SemesterOut Report
SemesterOut Report
SemesterOut Report
I am indeed grateful to the Almighty God for giving me life and good health and seeing me through
the semester out period and report writing period and also granting me the opportunity to be in
Takoradi Technical University in the first place Glory be into his name.
I also thank the management of Takoradi Technical University for introducing the semester out
program for Civil Engineering students which has aided students to gain adequate industrial and
My profound gratitude also goes to the management of the Resource Access Limited- RAL
and the various workers in the company who dedicated their time to help me learn, understand
and gain enough practical knowledge and experience. May the almighty God richly bless them.
1
DEDICATION
This report is dedicated to the management and stuff of Resource Access Limited- RAL for their
acceptance, tolerance, supervision and their willingness in helping me gain industrial experience
for the short period of time. This report is a proof that the time you spent to help me gain industrial
2
Table of Contents
ACKNOWLEDGEMENT .................................................................................................................................... 1
DEDICATION ...................................................................................................................................................... 2
CHAPTER ONE................................................................................................................................................... 6
CHAPTER TWO................................................................................................................................................ 12
2.1 DESCRIPTION OF THE NATURE OF WORK DONE AT THE EARTHWORKS DEPARTMENT. ..12
2.2.3. Excavator..................................................................................................................................................16
3
2.3.3 Preliminary Survey ...................................................................................................................................22
Instruments ........................................................................................................................................................29
CHAPTER THREE............................................................................................................................................ 34
3.1 DETAIL OF WORK DONE AT THE EARTHWORKS AND SURVEYING UNITS ON SITE ..............34
4.1. CONTRIBUTIONS MADE TO THE EARTHWORKS, SURVEY AND SAFETY AND TRAFFIC DEPARTMENT
4
Table of figures
Figure 11 Shows the laying of the geotextile and spreading of the chippings on site. ......... 36
5
CHAPTER ONE
1.0 INTRODUCTION
As part of the requirement to obtain a Bachelor of Technology degree in Civil Engineering (B-
Tech) from Takoradi Technical University, the semester out program has been designed to help
students to gain lots of work experience before Completing their program of study. The semester
out program helps student to learn to Communicate, Socialize and relate effectively with
Supervisors and Collogues which also increases their chances of employment that particular
institution after completing their program. Overall, the industrial attachment gives students of
Takoradi Technical University a competitive employment edge over their colleges in other
Universities.
The main objective of the industrial attachment is to help students acquire practical knowledge by
being exposed to the business and corporate world to equip them for their industrial development.
i. To apply knowledge obtained in the school in the various organizations that we find
ourselves.
iv. To help introduce students to organization cultures, norms, values and practices.
6
1.2 BACKGROUND OF THE ORGANIZATION
Resource Access Limited is a road construction company established in Ghana in the year 2006.
To date the company has undertaken the construction and rehabilitation of roads throughout the
country, notably, in the Eastern, Brong Ahafo, Greater Accra, Western and Volta regions.
The company has risen from ministry of Roads and Highways Financial Class A3B3 in 2006 to
A1B1 in 2013 which is a testament to the company’s growth and its ability to handle large and
complex projects.
The vision of Resource Access Limited ̶ RAL is to become the topmost leading provider of
This department comprises of two main organizational structures, that is the hierarchical
organization structure (which includes the CEO and various management departments underneath)
7
and the flat organization structure (which includes the human resource team with few people in
This is where the Human Resource Manager received my letter and processed it, upon which I
Safety Department
The safety department are responsible for the wellbeing of every personnel in the organization in
terms of the dos and don’ts in the construction field in in order to prevent hazards on and outside
of sites. The safety department also takes charge of the safety meeting every morning before work
starts on the various sites. The meeting, commonly known as toolbox meeting, is held on the
various sites with representative personnel from the department where safety and health talk is
given to the workers, then after which challenges and questions are addressed, then attendance is
taken by passing sheets round for all those present to sign by their names before we disperse to
It is under this department that I had my induction, where Mrs. Lordina Arthur, the head of the
safety management gave a presentation on the safety practices, the Do’s and Don’ts on the site and
taught us their slogan,″ SAFETY FIRST‼ ARRIVE SAFE, WORK SAFE, GO HOME SAFE
8
Survey Unit
This comprises of six members (all males), two main surveyors, two assistants one for each of the
main and likewise for the two interns. This section plays a very critical role on the site in general.
i. Set out the centre line, road median, road edge, walkway, culverts to be constructed
and so on.
ii. Check the levels for cut or fill during the laying of the road layers.
iii. Staking out design parameters for pit and other designs implementation including waste
iv. Calculate quantities in volume of materials needed on site either for layers or volume
Traffic unit
This department deals in the controlling of traffic on the road on site with the help of the flagmen
and flag lady. They are also responsible for the road furniture such as the jersey barrels, road traffic
signs, sign posts, reflectors and so on, to provide information and safety to the road users and help
in diverting traffic where necessary. They are also in charge of escorting the heavy duty vehicles
such as the excavator, the roller compactor etc. from one site to another.
9
Earthworks unit
Earthworks are engineering works carried out in and with granular soils, that is the movement of
This unit includes site engineers responsible to supervise the construction works on site, where
they determine whether a section needs to be stabilized, excavated and where land grading is to be
This section is made up of quantity surveyors, who are responsible on helping to estimate and
control costs for the project, material quantities and project timelines. They liaise with a range of
Mechanical department.
They include skilled persons in mechanical engineering works, where they deal in servicing and
maintenance of the vehicles and heavy-duty machines on the project such as the trucks, the
10
1.2.4. Major Concerns
Safety is a priority for Resource Access Limited (RAL). In order to prevent an incident from
occurring, a functional safety culture must be in place. This culture is established through ongoing
education, hazard assessment and reiteration of company ̓s safety policies which is done in RAL.
Resource Access Limited operates with very strict principles and values that lie in the heart of the
people in our company. At least six basic values are held in common by all, thus:
1. Entrepreneurship
2. Responsibility
3. Trust
4. Respect
5. Setting of an Example
6. Humility
• #Zero Harm.
11
CHAPTER TWO
The term ́ Earthworks ̀ refers to the removal or placement of soils and other excavated materials
during construction. This is commonly part of civil engineering works required in the construction
of roads, railways, land stabilization, and land grading to change the topography of a site.
Earthworks involve the removal of topsoil, along with any vegetation, before scraping and grading
the area to the finished ́ formation level ̀. This is usually done using a grader, bulldozer or a tractor
shovel, but the grader and the bulldozer were used on our site. Below the formation level, is the
subgrade, which is the soil beneath. The strength of the subgrade is first tested prior to the
earthworks beginning.
The earthworks are formed by cut-and-fill, so the ́ fill ̀ material is considered not only in terms of
physical properties, but the conditions in which it is to be used, and the method of compaction.
Subgrade strength
The required thickness of the various layers to laid until the final level of the road, that is the
wearing course is determined by the subgrade strength, so it makes it very necessary to make the
i. Removal of poor material in cutting and replacing with the selected fill.
12
ii. Compacting subgrade to a high dry density.
iv. Soil stabilization methods such as the use of bituminous materials, chemicals or
cement.
Formation level
The formation level is the level at which excavation ceases and construction commences. It is
the lowest point of the path structure. This level is the prepared ground on which the sub base
layer is laid.
Sub-base
The sub-base is the layer of aggregate material laid on the finished formation level, on which
the base course layer is laid. It is used to improve the constructability of the pavement layers
above the sub-base. This layer consists of mixture of course and fine crushed rocks and crushed
sand or laterite to achieve the desired bearing capacity and absorb traffic loads so that the
Base
A road base layer forms the foundation for the road surface. It is used as the foundation for
roads and driveways in situations where using asphalt would be cost-prohibitive. It is usually
13
Wearing course
This is upper layer or the surface layer of a pavement that takes the wear of traffic. It protects
optimally against weather influences and heavy or freight traffic that normally causes holes
and cracks on asphalt. To prevent rapid abrasion, the aggregate used must have a minimum
Binder course
This is the lower part of surfacing, it is a coarse aggregate bound with bitumen between the
foundation and the wearing course of an asphalt pavement. It is typically made of a type of
asphalt concrete with different grading of aggregates and types and quantities of binder
After every layer before the wearing and binder course is laid, it is compacted and a proof
rolling test is done before any layer is laid to ensure an excellent work done and to prevent
There was several equipment at the site to make work easy and faster. The equipment and their
14
2.2.1. Grader
The purpose of a grader was used to perform fine grading in civil engineering projects such as road
construction. The grader is used for precision scrapping and levelling which helps in creating
The compactor/roller was used to compact or compress materials such as sand, gravels and stones
in the soil to increase its density and fill in voids. Compacting is done in layers to obtain quality
work.
15
Figure 2 A Picture of Compactor Roller on site.
2.2.3. Excavator
I. Dredging.
II. Demolishing.
16
Figure 3 A Picture of an Excavator on site.
The dump truck was used for carrying and transporting materials to and from the site.
17
2.2.5. Pay Loader
The pay loader was used for moving soil or rocks in large volumes, as well as loading and
managing waste.
I. Excavation.
IV. Demolishing.
V. Landscaping.
VII. Desilting.
18
2.2.7. Bulldozer
In construction sites, bulldozers are used to clear shrubbery, obstacles and remains of buildings
and structures. The bulldozer is mainly used for pushing, digging, excavating and levelling
The water bowser is used for dust suppression and also used as a fire extinguisher during fire
hazard on site.
Surveying as a profession is very large and divers, in the actual construction field a professional
Surveyor has a huge role to play. Surveying applications and techniques are highly important in
The present document will be focused on the role and participation a Surveyor in a Road
construction project: From the Reconnaissance survey step where the Surveyor collect the
necessary information and description of the site to be survey. Followed by the Preliminary Survey
which is the detail studies of the road to be surveyed, mostly topographic studies. Then, the Final
location which is a series of studies based on the preparation of the Map using data collected during
the Preliminary Survey. And finally, the Construction Layout where the Surveyor provides the
neat alignments, grades which guide the Construction operations. Some of the most used
19
2.3.1 Reconnaissance Survey and Preparation
The reconnaissance survey is an extensive study of an entire area that might be used for a road or
airfield. Its purpose is to eliminate those sites which are impractical and to identify the more
promising for a successful survey. Existing maps and aerial photographs may be of great help.
Contour maps show the terrain features and the relief of an area. The reconnaissance survey report
should summarize all the collected information of the sites, including a description of the sites to
be surveyed, a conclusion on the economy of its use, the position of the sites, appropriate maps
Design
Design characteristics should be considered during the reconnaissance survey. The site surveyor
must keep in mind that future operations may require an expanded road net, so a good study of the
route plans and specifications is necessary. In the design study, the Surveyor will have to pay
i. Locate portions of the new road along or over existing roads, railroads, or trails, whenever
possible.
ii. Locate the road on a soil that is stable and easily drained, avoiding swamps, marshes, and
organic soil.
iii. Locate the road along ridges and streamlines, keeping drainage structures to a minimum. Keep
the grade well above the high waterline when following a stream.
iv. Select a route as near to sources of material as practical, and locate the road along contour lines
20
v. Locate the road on the sunny side of hills and canyons.
vi. Select locations which conserve engineer assets, avoiding rockwork and excessive clearing.
Here the surveyor uses the collected data to provide a basis of study showing the advantages of
the selected area of the site, including disadvantages if there are any, the effects of landslides, Soil
reference points, control points, structure sites, terrain obstacles, and any unusual conditions.
Use Of Maps
One of the main importance of the Reconnaissance is the elaboration of the Map Planimetric or
Topographic of the Area to be surveyed. The surveyor should locate and use all existing maps,
including up-to-date aerial photographs of the area. Large scale topographic maps are desirable
because they show the terrain in the greatest detail. The maps, with overlays, serve as worksheets
The surveyor begins a map study by marking the limiting boundaries and specified terminals
directly on the map. Between boundaries and specified terminals, the surveyor observes the
existing routes, ridge lines, water courses, mountain gaps, and similar control features. The
surveyor must also look for terrain which will allow moderate grades, simplicity of alignment, and
a balance between cut and fill. After closer inspection, the routes that appear to fit the situation are
21
classified. Typical data collected in a reconnaissance survey are Sketches of all the features
Preparation
The preliminary survey is a detail study of a road selected on the basis of reconnaissance survey
information and recommendations. It runs a Traverse along a proposed Road, establishes levels,
records topography, and plots results. It also determines the final location from this plot or
preliminary map. The size and scope of the project will determine the nature and depth of the
Survey
The surveyor establishes a traverse with control and reference points, sometimes it expands to
include levelling and topographic detail. Normally, obtaining the traverse, levelling, and
topographic data are separate survey, which the Surveyor proceed as follow:
Traverse
The Surveyor establishes the traverse line along the proposed Road by setting and referencing
control points, measuring distances, numbering stations, and establishing points of intersection.
He (She) also makes the necessary ties to an existing control, if available or required. When no
control is available, the Surveyor may assign a starting value for control purposes which can later
22
Levelling
In the levelling process, the Surveyor establishes benchmarks and determines the elevation of
selected points along the road to provide control for future surveys, such as the preparation of a
topographic map or profile and cross-section levelling. The Surveyor takes rod readings and
records elevations to the nearest 0.001 meter. It sets the benchmarks in a place well out of the
area of construction and marks them in such a way that they will remain in place throughout the
whole project. If there is no established vertical control point available, establish an arbitrary
The Surveyor secures enough relief and planimetric detail within the prescribed area to locate
any obstacles and allow preparation of rough profiles and cross sections.
Preparation
The final location survey is series of studies consisting of the preparation of a map from
preliminary survey data, projection of alignment and profile, and preliminary estimates of
quantities and costs are made and used as guidance for the final location phase. The surveyor
should not make any changes without consulting the Engineers and designer in charge of the
project.
23
Running the Centre line
The surveyor numbers the stations consecutively and sets them at usually 20-meter stations. The
surveyor also sets stakes at important points along the centre line, which will be useful later on
the project if there are any road intersections, beginnings and ends of curves, stops peed.
The control points established by the location survey determines the construction layout, so these
points must be carefully referenced. The surveyor should set the control point references far
After the centre line of the road, including the horizontal curves, has been staked, the next step in
the road layout is the determination of elevations along the centre line and across the road. The
LEVELLING, as separate operations but at the same time as the elevation of points along a centre
line or other fixed lines. The interval usually coincides with the station interval, but shorter
intervals may be necessary due to changes in terrain. The plotting of centre line elevations is known
as a PROFILE. From this profile, the DESIGN ENGINEER determines the grade of the road. The
cross-section elevations make it possible to plot views of the road across the road at right angles.
These plotted cross sections determine the volume of earthwork to be moved. The surveyor
establishes the cross-section lines at regular stations. All elevations are measured with a rod and
level, and distances from the Centre line are measured with a tape.
24
2.3.6. Construction Layout
Preparation
The construction layout is an instrument survey. It provides the alignment, grades, and locations
which guide the construction operations. The construction operations include clearing, grubbing,
stripping, drainage, rough grading, finish grading, and surfacing. The command must keep the
surveyors sufficiently ahead of the construction activity in both time and distance to guarantee
Alignment
The surveyor must place the alignment markers ahead of the crews engaged in the various phases
of construction. The surveyor may do a hasty alignment, marked by flags and rods, suitable for
guiding the clearing and grubbing operations. However, a deliberate location of the Centre line is
necessary for the final grading and surfacing operations. The surveyor marks the curves and
minor structures concurrently with the layout of the Centre line. Major structures such as tunnels
and bridges involve a site survey. The general demarcation of the site boundaries is carried on
with the establishment of the route alignment. The layout of the site proper is a separate survey.
Grade stakes indicate the exact grade elevation to the construction force. The surveyor consults
the construction plans to determine the exact elevation of the subgrade and the distance from the
25
Preliminary Subgrade Stakes
The surveyor sets preliminary subgrade stakes on the centre line and other grade lines, as
required. First, the surveyor determines the amount of CUT or FILL required at the centre line
station. The amount of CUT or FILL is equal to the grade rod minus the ground rod. The
surveyor sets the stakes by measuring the appropriate distance off the centre line and determines
the amount of cut or fill as outlined. The surveyor offsets the stakes along the travelled way,
roadbed, and ditches to prevent them from being destroyed during grading operations. The
construction foreman will specify to the surveyor, makes the decision as to how many and where
Once the rough grading is completed, the surveyor sets the final grade stakes. The elevation of
the final grade is determined and the value of the grade rod reading is computed. The surveyor
uses a rod target to set the grade rod reading on the rod. The rod is held on the top of the stake.
The surveyor marks the top of the stake to distinguish it from other stakes.
Sub Grade
It is the upper layer of the natural soil which may be undisturbed local material. Or may be soil
excavated elsewhere and placed as fill. In either case, it is compacted during construction to give
added strength. The subgrade receives the traffic load from the pavement, it should be strong
enough to take the load and doesn't fail the importance of sub grade lies in the fact that if it fails,
the performance of the whole road will be affected. A sub grade must be able to resist the effects
26
of both traffic and weather. Sub grade soil is not a uniform or homogeneous material, It
Sub-Base Course
Sub Base is a layer of granular material provided above Sub-Grade. It consists of natural gravel,
sandy gravel or a combination of the gravel, sand and clay. Sometimes Sub-Base is provided
Base Course
Base Course is the major structure component of a road (The main Load spreading a layer of the
pavement, Base course is the layer immediately under the pavement surface, it is subject to severe
loading consist of crushed stone or gravel, sands and sand clays stabilized with cement, lime or
bituminous.
Surface Course
The top layers of pavement which is in direct contact with the wheel of the vehicle. Usually
Bituminous Pavement:
27
2.3.8. Road Drainage
At the drainage stage, the Surveyor performs some series of levelling and horizontal distance
measurement (Traverse):
Levelling Task
Here the Surveyor determines the exact level in which the pipes, Manhole and all the required
The Surveyor performs a traverse to determine the correct horizontal distance in which the
drainage materials would be placed. The standard conditions or specifications must be respected
throughout his/her calculations. Here is a clear statement of the Standard condition for the
Manholes, taken from DESIGN MANUAL: GUIDELINES AND POLICY FOR THE DESIGN
that: Manholes should be placed at every change in horizontal and/or vertical direction or At a
maximum spacing of:100 m for pipes up to and including 900 mm diameter;150 m for pipes over
900 mm up to and including 1 200 mm diameter;200 m for pipes over 1 200 mm in diameter.
Standard Conditions At manholes with no drop inlets or no substantial side inflows or where the
change in horizontal direction is less than 4̊ the difference in invert levels is determined by the
difference in pipe diameters only provided pipes are laid "crown to crown".
28
2.3.9 Important Accessories/equipment Used by Surveyor in The Road Design
Instruments
1. Total Station
a. With a Total Station the Surveyor may determine angles and distances from the instrument to
points to be surveyed, applying Trigonometry and Triangulation, the angles and distances may
be used to calculate the coordinates of actual positions (Y, X, Z of surveyed points, or the
b. The data recorded by the Total Station can be downloaded to an external computer so that the
surveyor may use the data to generate a Map with the aid of appropriate software applications
2. Theodolite
v. Ranging
vi. Levelling
29
3. Global Positioning System (GPS)
GPS can be used for many tasks in construction surveying such as measuring the grading,
4. Automatic level
Used to determine the difference in height and establish the elevation between points.
30
Survey Instrument Accessories
1. Tripods
Tripods support and provide a fixed base for all types of surveying instruments
Figure 8 A Tripod.
31
3. Survey pegs
Are used to mark out residential boundaries and indicate points and positions on the site.
Figure 10 Pegs.
4. Tapes
The success of a Road construction project depends on many factors, one of the most important
is the reduced results of the entire Road Survey. Therefore, the Surveyor has to ensure that each
task is complete carefully to avoid gross errors or Blunders. Here below are some reformulations
The Surveyor follows the progress of the project from day one to the last day: Starting with the
Reconnaissance survey process during which the Surveyor take a general look of the site to be
surveyed. Followed by the Preliminary survey, process in which the Surveyor collect more
32
precise information required for the choice of best location for the project and to estimate the
The Final Location survey comes next; here the Surveyor allocates the exact position of the
Road by placing the CENTRE LINE, THE REFERENCE STAKES and performs a PROFILE
LEVELLING and CROSS SECTION LEVELLING as well. Then the Surveyor proceed to the
Construction Layout where he provides the necessary ALIGNMENT, GRADES and the
LOCATION guiding the project to the PAVEMENT CONSTRUCTION where different layers
of the Road are placed and settled. Finally, the Road Drainage, here the Surveyor performs some
33
CHAPTER THREE
During the semester out period, we were exposed to how earthworks is done on the site and the
reason for the earthworks. The initial nature of the soil before construction was clay. Due to the
expansion of the road, there had to be clearing of the side of the existing road to which the
extensions would be constructed. Due to the expansive nature of the clay soil and the high ground
water table level, it was necessary to replace it with a soil which is not expansive, has god
engineering properties and also a soil that can control the water table without any significant
decrease in bearing capacity. The cost of the soil materials to be used to replace the clay soil is
Considering the engineering properties of the soil materials, availability and their cost, three
different soil materials were used to solve the problem. One to replace the expansive soil, clay and
the other two to control ground water levels and ground water movement. Laterite, crushed rocks
Laterite was used to replace the expansive soil mainly because it is not expansive. Laterite also
has a very high bearing capacity when dry and compacted hence making it able to support high
amount of load exerted on it. The major weakness of laterite is that it has a very low bearing
capacity when wet. Since the Adiembra and Officers ̓ mess sites have high and very high ground
water tables in certain sections, it is likely to interfere with the bearing capacity of the laterite when
used. In order to solve the ground water problem, geotextiles and crushed rocks were used.
34
Geotextiles such as‶ Tencate Bidem″ and‶ Tencate Rock pet ″ were laid across the excavated and
cleared sections of the expansive soils to prevent the ground water from penetrating into the
laterite, then the crushed rocks(0/40mm) is spread on the geotextile and compacted before
In terms of cost and availability, laterite is one of the abundant soil materials in the tropical region.
The tropical climate greatly influences the formation of laterite through the weathering of different
rocks due to its high temperature and rainfall. Since Sekondi Takoradi in Ghana has a tropical
climate, the formation of laterite is very high hence making laterite a readily available material at
a lower cost. The crushed rocks(0/40mm) is also readily available from our co-company for this
In order to effectively use both the crushed rocks or chippings and the laterite for better
performance, certain steps and measures were put in place. First of all, the whole site was
excavated to an approximate depth range between 1.0m to 3.0m depending on the existing
topography of the land. The excavation is done in batches (area by area) due to the unstable weather
condition at that time. Areas of the site at high elevation were excavated to a deeper depth than
areas of the site at a lower elevation. This was done to get an even base level. After excavating to
the desired level, a geotextile membrane is placed on top of the base. The purpose of the geotextile
membrane is to separate the excavated ground level from the next layer of soil material. Then the
chippings is filled to obtain a layer thickness of about 0.3m and then compacted.
35
Figure 11 Shows the laying of the geotextile and spreading of the chippings on site.
Next after the laying of the geotextile, the crushed rocks(0/40mm) is placed on top of the geotextile
in layers of 0.15m to 0.30m and then compacted. After which another geotextile (Tencate Miragrid
) is laid on top of the compacted chippings, for subgrade stabilization and for soil reinforcement.
Then the laterite is spread on it in layers and compacted to the desired formation level. After each
layer of the laterite is compacted, a density test is done with the help of sand replacement test or
nuclear densometer to check the degree of compaction done. This process is repeated until the
When the laterite layers reach the finish-to-formation level and also the degree of compaction until
that level meets the projects specification, a proof rolling test is done for final confirmation that
36
Figure 12 Spreading of 0/40mm aggregate. Figure 13 Miragrid being laid.
The next layer after the formation level is the sub-base layer which is a mixture of laterite and the
37
The main purpose of the earthwork layers is to stabilize the soil (Soil stabilization). Soil
38
CHAPTER FOUR
4.1. Contributions Made to The Earthworks, Survey and Safety and Traffic
Department During The Semester Out Period
As students working to gain industrial experience, the management of RAL made sure to involve
us in many of their office and field works. Some of the contributions made to the Earthworks,
d. Assisting in picking of levels, setting out the right of way for the clearing and excavation.
The management of the Earthworks, Survey, and Safety and Traffic department gave us the
opportunity to acquire some skills related to construction. Some of these skills include,
39
b. How to use the GPS in taking levels.
High cost of living at the place of residence during the semester out.
40
CHALLENGES ENCOUNTERED AT THE SITE
4.4. Conclusion
In general, RAL is an institution where civil engineering students can gain adequate industrial
experience and other working skills in the construction and engineering sector.
Management and staff were willing to teach us what they know about the works done at the project
Most of the things learnt during the attachment period are related to my program of study (Civil
Engineering).
The semester out program has helped me experience that which goes on at the field of work.
4.5. Recommendation
The industrial attachment really helps the students to get more work experience in the industry
hence it should be done very often, at least two times in an academic year.
41
INDUSTRIAL ATTACHMENT REPORT ASSESSMENT FORM (3 Marks)
TAKORADI TECHNICAL UNIVERSITY
INDUSTRIAL ATTACHMENT REPORT ASSESSMENT FORM
FACULTY: ………………………… DEPARTMENT: …………………………………………
NAME OF STUDENT: ……………………………………..........………. REG. NO: ……………………….
STUDENT PHONE NUMBER: …………………………………
DISTRIBUTION OF MARKS
S/N Description of Key Headings Maximum Marks
marks Obtained
1 Cover Page 5
2 Table of Content 5
3 Objective of the industrial attachment 5
4 Background of the establishment/organization (Brief
history, vision/mission statement,
sections/units/department, major activities/concerns, 15
organizational structure of the
establishment/organization
5 Description of the nature of work done at the
section/unit/department where student was attached 10
6 Detailed description of the training or work performed 20
7 Contribution of student to the
establishment/organization (thus: value added by the 10
student to the establishment/organization)
8 Challenges, new practical skills or experiences acquired
and how they would help student’s understanding or 12
appreciation of theory taught
9 General comments by the student concerning the
exercise, observations or impressions and conclusion 10
10 Recommendations 5
11 Industrial Attachment Report Assessment Form 3
SUB TOTAL 100%
PENALTY
1 Pagination ½ per occasion
2 Inappropriate cover display ½ per occasion
3 Poor binding of report ½ per occasion
4 Failure to adopt correct format for reporting ½ per occasion
42
5 Failure to arrange chapter, main headings, sub headings,
etc in order ½ per occasion
6 Typographical error ½ per occasion
7 Inconsistent line spacing ½ per occasion
GRAND TOTAL after penalty
Total Marks after 40% conversion
43