Shift2Rail Joint Undertaking Governance and Process Handbook 20200303 v2.0
Shift2Rail Joint Undertaking Governance and Process Handbook 20200303 v2.0
Shift2Rail Joint Undertaking Governance and Process Handbook 20200303 v2.0
Version 2.0
2|Page
Table of Contents
Glossary .......................................................................................................................................................................... 6
1 Introduction .............................................................................................................................................................7
1.1 Context ...........................................................................................................................................................7
1.2 Purpose and scope of the handbook ................................................................................................................7
1.3 Position in the S2R JU documentation hierarchy ............................................................................................. 8
2 Legal Framework ....................................................................................................................................................10
2.1 S2R Regulation ..............................................................................................................................................10
2.1.1 Membership Agreements with Other Members .........................................................................................10
2.1.2 GB Decisions..............................................................................................................................................10
2.1.3 The Executive Director (ED) & ED Decisions ...............................................................................................10
3 Programme Cycle ................................................................................................................................................... 12
3.1 S2R Master Plan ............................................................................................................................................ 12
3.2 S2R Multiannual Action Plan (MAAP) ............................................................................................................. 12
3.2.1 Shift2Rail Research and Innovation ............................................................................................................ 13
3.2.2 Innovation Programmes ............................................................................................................................ 13
3.3 From the Annual Work Plan (AWP) to the Project Kick-Off ............................................................................. 16
3.4 Project life cycle ............................................................................................................................................ 19
3.4.1 Other Members Projects ........................................................................................................................... 19
3.4.2 Open calls Projects .................................................................................................................................... 21
3.5 IKOP and IKAA reporting Cycle ...................................................................................................................... 22
3.6 Project closure and final review .................................................................................................................... 22
3.7 Controls and audit ........................................................................................................................................ 23
4 S2R JU Governance ............................................................................................................................................... 25
4.1 Basis of Authority ......................................................................................................................................... 25
4.2 S2R JU Governance Structure ........................................................................................................................ 25
4.3 Programme Governance ............................................................................................................................... 26
4.3.1 ED Programme Board ........................................................................................................................... 26
4.3.2 The System Integration Working Group (SIWG) ......................................................................................... 27
4.3.3 Innovation Programmes’ Steering Committees ......................................................................................... 27
4.4 Working with ERA ......................................................................................................................................... 29
5 Programme implementation roles and responsibilities .......................................................................................... 33
5.1 Research and Innovation .............................................................................................................................. 33
5.1.1 Head of Research & Innovation................................................................................................................. 33
5.1.2 Programme Managers .............................................................................................................................. 33
5.1.3 Legal support - grants ............................................................................................................................... 34
5.1.4 IP/CCA Coordinators ................................................................................................................................. 34
5.1.5 TD/CCA Leaders ........................................................................................................................................ 35
3|Page
5.1.6 Project Coordinators and beneficiaries ..................................................................................................... 35
5.2 Administration and Finance .......................................................................................................................... 36
5.2.1 Head of Administration and Finance (HAF) ................................................................................................ 36
5.2.2 Finance team ............................................................................................................................................ 37
5.2.3 Legal officer .............................................................................................................................................. 37
6 RACI matrix ........................................................................................................................................................... 38
7 Quality Management ............................................................................................................................................ 40
7.1 Evaluation of proposals................................................................................................................................. 40
7.1.1 Evaluation process .................................................................................................................................... 40
7.1.2 Scoring method ......................................................................................................................................... 41
7.2 Financial Viability Check ................................................................................................................................. 41
7.3 Continuous monitoring ................................................................................................................................. 42
7.4 Criteria to be applied in the Project Control Gate assessment ....................................................................... 43
7.5 Use of S2R label and S2R position ................................................................................................................. 46
8 Risk Management ................................................................................................................................................. 48
8.1 Risk Policy..................................................................................................................................................... 48
8.1.1 Introduction ............................................................................................................................................. 48
8.1.2 Policy Objectives ...................................................................................................................................... 48
8.1.3 Risk Management Principles ..................................................................................................................... 48
8.1.4 Risk management Governance rules ......................................................................................................... 48
8.1.5 Alignment with European Commission...................................................................................................... 49
8.2 S2R JU Risk Management Organisation and Process ...................................................................................... 49
8.2.1 Background .............................................................................................................................................. 49
8.2.2 Framework principles ............................................................................................................................... 49
8.2.3 Organisation ............................................................................................................................................. 49
8.2.4 S2R JU layered approach .......................................................................................................................... 50
8.2.5 Internal Control ........................................................................................................................................ 52
8.3 Risk Management Process ............................................................................................................................ 52
8.3.1 Establish the context ................................................................................................................................ 53
8.3.2 Identify risks ............................................................................................................................................. 53
8.3.3 Analyse and evaluate risks ........................................................................................................................ 53
8.3.4 Treat risks................................................................................................................................................. 53
8.3.5 Monitor and review .................................................................................................................................. 53
8.3.6 Communicate and consult ........................................................................................................................ 53
8.4 Methodology ................................................................................................................................................ 54
8.4.1 Gross criticality ......................................................................................................................................... 56
8.4.2 Mitigating actions ..................................................................................................................................... 56
8.4.3 Net Criticality ............................................................................................................................................57
8.5 Reporting cycle ............................................................................................................................................. 58
9 Change Management ............................................................................................................................................ 59
4|Page
9.1 Changes to projects ...................................................................................................................................... 59
9.2 Changes to the Programme .......................................................................................................................... 60
10 Programme closure (1st approach) .......................................................................................................................... 61
10.1 Programme completion ................................................................................................................................. 61
10.2 Non-completed projects ................................................................................................................................ 61
10.3 Final Closure ................................................................................................................................................. 62
10.3.1 Financial obligations ............................................................................................................................. 62
10.3.2 Documenting and reporting.................................................................................................................. 62
10.3.3 Final Programme Report....................................................................................................................... 62
Annex A: Templates....................................................................................................................................................... 63
Annex B: Technical Demonstrators of each Innovation Programme and Work Areas of Cross-Cutting Activities .............. 64
Annex C: Contact persons of S2R JU ............................................................................................................................... 66
Annex D: S2R Cooperation Tool guidelines ..................................................................................................................... 67
Annex E: IP/CCA Rules of Procedure .............................................................................................................................. 68
Annex F: ED Decision 2016/017, Guidance for members and their appointed auditors_20161118 final .......................... 69
Annex G: list of official S2R technical positions and names of official S2R representatives in external working group ...... 70
Annex H: List of projects with level of ERA desired involvement ...................................................................................... 71
Annex I: Shift2Rail Executive Director Programme Board change management process ................................................. 73
5|Page
Glossary
6|Page
1 Introduction
1.1 Context
The Shift2Rail Joint Undertaking (hereafter referred to as the S2R JU) was established in 2014 as a new
public-private partnership in the rail sector1.
Shift2Rail is the first European rail joint technology initiative (JTI) to seek focused research and
innovation (R&I) and market-driven solutions by accelerating the integration of new and advanced
technologies into innovative rail product solutions. Shift2Rail will promote the competitiveness of the
European Rail Industry and will meet the changing EU transport needs. Through the R&I carried out
within this Horizon 2020 initiative, the aim is to create the necessary technology to establish a Single
European Railway Area (SERA).
The Shift2Rail programme is structured in five asset-specific Innovation Programmes (IPs), covering all
the different technical and functional (process) subsystems of the rail system:
1. IP1: cost-efficient and reliable trains, including high-capacity trains and high-speed trains;
2. IP2: advanced traffic management & control systems;
3. IP3: cost-efficient, sustainable and reliable high-capacity infrastructure;
4. IP4: IT solutions for attractive railway services;
5. IP5: technologies for sustainable & attractive European freight.
In addition, horizontal activities are performed through the Cross Cutting Activities and most recently
with some disruptive R&I and system architecture approach within IPx activities.
1 Council Regulation (EU) No 642/2014 of 16 June 2014 establishing the Shift2Rail Joint Undertaking
7|Page
The roles and responsibilities of the S2R JU and the Other Members towards other beneficiaries
and third parties involved in the Programme.
The position of the Shift2Rail Governance and Process Handbook is based on the overall document
hierarchy shown in Figure 1.
The Regulation of Shift2Rail defines the rules underpinning the JU as body of the European Union
entrusted with the implementation of the S2R Initiative.
The S2R Master Plan describes a forward-looking roadmap to drive innovation in the rail sector in the
medium-long term. It is this overall plan of the S2R JU that defines the technical targets and activities
as well as the programme structure towards the completion of the S2R Programme.
The Multiannual Action Plan (MAAP) is the translation of the S2R Master Plan into a detailed, medium-
long term R&I plan that concretely identifies the activities, milestones and deliverables to achieve the
overall Master Plan objectives. The MAAP also contain a “long-term vision” chapter, called Executive
view. Its therefore also provides a high-level view of what needs to be done to deliver the S2R vision
as from 2014 onwards. The MAAP is implemented through R&I activities awarded to the Other
Members and open calls in the form of grants or contracts. These calls will result from the detailed
specifications established in the AWP.
S2R
Regulation
S2R JU Governance &
S2R Master
Process Handbook
Plan
S2R Multiannual
Action Plan
8|Page
The S2R JU Governance and Process handbook describes the procedures, processes and actions
underpinning the implementation of the S2R Programme and the roles and responsibilities of the S2R
JU and its Other Members. The handbook defines and documents the Programme governance and
relevant business processes, including relevant templates and guidelines.
9|Page
2 Legal Framework
The legal framework of the S2R JU is described in the regulation and its operational aspects and targets
detailed in S2R Master Plan.
Council Regulation (EC) No 642/2014 of 16 June 20142 sets out the basis for the Joint Undertaking and
its legal basis for the establishment and execution of the S2R Programmes. As the Other Members of
the S2R JU have expressed in writing their agreement and acceptance of the Statutes to this
Regulation, as a consequence duly, they are bound to jointly contribute to and adopt the management
principles put in place by the S2R JU in order to execute agreed R&I activities.
Further adopted from the S2R Regulation are the Membership Agreements and GB decisions.
2.1.2 GB Decisions
The Governing Board has overall responsibility for the strategic orientation and the operations of the
S2R JU and shall supervise the implementation of its activities. In order to efficiently and effectively
manage this responsibility, the GB can decide on new actions or procedures by means of GB decisions.
Rules of Procedure of the Governing Board of the Shift2Rail Joint Undertaking 3;
Decision of the Governing Board adopting the revised financial rules of the Shift2Rail Joint
Undertaking4.
The ED shall:
prepare and submit for adoption to the Governing Board the draft annual budget, including
the corresponding staff establishment plan indicating the number of temporary posts in each
2 http://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32014R0642
3 http://shift2rail.org/wp-content/uploads/2013/07/Consolidated_GB_RoP.pdf
4 http://shift2rail.org/wp-content/uploads/2016/01/S2R-JU-GB_Decision-N-21-2015-revised-financial-rules.pdf
10 | P a g e
grade and function group and the number of contract staff and seconded national experts
expressed in full-time equivalents;
manage the calls and submit for approval to the Governing Board the list of actions selected
for funding;
organise, direct and supervise the operations and the staff of the S2R Joint Undertaking;
monitor the progress made by the IPs towards achieving the objectives.
For a complete description of the functions of the Executive Director, refer to the S2R Statutes 5.
The ED Programme Board has been created at the end of 2019 by ED decision (see annex I) as an
integral part of the decision-making procedure of the Programme supervised by the ED.
5 http://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32014R0642
11 | P a g e
3 Programme Cycle
The Master Plan of the S2R JU was developed by the European Commission services in close
cooperation with the eight S2R Founding Members, and in consultation with the European Union
Agency for Railways (ERA). Inter alia, it serves as a reference document for the call of associated
members to achieve a more competitive and resource efficient European transport system to address
major societal issues such as rising traffic demand, transport safety and security of energy and climate
change.
The Master Plan is a forward-looking roadmap to drive innovation in the rail sector in the medium-
long term. It is the key document to define the strategy of the S2R JU to develop, integrate and validate
innovative technologies and solutions. It defines the technical targets and activities as well as the
programme structure for the whole duration of the programme in order to define S2R’s contribution
to the improvement of the competitiveness and attractiveness of the Railway Sector in Europe.
As already indicated, the Multiannual Action Plan (MAAP) provides a high-level view of what needs to
be done; it explains why and by when. It sets the framework for the research and innovation (R&I)
activities to be performed within and beyond the S2R Programme and the deployment activities to be
carried out by all operational stakeholders, coordinated to achieve the Single European Railway Area.
The description of the visionary part which includes activities beyond the current framework in order
to build the necessary Railway Capabilities is called “Executive View – Part A”7. The second part called
“Part B” is the translation of the S2R Master Plan into a detailed, medium-long term R&I plan that
concretely identifies the activities, milestones and deliverables to achieve the overall Master Plan
objectives. The MAAP Part B is a live document and it has been recently updated taking into account
the latest technological advancement and with a more streamlined presentation of the Technological
demonstrators8. In addition, it was decided to maintain the original MAAP of 2015 as reference
document in cases of doubts with regard, for example, type of assets that the Members other than
the Union committed to provide for demonstration activities. The MAAP is implemented through R&I
activities awarded to the Other Members and open calls in the form of grants or contracts. These calls
will result from the detailed specifications established in the AWP.
This document includes the R&I activities to be carried out by the Other Members complemented by
the ‘open calls’, through calls for proposals and tenders, main deliverables and milestones per
6http://ec.europa.eu/transport/sites/transport/files/modes/rail/doc/2015-03-31-decisionn4-2015-adoption-s2r-masterplan.pdf
7 https://shift2rail.org/wp-content/uploads/2018/04/Maap_2018_FINAL_2.pdf
8 https://shift2rail.org/research-development/key-documents/
12 | P a g e
technical demonstrator (TD), integrated technical demonstrator (ITD) and finally system platform
demonstration (SPD).
9 Including railway research and innovation financed by the Union beyond the S2R Programme itself, as per S2R Basic Act.
13 | P a g e
common cross-cutting themes, the CCA. Together they constitute the S2R Programme, which ensures
a system integrated approach to railway R&I to meet the expectations of the users and stakeholders.
3.2.2.1 IP1: Cost-efficient and reliable trains, including high capacity trains and high-speed trains
The goal of this IP is to address the challenges generated by rail customers’ ever-evolving requirements
for rail passenger vehicles, such as higher quality of service, reliability, comfort, lower energy costs
and decreasing the stress on the economics of rail operations. In order to compete more effectively
and attract more passengers in the future, both the traditional approach to vehicle development and
an entirely new way of thinking on product development is needed. An innovative system approach
will be used to introduce the future generation of passenger trains.
Current systems do not sufficiently take advantage of new technologies and practices, i.e. automation,
satellite positioning technologies, Wi-Fi and high-speed data, to increase functionalities and become
even more competitive. R&I activities should support, by design, the rapid and broad deployment of
advanced interoperable traffic management and control systems to raise the competitiveness of
European solutions globally.
14 | P a g e
The aging of existing infrastructure will increase costs and maintenance. At the same time, reaching
the maximum capacity and being unable to deliver quality services are concerns that need to be
addressed. Automation and managing in a holistic approach (using lean operational practices and
smart technologies) can improve responsiveness, capacity and overall economics of rail
transportation.
Improved information technology made interoperable and increased cross-industry collaboration and
real-time information must help to create a personalised service, where customers can plan door-to-
door journeys seamlessly.
3.2.2.5 IP5: Technologies for Sustainable & Attractive European Rail Freight
The modal share of intra-EU rail freight transport has stagnated in the past decades, partly explained
by the existence of legal barriers restricting competition (including the track access regime, taxation,
etc.), but also by problems of an operational and technical nature. The challenge is to acquire a new
service-oriented profile for rail freight services based on excellence in on-time delivery at competitive
prices and to increase productivity, by addressing current operational and system weaknesses and
limitations.
Continued growth is expected in the intermodal segment, which relies on the use of container trains,
and the wagon load/block train activity segment, which relies on the use of specific freight wagons.
The potential growth in these market segments can be exploited by increasing reliability, service
quality, cost competiveness and improving overall transport time.
15 | P a g e
3.2.2.7 S2R System Architecture and CDM
In 2019, the activities under the acronym IPx were redesigned to also support the achievement of a
System of Systems Approach by starting to build a railway Functional System Architecture and a
Conceptual Data Model (CDM), introducing a structured approach to the functional evolution of the
railway systems. The objective is to provide the sector with a shared path and vision of the future
operations of rail systems, under the policy leadership of the European Commission and in strict
coordination and collaboration with the European Union Agency for Railways.
Concerning the Functional System Architecture, more concrete reflections on new system approaches
started on the control command and signalling side since the work initiated in 2018 by some
Infrastructure Managers with a Reference Command Control Signalling Architecture (RCA) and
recently by some Railway Undertakings with an Open CCS On-board Reference Architecture (OCORA).
This also in the continuation of work started almost a decade before on the EULYNX activities. During
2019, the S2R Programme agreed to launch more structured activities related to the development of
a Conceptual Data Model (CDM) that will contribute to overcome “data” and “systems” fragmentation
with a view to produce a system of systems approach and enabling well-defined modularity. The
developed approach is expected to become the standardised way for existing and new systems to
interact, ensuring their interoperability through “digital continuity”.
Initial activities on implementing a system of systems approach have started with LinX4Rail, a
Members’ project, started in December 2019, with the objective of developing the first railway
Functional System Architecture and defining a Conceptual Data Model (CDM), delivering a system-of-
systems approach and enabling seamless data exchange. The project will take into account the outputs
of existent activities from other IPs, RCA (Reference CCS Architecture), OCORA (Open CCS on-board
reference architecture), standardisation activities, and from initiatives such as EULYNX, railML, IFCRail,
Rail Topo Model (RTM) etc.
3.3 From the Annual Work Plan (AWP) to the Project Kick-Off
Taking into consideration the current legal framework (EU General Financial Regulation, H2020 Rules
of Participation, the S2R Financial Rules, etc.), the S2R Programme is implemented through Annual
Work Plans (AWPs) which detail the R&I activities to be performed in the years to come (from 12 to
48 months indicatively).
The AWP follows a specific management cycle in line with the provisions of the S2R Financial Rules. It
is established on the template provided by the Commission Services for all the Union JUs.
16 | P a g e
The AWP for year N is established as from October year N-2. The process starts with the request of
the Programme Office to the IP/CCA Steering Committees to provide their contribution to detail the
R&I activities expected to be awarded in year N in line with the overall planning foreseen in the MAAP.
The contributions received are grouped together in coherent “topics” by the IP/CCA coordinators
which detail how the activities are expected to be performed in order to ensure that the objectives of
each TD are duly achieved.
The IP contributions shall be provided to the respective S2R Programme Manager not later than end
of December of the year N-2, in order to ensure that the S2R JU ED is in the position to submit the
Preliminary Draft Budget for year N to the EC Services by 31 January N-1.
The Preliminary Draft Budget for year N includes the request to the Union in terms of Commitment
and Payment Appropriations necessary to realize the activities planned in the AWP year N.
The Preliminary Draft Budget for year N is discussed with the Commission Services and becomes part
of the overall negotiations with the Union Budget Authority, the European Parliament and Council.
During year N-1 and in view of the adoption of the AWP for year N at the GB planned in the month of
October N-1, the Programme Office will continue working with the IP Coordinators to finalize the AWP
and further detail as necessary the content.
The IP Steering Committees organized around March-April of year N-1 are the occasion for an in-depth
exchange on the content of the AWP for year N in perspective of the MAAP and the results achieved
through previous and ongoing R&I activities. The final contributions to the AWP for year N by the IP
Coordinators shall be provided to the respective Programme Manager not later than end of June N-1.
In the period March-April N-1, the S2R Scientific Committee (SC) and States Representatives Group
(SRG) will hold their respective meetings to examine the draft AWP at the relevant stage and provide
their scientific and political advice/input in line with the S2R Regulation. This will be taken into account
in the final draft of the AWP to be submitted to the GB.
The European Union Agency for Railways (ERA) shall be involved in the preparation process during the
full cycle, in line with the domains of activity of its responsibility and in agreement with the Programme
Office. Their input on the draft AWP is expected by March N-1.
During the same period, as far as possible, the draft AWP shall be presented also to the Commission
Services in order to anticipate any possible comments and suggestions to reduce the final approval
process within the GB.
As from July N-1 to the final submission to the GB early September N-1, the Programme Office
elaborate the final draft of the AWP for year N, running specific consultations with the IP Coordinators,
SC and SRG.
17 | P a g e
In September N-1, the final draft AWP is sent to the GB for its adoption by the end of October N-1. The
adoption of the GB shall be formalized after having duly consulted the SC and SRG.
The adopted AWP for year N is published on the S2R JU website on the date of the relevant GB
Decision. Unless the budget of the Union is adopted before that date, it shall contain a disclaimer
indicating that the final amounts and content are subject to the final adoption of the budget of the
Union for the relevant year.
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept
10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9
As a result of the AWP adoption, the ED instructs the Programme Office to launch the publication of
the draft call for proposals and/or call for tenders. The call(s) for proposals are expected to be available
in draft format on the H2020 Portal during the first half of November N-1 while the call for tenders
will be following the provisions of Title V of the Union General Financial Regulation.
The call(s) for proposals shall be open for submissions immediately after the adoption of the Union
budget; the close date should allow for sufficient time for the preparation of the proposals, indicatively
three months.
As from submission deadline, indicatively end of March, until early May of year N, all receivable
proposals are evaluated by panels which consist of the S2R JU Programme Manager that chairs the
meetings, a representative of the Commission Services and/or ERA as observers (where appropriate)
and independent experts. The latter are selected by the Programme Office from the H2020 database.
The first step of the evaluation consists of an individual assessment by the independent experts. These
individual assessments are provided to a rapporteur who will prepare the first draft of the evaluation
report. A consensus meeting for each of the panels is organised around mid-May. During the panel
meeting, all evaluators come together and try reaching consensus of the evaluation and relative score.
The process is observed by an independent expert (called observer) to assess any possible issue,
qualitative aspects, transparency, etc. This evaluation process is aligned with the evaluation of
proposals describe in Section 7.1.
18 | P a g e
In parallel to the operational evaluation, the administrative evaluation of the proposals is performed
by the S2R Finance and Administration with the support of some of the Commission Services and the
Research Executive Agency (REA).
The panel reports are transmitted to the S2R JU ED who, taking into account the outcome of the
evaluation process, submits a report to the GB including his recommendations on the proposals’
ranking and financing.
The Governing Board shall approve the list of actions selected for funding, subject to the relevant
provisions on Conflict of Interest. For more details we refer to Article 23 in the Statutes of the
Regulation. The GB meeting is planned to take place during the first half of June year N to ensure the
Grant Preparation phase during June – July. This shall allow the ED, with the timely cooperation of the
awarded consortia and Commission Services/REA, to sign the Grant Agreement with the project
coordinator before the month of August and start the R&I activities of the new Projects as from the
1st of September of year N. As from here, the ‘Project life cycle” starts.
Supervision and monitoring activities of the Programme Offices have been duly adapted, taking into
consideration the role of the Other Members in the JU compared to that of the Open Calls.
On 14 February 2017, the S2R JU transmitted a guidance document explaining the conditions for use,
status, functionalities, required input, etc. of the private part of the Multi-Projects Cooperation Tool,
called “20170213_Cooperation Tool - S2R memo”.
In addition, the S2R Multi-Projects Cooperation Tool provides the Projects with a public website that
is embedded in the S2R Website.
The Projects are nothing else than the administrative instrument to implement the S2R Programme
and the focus should be on the delivery of the Programme results through the means of Project
activities.
19 | P a g e
The review and monitoring of the Other Members’ Projects are based on a calendar year cycle (see
Figure 5). The reporting period for interim payment ends at the end of December each year. Based on
the rules of Horizon 2020, the Project Coordinator has 60 days as from that date to submit both their
periodic financial and technical reports (i.e. by the end of February N+1), through the H2020 Portal.
The S2R Cooperation Tool should be able to facilitate this reporting phase.
The last reporting period10 for final payment based on the rules of H2020 will coincide with the project
end, deviating therefore from the annual cycle.
As from then, the Programme Office has 90 days to proceed with the possible payment of the co-
funding. The Programme office, helped by independent experts when needed, may carry out the
review of the reporting/deliverables for the next 2 calendar years after the payment of the balance.11
Subject to the timely submission of the Financial and Technical Reports, the annual review called here
below “Control Gate” is carried out during April N+1, when the S2R Programme Managers supported
by experts and observers (IP Coordinator(s), external and/or ERA and/or Commission) will assess the
performance of the Projects in accordance with the criteria established in the S2R Financial Rules,
H2020 Rules of Participation and the Grant Agreement and summarized in Chapter 7 – Quality
management.
- Beyond the Control Gate, the S2R JU will monitor the progress of the R&I activities
through a bi-annual reporting, at the following conditions: twice per year, once by end
of July (for the period Jan – Jun of the year n) and once by the end of Jan n+1 for the
full previous year (the latter already in place and foreseen in accordance with the S2R
Regulation on IKOP/IKAA)
- only financial data (no men/months)
- Total Cost (is the total full cost sustained against which we measure co-funding at 44.44
%) per Member (including linked third parties) and Project
- per Member/project , the estimated % of the progress of the work compared to the
estimated planning (if available)
- directly per Member to the JU through the Cooperation tool, no transit through project
coordinators
- based on reasonable estimates if no other data available, especially for reporting at the
end of July.
The reporting will be consolidated by the JU and distributed to all JUs’ Members.
20 | P a g e
These indicators will also be reported to the meetings of the GB as well as the SC and SRG. Based on
the work performed on the indicators, the aforementioned three may be subject to revision.
Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct
9 10 11 12 1 2 3 4 5 6 7 8 9 10
Submit Continuous
Paym progress
project Review
ent overview via
reporting
cooperation
tool and
monitoring via
H2020 tool
Projects
Reporting
start
deadline
(1/9)
Principle: 90 days after
submission
The project review is performed through quantitative and qualitative data, as described in Chapter 7
– Quality Management.
In parallel to the Control Gate, the Financial Reporting will be subject to initiation and verification in
accordance with the S2R Financial Rules and any available vade mecum/procedure/guideline
applicable to H2020 Grants.
The results of the Control Gate and the Financial Review will converge in the proposal to the S2R
Authorizing Officer to accept them and proceed with the payment of the co-funding in accordance
with the relevant grant agreement provisions. Further details can be found in Articles 20, 21, 22, 42
and 43 of the Grant Agreement.
Where there would be the need for additional information, clarifications, etc. these will take place in
accordance with the procedure established in Article 17 of the Grant Agreement.
Based on the experience gained from the implementation of this approach to the first series of
Projects, S2R may decide to amend the Control Gate approach.
21 | P a g e
The S2R JU will assess the periodic review and will decide on a case by case basis on the need for a
project review with experts etc.
The Open Call Projects are not benefitting of the S2R Multi-Projects Cooperation Tool and they will
develop their own communication channels, both internal and external (public). S2R will ensure the
connection with its website to create a platform for the Railway R&I.
A visualization is depicted in Figure 6:
Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul
9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7
Principle: 90
Projects duration > days after
24 months End of submission
Submission
Projects reporting
deadline
start period
(1/9)
On 25 October 2016, the S2R JU transmitted the guidance on the IKOP and IKAA reporting and auditing,
which includes these costs definition. This document, named “Guidance for members and their
appointed auditors_20161118 final” was sent on 26 November 2016 (document reference ED Decision
2016/017) after a proposal and consultation process was made by the JU to the Other Members. See
below Annex
F.
The purpose of this document is to provide the Other Members with a framework for their IKOP and
IKAA reporting as well as for the in-kind contribution certification. For further details on the IKOP and
IKAA reporting and auditing we refer to the aforementioned document.
22 | P a g e
The objective of project closure is to ensure that the project is closed efficiently and effectively. This
is done by ensuring that the agreed scope has been completed, costs are line with the contract, status
is documented, project objectives have been achieved, no work or actions are left outstanding, and all
parties agree and have been informed of the project closure. Project closure takes place when a
project has completed all its goals or if a decision is taken to end the project early.
This process will take place in accordance with the procedures established in Articles 19, 20 and 22 of
the Grant Agreement.
A final review, compliant with the internal quality process, will be performed at the end of each
project. This review will follow the same process as the annual reviews, described in section 3.4.1.
According to Article 22 of the Grant Agreement, the S2R JU and/or the Commission can perform
checks, reviews and audit of the proper implementation of action by the Other Members.
The checks are conducted by S2R JU and, as an example it may consists in asking to the coordinator
(or directly to the beneficiaries) for additional information, mainly during the payment validation
process. If the check shows ineligible costs or serious breach of obligations, it may lead to cost
rejection or grant reduction and, if necessary, recovery (as per art. 42, 43 and 44 of the Grant
Agreement).
The reviews (Art. 22.1.2 of the Grant Agreement) normally concern mainly the technical
implementation of the action, but may also cover financial and budgetary aspects or compliance with
other obligations under the Grant Agreement. They consist in an in-depth examination of the progress
of the action and they could be conducted at any moment and up to 2 years after the payment of the
balance.
The audits normally concern mainly the financial implementation of the action by a beneficiary but
may also cover technical aspects or compliance with other obligations under the Grant Agreement
(e.g. use of the logo). They performed an in-depth examination by the Commission services or any
appointed entity on behalf of the S2R JU.
In addition the S2R JU will propose to the Other Members to organise on-site visits in order to share
experience in the financial management of H2020 projects.
In accordance with the Grant Agreement, audits, checks and verifications can be performed by the
European Court of Auditors and OLAF.
Please note that since the AWP2018 the S2R JU has applied the Lump Sum approach for the Grants
awarded to S2R Members. This is regarded as an administrative simplification as the costs actually
23 | P a g e
incurred are not relevant and therefore there is no need to report them, neither Certificate of Financial
Statements needs to be produced at the final payment anymore. It should be noted although that
records should be kept in the Members’ systems in accordance with their accounting practice. The
checks and reviews made by the S2R JU will focus on the full accomplishment of the work committed
in Annex 1, checking in each reporting period which work packages have been successfully concluded
and releasing the corresponding lump sum share amount only for those ones. During the final payment
possible partial releases of the lump sum share could happen. Audits on financial implementation are
therefore also not applicable and audits would focus on the technical aspects or compliance with other
obligations under the Grant Agreement. In general all kind of checks, reviews, audits and investigation
conducted by JU or ECA, OLAF are always possible under exceptional circumstances.
24 | P a g e
4 S2R JU Governance
This chapter introduces the elements of governance created to manage the different programmes and
describes the committees, boards and groups that are used to steer the programmes and their
activities.
Council Regulation (EU) No 642/2014 of 16 June 2014 sets out the basis for the S2R JU its objectives,
scope and tasks. The S2R JU shall constitute a body entrusted with the implementation of a public-
private partnership referred to in Article 209 of Regulation (EU, Euratom) No 966/2012. The S2R Joint
Undertaking shall be represented by its Executive Director. Its mandate goes beyond the resources
provided by the Union for its Railway R&I and include the management of all-rail focused research and
innovation actions co-funded by the Union.
25 | P a g e
S2R Regulation, complemented by ‘Rules of Procedures of the Governing Board of the S2R
JU’12;
The Executive director (ED), who is a Member of the staff of the JU, and responsible for the
day-to-day management of the S2R JU as well as managing the Shift2Rail Secretariat;
The Scientific Committee which will advise on the scientific and technological priorities to be
addressed in the Annual Work Plans (AWPs);
The States Representatives Group, representing EU Member States and countries associated
with the Horizon 2020 Framework Programme; inter alia, this group will offer opinions on the
strategic orientations of the JU and on the links between Shift2Rail activities and relevant
national or regional research and innovation programmes.
The Scientific Committee and the States Representatives Group are advisory bodies to the Shift2Rail
JU. The ED is also supported by:
European Union Agency for Railways;
IP Steering Committees;
Working Groups setup by the GB:
o User Requirements Working Group and Implementation and Deployment Working
Group;
o System Integration Working Group, including the Cross Cutting Activities subgroup, the
IP coordinators subgroup and temporary subgroup.
The ED Programme Board has been created at the end of 2019 by ED decision as an integral part of
the decision-making procedure of the Programme Governance supervised by the ED.
In order to create a reference architecture for railways and ensure its wide adoption, IPx will work in
conjunction with all IPs and CCA and liaise with the S2R Programme Board to streamline the change
management within the running projects, ensuring these follow well evaluated business cases for all
relevant stakeholders.
The “Change Management process for the S2R Common functional Railway System Architecture and
impact on the S2R programme” is reflected in the document of Annex I.
12 http://ec.europa.eu/transport/sites/transport/files/modes/rail/doc/2014-07-30-rules-of-procedure-of-the-governing-board-of-the-
shift2rail-ju.pdf
26 | P a g e
This work can become the base for a much more Programme and rail sector integration, starting with
achieving a European sectoral agreement on the way the system will be operated in the future, notably
with the use of the ERTMS game changers. This would set the ground for multimodal collaboration,
especially in area dealing with similar aspects such as air traffic management, smart mobility, etc. It
will also provide a new set of business cases and potentially new services that implementing a new
system of system architecture and a new approach in sharing data, will prove in S2R benefits and
performance that would potentially override any concerns on migration costs.
This Working Group shall meet in different configurations, taking into consideration the following
aspects to be examined:
SIWG in the Programme Management set up – IP SteCo Coordinators, TD Leaders and Project
Coordinators;
SIWG in the Programme Strategic View – Members’ representatives mostly GB members, to
which the IP SteCo Coordinators shall be invited based on the agenda;
Any possible other configuration as the need may arise.
The SIWG is chaired by the ED of the S2R JU. The SIWG may also establish on a case by case basis other
dedicated teams to prepare its work or ad hoc activities.
The GB also established two permanent subgroups:
The CCA Steering Committee, which operates similarly to the IP SteCo but focuses on the cross
cutting activities;
The IP Coordinators subgroup, where the IP coordinators (including the CCA coordinator) are
asked to take coordination actions on a needed basis.
27 | P a g e
a representative of each Associated Member participating in the Innovation Programme;
one or more representatives of the Programme Office13, as designated by the Executive
Director.
These Steering Committees are established to guide and monitor the technical functions of the TDs
and ITDs, and to take decisions on technical matters in line with the ED decisions. They discuss the
masterplan, annual work plan and relevant linked projects and report on the progress and status of
the programme.
Each Steering Committee has adopted its rules of procedures, based on a common model approved
by the GB. A chairperson, the IP/CCA coordinator, is selected amongst the Other Members by vote.
These Steering Committees are, in specific, responsible for:
proposing to the Governing Board a shortlist of a minimum of two candidates from which the
IP's representative in the Governing Board will be selected, as well as, where necessary,
establishing an order of rotation. Insofar as possible, the shortlist should reflect a balanced
representation of SMEs, of the research community and of actors from the entire rail value
chain, including from outside the traditional rail sector;
providing the relevant technical input to its IP, in particular for the development of the calls for
proposals with a view to approval by the Governing Board;
establishing the detailed annual implementation plans for the IP in line with the annual work
plans adopted by the Governing Board in accordance with Article 2(c);
ensuring the continuity and synchronicity of the activities to be undertaken in the framework
of the IP and in relation to other IP and cross-cutting activities;
reporting to the Executive Director on the basis of the key performance indicators defined in
Article 2(2) of this Regulation;
responding to requests, related to the IP, from the Executive Director or Governing Board of
the S2R JU;
nominating Technical Demonstrator leaders.
Each Committee meets every three months to handle disputes, propose possible budget re-allocations
and check the implementation of detailed plans. Extraordinary meetings are convened at the request
of the Chairperson or the Executive Director.
13 See art. 10.5 for Programme Office definition and art. 11.2 of the S2R Statute (annex 1 of the S2R Regulation)
28 | P a g e
contribute to a more rapid uptake and large-scale deployment of the solutions developed
through the Shift2Rail activities.
These two working groups have been clustered together for time being (URID-WG).
An ad-hoc group for the revision of the MAAP has also been created and it is called Tiger Team MAAP.
The S2R JU should “bring in the experience and expertise of the European Union Agency for Railways
(ERA) on issues relating to interoperability and safety”14 through different measures of cooperation.
This may include, in its role as regulator and, in this respect, subject to risks of conflict of interest,
facilitating market opening and exchangeability of components.
In the same manner, the relation between ERA and the S2R JU shall be interpreted at the light of the
role of the JU “to manage all rail-focused research and innovation actions co-funded by the Union”.
Firstly, ERA attends as observer the following meetings, with defined contact points maintained in the
S2R JU contact lists:
Governing Board;
IP and CCA Steering Committees;
System Integration Working Group;
Tiger Team MAAP ad hoc group;
User Requirement, Implementation and Deployment Working Group.
As the IP/CCA SteCo and SIWG benefit from the use of the S2R Multi-Projects Cooperation Tool set up
for the sharing of information and documentation, the S2R JU provided direct access to the ERA to
these sections of the Cooperation Tool. Similarly, ERA has access to the Members area of the S2R
website where the GB and SC meeting documentation is stored.
The S2R JU is also regularly informing ERA on matters relevant to their advisory role, though:
Regular email exchanges;
Ad-hoc coordination meetings and conference calls, happening on average every four months.
The S2R JU also requests ERA to provide inputs to the Annual Work Plans as indicated in the section
3.3 of this document. The S2R Regulation provide to the Agency a contributor role, “in particular
by performing the following advisory tasks:
(a) proposing possible amendments to the S2R Master Plan and to the annual work plans, in
particular to ensure that research needs relating to the realisation of the Single European
Railway Area are covered;
29 | P a g e
(b) proposing, after consultation with the stakeholders referred to in point (e) of Article 2(1) of
this Regulation, guidelines for research and development activities leading to technical
standards with a view to guaranteeing the interoperability and safety of results;15
(c) reviewing the common developments for the future system and contributing to defining
target systems in regulatory requirements;
(d) reviewing project activities and results with a view to ascertaining their relevance to the
objectives identified in Article 2(2) of this Regulation and to guaranteeing the interoperability
and safety of research results.”
Taking into account the above and in order to ensure that the results from the S2R projects do not
encounter a regulatory blocking point because of their novelty, the S2R JU has defined with ERA and
DG Move a process for collaboration at project level.
This process allow the ERA to “reviewing the common developments for the future system and
contributing to defining target systems in regulatory requirements” and “reviewing project activities
and results with a view to ascertaining their relevance to the removal of remaining TSI technical
obstacles and to guaranteeing the interoperability and safety of research results.” in the following way:
1. The S2R JU will provide the possibility to ERA to attend the evaluation of the call proposals as
observer. ERA does not have voting right but has the possibility to access to the relevant
documentation and provide to the JU and the independent evaluators with feedback on the
aspects related to interoperability and safety included in the proposals;
2. ERA will provide to the S2R JU, within 2 calendar weeks after the GB approval of the list of
actions/projects selected for funding, the “the level of desired involvement” in those projects
within the scope of its activities16;
3. The S2R JU will discuss the involvement of ERA in the indicated projects with the relevant
Project Coordinator to ensure their participation as appropriate. This should be defined during
the Grant Agreement Preparation (GAP) phase, as far as possible;
4. ERA will provide to the S2R JU by August 1st the name and contact details of the ERA
representative who will be following up the indicated projects;
5. S2R will provide the possibility to the ERA representative(s) to attend the respective Project
Kick-off meeting, which is expected to starting as from September 1st, and may involve him/her
as observer during the Review meetings or Projects checks and may request ERA to provide
written advice on specific Project deliverables or reports.
15A compendium on Safety and Interoperability has already been developed together with the ERA and published on the
S2R website: https://shift2rail.org/wp-
content/uploads/2020/02/Compendium_on_safety_and_interoperability_2019.pdf
16 see Annex H
30 | P a g e
ERA has minimal direct interest/competence and does not attend any meeting,
0 conference, seminar, workshop or any other event organised and managed by the
S2R research project management.
ERA attends at least one of the major events organised and managed by the S2R
1
research project, e.g. kick-off, final conference, mid-term meeting or workshop.
ERA follows on a regular basis open meetings organised and managed by the S2R
2 research project. The Agency follows the discussion and has knowledge of the
research project management activities.
ERA shows particular interest in the research project due to the specific match with
3 its competence. In particular ERA follows the development of results by attending
meetings and may act in a particular role, e.g. member of an advisory board.
For the level of involvement “2” and “3” the S2R JU will discuss bilaterally with the Project consortium
during the GAP and identify on a case by case analysis the Work Packages and appropriate meetings
where the ERA could be directly involved, as well as access to project documentation. This involvement
be formalised, including the possibility to assign to the ERA a specific role within the project (e.g.
member of an advisory board), as far as possible in the Project Grant Agreement preparation.
During the course of the project, in case ERA estimate that a different level of involvement into the
project is necessary, this will be communicated to the S2R JU and following the same above procedure,
then the S2R JU will discuss it with the Project Coordinator.
In case ERA would like to have access to Project documentation where they have no access or that is
not yet available (because not yet submitted as deliverable), ERA will provide the request of access to
the S2R JU. ERA will explain the need, possible time constraints and any other information that is
important to take into account. The S2R JU will agree with ERA the most appropriate course of action
and discuss it with the Project Coordinator.
For the CFM Projects using the S2R Multi-Projects Cooperation Tool, the S2R JU will also ask on a
bilateral basis to the Project Coordinator the authorisation to provide access to the project part of the
tool, in its entirety or partially.
The ERA staff is subject to the Provisions of the Union Staff Regulations and in particular specific
obligations in terms of confidentiality and non-disclosure in the performance of their duties, also after
the end of their work contracts.
In a reciprocity manner, the S2R JU will be attending the relevant ERA Committees working groups,
including, for example, the participation of the S2R ED to the ERA Management Board as observer in
particular when matters related to the scope of activities of the JU are mentioned.
The S2R JU will also provide representatives (from its staff or Members) to the ERTMS Stakeholders’
Platform meeting at Board level as well as in the relevant subgroups of the Platform created for
31 | P a g e
addressing specific topics linked, for instance, to the “ERA Longer Term Strategy” (ATO project, Next
Generation Telecommunications coordination group, and any other future groups to be created by
ERA). The Coordination subgroup of the ERTMS Stakeholders’ Platform may also be considered.
This initial setup should be further considered in the future to avoid overlapping between design and
R&I of innovative solutions and their certification and authorization.
In addition, ERA will also provide access to the nominated S2R JU representatives to other relevant
committees linked to CCS activities (including ERTMS/ETCS) such as the ERA CCS Working Party or the
ERA ERTMS Control Group.
ERA will provide also access to the S2R JU staff representatives to its Extranet and calendar of activities.
ERA will add in their relevant distribution lists the nominated S2R JU staff representatives, ensuring
the proper dissemination of the activities and information on workshop/events.
ERA will also request the S2R JU staff representatives to attend their internal RSG (Research Steering
Group), to ensure full alignment of activities.
32 | P a g e
5 Programme implementation roles and responsibilities
This paragraph describes the roles and responsibilities of the JU staff accountable for the successful
implementation of the S2R Programme. In Annex C, the Programme Contact Persons of the S2R JU can
be found.
The Programme Manager assists in management, monitoring and evaluation of all aspects of the JU
IPs and their specific projects with a view to ensuring that these contribute to fulfil the objectives of
the S2R Master Plan. He/she will ensure the following tasks:
Being the central contact point for S2R actions (awarded grants, projects), supervise those
actions and the fulfilment of the contractual obligations; check, deliverables, periodic reports,
perform on-site reviews, etc. maintaining an overview of progress and financial expenditures
of projects under his/her responsibility;
Review and approve projects deliverables and milestones completion and their alignment with
the Multi-Annual Action Plan;
Participate, as required, to projects progress reviews and other verifications;
Assist in evaluating proposals submitted to S2R calls for proposals or tenders;
33 | P a g e
Follow up Innovation Programme Steering Committees and Cross Cutting Activities and ensure
their work alignment with the Master Plan objectives;
Follow up S2R Working Groups;
Prepare input for S2R bodies;
Safeguard a culture of consistent compliance with rules and regulations as well as ethical
behaviour;
Draft reports and meeting minutes;
Contribute to the finalization of the S2R documentation.
The IP/CCA Coordinator are also chairing the respective IP/CCA Steering Committee and shall have
overall responsibility for the technical and organisational coordination of the Activities launched for
the completion of their IP/CCA.
34 | P a g e
• Notify the TD/CCA Area Leaders and Activities Coordinators of any decision taken by the IP
Steering Committee regarding organisational, financial, technical matters or any other subject
that impacts the TD working activities,
• Cooperate with the Activities Coordinators in order to foster and promote synergies between
TDs and CCA Area, different Activities of other IPs and CCA, H2020 1st call projects, etc.
The Project Coordinator report to the JU through the S2R Programme Manager that is responsible for
that Action by monitoring the progress against the project Work Plan and budget to the timely
execution and proper implementation20 of the projects under his/her responsibility.
35 | P a g e
• Provide all data (financial and technical) requested by the S2R JU;
• Inform the S2R JU of any event that might affect the implementation.
Main
The figure 8 below interactions
summarises & rolesand
the main interactions with
rolesActions/projects
with Actions/Projects:
S2R
Role of S2R JU’s Programme Manager
• Ensuring with the IP/CCA SteCo the fullfilment of the Master Plan
• Central Contact Point for Actions.
• Supervise Actions and the fulfilment of contractual obligations
• Check, deliverables, periodic reports, perform on-site reviews,
etc.
• Check financial statements.
36 | P a g e
5.2.2 Finance team
The Finance team reports to the Head of Administration and Finance of the S2R JU. The activities
expected from the finance department cover a wide range from basic financial statements to providing
clear information to assist management in making strategic decisions, as well as being responsible for
managing cash flows and ensuring sufficient funds are available. In particular, the finance department
will carry out following tasks:
Financial initiation transactions, i.e. invoices, cost statements, payments, in-kind contribution
declarations, etc.;
Financial support to S2R JU operational activities (including assisting Programme Managers,
analysing financial viabilities and following up financial implementations of grants);
Advice on financial practices in line with S2R JU budgetary, financial and contractual rules;
Provide assistance for control and audit missions;
Prepare financial reporting tables and reports.
The Legal Officer reports to the Head of Administration and Finance. His role is to ensure the legal
soundness of the actions and decisions of the S2R JU. In addition to overseeing the work of the legal
support - grants function, the Legal Officer is responsible for the following:
37 | P a g e
6 RACI matrix
Via a RACI matrix (Table 1) an overview is created of which role needs to do what during a certain task
or event.
Actions
TD/WA Leaders
Coordinators
Coordinators
Independent
Head of R&I
IP SteCo
experts
Project
IP/CCA
HAF
SRG
GB
ED
SC
Content & budget for A R C C C C C
AWP
Publication of calls A R C I I I
Evaluation of proposals A R C C I C
Evaluation of (interim) A R C C C
project results
Payment of Other A C R I I I
Members conducting
projects
Scope changes to the A C R C C C C C C
projects/programme
Audit preparation A I R C
Verify end deliverables A R R C
IT security (S2R A C R C C
Cooperation Tool)
Communication and A C R R
Dissemination
Risk management A C R C C
Change management A R R C R C C C
Responsible: “R”: Refers to the person who must ensure that activities are completed
successfully. In a RACI chart, answers the question: Who is getting the task done? Roles taking
the main operational stake in fulfilling the activity listed and creating the intended outcome.
Accountable: “A”: The individual, group or entity that is ultimately responsible for a subject
matter, process or scope. In a RACI chart, answers the question: Who accounts for the success
of the task?
Consulted: “C”: Refers to those people whose opinions are sought on an activity (two-way
communication). In a RACI chart, answers the question: Who is providing input? Key roles that
provide input. Note that it is up to the accountable and responsible roles to obtain information
38 | P a g e
from other units or external partners, too; however, inputs from the roles listed are to be
considered and, if required, appropriate action has to be taken for escalation, including the
information of the process owner and/or the steering committee.
Informed: “I”: Refers to those people who are kept up to date on the progress of an activity
(one-way communication). In a RACI chart, answers the question: Who is receiving
information? Roles who are informed of the achievements and/or deliverables of the task. The
role in ‘accountable, of course, should always receive appropriate information to oversee the
task, as do the responsible roles for their area of interest.
39 | P a g e
7 Quality Management
The evaluation should take into consideration the coherence of the proposal with the MAAP, which
provides a benchmark for the different criteria evaluated (i.e. expected level of technical ambition,
expected level of innovation potential, expected level of progress beyond state of the art, or expected
level of impact of the proposals).
After the individual evaluations, consensus meetings are conducted in the different established
panels, covering the different IPs and cross-cutting themes, which attribute scores (0 to 5) on 3 core
capabilities:
40 | P a g e
This consensus meeting is held in Brussels where the different evaluators start their discussion from
the individual evaluations. First, an agreement must be found on comments before a final score can
be given.
All proposals considered for funding are subject to ethics screening and possible assessment.
•The proposal fails to address the criterion or cannot be assessed due to missing or incomplete
0 information.
•Poor. The criterion is inadequately addressed, or there are serious inherent weaknesses.
1
•Fair. The proposal broadly addresses the criterion, but there are significant weaknesses.
2
•Good. The proposal addresses the criterion well, but a number of shortcomings are present.
3
•Very Good. The proposal addresses the criterion very well, but a small number of
4 shortcomings are present.
•Excellent. The proposal successfully addresses all relevant aspects of the criterion. Any
5 shortcomings are minor.
21 Main conditions for beneficiaries subject to a financial viability check: coordinators (no public bodies nor international organisations
and no mono-beneficiary) if the project requested JU co-funding for the action is ≥ 500.000 EUR
41 | P a g e
In other cases (i.e. for entities that are not coordinators of for coordinators where the project
requested JU co-funding is below the threshold), the financial viability may be checked only if the
request is duly justified by the JU.
In the circumstance where the financial viability check result is weak, the JU Finance Team will:
1. Investigate the possibility for the Other Member concerned to have joint and several liability
(in this case the entity with joint and several liability should itself be made subject to an on-
demand financial viability);
2. Request clarifications from the Other Member concerned (e.g. bilateral meeting) in order to
address the issue, for example through additional complementary information to ensure there
is the necessary financial capacity to implement the project (and being coordinator) through a
risk analysis for the project;
3. Submit the results of these additional steps to the Executive Director who will assess the
situation and, taking into consideration the views of the Other Member concerned, take the
most appropriate measures.
Where following the overall assessment of the situation, the viability check remains classified weak,
the JU shall implement reinforced monitoring, such as an annual update of the viability assessment,
risk profile of the project and its achievements, etc. (see also Grant Preparation Report), evidence of
the transfer of the pre-financing/interim and final payments to the consortium’s beneficiaries and any
other measure deemed appropriate to protect the financial interest of the Members, the JU and the
Union.
Monitoring is a continuous task that takes place in various forms throughout the project (and beyond).
In order to ensure good implementation, therefore the projects are monitored on:
The S2R Project Managers are responsible for the monitoring and liaising with other colleagues for
legal, financial, or administrative issues. They are assessing the deliverable at any moment before
approving the periodic reports (these latter are assessed accordingly to the timeline indicated in the
sections 3.4.1 and 3.4.2 of this document).
42 | P a g e
Beneficiaries are requested to regularly report, in 2 different ways22:
periodic reporting (at the end of each reporting period), for:
o periodic reports, including financial statements;
o final report.
continuous reporting, for the:
o summary for publication;
o deliverables;
o progress in achieving milestones;
o follow-up of critical risks;
o answers to questionnaires (H2020 and S2R (KPIs) indicators);
o etc.
Within the Project Control Gates being the interim or annual review supported by the Periodic reports,
the S2R JU assesses the Project according to project management and project results factors.
The S2R JU requests the Project to submit the Technical Periodic Report following a standard S2R
template providing some guidelines for use, it is made available in Annex A below. The objective of
the process is to have a comprehensive evaluation of the Project status and of its orientation, at a
certain moment in time. Beside the decision on interim payments, the main consequence of the
Control Gate is an agreement (or not23) to the Project to proceed, possibly under certain conditions
and with possible changes to the plan. The Control Gate will be subject to initiation and verification in
accordance with any available procedure/guideline applicable to H2020 Grants.
Project Control Gates assess in a qualitative and quantitative manner, using all the available project
management and project results related criteria and the corresponding indicators or measurements.
During the Project Control Gates, Projects are evaluated looking both backward (how has the project
performed up to now?) and forward (is the plan for the future still adequate?). The evaluation aims to
answer the two following questions:
o “Is the Project delivering the expected result and contributing to the right Programme
outputs?” This factor encompasses evaluation criteria related to the alignment of the
Project DoA/plan (scope, content and schedule) vis-à-vis the needs of the Programme,
43 | P a g e
the submission of project deliverables on time and at the expected level of quality,
achievements of milestones, main scientific/technological achievements etc.
o “Is the Project properly managed and under control?” This encompasses evaluation
criteria related to the quality of the project execution i.e. adherence plan and
dependencies, the effectiveness of the follow-up of previous project control gates
actions, as well as of mitigation actions for risks and opportunities, and the effort
consumed in relation with the actual delivery of the project.
The S2R Programme Office is also assessing the proper dissemination & exploitation of project results,
coming from the project in a programme context.
The major input for the Project Control Gate is the Periodic Report, and in particular the Technical one,
submitted by the Project Coordinator, established in accordance with the provisions of the grant
agreement. Each milestone and deliverable, as defined in the Grant Agreement Annex 1, Sections 1.3.2
and 1.3.4 shall be assessed at the Control Gate together with the Technical Report in order to gain
reasonable assurance regarding the effectiveness, efficiency and economy of operations, the reliability
of reporting, the safeguarding of assets and information, the prevention and detection and correction
of fraud and irregularities and their follow-up, and the adequate management of the risks relating to
the legality and regularity of the underlying transactions, taking into account the multiannual
character of programmes as well as the nature of the payments concerned.
This is more relevant in the context of Projects belonging to an integrated Programme such as S2R
where deliverables may have interdependencies and the final success of the activities build upon the
contribution of each single element.
The Control Gate shall be organized by IP/CCA and all the Projects belonging to an IP/CCA shall
be assessed together by the same panel as far as possible;
The assessors will be provided access to the Technical Reports, including deliverables and
milestones available in the H2020 Portal per IP/Project;
The Programme Manager shall invite the Project Coordinator(s) and the WP Leaders to a
Control Gate meeting (or web-conference) within 20 working days from the launch of the
Control Gate procedure. The respective IP/CCA Coordinator shall be invited as well;
At least 4 working days before the Control Gate meeting, the Programme Manager shall discuss
with the panel their individual assessment; any major aspect shall be brought to the attention
of the Head of R&I;
At the Control Gate meeting all the relevant aspects coming from the panel assessment shall
be discussed in order to reach a conclusion on the sound financial management of the Project
in accordance with the S2R Financial Rules;
44 | P a g e
At the end of the Project Control Gate, the Project also receives a status by the S2R JU:
In addition to the official and in depth control process that it is done through the reporting period
Checks and Reviews, the S2R JU Programme Office is implementing a regular project status analysis
during each IP/CCA Steering Committee meetings. Each project Coordinator and/or TD Leader is
requested to fill in a PowerPoint template (see annex A) indicating various KPIs of the project and the
IP/CCA Steering Committee with the respective S2R Programme Manager will assess the overall status,
represented by the following colours code:
Green: the Project is under control and objectives to date have been achieved. A ‘GREEN’
status is the recommendation to continue with the project as planned. Nevertheless, there
may be an action plan with minor corrective actions to be completed. In essence, this covers
issues and improvements identified at the review that impact on the Project, such as process
improvement, schedule alignment, content refinement etcetera.
Amber: significant issues have been identified which pose a significant threat to a successful
outcome of the Project or Projects and its / their deliverables. An ‘AMBER’ status is a
recommendation to continue with the Project against a corrective action plan, which will be
monitored by the S2R JU.
Typical reasons for an amber status may include but are not restricted to some of the
following:
Material delay to deliverables and/or project milestones;
Project management team not demonstrating adequate control;
Significant non-synchronisation of dependencies;
Overconsumption of effort in comparison with the achievements of the Project;
Inadequate technical coherence and non-alignment with overall Programme
plan (content, scope, schedule);
High level of risk identified by the Project but with few and/or ineffective and/or
not implemented action plans.
Red: gross deficiencies have been identified with the Project’s management and control and/or
the technical quality and direction. The project with a ‘RED’ status is seen to need suspension,
termination, or major realignment to overcome the significant problems encountered. In this
circumstance, the S2R JU ED takes action to either reorient drastically or close the project; the
relevant IP SteCo and the SIWG will be consulted as necessary.
Typical reasons for a red status may include but are not restricted to some of the
following:
Highly significant delay to project deliverables and milestones;
Excessive scope change;
Key deliverables assessed as critically deficient or with major reservations;
45 | P a g e
The level of risk (net criticality) is very high without any mitigation action
planned.
Following the overall Project Control Gate and in particular after the Check or Review of the Reporting
phase, the Programme Manager formulates, via the Head of R&I, the operational proposal to the S2R
JU Executive Director to accept in whole or in part the Interim Technical Report in view of the approval
process for the co-funding.
The proposal to the S2R JU Executive Director for acceptance of the Interim Technical Report including
related efforts, conditions to authorise the Project to continue, and actions to be taken, are registered
in a Project Control Gate Report.
From a contractual standpoint, the Periodic Technical Report constitutes the Contractual Deliverable
against which the Periodic Financial Report is assessed.
Within the meaning of the S2R Financial Rules, the Project Control Gates constitute a key component
of the Authorisation process for the acceptance of the deliverables to become eligible for the co-
funding.
The Interim Financial Report is assessed taking into consideration, as necessary, the guidance material
developed in the context of H2020.
The positive conclusion of the authorisation process – Project Control Gate and Financial assessment
leads to the payment of the co-funding by the S2R JU.
The S2R funded Projects can and must make use of the S2R logo as described in the Grant
Agreement art.29.4.
A particular attention should although be paid on Projects documents with the S2R logo, or
documents developed within a S2R project (by beneficiaries of S2R JU Grant Agreements or external
contractors of S2R JU procurement contracts) for external stakeholders (e.g. standardisation
organisations), which they can only represent a S2R position if the following conditions are all met:
a) There is an agreement within the Project and following the Project decisional procedure set
in the respective Consortium Agreement or Grant Agreement
b) There is an agreement within the respective IP/CCA SteCo and following the decisional
procedure se t in the IP/CCA SteCo RoP
c) There is an official agreement from the S2R JU, through a written confirmation of the S2R ED
46 | P a g e
Each Project beneficiary should therefore not distribute documents labelled S2R without having
taken the above steps or taken the necessary measures to explain that the document do not
represent a S2R position.
Similarly, any Project beneficiary or S2R Member can only officially represent a S2R position if:
the conditions a, b and c above are all met in case of a Project beneficiary
the conditions b and c above are all met in case of a S2R Member
The Project Coordinator or the concerned S2R Member will need to promptly inform the S2R
Programme Manager assigned to the Project or the S2R Head of R&I should such cases arise.
A list of official S2R positions, including possible names of official S2R representatives in external
working groups will be listed and made available in Annex G.
47 | P a g e
8 Risk Management
8.1 Risk Policy
8.1.1 Introduction
The S2R Joint Undertaking is responsible for the execution of the S2R Master Plan leading to the
modernisation of the European Rail system, and contributes to the completion of the Single European
Rail Area (SERA); it is therefore essential to set up a risk management system to enable the Joint
Undertaking to fulfil its mission in the most efficient way.
Risk is defined as: “Any event that could occur and adversely impact the achievement of the S2R Joint
Undertaking strategic and operational objectives. Lost opportunities are also considered as a risk”.
48 | P a g e
The process to identify risks starts at any level within the system: project, Innovation Programme (IP),
Cross Cutting Activities (CCA), overall Programme and Joint Undertaking. Escalating or cascading
process ensures that risk is managed at the appropriate level.
The creation of a risk register ensures awareness within the system. The risk management activities
coordination falls within the responsibilities of the Head Administration and Finance.
8.2.1 Background
The complexity of the S2R JU activity with the involvement of many stakeholders participating to the
execution of the programme organised on the five Innovation Programmes (IPs) and the Cross Cutting
Activities (CCA) with many projects interconnected one with the others, calls for the adoption of a
common framework to manage risks and opportunities at the different levels. This introduces
common language, process, procedures and methodology, providing a benchmark against which the
S2R JU could assess the progress made. This, based on the risk policy, also ensures consistency of
information and data related to risks and opportunities enabling a comprehensive risk analysis at the
level of the Programme and of the Joint Undertaking.
8.2.3 Organisation
The following picture shows the organisation of the S2R Risk Management system:
49 | P a g e
The overall coordination of the risk management activities remains within the responsibility of the
Head of Administration and Finance. He reports to the Executive Director who in turn reports to the
JU Governing Board who is responsible to oversight the execution of the S2R JU.
Operational risks:
Here are managed risks which may impact the achievement of the strategic objectives. The scope
encompasses all the Joint Undertaking activities including governance, funding and resources risks.
The Executive Director is responsible to take action on these risks informing the Governing Board and
where necessary the EU budgetary Authorities.
Here are managed risks which because of their criticality may affect the effective execution of the
Programme. Considering the interdependency among projects within the same Innovation
Programme and with the other IPs and CCA, focus should be put on those risks that may have an
impact throughout the Programme. The responsibility of risk management is with the Head of
Research & Innovation24 who with the support of the Programme Managers will identify and analyse
risks and implement mitigating actions. The Head of Research & Innovation will report to the Executive
Director.
24 This role is now held by the Programme Coordinator (ED decision 17-02)
50 | P a g e
Layer 3 Project level
Here are managed risks related to meeting objectives and performances of individual projects. The
Programme Manager is responsible for risk management for the project he/she is responsible for and,
with the IP/CCA coordinator, for escalating at the level of Programme when required. The risk
management of projects is also part of the section 7 Quality management described above.
The following table shows how risk management is distributed in respect of operational risks:
As above
Here are managed risks relating to the support functions that may affect the efficient and effective
execution of the Programme, and may jeopardise the legality and correctness of the activities
performed by the Joint Undertaking. The responsibility to manage these risks is with the Head of
Administration and Finance. However, risks relating to the Human Resources and Communication are
directly under the responsibility of the Executive Director.
Staff of each sector is responsible to identify and manage risks which are related to their activities and
which may jeopardise the achievement of the specific sector objectives set. They will escalate the risk
at the level above as appropriate.
51 | P a g e
This approach implies that risk management albeit centrally coordinated by a specific function
facilitating and fostering compliance with the S2R JU risk policy and application of the common
framework and its processes, is a business owned and driven process.
Internal Auditor plays an important role in evaluating the effectiveness of the S2R JU risk management
process, regular review should be part of the Internal Auditor annual work plan. It should be noted
however that to preserve its organisational independence and objective judgement, Internal Auditor
should not take any direct responsibility for making risk management decisions or taking risk
management functions.
The process is built on different steps and is iterative, the picture below gives a clear idea of how it is
organised.
52 | P a g e
8.3.1 Establish the context
A clear Risk policy communicates to the staff and stakeholders how the S2R JU positions itself against
risks defining what is the level of uncertainty is willing to accept (risk appetite) in respect to the
achievement of its objectives and how it will manage it. The Executive Director approves the policy
and set the tone, staff at the different levels implement the policy. The strategic objectives of the S2R
JU are set in the Regulation 642/2014 and are the reference to assess risks and opportunities. The
strategic objectives are then broken down in specific objectives relating to the effective use of
resources, reporting relating to the reliability of report giving a true and clear situation of the activities
performed, and compliance objectives related to the respect of applicable laws and regulations.
53 | P a g e
8.4 Methodology25
The evaluation of a risk or an opportunity is influenced by the scenario in which the S2R JU operates,
this is the present environment or the future predicted one. The criticality of a risk is the result of the
combination of the severity of the risk, and the probability that the risk actually occurs. The severity
can be assessed as the impact of the risk occurrence on the activities of the S2R JU. The severity of a
risk can be assessed considering the impact on the S2R JU activities and reputation. As an initial
proposal the following impact can be considered:
Cost;
Delay;
Performance;
Reputation.
25 Methodology for operational risks: considering the similarity of risks identified at project level – Layer 3 (i.e. similar risks in different
projects/grant agreements) - the Programme Managers will use the methodology developed in this chapter and escalate to the
Programme Activities – Layer 2 – those risks identified as unique or as recurrent and that may have an impact throughout the
Programme.
54 | P a g e
4 High Determines non-compliance with set milestones with significant impact on
interdependencies and causing substantial re-planning
5 Very High Determines an unrecoverable delay affecting the whole execution of the
Programme
Probability Matrix
# Impact Description
1 Very low Improbable – so unlikely that probability is close to zero
2 Low One or no occurrence during the execution of the S2R JU Programme
3 Medium Few occurrences may happen during the execution of the S2R JU Programme
4 High Several occurrences may happen during the execution of the S2R JU Programme
5 Very High Will almost certainly happen many occurrences expected during the execution
of the S2R JU Programme.
55 | P a g e
8.4.1 Gross criticality
Gross criticality is the combination of the probability and severity of the risk and is assessed before
the any action is undertaken to reduce it.
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
Likelihood
2 2 4 6 8 10
1 1 2 3 4 5
1 2 3 4 5
Severity
This is a conservative approach, which is sound with the activity performed by the S2R JU.
As shown in the above matrix, the criticality assessment results in four levels:
Green – Very low / low criticality (from 1 to 6)
Yellow – Medium criticality (from 8 to 12)
Orange – High criticality (from 15 to 16)
Red – Very high criticality (from 20 to 25)
56 | P a g e
Accepting the risk whereas the impact falls within the limit set as risk tolerance, or when
mitigating actions are not possible.
5 5 10 15 20 25
4 4 8 12 16 20
Likelihood
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
1 2 3 4 5
Severity
57 | P a g e
The net criticality indicates the residual risk the S2R JU has to manage and is an indication of the
urgency and effectiveness of further actions as needed in order to secure the execution of the activities
in line with the Programme.
Risk Management is part of the planning process insofar it identifies, analyses and treats risks which
may jeopardise the achievement of the objectives set in the plan. Concerning the S2R JU activity, risk
management is encompassed in the Annual Work Plan process whereas risks and mitigating actions
are identified and analysed. The actual results are then reported in the Annual Activity Report. These
documents are drafted once a year providing stakeholders with an overall picture of the S2R JU
progress in the execution of the Programme.
Identification of risks
Preparation of
in relation to the
draft AWP N(x)
foreseen
Adoption of
activities/objectives
Risk AWP N(x)
Assessment
Follow-up on risk
year N(x) Follow-up and specific risk review
management
Reporting on risks
draft/final AAR N(x)
Reporting Risk
Assessment
exercise Year
N(x)
58 | P a g e
9 Change Management
The objective of change management is to effectively control changes and emergency maintenance
services throughout the execution phase of the projects or programme. This can be done by means of
standards and procedures and by outlining the necessities towards the prioritisation and
authorisation, impact assessment, tracking, reporting, closure and documentation of changes.
In the context of the S2R JU Programme, changes on scope, schedule and budget are considered. For
instance, specific changes to projects can be made, as well as more generic changes to the programme.
Change can be required for various reasons, but often act upon service requests, incidents or
problems, for example, risk management, unavailability of resources, under- or overestimated
workload, technical issues etc.
Possible changes shall be discussed at the lowest operational level and escalated at the correct
decision making level, up to the Executive Director, in accordance with the approach defined in the
S2R Regulation. The relevant IP/CCA Steering Committee may act as advisory board to the Programme
Manager on the proposed change(s).
The following sections, visible in Figure 11, describe a standard procedure which can be applied. After
identifying which elements are or need to be changed, it is key to analyse the situation with all relevant
stakeholders and to define an appropriate approach. After implementation, the results are monitored
via the quality management process.
During the project implementation (Project Control Gate or in another period as necessary), or
following the “Change Management process for the S2R Common functional Railway System
Architecture”, changes to the scope, timing, budget, etc. of the project may become necessary..
Proposed changes shall be brought to the attention of the Programme Manager who, with the
assistance of the S2R JU services, will recommend the necessary level of formalization, including a
grant amendment as necessary.
If changes entail a change to the Grant Agreement, a formal amendment to the agreement is
required. Project participants therefore need to define the nature of the change and on that basis
59 | P a g e
assess what action is required. It should be noted that for Lump sums Pilot Grant Agreements
specific rules apply to amendments,
Detailed guidance on the action required for different categories of changes is available in the
following H2020 information:
- https://ec.europa.eu/research/participants/docs/h2020-funding-guide/grants/grant-
management/amendments_en.htm
- https://ec.europa.eu/research/participants/data/ref/h2020/other/gm/h2020-guide-amend-
types_en.pdf
Project Coordinator is asked to follow the formal steps in the Horizon 2020’s ‘Funding & tender
opportunities’ website and to use the amendment request template to explain the changes to the
GA (cf. Annex A).
Possible Changes which may have an impact at Programme level shall be brought to the attention of
the SIWG by the IP Coordinator together with the S2R Head of R&I. Where necessary, these changes
will be formalized in amendments to the AWP to be proposed by the ED to the GB.
60 | P a g e
10 Programme closure (1st approach)
The following chapter highlights the most important deadlines in order to close the Programme
successfully. However, after Programme closure, a number of obligations may still remain.
Final date of eligibility of ‘calls for proposals’: this date is stated in the Programme Regulation as
no later than 31 December 2020 under the Horizon 2020 Research and Innovation Programme (In
justified cases, calls for proposals may be launched until 31 December 2021 at the latest).
Physical Programme completion date: this is when all outputs and deliverables in the project have
been completed and all costs have been paid.
Official Programme completion date: this is the date referred to in Article 1 of the Regulations
where the S2R JU shall be established until 31 December 2024.
The programme is completed when the final programme report (FPR) is approved and all outstanding
financial obligations are settled. This final programme report will provide an overall assessment of the
Programmes results and deliver a final balance. The FPR may not be drafted as long as bilateral
activities, closing actions, outstanding issues, etc. are still being implemented.
At the time of the submission of the closing documents, Other Members have to ensure that all
projects included in the programme closure are functioning, meaning completed, and in use.
The Other Members may decide, exceptionally and on a case-by-case basis, provided that adequate
justification exists, to include expenditure paid for a non-functioning project. In doing so it should take
into account the reasons why a project is non-functioning and it should verify that the financial impact
of the project justifies this special treatment.
By including a non-functioning project in the closing documents, the Member agrees to complete the
project after the initial deadline, within a timeframe which is to be decided by the GB. The Project
Coordinator should ensure funds are made available to complete the project in a timely manner. If
after this new deadline the project is still reported as incomplete, the Project Coordinator will
reimburse the funds granted.
In the final programme report a list of all non-functioning projects will be included in order to be able
to closely monitor these projects.
61 | P a g e
10.3 Final Closure
In order to fully close the Programme and submit the final programme report some administrative and
operational tasks, i.e. financial obligations, reporting, communication, etc. need to be finalised first.
The Central Audit Service shall submit a final audit report and closure declaration to assess the validity
of payments in the final balance.
62 | P a g e
Annex A: Templates
Collaboration agreement
https://shift2rail.org/wp-content/uploads/2020/06/Collaboration-agreement.docx
Meeting Minutes
https://shift2rail.org/wp-content/uploads/2020/06/Meeting-Minutes.docx
Deliverable templates:
https://shift2rail.org/wp-content/uploads/2021/03/S2R-deliverable-template.docx
Project: https://shift2rail.org/wp-content/uploads/2020/03/Template-Project_reporting_2020.pptx
63 | P a g e
Annex B: Technical Demonstrators of each Innovation Programme and
Work Areas of Cross-Cutting Activities
IP1 is built up 7 Technical Demonstrators (TDs), covering all the Research & Innovation areas indicated
in the Shift2Rail Masterplan:
TD1.1 Traction systems
TD1.2 Train control and monitoring system (TCMS)
TD1.3 Carbody shell
TD1.4 Running gear
TD1.5 Brakes systems
TD1.6 Doors and access systems
TD1.7 Train modularity in use (TMIU)
TD1.8 Heating, Ventilation and Air-Conditioning (HVAC)
64 | P a g e
TD3.11 Future Stations
The work in IP4 Programme is structured around 6 Technical Demonstrators (TDs) which cover the
three areas: Technical Framework, Customer Experience Applications and Multimodal Travel Services
and 1 Integrated Technical Demonstrator (ITD) for the overall IP4 coordination and demonstration.
TD4.1 Interoperability Framework
TD4.2 Travel Shopping
TD4.3 Booking & Ticketing
TD4.4 Trip Tracker
TD4.5 Travel Companion
TD4.6 Business Analytics
ITD4.7 Integration and Demonstration
65 | P a g e
Annex C: Contact persons of S2R JU
Travaini Giorgio
ALL Vincent Declerfayt
IP1 Javier Ibanez de Yrigoyen Nadia Debza
IP2 Léa Paties Sandro Benidio
IP3 Sébastien Denis Cosmina Junjan
IP5
Manuel Alarcon Espinosa
IP4 Ester Bravo Barquero
CCA Judit Sándor
IPX Gorazd Marinic
Transversal Van Wortel Monique
To contact us : https://shift2rail.org/about-shift2rail/contact/
66 | P a g e
Annex D: S2R Cooperation Tool guidelines
S2R Multi-projects cooperation tool – MEMO on the use of the internal components of the tool:
https://shift2rail.org/wp-content/uploads/2017/11/Annex-D-20170213_Cooperation-Tool-S2R-memo.pdf
https://www.cooperationtool.eu/projects/documentation/Communications_Guidelines.pdf
Cooperation Tool 4 (CT) – Guidelines for Shift2rail publication and approval of CT objects:
https://www.cooperationtool.eu/projects/documentation/Publications_User_Manual.pdf
https://www.cooperationtool.eu/projects/documentation/Guidelines_for_implementation_of_Collaboration_Agreemen
ts_v1_0.docx.pdf
TPC(IKOP)/IKAA Management:
https://www.cooperationtool.eu/projects/documentation/Cooperation_Tool_4_TPC(IKOP)-
IKAA_Guide_Consolidated_20170117_v04.pdf
67 | P a g e
Annex E: IP/CCA Rules of Procedure
Example IP1
https://shift2rail.org/wp-content/uploads/2017/11/Annex-E-IP_CCA-Rules-of-Procedure.pdf
68 | P a g e
Annex F: ED Decision 2016/017, Guidance for members and their
appointed auditors_20161118 final
https://shift2rail.org/wp-content/uploads/2017/11/Annex-F-ED-Decision-2016017-Guidance-for-members-and-their-
appointed-auditors_20161118-final.pdf
69 | P a g e
Annex G: list of official S2R technical positions and names of official S2R
representatives in external working group
- Olivier Eudes, KONTRON: IP2 representative in the European Union Agency for Railways’
Coordination Working Party on Evolution of GSM-R.
o https://projects.shift2rail.org/download.aspx?id=06adfb88-4d31-4938-ae3a-ba783a371b9b
70 | P a g e
Annex H: List of projects with level of ERA desired involvement
ERA Level of
PROJECT NAME
involvement
IN2RAIL 1
Smart Rail 1
ROLL2RAIL 1
IT2RAIL 1
PINTA 1
SAFE4RAIL 1
CONNECTA 2
X2RAIL1 1 to 3
CYRail 2
MISTRAL 2
IN2TRACK 2
In2SMART 1
S-Code 1
Coactive 1
ATTRACkTIVE
GoF4R 2
ST4RT 1
FFL4E 1
FR8RAIL 1
DYNAFREIGHT 1
INNOWAG 1
IMPACT1 3
NEAR2050 3
FINE 1 1
OPEUS 1
DESTINATE 1
Go-SAFE RAIL 2
X2Rail2 2 to 3
ASTRail 1 to 2
ETALON 1
My-TRAC 2
OPTIYARD 2
IN2STEMPO 2
IN2DREAMS 2
IMPACT-2 3
CONNECTIVE 2
71 | P a g e
SMaRTE 2
MOMIT 1
PLASA-2 3
PINTA2 1
CONNECTA-2 2
X2Rail-3 3
IN2TRACK2 2
MaaSive 1
FR8RAIL II 2
Safe4RAIL-2 2
MOVINGRAIL 2 or 3
GATE4RAIL 1
EMULRADIO4RAIL 2
Assets4Rail 1
SPRINT 1
Shift2MaaS 2 or 3
M2O 2
FLEX-RAIL 2
TER4RAIL 2
FINE-2 1
PIVOT2 2
X2RAIL-4 3
IN2SMART2 2
FR8RAIL III 2
LINX4RAIL 3
TRANSIT 1
CARBODIN 2
NEXTGEAR 2
4SECURAIL 1
OPTIMA 2
FUNDRES 2
RIDE2RAIL 2
LOCATE 2
SMART2 1
RAILS 2
Translate4Rail 3
72 | P a g e
Annex I: Shift2Rail Executive Director Programme Board change
management process
https://shift2rail.org/wp-content/uploads/2020/01/20191219_ED-PB-Change-Management-process_final.pdf
73 | P a g e