SF 05 22
SF 05 22
SF 05 22
IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of
all. The effectiveness of the IMCA Safety Flash system depends on Members sharing information and so avoiding repeat
incidents. Please consider adding safetyreports@imca-int.com to your internal distribution list for safety alerts or manually
submitting information on incidents you consider may be relevant. All information is anonymised or sanitised, as appropriate.
An electrician installed fuses on a 930V DC electrical system while the system Life Saving
was live. Under deck carousels were mechanically and electrically isolated as Rule(s) Bypassing
Energy
a precaution for maintenance work. Several other important vessel systems Safety
Isolation
Controls
were powered from the same drive cabinet. The electrical isolation was
conducted by removing the fuses for the carousel drive unit.
When the fuses were originally removed, the vessel was in port and none of the other vessel systems driven from
this same drive cabinet were powered up. The electrician isolated the power to the entire drive cabinet by isolating
the breakers and removing the fuses. The electrician then left the fuses at the bottom of the cabinet. Tags were not
applied, and the cabinet was left unlocked. On completion of the maintenance work another electrician re-installed
the fuses, believing the power to the cabinet was isolated. He opened the cabinet, removed the protective mesh,
and installed the fuses using a fuse insertion tool rated to 1000V. When inserting the second fuse, an arc flash
occurred, and the fuse blew. The electrician was not injured.
IMCA store terms and conditions (https://www.imca-int.com/legal-notices/terms/) apply to all downloads from IMCA’s website, including this document.
IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall not be liable for any guidance and/or
recommendation and/or statement herein contained. The information contained in this document does not fulfil or replace any individual’s or Member's legal, regulatory
or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.
© 2022 Page 1 of 5
• Additional work team requirements with regard to the isolations had been discussed in the Toolbox Talk (TBT)
but were not carried out;
• The electrician re-installing the fuses did not check if the power to the drive cabinet was isolated before starting
work - failing to follow the instructions written on the cabinet and the work instructions given him.
Actions
• Review of procedures, work instructions, task risk assessments etc. with regard to Permit to Work and electrical
isolations;
• Review of Toolbox Talks to ensure they cover all aspects of the work including PTW and isolations;
• Check that the system you are going to work on is isolated – BEFORE you start work;
• Follow the instructions and warnings signs posted in the workplace. If in doubt, ask!
Members may wish to refer to:
• Electrician suffered flash burn to hand
• Fault in high voltage equipment
• Agitator started moving during mud tank cleaning – leading to injury
Members may also wish to refer to the following incidents involving the word “grating” where someone has fallen
through grating or otherwise grating has played a role in an incident: www.imca-int.com/safety-
events/?searchitem=grating
and needed repair. The worker started work to repair the conveyor line, when it started moving and his arm became
entangled, which caused muscle and tissue damage.
Investigation found that the site supervisor, who had control of the site in the absence of the site manager, was
responsible for completing a Permit to Work for the repair work and isolating the line. However, on his way to
complete the Permit to Work he became distracted by another matter and the Permit to Work and isolation were
not completed. This meant that the conveyor belt restarted during the repair work injuring the employee.
The inspector said: “The site supervisor failed to implement company policy and procedure in respect of Permits to
Work and isolation. This incident could so easily have been avoided by simply carrying out correct control measures
and safe working practices.”
Heavy weather had caused damage to welded plates on deck. While manually handling the plate back into position
with another crew member, the injured person suffered a pinch injury to his finger which was trapped between the
plate and frame. Following a medical review, the vessel headed into port to permit further diagnosis at hospital.
An X-ray showed a distal fracture to the tip of the finger and the wound required stitches.
There was an uncontrolled release of around 15 tonnes of LPG through a valve near to the main roadway used by
LPG road tankers visiting a refinery in Fawley, Hants, UK. The leak went undetected for around four hours before
being discovered by an employee on his way home. It took a further hour to establish the source of the leak with
on-site emergency personnel having to enter the area to reset the valve.
An investigation by the Health and Safety Executive (HSE) found that the leak occurred because:
• LPG was put through the pipe work at too a high a pressure for the valve;
• There was no process in place to detect the discrepancy in the flow in the pipe;
• The company had failed to take all measures necessary to prevent a major incident.
The inspector said “The measures required to prevent incidents should be proportionate to the risks. Where
companies handle large quantities of substances that can cause major incidents, such as LPG, they are required to
have layers of protection in place to prevent incidents.
In this incident a number of those layers either failed or were not in place resulting in a significant leak. Even though
there was no fire or injury on this occasion, there was potential for a major incident. The prosecution has been
brought to highlight the importance of maintaining the layers of protection and preventing this kind of major leak.”
(IMCA emphasis)