FIDIC Green Book
FIDIC Green Book
FIDIC Green Book
Published by
its appreciation of the time and effort devoted by all the above.
0 FlDlC 1999
FOREWORD
ons will together comprise the Conditions governing the rights and
tion of tenders.
8 FlDlC 1999
CONTENTS
Acceptance
Appendix
General Conditio
1 GENERAL PROVlSl ............................. 1
EEMPLOYER ........................................ 2
Authorised Person
Employer's Representative
9 REMEDYING EFFECTS . . . . . . . . . . . . . . . . . . . . . . . . . . .5
9.1 Remedying Defect
9.2
10 ................................ 6
10.1
10.2
10.3
10.4
10.5 Claim Procedure
12 DEFAULT .......................................... . . . .8
12.1 Default by Contractor
12.2 Default by Employer
12.3 Insolvency
12.4 Payment upon Termination
Particular Conditions 13
..................................31
8 FlDlC 1999 C
1
-
1 .
OFFER
The Contractor has examined the document ndix which forms part of this
UJ Agreement and offers to execute the Works the Contract for the sum of
0
f
0
s
- _. - (date)
Signature: . Date: . . . - ._
EPTANCE
e Employer has by signing below, accepted the Contractor's offer and agrees that in
when the Contractor receives one original of this document signed by the Employer.
"
Signature: -~ ___ _. - .
Date: .. --
Name: - -. - -- - Authorised to sign on behalf of (organization
name): - . .- -.-
Capacity: - - .- - - -- -
i Q FlDlC 1999
APPENDIX
I Note: with the exception of the items for which the Empolyer)Q?gl&pmdnst
6% have
been inserted, the Contractor shall complete the
submitting his offer. ]
The Agreement . . . . . . . .
Particular Conditions . , . . .
General Conditions . . . . . . .
The Specification . . . .
The Drawings . . . -
The Contractor's te
design
(9) The bill of quan
(h) ...
-. .- , . -. .
Amount . . . . . . . . . . . . . . . . 4.4 . . . . .
0 FlDlC 1999 ii
Sub-clause Data
- - - --
n
Requirements for Contractor's
design (if any) . . . . . . . . . . . . . . 5.1 .....
Programme:
I
..- - -.. -. --
Valuation o
Plant 90%'
Workers
Other cover*
Arbitration
Q FlDlC 1999 iv
General Conditions
p
Geniral Provisions
1.1
Definitions In the Contract as defined below, the words and expre
following meanings assigned to them, except where the -
n
"Specification" means the documen n the Appendix, including a
Employer's requirements in res o be carried out by the
Contractor, if any, and any Variati
Dates, Times and 1.1.7 " C w e n t Date" means the date 14 days after the date the
Periods Agree omes into effect or any other date agreed between the Parties.
for Completion" means the time for completing the Works as stated
the Appendix (or as extended under Sub-clause 7.3),calculated from the
ommencement Date.
Money and Pay means all expenditure properly incurred (or to be incurred ) by the
Contractor, whether on or off the Site, including overheads and similar
charges, but does not include profit.
/
1.1.15 "Materials" means things of all kinds (other than Plant) intended to form or
forming part of the permanent work.
1-2 - _. . .. . . - - __ .. . . . --
Law
1.5 . - ...
Communications
1.6
ontractor shall comply with the laws of the countries where activities are
med. The Contractor shall give all notices and pay all fees and other charges in
The Employer shall provide the Site and right of access thereto at the times stated in
the Appendix.
2.2 . .. .. ..... -. -
Permits and Licences The Employer shall, if requested by the Contractor, assist him in applying for permits,
licences or approvals which are required for the Works.
2 0 FlDlC 1999 Short Fonn of Contract
2.3 The Contractor shall comply with all instructions given by the Employer in respect of
Employer's Instructions the Works including the suspension of all or part of the Works. 5
W
2.4 5
W
'II:
Approvals No approval or consent or absence of comment by the Employer or the Employer's CI)
a
representative shall affect the Contractor's obligations.
-
er's Representatives
3.1
Authorised Person One of the Employer's personnel shall have
person shall be as stated in the Appendix, or as 0th
the Contractor.
. - _.---
Employer's
Representative appointee may be named in the A by the Employer to the
Contractor from time to time. The Emp ontractor of the delegated
4.1
General Obligations The Contractor shal
Contract. The Contr
4.2
Contractor's mit to the Employer for consent the name and particulars of
Representative
4.3
Subcontracting
part of the Works without the consent of the Employer.
4.4 . - - _._
Performance Secur
The Contractor shall carry out design to the extent specified, as referred to in the
Appendix. The Contractor shall promptly submit to the Employer all designs
prepared by him. Within 14 days of receipt the Employer shall notify any comments
or, if the design submitted is not in accordance with the Contract, shall reject it
stating the reasons. The Contractor shall not construct any element of the
permanent work designed by him within 14 days after the design has been
General Conditions 8 FlOlC 1999 3
submitted to the Employer or where the design for that element has been rejected.
Design that has been rejected shall be promptly amended and resubmitted. The
Contractor shall resubmit all designs commented on taking these comments into
account as necessary.
5.2
6.1
Employer's Liabilities In this Contract, Employer's Liabilities mean
7.2
Programme Within the time stated in the Appendix, the Contractor
, .
programme for the Works in the form stated in the
7.3 -. .. . . . . .
Extension of Time
the Time for Completion if he is or will be
Liabilities.
c
On receipt of an application from th ployer shall consider all
supporting details provided by the I extend the Time for
1
Completion as appropriate.
7.4 - . .- .. . . - -. . - . -. . - --
Ta
8.1
Completion
8.2
Taking-Over Notice r when he considers that the Contractor has
accordingly. Alternatively, the Employer may
ntractor that the Works, although not fully complete, are ready for taking
9.1
Remedying Defects The Employer may at any time prior to the expiry of the period stated in the Appendix,
notify the Contractor of any defects or outstanding work. The Contractor shall remedy
at no cost to the Employer any defects due to the Contractor's design, Materials,
Plant or workmanship not being in accordance with the Contract.
General Conditions 8 FlDlC 1999 5
The cost of remedying defects attributable to any other cause shall be valued as a
I-
z
W
Variation. Failure to remedy any defects or complete outstanding work within a
B
W
reasonable time of the Employer's notice shall entitle the Employer to carry out all
necessary work at the Contractor's cost.
d 9.2
Uncovering and Testing The Employer may give instruction as to the uncovering and/or te
Unless as a result of any uncovering andor testing it is est
Contractor's design, Materials, Plant or workmanship are not
Contract, the Contractor shall be paid for such uncoverin
Variation in accordance with Sub-clause 10.2.
z
0
50
0
2
n
a 10.1
Right t o Vary The Employer may instruct Variations.
10.2 -- .-
W
9
I?
Valuation of Variations Variations shall be valued as follows:
3
8 a) at a lump sum price agree
10.3
Early Warning
ontractor shall be entitled to the amount of such Cost. If as a result of any of the
The Contractor shall submit to the Employer an itemised make-up of the value of
Variations and claims within 28 days of the instruction or of the event giving rise to the
claim. The Employer shall check and if possible agree the value. In the absence of
agreement, the Employer shall determine the value.
11.2 .. - __
Interim Payments Within 28 days of delivery of each state oyer shall pay to the Contractor
the amount shown in the Contrac less retention at the rate stated in
the Appendix, and less any mployer has specified his reasons
for disagreement. The Emplo by any sum previously considered
by him to be due to the Contr
11.4
Payment of First Half of One half of the fete be paid by the Employer to the Contractor within 14
Retention days after iss@ der Sub-clause 8.2.
11.5
Payment of Second Half The remainder shall be paid by the Employer to the Contractor within
of Retention r either the expiry of the period stated in the Appendix, or the remedying
days&
of notif efects or the completion of outstanding work, all as referred to in Sub-
hever is the later.
11.6
6@*
Final Payment days of the latest of the events listed in Sub-clause 11.5 above, the
ctor shall submit a final account to the Employer together with any
docu entation reasonably required to enable the Employer to ascertain the final
ontfact value.
11.7
Currency
@8 Within 28 days after the submission of this final account, the Employer shall pay to the
Contractor any amount due. If the Employer disagrees with any part of the
Contractor's final account, he shall specify his reasons for disagreement when making
payment.
Default by Contractor If the Contractor abandons the Works, refuses or fails to comply with a valid
---1
referring to this Sub-clause and stating the default.
Default by Employer If the Employer fails to pay in accorda act, or is, despite a written
W complaint, in breach of the Contract, t give notice referring to this
0
Sub-clause and stating the default. If
$
0 the Employer's receipt of this noti
s or parts of the Works.
If the default is not rem days after the Employer's receipt of the
Contractor's notice, the
21 days, terminate the
12.3
Insolvency under any applicable law, the other Party may by notice
iately. The Contractor shall then demobilise from the Site
case of the Contractor's insolvency, any Contractor's
mployer instructs in the notice is to be used until the
12.4
Payment upon be entitled to payment of the unpaid balance of
Termination of the Materials and Plant reasonably delivered
The net balance due shall be paid or repaid within 28 days of the notice of
termination.
13.2 L-----
14.1
Extent of Cover e Contractor shall, prior to commencing the Works, effect and thereafter maintain
joint names of the Parties:
for loss and damage to the Works, Materials, Plant and the Contractor's
Equipment,
b) for liability of both Parties for loss, damage, death or injury to third parties or
their property arising out of the Contractor's performance of the Contract,
including the Contractor's liability for damage to the Employer's property other
than the Works, and
c) for liability of both Parties and of any Employer's representative for death or
injury to the Contractor's personnel except to the extent that liability arises from
the negligence of the Employer, any Employer's representative or their
employees.
General Conditions Q FlDlC 1999 9
14.2 All insurances shall conform with any requirements detailed in the Appendix. The
Arrangements policies shall be issued by insurers and in terms approved by the Employer. The
Contractor shall provide the Employer with evidence that any required policy is in force
and that the premiums have been paid.
All payments received from insurers relating to loss or damage to the Works shall be
1 held jointly by the Parties and used for the repair of the loss
compensation for loss or damage that is not to be repaired.
14.3
Failure to Insure If the Contractor fails to effect or keep in force any of t
previous Sub-Clauses, or fails to provide satisfactory
z the Employer may, without prejudice to any other ri ect insurance for
the cover relevant to such default and pay the pr d recover the same
0 as a deduction from any other monies due to the
O
2
N
a=l AA
of Disputes
15.1
Adjudication Unless settled amicably, an nce which arises between the
Contractor and the Employer n with the Contract, including any
valuation or other decision be referred by either Party to
adjudication in accordan Rules for Adjudication ("the Rules"). The
adjudicator shall be any e Parties. In the event of disagreement,
the adjudicator shall be rdance with the Rules.
15.2
Notice of Dissatisfaction
\$
If a Party is d i s s a t i s f i a h e decision of the adjudicator or if no decision is given
Rules, the Party may give notice of dissatisfaction
hin 28 days of receipt of the decision or the expiry of
n. If no notice of dissatisfaction is given within the specified
e final and binding on the Parties. If notice of dissatisfaction
led time, the decision shall be binding on the Parties who shall
delay unless and until the decision of the adjudicator is revised
by an
15.3
Arbitration hich has been the subject of a notice of dissatisfaction shall be finally
arbitrator under the rules specified in the Appendix. In the absence
ement, the arbitrator shall be designated by the appointing authority specified
Any hearing shall be held at the place specified in the Appendix and
referred to in Sub-clause 1.5.
sub-c1@ 10
Page
&@
Adjudication
Approvals 3
Arbitration 10
Arrangements, Insurance .1 10
Authorised person 3
Communications 2 J
7
Completion 5 i9
Contractor's Care of the Works 9
Contractor's Design 3
Contractor's Representative 3
Currency 7
Default by Contractor a
Default by Employer 8
Definitions 1
Delayed Payment 11.8 7
14.3 10
Final P 11.6 7
13.2 9
4.1 3
12.3 8
11.3 7
terpretation 1.2 2
Statutory Obligations 2
Subcontracting 3
Note It is intended that the Short Form of Contract will work satisfact
Particular Conditions. However, if the requirement of
amend any Clause or to add provisions to the Cont
additions should be set out on pages headed Particular
taken with the drafting of such Clauses especially in
the Particular Conditions by Sub-clause 1.3.
0 FlDlC 1999 13
I
i
IY W
W
[r
&$i
(I)
z
JO
$E
luc3
djudication shall
66
ffV
Terms of Appointment 6 The A to be, and is to remain throughout his appointment, impartial
pendent of the Parties and shall immediately disclose in writing to the
nything of which he becomes aware which could affect his impartiality
The Adjudicator shall not be called as a witness by the Parties to give evidence
concerning any dispute in connection with, or arising out of, the Contract.
9 The Adjudicator shall treat the details of the Contract and all activities and
hearings of the Adjudicator as confidential and shall not disclose the same
without the prior written consent of the Parties. The Adjudicator shall not,
without the consent of the Parties, assign or delegate any of his work under
these Rules or engage legal or technical assistance.
10 The Adjudicator may resign by giving 28 days' notice to the Parties. In the event
of resignation, death or incapacity, termination or a failure or refusal to perform
the duties of Adjudicator under these Rules, the Parties shall agree upon a
replacement Adjudicator within 14 days or Rule 4 shall apply.
Rules for Adjudication Q FlDlC 1999 15
11 The Adjudicator shall in no circumstances be liable for any claims for anything
done or omitted in the discharge of the Adjudicator's duties unless the act or
omission is shown to have been in bad faith.
12 If the Adjudicator shall knowingly breach any of the provisions of Rule 6 or act
reimburse each of the Parties for any fees and expenses pro
if, as a consequence of such breach any proceedings o
Adjudicator are rendered void or ineffective.
6
in bad faith, he shall not be entitled to any fees or expenses hereunder and shall
paid to him
s of the
L
?
v
-
Payment 13 The Adjudicator shall be paid the fees and e x p e n k w e Adjudicator's
Agreement.
15 The daily fee shall be pay rking day preparing for or attending
Site visits or hearings isions including any associated travelling
time.
16 The retainer and remain fixed for the period of tenure of the
Adjudicator.
17 nv
All payments q t R q judicator shall be made by the Contractor who will be
sed half by the Employer. The Contractor shall pay
im within 28 days of receipt. The Adjudicator's invoices
retainer shall be submitted quarterly in advance and invoices
expenses shall be submitted following the conclusion of a Site
. All invoices shall contain a brief description of the activities
relevant period. The Adjudicator may suspend work if any
the Contractor.
Procedure for 0 A dispute between the Parties may be referred in writing by either Party to the
Adjudicator for his decision, with a copy to the other Party. If the Adjudicator
has not been agreed or appointed, the dispute shall be referred in writing to the
other Party, together with a proposal for the appointment of an Adjudicator. A
reference shall identify the dispute and refer to these Rules.
20 The Adjudicator may decide to visit the Site. The Adjudicator may decide to
conduct a hearing in which event he shall decide on the date, place and
duration for the hearing. The Adjudicator may request that written statements
from the Parties be presented to him prior to, at or after the hearing. The Parties
shall promptly provide the Adjudicator with sufficient copies of any
documentation and information relevant to the Contract that he may request.
46 0 FlDlC 1999 Short Form of Contract
21 The Adjudicator shall act as an impartial expert, not as an arbitrator, and shall
have full authority to conduct any hearing as he thinks fit, not being bound by 5
any rules or procedures other than those set out herein. Without limiting the ' W
E
W
foregoing, the Adjudicator shall have power to: w
U
9
(a) decide upon the Adjudicator's own jurisdiction, and as to the scope of
any dispute referred to him,
(b) make use of his own specialist knowledge, if any,
(c) adopt an inquisitorial procedure,
(d) decide upon the payment of interest in acc
(e) open up, review and revise any opinion
certificate or valuation, related to the di
Identificationof Project:
- . .-_- -.
(the "Project")
J .. . . --
(the "Employer")
- .
(the "Contractor")
- . .
and the dispute provisions of the Contract shall form part of this
Agreement.
Expenses (including the cost of telephone calls, courier charges, faxes and
telexes incurred in connection with his duties; all reasonable and necessary
travel expenses, hotel accommodation and subsistence and other direct travel
expenses).
4.
5.
*
The Adjudicator agrees to act as adjudicator in accordance with the Rules and
has disclosed to the Parties any previous or existing relationship with the
Parties or others concerned with the Project.
Address
Date
0 FIDIC 1999 19
Notes for Guidance
(not forming part of the Contract)
One result of the simple for that there is an increased burden on the
Employer to set out in the and Drawings the full scope of works,
including the extent of any ne by the Contractor.
Agreement
required,
q-. no overall limit on the Contractor's liability. If such a limit is
lause should be inserted in the Particular Conditions.
.
$i
!J@ s and uncertainties that surround "letters of acceptance" and "letters of
as thought preferable to promote a clear and unambiguous practice.
+&
It is in ended that the Employer will write in the Employer's name in the Agreement
d fill in the Appendix where appropriate and send two copies to tenderers together
h the Specification, Drawings etc forming the tender package. In respect of both
copies, the Contractor is to complete, sign and date the Offer section and complete
any remaining spaces in the Appendix. Having decided which tender to accept, the
Employer signs the Acceptance section of both copies and returns one copy to the
Contractor. The Contract comes into effect upon receipt by the Contractor of his copy.
General Provisions Definitions. Th ese Conditions are not all the same as
those to be fou Contracts. This is as a result of the need
s sort. Significantly different definitions
, Variation and Works.
Particular Conditions and given priority over the General Conditions. If none,
delete the reference.
The Specification should set out in clear terms any design that the
Contractor is required to undertake, including the extent to which any
design proposals are to be submitted with the tender. If none, the reference
to the Contractor's tendered design should be deleted.
If there are additional documents which are required to form part of the
Contract, such as schedules of information provided by the Contractor,
these should be added by the Employer. Consideration should be given in
each case to the required priority.
1.1.14 "Force Majeure" may include, but is not limited to, exceptional events or
circumstances of the kind listed below, so long as all of the four conditions
stated in the definition have been satisfied: n
foreign enemies,
or usurped
contamination by radioactivity,
activity, and
volcanic activity.
1.1.19 "Works". The term "Works" ' to cover all the obligations of the
Contractor, including any e remedying of defects.
1.6
._. - .- - . ~
The Employer ess the Parties have agreed otherwise, the Site must be handed over by
Contractor on the Commencement Date. This is 14
er the Contract has come into effect, which occurs when the signed
returned by the Employer to the Contractor (see also
-Clause 1.1.7 above).
If for any reason, permits etc may also be required from places other than
the Country, this Sub-clause could be limited by the addition at the end of
the words:
2.4 The term "approval" is only used in the Conditions in relation to the
performance security at Sub-clause 4.4 and insurances at Sub-clause
14.1. It is important that risks such as those of poor workmanship or
Contractor's design are not transferred to the Employer unintentionally. The
Sub-clause is intended to prevent argument.
Employer's 3 Two principles guided the drafting of this Clause. Firstly, the Contractor
Representatives should know who in an Employer organisation is authorised to speak and
Notes for Guidance 0 FlDlC 1999 23
act for the Employer at any given time. This is achieved by Sub-clause 3.1 :
the authorised individual should be named in the Appendix.
I
representative, he should
order to avoid the risk of
1 The Contractor 4.1 Most contracts do act standard required for each element
would be desi
Design by Contractor with all design-build contracts it is essential that the Employer's
requirements are set out clearly and precisely. The Appendix should indicate
to tenderers the Sub-Clause(s) in the Specification that set out the design
requirement. Where the Employer procures any part of the design, the
responsibility for design will be shared as this Contract makes the
Contractor responsible only for design prepared by him. The extent of the
Contractor's design obligation should therefore be clearly stated if disputes
are to be avoided. The Conditions avoid the confusing concept of approval
of design. Designs are submitted and may be returned with comments or
rejected. The Employer need not react at all.
5.2 The Contractor's responsibility for his design remains, as is made clear here
and in Sub-clause 2.4. In the event of conflict between the Specification
and Drawings and the Contractor's tendered design, the order of priority in
the Appendix makes it clear that the Employer's documents prevail. This
means that if the Employer prefers the Contractor's tendered solution, the
Specification and Drawings should be amended before the Contract is
signed by the Parties.
24 8 FlDlC 1999 Short Form of Contract
The Contractor will have an absolute obligation to ensure that the parts of
the Works designed by him are fit for their purpose, provided that the
intended purposes are defined in the Contract. The Employer must
therefore make clear in the parts of the Specification that impose design
obligations, the intended purposes of the part of the Works to be designed
by the Contractor. This should be done even where this seems obvious in
order to avoid argument about whether an intended p u r p o s w e f i n e d or
not.
Time for Completion 7.2 The Appendix should stipul requirements as to the form
and level of detail of prog bmitted. Where Contractor's
design is required, the App ate that the programme should
show the dates on which prepare and submit drawings etc.
Taking-Over 8.2 with normal practice, it is not envisaged that the Works need be
There is no defined Defects Liability Period but during the period - normally
12 months - from the date of taking-over, the Employer may notify the
Contractor of defects. The Contractor must remedy such defects within a
reasonable time. If he fails to do so, the Employer may employ others for
that purpose at the Contractor's cost. The Employer may also notify defects
at any time prior to taking-over,
The liability of the Contractor for defects will not normally end with the expiry
of the period stated in the Appendix. Although he is then no longer obliged
Nates for Guidance Q FlDlC 1999 25
to return to Site to remedy defects, the defect represents a breach of
contract for which the Contractor is liable in damages. This liability remains
for as long as the law of the Contract stipulates, often 3, 6 or 10 years from
the date of the breach. If this long-term liability is to be reduced or
eliminated, a Clause in the Particular Conditions is required.
I
0
z < Variations and Claims 10.1 Variation is defined to include any change to the Spe
JO included in the Contract. If the Employer requires
gg Works designed by the Contractor either
55 I Contract was awarded, then this is to be
C!lo
2
I
' Contractor's design.
0 1
$ 1
3:
0 10.2 This Sub-clause sets out alternative pr
Variations, to be applied in the ord
omissions as to additional works.
Contract Price and Normally only one of the options in the Appendix should be used to indicate
how the sum in the offer is be calculated and presented. The following
explains what is intended:
Lump sum price A lump sum offer without any supporting details.
This would be used for very minor works where
Variations are not anticipated and the Works will
be completed in a short period requiring only one
payment to the Contractor.
11.5 The release of the second part of the retention will serve as confirmation that
all notified defects have been remedied.
uch equipment. Local law will often protect the Employer from
e and reckless removal of essential items.
J
Q& 15.3
It is intended that all decisions made by the Employer or his representative
should be capable of being reviewed by an adjudicator and, if required, by
an arbitrator.
Arbitration may not be commenced unless the dispute has first been the
subject of an adjudication. The Rules of arbitration should be stipulated in
the Appendix. The UNCITRAL Rules are recommended. However, if
administered arbitration is required, that is arbitration overseen and
administered by an arbitral institution, the ICC Rules could be specified. The
ICC Court of Arbitration and its Secretariat in Paris appoints and replaces
arbitrators, checks the form of terms of reference and awards and generally
monitors progress and the performance of arbitrators. Where alternative
Notes for Guidance 0 FlOlC 1999 29
I-
H !
W
W
I
'
3 i I