LTCC
LTCC
LTCC
Construction
Contracts
Methods
1. Percentage of Completion (POC) Method - with reliable estimates
a. Input measures - cost incurred, labor hours, machine hours
b. Output measures - estimates, surveys of engineers and architects
Percentage of Completion =
Total estimated costs to complete
Problem 1
● Cost incurred in obtaining the
contract previously written off 280,000
● Depreciation of equipment used
on the project 480,000
● Payroll of design and technical
department allocated in the
contract 320,000
● Insurance cost
(⅓ for the project) 720,000
● Costs of contracted research
and development 420,000
● Depreciation of idle equipment
not used on a particular contract 240,000
● Selling costs 180,000
● General and administrative expenses
specifically included under the term
of the contract (chargeable to
Problem 1
customer) 120,000
● Borrowing cost incurred during the
construction period 520,000
● Advances made to subcontractors 400,000
Answer: 500,780
Problem 2
On January 1, 2021, Company X entered into a contract to construct a building for a customer.
Company X identified its performance obligation to be satisfied over time. The company uses
the input method based on costs to measure its progress on the contract. The contract price is
P9,000,000. Information on the construction is provided below:
Compute for the revenue, cost of construction, and gross profits in 2021, 2022, and 2023
under:
a. Percentage of completion method
b. Zero-profit method
Problem 2
POC 2021 2022 2023
ANSWERS: Cost of
2,760,000 3,540,000 500,000
Construction
Cost of
2,760,000 3,540,000 500,000
Construction
2. Assuming that the company used the zero-profit method, how much is the
realized gross profit for the year ended December 31, 2023? Answer: (1,000,000)
3. Assume a budget of 80,000 hours to complete the project, how much is the
realized gross profit for the year ended December 31, 2022 if the input method
based on labor hours was used? Answer: 1,050,000
4. Assuming the company used the output method based on value of the work
certified by an expert, how much is the realized gross profit for the year ended
December 31, 2022? Answer: 1,200,000
Problem 4
On April 1, 2022, Company X obtained a contract to construct a building. The building was
estimated to be built at a total cost of P17,500,000, but that amount will be reduced depending on
when construction of building is completed and is scheduled for completion on October 2024.
The contract contains a penalty clause to the effect that the other party was to deduct P35,000
from the contract price for each week of delay.
On December 31, 2022 and 2023, Company X cannot predict the variable consideration regarding
the completion of the project on time because of the different outcomes possible based on the
company’s construction schedule and its experiences with past projects.
On year 2024, due to bad weather conditions, the company does not expect that it can finish the
building on time. The completion of the project was delayed for 5 weeks. Below are the following
data pertaining to the construction periods.
Problem 4
2022 2023 2024
Cost incurred 1,750,000 6,440,000 1,085,000
Estimated cost to complete 7,000,000 910,000 –
Progress Billings 1,400,000 15,225,000 4,200,000
1. Using the percentage of completion method, what is the realized gross profit (loss) in 2023?
Answer: 8,260,000
2. Using the percentage of completion method, what is the realized gross profit (loss) in 2024?
Answer: 840,000
Problem 5
On January 1, 2021, a contractor enters into a construction
contract which includes a fixed contract price of P144,000,000
to build a bridge. The contract has a December 31 year-end.