201
Friday, January 22, 2021
5:32 PM
9. In comparative selection, during which step does the client issue the
ToR for the project?
a. Invitation
b. Pre-qualification
c. Interview
d. Verification
e. Evaluation
10. What service is rendered when the architect attends conferences
upon the client's request?
a. Architectural research
b. Promotional services
c. Representation
d. Consultation
e. Project definition
14. The architect was asked to analyze the site's potentials, the context
of the site as well as its surroundings. Which service was rendered?
a. Architectural programming
b. Site utilization and land-use studies
c. Site selection and analysis
d. Consultation
e. Space management studies
15. It incorporates a space program with characterizations of the
envisioned spaces such as ambiance, cost range, etc.
a. Architectural programming
b. Space programming
c. Space planning
d. Consultation
e. Space management studies
1. In this phase of the regular design service, the architect prepares the
initial line drawings representing design studies that will lead to a
recommended solution
a. Project definition phase
b. Schematic design phase
c. Design development phase
d. Predesign phase
3. How many sets of drawings should the architect give to the client as
part of the regular design service?
a. 3 sets
b. 5 sets
c. 7 sets
d. 9 sets
4. Once the architect has completed the detailed design and contract
documents phase, the architect is entitled to collect how much of his
fee?
a. 100%
b. 90%
c. 85%
d. 70%
8. In this phase, the architect consults with the owner to ascertain the
conceptual framework and related requirements of the project and
confirms such requirements with him.
a. Predesign phase
b. Project definition phase
c. Consultation phase
d. Schematic design phase
e. Conceptual design phase
9. In this phase, the architect prepares the initial line drawings
representing design studies leading to a recommended solution,
including a general description of the project for approval by the
Owner.
a. Predesign phase
b. Project definition phase
c. Consultation phase
d. Schematic design phase
e. Conceptual design phase
11. In which phase are the technical specifications prepared and issued?
a. Predesign phase
b. Schematic design phase
c. Design development phase
d. Contract document phase
e. Bidding phase
12. In which phase are the outline specifications prepared and issued?
a. Predesign phase
b. Schematic design phase
c. Design development phase
d. Contract document phase
e. Bidding phase
13. Which is NOT a duty of the architect in the regular design service?
a. Responding to questions from bidders
b. Gathering and turning over to the owner written
guarantees required of the contractor and Sub-
contractors
c. Describing the type and quality of materials, finish,
manner of construction and the general conditions
under which the project is to be constructed
d. Assisting the owner in filing the required documents to
secure approval of government authorities
e. All of these are duties of the architect in the regular
design service
14. What is the extent of site visits the architect must conduct in the
course of rendering the regular design service?
a. Periodic
b. Once a week
c. Twice a week
d. Twice a month
e. At the client's pleasure
15. In which phase/s is the architect not expected to update the SPPCC?
a. Schematic design phase
b. Design development phase
c. Contract document phase
d. Bidding phase
e. Both C and D
Part 2. Using the building classifications in SPP 202, identify which group
the following buildings belong to. Choose from Groups 1-10.
1. Parking building
2. Convent
3. Convention center
4. Observatory
5. Shophouse
6. Museum
7. Mortuary
8. Restaurant
9. Fire station
10. Renovation
11. Stadium
12. Race track
13. Warehouse
14. Laundry
15. Serviced apartment
Quiz 5: SPP Docs. 203-205
Friday, January 22, 2021
8:44 PM
2. All of the following are part of the scope of the full-time supervision
service except for:
a. Quality control
b. Evaluation of construction work
c. Preparation of daily inspection reports
d. Filing of documents
e. Cost and time control
11. Which of the following is not part of the scope of services for
construction management?
a. Quality control
b. Evaluation of construction work
c. Building and facilities administration
d. Filing of documents
e. All of these are part of the scope of work for
construction management services
12. Which SPP Document covers services that deal with specific expertise
for the further enhancement of the architectural interior and exterior
components of a project?
a. SPP Doc. 201
b. SPP Doc. 202
c. SPP Doc. 203
d. SPP Doc. 205
e. SPP Doc. 207
9. Who will plan, program and monitor the various activities, and will
act as an adviser on material costs and construction methods?
a. The project manager
b. The construction manager
c. The quantity surveyor
d. The project planner
e. The cost consultant
13. Specialist personnel who may be consulted by the Jurors during the
conduct of the ADC to permit them to obtain all necessary relevant
information
a. Specialist consultants
b. Technical advisors
c. Professional advisors
d. Competition secretariat
e. Technical consultants
14. Who may determine the minimum number of years of active and
relevant professional training and experience in the chosen field of
specialization required for Professional Consulting Architects?
a. IAPOA
b. PRBArch
c. PRC
d. A, B, and C
e. B and C only
*A Professional Consulting Architect (PCA) must possess all of the
following qualifications: Must have the minimum years of active and
relevant professional training and experience in the chosen field/s of
specialization as may be determined by the IAPOA and the
PRBoA/Commission;
15. In design-build services, the owner is given an estimate of the
project. If upon completion, there is realized savings from the
estimated project construction cost, what happens to the savings?
a. It goes to the owner in all cases
b. It goes to the architect in all cases
c. The owner and the client share in the savings 50-50
d. It goes to the owner if there is no stipulation that both of
them will share it 50-50
e. It goes to the architect if there is no stipulation that both
of them will share it 50-50