Eot Sop
Eot Sop
Eot Sop
TIME
October,2022
Page 1of12
REVTSED SOP FOR PROCESSING OF EXTENSION OF TIME (EOT)
CASES IN NTDC CONTRACTS (2022)
1. PREFACE
1.1 NTDC is dealing with multiple conhacts. Claims of EOT from tlte contractors
/ consultants are quite common. The existing SoP does not address the issue
and also in conflict with different contract provisions. Resultanfly, the cases are
piled up for years making it stagnant to close the contracts/ projects.
1.2 Guidelines mentioned in this SoP shall be followed to deal with claims of the
contractors / consultants.
1.3 This SOP shall supersede the existing SoP issued vide Company Secretary
NTDC Notification No. C.S./NTDC/1279-83 dated 13-10-2010 approved by
Board of Directors of NTDCL in its 50ft meeting held on 30-09-2010 for
handling the cases for extension of time for contractors/ supplier.
t.4 Wherever any provision of this SOP shall be in conllict with provisions of any
applicable guidelines of Intemational Financial Institutions (IFIs), or any other
applicable Statute / Law or Rule, the provisions of such applicable guidelines,
laws or rules shall prevail.
1.5 This SOP shall become a part of the future Bidding Documents or its provisions
may be incorporated in the Bidding Documents.
t.6 The procedures in this SoP are categorized for different tlpes of Contracts i.e.,
Supply Contracts, Construction/EPC Contracts and Consultancy Services.
1..7 This SoP does not in any way impact the rights/obligations of the parties
defined in the contract agreements unless amended with mutua1 consent of the
parties. Accordingly, the contract provisions dealing with the claims
management will hold prevalence over this SoP in case of any contradictions.
Page 2 of 72
Notice shall be submitted within 28 days or any other time agreed between
the parties, of occurrence of each event.
2. The final request for Extension of Time (EOT) with detailed particulars will
be submitted by the Contractor within 42 days from the date of delayed
event attributable to the Purchaser as per Contract, afterwards, the case will
be considered as barred by time. Only those reasons of delay will be
considered for which timely Notice was served by the Contractor.
7. If the Purchaser does not conclude the case within 3 months from the date
of receipt of Claim from the Supplier or as otherwise agreed between the
parties, the claim of the Supplier shall be deemed as approved
Page 3 of 72
(i") Chief Engineer or Equal to 1/4 of scheduled delivery
equivalent period mentioned in the Contract
upto maximum of 45 days for each
Contract.
(") In case of EoT Managing Director EOT upto limits specfied above and
involves additional cost of up to 15% of
additional cost Contract Price.
Board of Directors In all other cases.
B) FORCONSTRUCION/EPCCONTRACTS
1. The Contractor shall give a Notice to the Engineer with a copy to the
Employer, describing the event or circumstance (specified in the contract as
Employer's risk or exceptional event or otherwise defined) giving rise to the
delay for which the Claim is made as soon as practicable, and no later than
28 days after the Contractor became aware, or should have become aware,
of the event or circurnstance.
2. If the Contractor fails to give a Notice of Clain within this period of 28 days,
the Contractor shall not be entitled to any EoT, and the Employer shall be
discharged from any liability in connection with the event or circumstance
giving rise to the Claim.
3. Within either: (i) 84 days after the Contractor became aware, or should have
become aware, of the event or circunutance giving rise to the Claim, or (ii)
such other period (if any) as may be proposed by the Contractor and agreed
by the Engineer the Contractor shall submit to the Engineer a fully detailed
Claim.
Page 4 of 12
4. If within this time limit the Contractor
fails to submit the detailed statement,
the Notice of Claim shall be deemed to have lapsed, it shall no longer be
considered as a valid Notice.
6. This final fully detailed Claim shall give the total amount extension of time
claimed.
9. The Engineer shall give the Notice of his/her determination within 90 days
or within such other time linit as may be proposed by the Engineer and
agreed by both Parties. \4rhi1e reaching at fair determinatioru the Engineer
may seek the comments of Design office, CFO, Supervision Consultant or
the Employer about the relevant events related to their offices.
10. The Engineer shall seek corrments from the relevant offices, if required,
within 7 days of receipt of Claim of the contractor. The concemed
formations will reply within 21 days of receipt of request from the Engineer.
The Engineer shall make its determination and seek consent of the
Employer if required within 21 days. Accordingly, approval of the
competent authority as mentioned in Table-2 below/ notification of
determination shall be made within 7 days with a copy to MD G\I[DC).
Page 5 of 12
11. Cases falling under comPetency of MD (NTDC) and BoD (NTDC) shall be
forwarded by the Engineer for approval of MD (NTDC) which shall be
referred to Scrutiny Committee within 7 days of its receiPt. The Committee
shall decide within 21 days and will be approved by MD (NTDC) within 07
days of the receipt of report by the Committee.
PaEe 6 of 72
be communicated to next higher authority with proper
justifications for reporting and control purposes'
15. The Engineer shall make his deternrination after due consultation with the
Employer and the Contractor and shall notify the Contractor of the
determination, with a copy to the Employer.
16. The Engineer will maintain a log/register for EoT determinations made
during currency of the Contract alongwith Proper reasons/iusffi91ti1n1
-substantiated
dully by documentary evidence' The detail of all EoT
submittals/ determinations and subsequent changes to the schedule shall be
made part of Project Completion report.
Extension of Time (EOT) under Civil Wor ty'ffC/oesig+ Supply and Installation
Contracts (Contract is Awarded by BOD)
Sr. Nature of Power Competent authority "Days per event/cause
No.
(i) Managing Directot Upto 365 days
Power to Grant Extension
l1 of Time and/ or for Director U 180 s
111
interim determination of General Mana U to 720
(i") Extension of Time in cases Chief Engineer/ Project Upto 60 days
of events Engineer
If extension of time does
not involve any
additional cost excePt
non recovery of
liquidated damages
Page 7 of 12
(v) In case of EoT involves Managing Director EOT upto 355 days and
additional cost excePt non additional cost of up to
recovery of liquidated 15% of Conhact Price.
damages and price Board of Diectors ln all other cases.
adjustment
Grant of Extension of Time (EOT) beyond sche duled completion of contracts (In
case of Contract is not awarded by BOD)
* powets specilied in above toble con be exercised Jor interim os well os finol determinqtion oI
The
extension of time cose, However, in cose some event hos continuing effect, competency will be
determined on oggregdte / occumulative bosis.
c) FORCONSULTANTS
(a) the Consultant shall inform the Client of the circumstances and
probable effects;
(b) the increase in scope and/ or costs shall be regarded as Additional
Services; and
(c) the time for completion of the Services shall be increased accordingly
2. The Consultant is bound to notify the Client of his claim giving rise to the delay
for which the Clairn is made as soon as practicable, and no later than 28 days
aJter the Consultant became aware. or should have become aware, of the event
or circumstance.
3. \ /hile submitting the case for EoT, Consultant is required to elaborate reasons
for extension, rational and acfual status of utilization of man months with
proper justificatiory apportioning responsibility and all submit all necessary
documents.
Page I of 12
4 lllhile determining Extension of Time for corsultanry services, the client shall
take into account the status of project and rational for any extensions glanted to
the Contractor.
5. The Client shall seek comments / recommendations from project office/ Ploject
Manager or any other relevant office within 07 days of receipt of Claim from the
Consultant. The concerned office(s) shall reply within 21 days of receipt of letter
from the Client.
6. The Client shall arrange approval from the competent authority as per Table-3
below and will make its determination within 21 days from receipt of response
/ recommendations from the stakeholders.
7. Lr case MD (NTDC) or BoD (NIDC) is the competent authority, case will be
referred to scrutiny Committee within 7 days of its receipt from the Client
which shall be decided by the Committee within 21 days and will be approved
by MD (NTDC) within 07 days of the receipt of report by the Committee'
Page 9 of 12
Note: - Sane procedure as delineated abooe shall be applicnble in cne of maltiple claims
aggregate basis'
for EOT, hotoeoer, competuncy shall be detetmircd on
NOTES:
(0 The officer awarding EOT shall also notify its determination to the
Employer, concemed General Manager, Deputy Managing Director (Asset
Development & Management) and Managing Director for information'
Managing Director (NTDC) may, however, refer any case to Scrutiny
Comrrrittee for internal control purposes.
(i") Each case for Extension of Time falling in the competency of MD (NTDC) /
BoD (NTDC) is to be approved after vetting by the EOT Scmtiny Committee'
(The members of the iommittee should be independent from the offices of
Employer/Engineer/Project Manager and Design Engineer)' Following
Committee is proposed for scrutiny of cases where required: -
GeneralManager(PerformanceAssessment) Convener
Chief Engineer (Reliability & Compliance) Member
Chief Engineer (Contract Management) Member
CFO or his/her authorized Representative Member
CLO or his/her authorized Representative Member
(MD (NTDC) may add any member or Committee may co-oPt the members
with tiie consent ot UO lNmC;. Chief Engineer (EHV/Project Delivery North
/ South will act as co-opted members/ departmental representative for
technical support and assistance to the Committee).
(") In such cases where case is deemed approval due to delay on part of the
purchaser/ Employer, ftrutiny Committee and / or any other office,
di".iplioury action will be taken as per E&D Rules against the person
responsible.
Page 10 of12
("ii) It willbe binding to provide quantification against each delay by the
contractor / consultant.
(ir) Realistic schedule must be given in the bidding documents. The Program/
/
schedule should be approved by the Engineer Program as baseline
schedule which shall become reference document for determination of EoT
claims. The Contractor shall at all times made his reasonable efforts to
minimize the delay in performance of his obligations under the Contract'
(r) If NTDC has to provide material from their own stores, then the timelines
for supply of material should be mentioned so that bidder / contractor
considers the same while preparing their construction schedule.
(xi) The Engineer shall keep the Employer informed about status of submission
of EOT requests by the Contractor and its determination thereof to avoid
unwarranted imposition of Liquidated Damages to the Contractor.
(xii) The Liquidated Damages once deducted shall not be reimbursed without
approval of Managing Director (NTDC) and approval of EOT.
(*iii) If any / /
case of Supplier Contractor Consultants shall be pending before
the Employer EngSneer Project Manager for determination, Liquidated
/ /
Damages shall not be deducted till its determination. Engineer/ Project
Manager shall keep the Employer informed about such cases'
(xiv) The Supplier / Contractor shall not stop the delivery of the material and /
or r.rspend / slow the Progress at site as the case may be, merely based on
their pending Claim for determination. In such cases, delay shall be
attributable towards their account. (Similarly, the Consultants shall not
suspend their work based on aforementioned grounds).
(*u) Regular reporting of the projects shall be made to the BoD (NTDC) either
through Dashboard and / or any other format desired by the BoD Of-fDq'
(xvii) This SoP shall be subject to review by the management after one year and
any changes made in the SoP shall be conveyed to BoD (NTDg.
Page 11 of 12
Annexu:e-A
Page 12 of 12