ITS Project Management Methodology
ITS Project Management Methodology
ITS Project Management Methodology
Methodology
Information Technology Services
Project Management Group
11/17/2014
Version 2.1
Change Record
Reviewers
Distribution
Copy Name
Number
Table of Contents
1 BACKGROUND
2 DEFINITIONS
2.1 Problem/Opportunities
2.2 Project
2.4 Program
3 PROJECT CLASSIFICATION
4.1 Define
4.1.1 Activities
4.1.2 Outputs and Deliverables
4.2 Plan
4.2.1 Activities
4.2.2 Outputs and Deliverables
4.3 Launch
4.3.1 Activities
4.3.2 Outputs and Deliverables
4.4 Manage
4.4.1 Activities
4.4.2 Outputs and Deliverables
4.5 Close
4.5.1 Activities
4.5.2 Outputs and Deliverables
7.11 Customers
7.12 Stakeholders
8 GLOSSARY
1 Background
Project methodology makes assumptions about the use of specific terms and
project management issues. This section defines some of the key terms and
differentiates their use. Specific project roles are defined in Section 4—Standard
Roles and Responsibilities.
2.1 Problem/Opportunities
Problem/opportunities are those campus IT endeavors vetted and communicated
beyond the boundaries of the organization. They are those efforts that meet any
of the following conditions:
▪ Have an impact beyond the division sponsoring the effort (e.g. changes or
creates a new process or a procedure or function)
▪ Create benefits beyond the sponsoring division
▪ Initiate a partnership with an external stakeholder (e.g. Regulatory
requirements)
▪ Influence or are influenced by strategic planning
▪ Require resources external to the unit/organization to successfully
complete the problem/opportunities
Through the process of program and project structuring each campus
problem/opportunities may develop into programs or a set of projects for
implementation.
2.2 Project
A project is group of related work activities organized under the direction of a
project manager which, when carried out, will achieve specified objectives within a
stated timeframe.
A project has a defined scope, deliverables or outcomes, work steps, duration, and
budget as defined in a Project Charter.
A project
▪ Is temporary with a distinct beginning and end
▪ Is a minimum of 80 hours
▪ Is defined by specific deliverables
▪ Is conducted by a temporary team that exists for its execution
▪ Has a single project manager who is responsible for its success
▪ Is defined by identifying the starting point, the goal/objectives, and the
route between them
2.3 Project Management
Project management defines managing single projects that meet the following
general guidelines:
▪ The project has a logical scope.
▪ Duration is typically from 3 months to 5 years.
▪ Team size is typically less than eight members including the project
manager.
▪ There is a single project sponsor.
▪ There is a single project manager.
2.4 Program
A Program is a group of related projects that address a common business goal or
problem/opportunities.
Individual projects comprising a program are interdependent and must be
successfully completed for the business program to meet its objectives.
Programs provide a means of organizing and managing large, complex, or
longer-term project efforts. The overall effort is subdivided into a set of small
interdependent projects, each of which implements some portion of the overall
solution.
Figure Number 1
Project Management Phases
Each phase addresses a specific aspect of managing a project from define through
close. Although these phases are described sequentially in practice, some may
overlap or be applied concurrently.
The results of each phase are described by a set of project management
deliverables or artifacts. These artifacts provide visibility to application of the
methodology and clear communication to project stakeholders. Each of these
phases and deliverables are described in more detail in the sections that follow.
4.1 Define
The first phase of the project management life cycle is the define phase. This
phase is the one most often given the least attention. The define phase scopes the
project.
When a project is in the early phases an initial high level Project Proposal should
be created. This allows the project sponsor and project manager to quickly
understand the dimensions of the project and identify alternate approaches. At
this phase, the process is exploratory in nature and it is not always certain that the
project will proceed. It is not advisable to spend too much effort on scoping the
project. A rough order of magnitude estimate of project resources (costs, FTE’s)
and schedule will suffice for moving the project through the first phase of the
project management process.
4.1.1 Activities
Once the initial definition of the project is complete, it is documented in the form
of the Project Proposal. The Project Proposal is a brief document (usually one
page) that describes, in the language of the business, the following.
▪ What is the problem or opportunity to be addressed by the project?
▪ What are the projects’ goal and objectives?
▪ How will success be measured?
▪ What is the high-level budget and timeline for the project?
▪ What assumptions, risks, and obstacles may affect the project that you
wish to call to the attention of senior management?
At this point, a “Go/No Go” decision is made by the project sponsor and an ITS
Manager, for class 1 and 2 projects, or ITS Senior Management Team (SMT), for
class 3 and larger projects.
○ If the project is approved at this phase, it moves to the next phase, Plan
where the project charter is developed.
○ If the project is not approved for further consideration then the reasons
for not approving it and the initial project charter serve as a record of the
governance process.
4.2.1 Activities
Using documents produced in the define phase, the project manager, core team
and key client representatives develop a detailed project plan. The plan defines the
time, cost, and resource requirements needed to deliver the functionality identified
in the define phase.
Key questions that need to be answered in this phase are:
▪ Why is the program or project needed? (Objectives)
▪ What outputs or results will the project need to produce? (Deliverables
and Outcomes)
▪ How long will the project take and what people and roles will be needed
to execute it? (Workplan)
▪ What are the project costs and benefits?
▪ How will risks be managed?
▪ What are the detailed resources (costs, FTE) required?
The Project Charter is refined to identify specific resources and roles, approach,
deliverables and a work plan. In addition, a project risk assessment should be
developed.
A risk assessment identifies potential risks and defines the appropriate risk
mitigation strategies. The risk assessment may result in changes in the project
scope, timing, role assignments, and cost. The Project Charter should be updated
reflecting this new information.
Once the more detailed Project Charter has been developed, the project will be
subject to a second “Go/No Go” decision by the project sponsors and the IT
Portfolio Management governance process. If the project is approved on this
second iteration, resources will be assigned and the project will be launched.
During the Plan phase, a temporary project manager may be assigned to work
with the sponsor(s) to develop the Project Charter, project plan and risk
assessment. Once the project is approved for mobilization, the final project
manager assignment will be made.
For governance reasons and for practical purposes the project charter is
developed in an iterative manner. Two “Go/No Go” decision points are included
in the Plan phase to move the project from concept to launch.
4.2.2 Outputs and Deliverables
Outputs and deliverables from the Plan phase of the project management life
cycle are:
▪ Sponsor approval
▪ ITS Manager approval (small projects)
▪ ITS SMT approval (large projects)
▪ Completed Project Charter
▪ Completed Project Budget
▪ Assigned and approved project staff resources
▪ Analysis of APM User Interface Standards
4.3 Launch
At this phase, a specific project governance structure is established (Executive
Sponsor, Project Sponsor, Steering Committee etc.). The project organization is
finalized. Project team members are cast in their roles and briefed on the project
by the assigned project manager. The project team members refine the project
work plan as necessary and are assigned responsibility for their specific tasks and
deliverables.
The figure below shows a typical project organization structure. The roles in the
diagram are described in the Standard Roles and Responsibilities section.
Figure Number 2
Typical Project Organization
The project manager leads and coaches the team to achieve the goals of the
project. The project manager works collaboratively with the Project sponsor to
guide the efforts, update the plan, resolve project issues, and to obtain key
business decisions when necessary.
During this phase, the project issue log is a key tool to capture issues and their
resolution. An issue is a formally defined matter that may impede progress of a
project or a program for which no agreement has been reached. The project issue
log tracks issues and key decisions.
4.3.1 Activities
▪ Project kick-off meeting
▪ Team assignments
▪ Assess and review project plan
4.4 Manage
The Manage Phase of a project includes all of the tasks that the project manager
and team must do in order to keep the work of the project moving along as
planned. This phase runs throughout the life of the project to keep stakeholders
informed and to engage their active involvement and sponsorship for the project
or program.
Reporting project status is a critical success factor at this phase for managing
expectations of project sponsors, the project steering committee, and other key
stakeholders. Regular and effective reporting is critical synchronization of multiple
projects within a program.
The two aspects to communications in this phase are internal and external project
communication and formal or informal communication.
○ Formal reporting may be sponsor or committee briefings, presentations,
or written reports.
○ Informal reporting can be minutes, “management by walking around”, or
sponsor and team discussions.
Formal external reporting to Steering Committees and Executives should be built
into the project calendar. This allows time for preparation and alignment with the
end of major project phases or the key milestones. Project manager/project
sponsor meetings should focus on
▪ resolving issues
▪ reviewing deliverables and work products
▪ project milestone progress
For formal internal reporting, standing meetings should be established for the
project team and the project sponsor and project manager. The frequency of these
meetings should be appropriate to the duration of the project. At minimum, these
should be weekly meetings. Project team meetings should focus on
▪ reviewing task progress from the previous period
▪ reviewing tasks for the next period
▪ reviewing the issue log
Meetings of the project team, project manager/sponsor should be scheduled to
give project team a sense of the larger context of the project and to enable
interaction between the project sponsor and the whole team. This interaction is
important from a collaboration perspective and provides an opportunity for the
project sponsor to demonstrate their interest and active sponsorship in the
project.
A regular and appropriate reporting mechanism for the project can be a fine
balancing act. Over- or under-communicating leads to “tuning out” or feeling “in
the dark”. The need for formal, regular reporting for the project manager and
project sponsor can cost the team too much time in meetings and writing reports.
This can detract from other project activities or can lead to inadequate status
reporting. A defined minimum level of reporting must be implemented. Team
members need to meet these minimal reporting requirements.
4.4.1 Activities
The project work is underway and the focus of the project manager changes from
project planning to project execution. The project manager’s job will be to manage
the work of the project.
Documentation is an integral part of the change control process. All project scope
changes should follow the same change control procedure. The process is initiated
with the submission of a change request from the manager or client and the form
is forwarded to the sponsor for review. The sponsor may either accept the change
or return it to the manager/customer for rework and resubmission. All changes to
scope are documented and authorized by the relevant stakeholders. Once the
change request has been accepted, it is forwarded to the project manager for an
impact review. Any change to project scope must be communicated to the project
manager.
The project manager ensures that the change request form has been completed
and reviews the form to see if there is an impact to the schedule. If any task,
schedule, or resource information has been changed, the project manager needs to
communicate the changes to the project team. The project manager also needs to
communicate any change in the committed timelines to the relevant stakeholders
(manager, customer, or any other project manager whose project is dependent on
the completion of this project). The request is analyzed by the project manager
and project team. Based on the estimated effort, time and cost required
implementing the change; it is approved, denied, or returned to the requestor for
additional information. Changes resulting in additional costs require a new budget
analysis be done. Any change needs to be communicated to the governance
structure. The project manager and established governance may approve or deny a
change request. They may decide if the customer needs to pay for implementing
the change.
4.5 Close
Program and project management is a temporary endeavor. All programs and
projects end. The ending needs to be a deliberate and explicit process to ensure
the project closes with the appropriate hand-offs and knowledge transfer. The
Close phase is conducted once the project team has met all deliverable
commitments. In some cases, the project will be terminated due to changes in
business circumstances, changes in sponsorship or a failure to meet project
objectives.
The Close phase is used to:
▪ Formally end the project.
▪ Evaluate the project assessing performance against objectives, budget, and
schedule.
▪ Examine the project for improvements in approach for future projects.
▪ Package information for reference by future projects.
The Close phase provides a basis to continuously improve and enhance project
management methodology using examples, templates, lessons learned, and process
and technique improvements.
4.5.1 Activities
There are several activities in the Close phase of a project.
▪ Acceptance of deliverables – This activity is usually accomplished via a
checklist. This can be a very formal or informal process.
▪ Transition to production – For most projects there is some form of
transition to production and/or operations.
▪ Administrative closure – The project is not done until the paperwork is
filed.
▪ Lessons learned – This is an evaluation review of the project’s goals and
deliverables as measured against the project proposal or charter as a
baseline.
▪ Release resources
▪ Celebrate
The number of activities required for a given project depends upon the class into
which the project is categorized. A class 1 project will involve only a few of these
activities. A class 5 project will involve all the activities in the framework. The
activities required for each class are the bare minimum. It depends upon the
discretion of the project manager to perform other activities (even if they are not
recommended) if he or she feels that the activity is needed for the project.
The Methodology Requirements Matrix shows how the activities are currently
mapped to the project classes along with the appropriate artifacts for each activity.
Artifact templates are not contained within this document but can be found at the
ITS Project Management Group website at
<http://its.ucsc.edu/project-management/templates.html >.
The required activities for each project class are the minimum needed for effective
management and status reporting of a project. The project manager and project
team may add additional activities. The additional activities should not be added
merely as an exercise but should contribute added value to the project.
Table 4.1 - ITS Project Classification Methodology Requirements
Matrix
6 Project Initiation Process Flow
Figure Number 3
UCSC ITS Project Initial Process Flow – Determine Type of Work
Figure Number 4
UCSC ITS Project Initial Process Flow - Define
Figure Number 5
UCSC ITS Project Initial Process Flow – Plan through Close Class 1
Figure Number 6
UCSC ITS Project Initial Process Flow – Plan through Close Class 2
Figure Number 7
UCSC ITS Project Initial Process Flow – Plan through Launch Class 3
Figure Number 8
UCSC ITS Project Initial Process Flow– Plan through Launch Class 4
Figure Number 9
UCSC ITS Project Initial Process Flow– Plan through Launch Class 5
Figure Number 10
UCSC ITS Project Initial Process Flow– Plan through Close Class 3+
7 Standard Roles and Responsibilities
This section describes typical roles and responsibilities for projects and programs.
Roles may be assigned to one or more individuals. Conversely, individuals may
play one or more roles.
7.11 Customers
▪ Initial identifier of need or service
▪ May be designated as subject matter experts (SME) for functional
requirements definitions and testing
7.12 Stakeholders
▪ Community member affected by or participating in the project
▪ May be internal or external to the organization
8 Glossary
Term Definition
Activities The next level of detail below deliverables. A deliverable is complete when all its activities are done.
“Procure and set up 4 VM machines with Windows OS…”
Change Control The review, approval/disapproval, implementation, tracking, closure, and status reporting of proposed
changes to project deliverables.
Closure The last phase of a project life cycle resources are released, contracts are closed, deliverables are
accepted by the customer, lessons learned are documented, project team celebrates.
Contingency Plan An alternative for action if things do not go as planned or if an expected result fails to materialize.
Critical Path The sequence of tasks in a project with zero slack time. Defines the minimum project duration.
Decomposition The act of breaking work down into activities, tasks, subtasks, and work packages.
Deliverable A report or product that must be completed to ensure satisfaction of project requirements.
Dependencies A relation between project activities, such that one requires input from the other. The relationship can
exist within a single project or across a suite of projects.
Goals Project performance indicators set at the beginning of the project that reflect directly on the key
objectives of the project and provide the basis for ratings during project status appraisals.
Governance The processes, decision rights, and accountability at various levels of the institution to manage ITS
functions.
Investment Those endeavors with impact and benefit beyond the sponsoring division. They may have external
opportunity stakeholders, be influenced by strategic planning or require external resources for success.
Issue A formally defined matter that may impede progress of a program or project.
Labor (or Effort) The amount of “work” associated with completing a task, usually expresses in personhours. Think of it
as the amount of time it would take for one person to do a task in one continuous period without
interruption.
Launch The process of preparing for, assembling resources and getting work started. It is the process of
committing an organization to begin a project.
Milestone An action or event marking completion of a major deliverable or other significant change in a project.
Phase gate Approval points during a project lifecycle phase where decision are made to move the project to the
next phase or to closure.
PMBOK Project Management Book of Knowledge – The highlevel guide to project management methodology
published by the Project Management Institute (PMI).
Portfolio Process by which a set of campus problem/opportunities are identified, evaluated, ranked, matched to
Management available resources and approved for implementation.
Program Means by which multiple projects are managed to achieve a common strategic business goal or
Management objective.
Project A group of related work activities organized under the direction of a project manager which, when
carried out, will achieve specified objectives within a stated timeframe.
Project Charter A document consisting of a problem/opportunity statement, background, purpose, and benefits, goals
Document and objectives, scope, assumptions and constraints.
Project Duration Total time it will take to complete the project in calendar days/months/years.
Project Life Cycle The complete history of a project through define, plan, launch, manage, and close phases.
Project Application of modern management techniques to execute a project from start to finish, achieve
management predetermined objectives of scope, quality, time and cost, to the equal satisfaction of those involved.
Project A set of general project activities and deliverables mapped into the five phases of the project lifecycle.
Management
Methodology
Project Plan An optimized, detailed, living schedule of all tasks and resources in a project.
Project Proposal A document consisting of a problem/opportunity statement, including background, purpose, and
benefits, a goal, objectives, scope, assumptions and constraints. A Project Proposal clearly documents
project definition in order to bring a project team into necessary agreement.
Risk The cumulative effect of the chances of uncertain occurrences adversely affecting project objectives.
Scope Creep Ongoing requirements increase without corresponding adjustment of approved cost and schedule
allowances via change management process.
Sponsor Individual(s) with ultimate authority, approval, and responsibility for a project.
Stakeholders Campus community member affected by or participating in a project. One with a stake or interest in the
outcome of the project. Also one affected by the project.
Work Breakdown Tool that defines the hierarchal breakdown of all work in a project.
Schedule (WBS)
Work Package Detailed shortspan tasks that represent a further breakdown of the project work breakdown schedule
(WBS)