Risk Assessment of Plaster work.

Resultant Risk
Sr. No. Sub activity Hazards Risk Severity Probability Control Measures Required Additional control measure. Severity Probability Resultant risk Risk Level
risk Level
1.Unauthorized operator.
1.Transportation to be done by authorized
operator,
2.Damage 1.Major & Minor
Sand, cement 2.Proper access to be provided for
1 equipment. 3.workers hit injury. 4 2 8 M 4 1 4 L
delivery at site Vehicle.
by machine. 2.causality
3.Training and TBT given
4.Im proper access
.
1.Fall of material. 1.Major ,Minor 1.Job specific training given.
2.Fall of person during injury, 1.Third party inspection shall be done of 2.TBT given.
pulling of bucket. 3.Failure crane. 3.Close supervision.
of machine. 2.casuality, 2.Physical fitness of machine shall be 4.Crane checklist to
Material shifting 4. Dust hazard. 3.skin diseases. checked prior to use. be followed.
2 4.Respiratory 4 3 12 H 5.Nose 4 1 4 L
by crane. 3.Over load prohibited.
disease. 4.Job specific mask shall be used.
PPEs used. 6.Dust
5.Proper edge protection provided. control mesaure shall be
followed.
1.Flying object. 1. Eye injury. 1.Proper working platform provided. 1.TBT and training given.
2.Improper tools. 2.Cut injury. 2.Full body harness,Safety helmet,safety 2. Safe
3.Damage tools. 3.Major/Minor shoes shall be used. working platform provided.
4.Fall from injury. 3.Over head protection provided.
Chicken mess height. 3.Close supervision required.
3 fixing and bull 5.Fall of material 4.Casualty 4 3 12 H 4. Height work permit shall be used. 4 1 4 L
marking. 5.scafolding platform shall be inspected
before use.
6.Right tools shall be used.
7.Tools shall be checked
before used.
1.Fall of object. 2.Improper 1.Major/Minor Injury 1.Secure working platforms. 1.Job specific training given.
base. 3.Untrained worker. 2.casualty. 2.No opening. 2.TBT given.
4.Improper communication. 3. No loose materials on the 3.Close supervision.
height. 4.Scaffold material to be check
4.Throwing of materials is strictly before use.
Scaffold and prohibited. 4.Scaffold rect by trained
4 4 3 12 H 4 1 4 L
working platform. 5.Only trained and experienced scaffolder.
scaffolder to be engage for erection work. 6. Cautionary signage
shall be displayed.
7.Barricading under the work
area

1.Full body harness, safety helmet shall be


used.
2.Guard rail shall be provided. 1.Required PPE's used.
1.Fall of person from 1.Major injury.
4 4 16 H 3.Safety net ,life line shall be installed. 2.Training and TBT given. 4 1 4 L
height 2.casualty
3.Close supervision.
4.Work at height training to be given.
5.Work permit to be used.
1.Avoid over load.
2.Scaffolding as per standard. 3.Scaffolding
1.Job specific training and TBT
tag to be
given.
1.Major injury. used and signed by competent person.
1.Collapse of scaffolding 4 3 12 H 2.Close supervision. 4 1 4 L
2.casualty
3.sufficient support
4.Sacaffolding material to be
to be provided.
in good condition and check before use.
1.Physical fitness of machine shall be
checked prior to use.
2.All electrical connection shall be
1.Skin corrosion. 1.Skin diseas. route from 30ma RCCB.
Mortar mixing by 1. TBT and training given .
2.Flying object. 2.Eye injury. 3.Electrical cable shall be
5 manually 3 3 9 M 3 1 3 L
3.Dust inhalation 3.Respiratory free from damge.
/machine. 2.Proper supervision.
4.Electrical hazard. disease 4.Earthing
connection shall be done.
5.white goggle ,nose mask,hand gloves shall
be used
1.Proper working platform provided,
2.Full body harness used.
1.Improper working
3.Over head protection
platform
1.Physical Injury. provided.
2.Fall of person.
2.Property 4.All drivers should be trained to maintain 1.Training and TBT given.
6 Plaster work 3.Fall of material. 4 3 12 H 4 1 4 L
damage . safe distance between the vehicle and the 2.Close supervision.
4.No use of fall protection
3. Casualty working platform. 5. height
system.
work permit shall be used.
5.Scaffold hit by object.
6.scafolding platform shall be inspected
before use.

1.Good housekeeping should be maintained


1.Slip hazard. and followed.
2.Material and 1.Major/Minor body
2.Matreial and machine should be removed 1.TBT and training given.
equipment over the work injury.. 2.Property after complete the work. 2.Safety helmet, Safety shoes
7 Housekeeping. 3 4 12 H 3 1 3 L
place. damage.
3.Proper Supervision. shall be used.
3.Flyying hazard. 3.Eye injury
4. Material shall be
coverd and stacked a designated location.
Sr. No. Activity Hazard Identification Risk Assesments

Type of hazards Catogry of hazards Type of risk


Hierarchy of controls
Control Measures