. and St. Pe-
tersburg, simply because of the time involved to make the trip. (The customer is in the United States.) (Id., Ex. 16
3
CISG-online 925

Mr. Forberich sent Mr. Owczarzak a letter stating that Forberich could not ship the rails be-
cause «[s]ince the last 3 weeks the port is as well as frozen and nothing is possible.» (D.E.19,
Ex. 8).

Legal Standard

Summary judgment is proper where «the pleadings, depositions, answers to interrogatories, 8


and admissions on file, together with the affidavits, if any, show that there is no genuine issue
as to any material fact and that the moving party is entitled to a judgment as a matter of law.»
Fed.R.Civ.P. 56(c). In determining whether there is a genuine issue of fact, the court «must
construe the facts and draw all reasonable inferences in the light most favorable to the non-
moving party.» Foley v. City of Lafayette, 359 F.3d 925, 928 (7th Cir. 2004). Once the moving
party satisfies this burden, the nonmovant must set forth specific facts showing that there is
a genuine material issue for trial. Outlaw v. Newkirk, 259 F.3d 833, 837 (7th Cir. 2001). To
avoid summary judgment, the opposing party must go beyond the pleadings and «set forth
specific facts showing that there is a genuine issue for trial.» Anderson v. Liberty Lobby, Inc.,
477 U.S. 242, 250, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

Discussion

As set forth above, it is undisputed that Forberich was contractually obligated to ship 15,000 9
to 18,000 metric tons of rail to RMI and that it failed to do so. Thus, Forberich’s ability to avoid
summary judgment is dependant on whether it has presented sufficient evidence to support
its affirmative defense of force majeure based on the theory that it was prevented from per-
forming by the freezing over of the St. Petersburg port.8 For the reasons explained below, the
Court denies Plaintiffs motion for summary judgment.

A. Applicable Law

The parties agree that their contract is governed by the Convention on Contracts for the In- 10
ternational Sale of Goods («CISG»). (D.E. 18 at 5; D.E. 20 at 9.) Although the contract does not
contain an express force majeure provision, the CISG provides that:

A party is not liable for failure to perform any of his obligations if he proves that failure
was due to an impediment beyond his control and that he could not reasonably be

at 1.) So, to the extent things are clear from the limited information provided, it appears that some of the «sev-
eral» shipments may have been sitting on a dock or in a warehouse before they eventually were delivered over
the extended period of time. If that is true, then it would appear possible that the rail initially delivered on Jan-
uary 20, 2003, also may have been sitting somewhere (or was the subject of an indirect route to the U.S. from
St. Petersburg). In any event, Plaintiff has not foreclosed these factual questions. In addition, as noted above,
although shipments to the U.S. from St. Petersburg normally take 3–4 weeks, Mr. Forberich testified that the
unusual ice conditions in the winter of 2002–2003 delayed deliveries by months. (D.E. 21, Ex. F at 106.)
8
In its memorandum in support of its motion for summary judgment, RMI appears to anticipate that Forberich
would base its force majeure defense on the default of Forberich’s supplier, Imperio. (D.E. 18 at 7–8.) However,
Forberich has not made such a contention. (D.E. 20.)
4
CISG-online 925

expected to have taken the impediment into account at the time of the conclusion of
the contract or to have avoided or overcome its consequences.

CISG Art. 79.

RMI asserts that «[w]hile no American court has specifically interpreted or applied Article 79 11
of the CISG, caselaw interpreting the Uniform Commercial Code’s («U.C.C.») provision on ex-
cuse provides guidance for interpreting the CISG’s excuse provision since it contains similar
requirements as those set forth in Article 79.» (D.E. 18 at 8 n. 5.) This approach of looking to
case law interpreting analogous provisions of the UCC has been used by other federal courts.
See, e.g., Delchi Carrier SpA v. Rotorex Corp., 71 F.3d 1024, 1028 (2d Cir. 1995) («caselaw in-
terpreting analogous provisions of Article 2 of the Uniform Commercial Code («UCC») may
also inform a court where the language of the relevant CISG provisions track that of the UCC»);
Chicago Prime Packers, Inc. v. Northam Food Trading Co., No. 01-4447, 2004 WL 1166628, at
*4 (N.D. Ill. May 21, 2004) (same). Furthermore, Forberich does not dispute that this is proper
and, in fact, also points to caselaw interpreting the UCC. (D.E. 20 at 9 n. 6.). Accordingly, in
applying Article 79 of the CISG, the Court will use as a guide caselaw interpreting a similar
provision of § 2-615 of the UCC.

Under § 2-615 of the UCC, «three conditions must be satisfied before performance is excused: 12
(1) a contingency has occurred; (2) the contingency has made performance impracticable; and
(3) the nonoccurrence of that contingency was a basic assumption upon which the contract
was made.» Waldinger Corp. v. CRS Group Engineers, Inc., 775 F.2d 781, 786 (7th Cir. 1985).
The third condition turns upon whether the contingency was foreseeable; «[i]f the risk of the
occurrence of the contingency was unforeseeable, the seller cannot be said to have assumed
the risk. If the risk of the occurrence of the contingency was foreseeable, that risk is tacitly
assigned to the seller.» Id. RMI does not dispute that the freezing over of the port in St. Pe-
tersburg was a contingency. Rather, RMI essentially argues that it is entitled to summary judg-
ment because the second and third conditions do not apply inasmuch as the undisputed facts
show that the frozen port did not prevent Forberich from performing the contract and that
the freezing of the port was foreseeable. Based on the record material cited by the parties,
the Court respectfully disagrees.

B. Whether the Frozen Port Could Have Prevented Performance

As mentioned above, RMI contends that the frozen port could not have prevented Forberich 13
from performing because the port did not freeze over until mid-December 2002, and, since it
takes 3–4 weeks for a ship carrying rail to travel from St. Petersburg to the United States,
Forberich would have had to have shipped out the rail before the port froze in order for the
shipment to arrive by the December 31, 2002 deadline. (D.E. 22 at 7–8.) RMI’s argument is
premised on its contention that it has established beyond genuine dispute that Forberich was
obligated to ship the materials so that they would arrive by December 31, 2002 (rather than
just load the ships by that date, as Forberich contends). In this regard, RMI asserts that
Forberich’s admission in its answer that it «promised to deliver the aforementioned goods at
RMI’s place of business on or before June 30, 2002,» (D.E. 9 at 2.), is a judicial admission. While
the Court agrees that this statement in RMI’s answer is a judicial admission that establishes

5
CISG-online 925

beyond contention the fact that Forberich initially promised to deliver the rail at RMI’s place
of business on or before June 30, 2002, see Solon v. Gary Community School Corp., 180 F.3d
844, 858 (7th Cir. 1999) («That Gary Schools admitted the length of Bohney’s service in its
answer was not simply evidence as to this eligibility criterion, but a judicial admission which
removed this point from the realm of contested issues»), this does not establish the inapplica-
bility of the force majeure defense for at least two independent reasons.

First, even assuming that Forberich was obligated to deliver the rails by December 31, 2002, 14
Forberich has nonetheless presented evidence (which the Court must construe in the light
most favorable to Forberich) that the frozen port prevented it from meeting this obligation.
In particular, Mr. Forberich testified that ice interfered with shipping not just in mid-Decem-
ber, but as early as the end of November. (D.E. 21, Ex. F, at 106.) The fact that a Forberich ship
left the port on approximately November 20, 2002 is not inconsistent with the port freezing
in the remaining ten days or so of that month. Furthermore, as noted above, no conclusive
evidence has been presented that any ships left the St. Petersburg port until months after
November 20, 2002. In light of the undisputed fact that delivery to a port in the U.S. from
St. Petersburg takes at least 3–4 weeks and Mr. Owczarzak’s testimony that he «would have
been satisfied had the 15,000 to 18,000 tons, metric tons of rail, been delivered to a port in
the United States as of December 31st, 2002,» (D.E. 19, Ex. 3 at 55), Forberich has presented
evidence that it would have been in position to meet a December 31, 2002 deadline for deliv-
ery to the U.S. by shipping out rail in the last week or so of November or the first few days of
December but was prevented from doing so by the frozen port. Thus, for this reason alone,
there is a disputed question of fact as to whether the frozen port prevented Forberich from
performing its contractual obligations.

The second reason RMI has failed to demonstrate that the frozen port did not prevent 15
Forberich’s performance is that although it is established beyond contention that Forberich
promised in the February 7, 2002, written agreement that Forberich would deliver the rail at
RMl’s place of business on or before June 30, 2002, an issue of fact exists regarding the nature
of the extension Mr. Owczarzac orally agreed to for the time for performance of the contract.9
Neither side has presented evidence of what exactly was said by Mr. Owczarzak and
Mr. Forberich during the initial telephone conversation in which Mr. Owczarzak agreed to an
extension. On June 27, 2002, Mr. Owczarzak sent Mr. Forberich a letter stating «[w]ith refer-
ence to our telephone conversation of Wednesday, [sic] Jun 26, 2002, RAW MATERIALS, INC.
has agreed to extend the delivery date from June 30, 2002 until a later date during this calen-
dar year on CONTRACT FORB 3464/02. This later date will be confirmed sometime during your
visit to Chicago in July of this year.» (D.E. 23 at 4; D.E. 21, Ex. O.) However, this letter contem-
plates further discussions and, although the parties apparently did not meet in Chicago in July,
Mr. Owczarzak testified that they did have further discussions, though he did not testify to the
content of these discussions in detail. (D.E. 19, Ex. 3, at 55.) Mr. Owczarzak also testified that
he conveyed to Mr. Forberich that delivery to any port in the U.S. by December 31, 2002 would

9
As indicated by the fact that the parties agreed to the extension, there is no requirement in the contract that
any modification be in writing. Furthermore, under the CISG, «[a] contract may be modified or terminated by the
mere agreement of the parties.» CISG Art. 29.
6
CISG-online 925

be satisfactory but he did not specify when or how (orally or by letter) he made this commu-
nication. (Id.) In his declaration, Mr. Forberich stated that his understanding was that
Forberich was given an extension «until December 31, 2002 to load the rails and execute a bill
of lading to be in compliance with the contract.» (D.E. 21, Ex. C, ¶ 11.) Given that the original
contract obligated delivery to RMI’s place of business in Chicago Heights by June 30, 2002, it
appears unlikely that Mr. Owczarzak would have done more than agree to extend the delivery
date to December 31, 2002, and change the delivery location to any U.S. port, but the evidence
is unclear and contradictory and it is not the Court’s role in deciding a summary judgment
motion to weigh evidence. See, e.g., Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255 (1986);
see also David Copperfield’s Disappearing, Inc. v. Haddon Advertising Agency, Inc., 897 F.2d
288, 292 (7th Cir. 1990) (stating that «the intent of the parties to an oral contract is generally
a question of fact.»). Thus, a question of fact exists as to whether Forberich was obligated to
deliver the rail to the U.S. by December 31, 2002 or whether Forberich was merely required
to load the rail by that date. Consequently, since it cannot yet be determined whether
Forberich would have met its contractual obligations by shipping rail from the port at the end
of December, a question of fact exists as to whether the port’s freezing prevented Forberich
from performing its obligation, even assuming the port froze in mid-December.

C. Foreseeability

RMI’s sole basis for its contention that the early freezing of the port was foreseeable is the 16
assertion, without citation to the record, in its brief in support of summary judgment, that «it
hardly could come as a surprise to any experienced shipping merchant (or any grammar school
geography student) that the port in St. Petersburg might become icy and frozen in the Russian
winter months.» (D.E. 18 at 12.) However, Forberich presented evidence that the severity of
the winter in 2002 and the early onset of the freezing of the port and its consequences were
far from ordinary occurrences. It is undisputed that although the St. Petersburg port does
usually freeze over in the winter months, this typically does not happen until late January, and
such freezing does not prevent the vessels from entering and exiting the port. (D.E. 23 at 6.)
More to the point, Mr. Forberich testified that although ice breakers are normally used to
allow for shipping, the winter of 2002 was the worst winter in St. Petersburg in almost sixty
years and that ice interfered with shipping at the end of November and that even the ice-
breakers were stuck in the ice. (D.E. 21, Ex. F, at 106.) He also testified that these were «un-
expected weather conditions.» (Id. at 77.)

Whether it was foreseeable that such severe weather would occur and would stop even the 17
icebreakers from working is a question of fact for the jury. In so holding, the Court notes that
the freezing over of the upper Mississippi River has been the basis of a successful force
majeure defense. See Louis Dreyfus Corp. v. Continental Grain Co., 395 So.2d 442, 450 (La. Ct.
App. 1981). In sum, because questions of fact exist as to whether the early freezing of the port
prevented Forberich’s performance and was foreseeable, Forberich’s force majeure affirma-
tive defense may be viable and summary judgment would be inappropriate. 10

10
Because the Court has denied Plaintiffs motion as to liability, it need not reach the issue of damages.
7
CISG-online 925

Conclusion

For the foregoing reasons, Plaintiffs motion for summary judgment is denied. 18

You might also like