S.

No WBS Task Name Duration


11 Oracle ERP Implementation Project 133 days
2 1.1 Project Readiness 5 days
3 1.2 Advisory Phase 15 days
4 1.2.1 High Level Analysis 10 days
5 1.2.1.1 Oracle ERP High Level Analysis 10 days
6 1.2.2 Requirement Document Creation 5 days
7 1.2.2.1 Oracle ERP - Requirments Documents Creation 2 days
8 1.2.2.2 Requirment Document Submission 1 day
9 1.2.2.3 Requirement Document review & sign-off 2 days
10 1.3 Design Phase 60 days
11 1.3.1 System Development 20 days
12 1.3.1.1 Development 20 days
1.3.1.1.1 Metadta, Forms, Rules, Tasklist and other system
20 days
13 development acitvities
14 1.3.1.1.2 Integrations 20 days
15 1.3.1.1.3 Reports and Summaries 20 days
16 1.3.2 Conference Room Pilot1 (CRP1) 14 days
17 1.3.3 Client Data Preparation - CRP2 - (Sample Data) 10 days
18 1.3.4 Conference Room Pilot (CRP2) 29 days
19 1.3.4.1 Conference Room Pilot (CRP2) Configuration 15 days
20 1.3.4.1.1 CRP1 Fit-gap fixes 15 days
21 1.3.4.2 Load & Validate Sample Data 3 days
22 1.3.4.2.1 Oracle ERP - CRP2 Data Load 2 3 days
23 1.3.4.3 Conference Room Pilot (CRP2) Workshops 11 days
24 1.3.4.3.1 Oracle ERP CRP2 Demo 3 days
25 1.3.4.3.2 CRP2 Gap Fit Analysis& Fixes 7 days
26 1.3.4.3.3 Conference Room Pilot 2 (CRP2) Sign Off 1 day
27 1.3.5 Sit - System Integration Test 3 days
28 1.4 Orchestrate & Prepare Phase 20 days
1.4.1
Key User Training (KUT) & User Acceptance Testing (UAT) 20 days
29
30 1.4.1.1 Preparation 5 days
31 1.4.1.1.1 Oracle ERP - User manual preparation 3 days
32 1.4.1.1.2 Oracle ERP - Testing scripts preparation 2 days
33 1.4.1.2 KUT & UAT - Workshops 10 days
34 1.4.1.2.1 Oracle ERP - User manual Pre. 10 days
35 1.4.1.3 KUT - UAT Fixes 3 days
36 1.4.1.3.1 UAT bug fixes 3 days
37 1.4.1.4 KUT - UAT Sign off (M4) 2 days
38 1.5 Transition Phase 13 days
39 1.5.1 Production Setup & Go Live 13 days
40 1.5.1.1 Production Configuration 3 days
41 1.5.1.1.1 Oracle ERP - Config. Acitivites 3 days
42 1.5.1.2 Application Migration 7 days
43 1.5.1.2.1 Metadata migration 1 day
44 1.5.1.2.2 Migration of Application artifacts 2 days
45 1.5.1.2.3 Migration of Integrations 2 days
46 1.5.1.2.4 Sanity Check 2 days
47 1.5.1.3 Conduct Final Validation Review with Key Users 2 days
48 1.5.1.4 Schedule All Integrations 1 day
49 1.6 Declare Go - Live 1 day
50 1.6.1 Approval for Go Live 1 day
51 1.6.2 Go Live Sign-off (M6) 0 days
52 1.7 Post go-live support Phase 22 days
53 1.7.1 Post Go-Live Support - Onsite 22 days
54 1.7.2 Post Go-Live support Sign-off (M7) 0 days
Start Finish Resource Names % Complete
Mon 22-04-24 Wed 30-10-24
Mon 22-04-24 Sun 28-04-24
Mon 29-04-24 Sun 19-05-24
Mon 29-04-24 Sun 12-05-24 0%
Mon 29-04-24 Sun 12-05-24
Mon 13-05-24 Sun 19-05-24
Mon 13-05-24 Tue 14-05-24
Wed 15-05-24 Wed 15-05-24
Thu 16-05-24 Sun 19-05-24
Mon 20-05-24 Thu 15-08-24
Mon 20-05-24 Thu 20-06-24
Mon 20-05-24 Thu 20-06-24
Mon 20-05-24 Thu 20-06-24
Mon 20-05-24 Thu 20-06-24
Mon 20-05-24 Thu 20-06-24
Sun 23-06-24 Wed 10-07-24
Wed 03-07-24 Tue 16-07-24
Wed 03-07-24 Mon 12-08-24
Wed 03-07-24 Tue 23-07-24
Wed 03-07-24 Tue 23-07-24
Wed 24-07-24 Sun 28-07-24
Wed 24-07-24 Sun 28-07-24
Mon 29-07-24 Mon 12-08-24
Mon 29-07-24 Wed 31-07-24
Thu 01-08-24 Sun 11-08-24
Mon 12-08-24 Mon 12-08-24
Tue 13-08-24 Thu 15-08-24
Tue 13-08-24 Mon 09-09-24
Tue 13-08-24 Mon 09-09-24
Tue 13-08-24 Mon 19-08-24
Tue 13-08-24 Thu 15-08-24
Sun 18-08-24 Mon 19-08-24
Tue 20-08-24 Mon 02-09-24
Tue 20-08-24 Mon 02-09-24
Tue 03-09-24 Thu 05-09-24
Tue 03-09-24 Thu 05-09-24
Sun 08-09-24 Mon 09-09-24
Tue 10-09-24 Sun 29-09-24
Tue 10-09-24 Sun 29-09-24
Tue 10-09-24 Thu 12-09-24
Tue 10-09-24 Thu 12-09-24
Sun 15-09-24 Tue 24-09-24
Sun 15-09-24 Sun 15-09-24
Mon 16-09-24 Tue 17-09-24
Wed 18-09-24 Thu 19-09-24
Sun 22-09-24 Tue 24-09-24
Wed 25-09-24 Thu 26-09-24
Sun 29-09-24 Sun 29-09-24
Mon 30-09-24 Mon 30-09-24
Mon 30-09-24 Mon 30-09-24
Mon 30-09-24 Mon 30-09-24
Tue 01-10-24 Wed 30-10-24
Tue 01-10-24 Wed 30-10-24
Wed 30-10-24 Wed 30-10-24