Report
Report
Report
Branch – EE
P age |2
Index
Declaration
Acknowledgement
1. About CG
2. Introduction
3. Principle of Working
4. Different Parts and Components of Transformer
5. Process Flow chart Loco Transformer Manufacturing
6. Quality Check
7. Core Building
8. Winding
9. Core coil assembly
10. Autoclave
11. Insulation
12. Cooling Arrangement
13. Transformer Tank
14. Some Important Components
15. Test
16. Factor affecting life of Transformer
17. Name plate of Loco Transformer
18. Conclusion
P age |3
Acknowledgement
Abhishek Tiwari
P age |4
DECLARATION
Roll-No.-2102028
Certified that the above statement made by the student is correct to the
best of my knowledge and belief.
1. About CG
1.1 History
1.2 CG Offering
Power System includes the business area related to transformers, Switch Gears,
Circuit Breakers, Vacuum interrupters, network protection and gear control, as
well as design, execution and servicing of turnkey T&D as well as substation
projects. This is the largest business which is now well entrenched throughout the
world.
CG is among the top 10 transformer manufacturers in the world., and one of the
very few companies worldwide that designs and manufactures a wide range of
power and distribution transformers and reactors.
The range of power Transformers offered is from 25 KVA to 600 MVA and 11KV to
765 KV class, and reactors from 10 MVAr to 125 MVAr, and 33 KV to 765 KV class.
These products are conforming to IEC, ANSI, IS, BS and other international
standards.
P age |7
2. INTRODUCTION
The transformer is a static device, which transform power from one AC
circuit to another AC circuit at same frequency but having different
characteristics. These circuits are conductively disjointed but magnetically
coupled by a common time varying magnetic field. It can raise or lower the
voltage with a corresponding decrease or increase in current.
In all the electric locomotives, limiting the value of current during starting,
speed control is achieved by supply of variable voltage to the traction
motors. This variation of applied voltage can be carried out easily by the
use of transformer along with tap changer provided in the locomotive.
The windings which form the electrical circuit must fulfill certain basic
requirements, particularly the di-electric, thermal and mechanical stresses
imposed on it during testing as well as in service and cater for over loads
under adverse conditions.
P age |8
3. PRINCIPLE OF WORKING
a. When a conductor cuts the magnetic flux or magnetic flux cut the
conductor, an emf is induced in the conductor.
E = -dφ/dt
Where, E = emf
φ = flux
Kinds of emfs
An emf induced in a coil due to variation of flux in another coil placed near
to first is called mutually induced emf. The emf induced in a coil due to
change of its own flux linked with it is called self-induced emf. (In case of
autotransformer) In its simplest form, a transformer consists of two
conducting coils. The primary is the winding which receives electric power,
and the secondary is one which delivers the electric power. These coils are
wound on a laminated core of magnetic material.
i.e. E = M di/dt
2. Transformer tank
4. LV bushings
5. HV bushings
6. Main bushing
7. Conservator
8. Breather
9. Radiator
Start Finish
Pressure
Test
Autoclave
Process
of Main
Winding Expansion
Core Coil Tank Filling
Connections and Oil Top Up
Assembly
6. Quality check
There are Two ways of Quality Check :-
1. Physically- In this way the components are checked physically i.e. there
should be no cracks, no impression or no damage to the components.
7. Core Building
The constructional features of a traction transformer are more or less same
as other power transformers. The locomotive transformer core is made
from cold rolled grain oriented steel of best grade and provides magnetic
circuit.
The core is clamped using structural steel clamps which provide high
strength under both static and dynamic mechanical loads. The clamps are
very lightweight for their strength and provide a smooth surface facing the
winding ends, eliminating regions of high local electrical stress.
P a g e | 12
8. Winding
In loco transformer the radial type of windings are done. This arrangement
provides the highest short circuit strength while providing good cooling of
conductor surfaces. The two limbs are provided with HV, LV, filter and
auxiliary windings. There are four traction windings on the LV side which
give power to the induction motor.
There is one filter winding which is responsible for reducing harmonics and
Bur winding which gives supply to the auxiliaries like fan, tube light and
charging ports.
Since the windings are of radial type between every disc there is a block
which avoids the direct contact of the two discs. Because direct contact of
two discs can burn the insulation and short circuit can take place. Between
the windings and the core spacers are placed. Some gap is left between
the two turns of the same disc so that the oil reaches between the coils.
SOD and GOD windings are also used.
Oil flow through the windings is directed in zigzag pattern to ensure cooling
of all conductor surfaces and to limit the hot spot temperature. Careful
attention is paid to ensure an even distribution of oil to all windings.
P a g e | 13
Now necessary connections are made as per the tapings. After this the
upper yolk is setup and coil compartment is clamped around the windings.
After the connections are made the insulation paper is wrapped on the
conductor.
Sufficient ducts are provided between the coils to ensure heat dissipation
through circulation of oil. Best quality insulation is provided at all joints and
gaps. The optimum design of Core-Coil Assembly is achieved by
considering the required technical particulars including cooling, size
compactness and tapping arrangement. All leads and conductors are rigidly
supported by special clamping arrangement.
10. Autoclave
Industrial autoclaves are pressure vessels used to process parts and
materials which require exposure to elevated pressure and temperature.
The manufacture of high-performance components from
advanced composites often requires autoclave processing
An autoclave applies both heat and pressure to the workload placed inside
of it. Typically, there are two classes of autoclave. Those pressurized
with steam process workloads which can withstand exposure to water,
while circulating heated gas provides greater flexibility and control of the
heating atmosphere.
1. First time the only the winding goes in the autoclave for about 36
hours. It is done to remove moisture from the winding assembly.
2. Second time the core coil assembly goes in the autoclave after the
brazing and connections are done for about 27 – 28 hours. It is again
done to remove the moisture. Because the till the time brazing and
connection are done the core coil assembly again gain moisture.
3. Third time the core coil assembly with the tank goes into the
autoclave for oil filling. It takes about 12 hours.
11. Insulation
Since insulation is the most important factor for the traction transformer
winding, this requires much attention for the same. The insulation is pre-
compressed pressboard, which does not chip or get crushed under shock
loads. The entire coil assembly is carefully shrunk pre-determined clamping
pressure and controlled heat. A further safe guard against any minor
shrinkage in service, spring-loaded pressure pads are employed which
exerts a steady pressure on all the windings through sturdy steel plate.
the oil cooler. The conservator is fitted to the top of the transformer through
a pipe. At the top of conservator a spring loaded safety valve is fitted.
Above this safety valve, there is an oil overflow chamber with a discharge
pipe which discharges the oil down underneath the locomotive body. The
oil pump and the cooler are both connected to the conservator by a venting
pipe. The air does not come into contact with oil in the conservator directly,
and is dried before by means of a silica gel air dryer.
The mild steel tank, oil conservator and cooling pipe work are fabricated to
close tolerances to facilitate their mounting in limited space in the
locomotive. In their design, care is exercise to keep their weight down to
bare minimum but at the same time ensuring sufficient strength. The tank
ring and cover are carefully matched to ensure oil tightness under the worst
operating condition encountered during acceleration or retardation of the
locomotive, which brings in additional oil pressure at the joints. The cover
suspended transformer is provided with special screws to adjust the height
of the assembly, so that in fully tighten position it sits evenly on the base
pads.
P a g e | 17
14.1. Conservator
14.2. Breather
15. TESTS
Following common tests to be carried out in the transformer –
normal head of oil for a period of 24 hours. There shall be no oil leakage
from the tank.
15.2.1 No load test – In this test core losses are measured. It measures
eddy current losses and hysteresis losses and Stray losses. No load
primary current and losses shall be measured with 50 Hz sinusoidal voltage
applied to high voltage winding. However, this measurement can also be
carried out by energizing Auxiliary/hotel load winding. No load current and
losses for the primary winding shall be measured at 17.5 KV – 27.5 KV in
steps of 2.5 KV.
15.2.2 Short circuit test – In this test copper losses of the transformer is
measured. The losses due to heating of winidng because of high current.
1. Moisture
2. Oxygen
3. Solid Impurities
4. Varnishes
5. Slackness of winding
P a g e | 20
S. No.-CGPISL-7.775-06-18-BHI0964/05
Frequency -
Phase 1 Year - 2018
50 Hz
Power - 7775 KVA Type Lot - 7775
1U V 25000 V
I 311 A
4x1269/1154(1000)(2x960
2U V
)V
4x1142/347(334)(2x648)
I
A
Oil IEC60296
core and coil 5950 Kg
Quantity of Oil 1600 Kg
Complete Transformer 9950 Kg
Reactor
No.
Phases 1 Type 2 SOD 240
CGTN205391
Power - 2x236.9 KVAr at 50 Hz Frequency - 100 Hz
1 Nom -
L - 2x0.551 mH
2x984 A
2.8 mΩ/75°C
Weight - 585 Kg Loc. Type - WAP 5
Reactor
No.
Phase 1 Type 6 GOD 120
CGTN205392
Frequency - 100 Hz Rip
Power - 3x2x117 KVAr 50 Hz
38.6%
1 Nom -
L - 3X2X13 mH
3x2x155 A
54 mΩ/75° C
Weight - 570 Kg
P a g e | 21
18. Conclusion
From this visit, we got the information and practical knowledge about loco
Transformer manufacturing . We got the knowledge about different outer
and inner part of transformer like core, winding and different type of
transformer testing. We came across manufacturing processes. At last
I would like to say that this training was a success for me, as I learned a lot
about the manufacturing ,design and other aspects of transformer which
could not have been learned otherwise.