Seminar
Seminar
Seminar
MANAGEMENT) OF
BY
Mr: Vipul Sonawane
EXAM SEAT NO
10129
UNDER THE
GUIDANCE OF
Prof. Aditya Desai
DEPARTMENT OF
CIVILENGINEERING TSSM's
YEAR 2022-2023
TSSM's
Technology Pune-411021
DEPARTMENT OF CIVIL
ENGINEERING
CERTIFICATE
This work is being submitted as the part of term work for the Subject M.E. Seminar. It is
submitted in the partial fulfillment of the prescribed syllabus of Savitribai Phule Pune
University, for the academic year 202-23 for M.E. (Civil-Construction Management)
course.
I wish to express my deep sense of gratitude towards my guide Prof. Aditya Desai
(Civil Engineering Department) for giving me an opportunity to work on this
topic. They have always encouraged me with new ideas & helped me to develop
interest in this field. There valuable inputs, precise guidance, unremitting
encouragement & vigilant supervision were instrumental in carrying out this topic.
I would also like to thank Dr. R.S.Pawar (Principal, PVPIT), Dr.D.B. Jasutkar
(H.O.D. Civil Engineering Department, PVPIT), Dr.V.O.Biradar (PG
Coordinator), & all Civil Engineering faculties for their kind advice & support. I
also thankful to my parents for their moral support, motivation & encouragement.
Thank you.
Acknowledgement i
Abstract ii
List of Figures. iii
1.0 INTRODUCTION 01-
07
1.01 Introduction of the Project Work 01
1.02 Components of material management 02
1.03 Objectives 03
1.04 The functions of materials management 03
1.06 Planning 04
1.07 Procedure of Material Purchasing 04
1.08 Receive 05
1.09 Inspection
05
1.10 Stacking and Storage
05
1.11 Issuing Material
06
3.0 CONCLUSSION 08
4.0 REFERENCES 09
LIST OF FIGURES
Materials management is a process for planning, executing and controlling field and
office activities in construction. The goal of materials management is to insure that
construction materials are available at their point of use when needed. The materials
management system attempts to insure that the right quality and quantity of materials
are appropriately selected, purchased, delivered and handled on site in a timely manner
and at a reasonable cost. Materials management is the system for planning and
controlling all of the efforts necessary to ensure that the correct quality and quantity
of materials are properly specified in a timely manner, are obtained at a reasonable cost
and most importantly are available at the point of use when required. Thus Materials
management is an important element in project management. Materials represent a
major expense in construction, so minimizing procurement costs improves
opportunities for reducing the overall project costs.
1.06 Planning
The most commonly used basis for planning things out for the project is the BOQ
prepared by the client. Companies may have two major levels in planning- micro
and macro level. Time, cost, material and labour are the four major types of
planning undertaken on sites. The planning should be revised as frequently as
possible in order to monitor whether work is progressing as planned.
1.09 Inspection
Inspection can happen in two ways
1. Pre- dispatch inspection
2. Inspection on site
It is the responsibility of the inspector to inspect all materials delivered to the site prior
to their being used in the work. It is desirable to perform inspection of materials or
fabricated products prior to their delivery at site. E.g.: precast members. The inspector
shall have rights to reject faulty material and have it removed from site. With respect to
manufactured goods, the quality requirements should be specified in the purchase order.
Methods of Inspection
There are three methods of inspection:
1. Visual
2. Tactile
3. Statistical
\
4.0 REFERENCES