CE443 Handout - 5.3.24
CE443 Handout - 5.3.24
CE443 Handout - 5.3.24
• 1 Class/week
1
Syllabus (T.M. Al-Hussaini):
Reference Materials:
• Class Lecture
• Class Handouts
• Text Book Chapters
• Assignments
• Internet Sources
2
Introduction to Retaining
Structures
Source: Internet
CE 443 slides by T.M.Al-Hussaini 6
3
Gravity Retaining Wall
4
CE 443 slides by T.M.Al-Hussaini Source: Internet 9
5
CE 443 slides by T.M.Al-Hussaini Source: Internet 11
Source: Internet
CE 443 slides by T.M.Al-Hussaini 12
6
CE 443 slides by T.M.Al-Hussaini Source: Internet 13
Turkey
7
Reinforced Retaining Wall
Source: Internet
8
Sheet Piling
for Water Front Structure
Source: Internet
CE 443 slides by T.M.Al-Hussaini 17
Sheet Piling
9
Braced
Excavation
Source: Internet
Construction Dewatering
10
Construction Dewatering
11
Lateral Support
It is often necessary to retain soil to
prevent lateral soil movements.
Tie rod
Anchor
Sheet pile
Mayne and Kulhawy (1982), after evaluating 171 soils, recommended a modification to
Eq. (13.5):
12
Lateral Earth Pressure at Rest (contd.)
v’
SOIL
h’ X
13
Active/Passive Earth Pressures
Source: Sivakugan (2001) - in granular soils
Wall moves
away from soil
Wall moves A
towards soil
B
smooth wall
1 sin
KA tan 2 ( 45 / 2)
1 sin
CE 443 slides by T.M.Al-Hussaini 28
14
Passive Earth Pressure
Source: Sivakugan (2001)
v’
h’ increases till failure occurs.
h’ B
Passive state
1 sin
[ h ' ] passive K P v ' KP tan 2 ( 45 / 2)
1 sin
WALL SOIL
h’
Passive state
Active state
K0 state
Wall movement
(not to scale)
Source: Sivakugan (2001)
CE 443 slides by T.M.Al-Hussaini 30
15
Rankine’s Earth Pressure Theory c-
soil
[ h ' ]active K A v '2c K A
Sheet Pile
16
Sheet pile walls consists of series of sheets driven side by side into the
ground thus forming a continuous vertical wall to retain earth or other
fill material. These walls are thinner in section as compared to other
retaining walls. Sheet pile walls are generally used for the following:
1. Water front structures, for example, in building wharves, quays, and
piers
2. Building diversion dams, such as cofferdams
3. River bank protection
4. Retaining the sides of cuts made in earth
17
Source: Marcel Dekker Inc.
18
Sheet pile Driving
Russia 2018
19
Steel sheet piling is the most common because of several advantages
over other materials:
20
Construction steps of Sheet pile walls:
1. Laying out a sequence of sheet pile sections, and ensuring that sheet
piles will interlock.
2. Driving (or vibrating) the individual sheet piles to the desired depth.
3. Driving the second sheet pile with the interlocks between the first
sheet pile and second "locked"
4. Repeating steps 2 & 3 until the wall perimeter is completed
5. Use connector elements when more complex shapes are used.
Source: Internet
CE 443 slides by T.M.Al-Hussaini 42
21
Sheet Pile Installation (contd.)
22
Sheet Pile Installation (contd.)
23
Cantilever Sheet Pile
Cantilever sheet piles depend for their stability on an adequate
embedment into the soil below the dredge line. Since the piles are
fixed only at the bottom and are free at the top, they are called
cantilever sheet piles. These piles are economical only for moderate
wall heights (up to say 10 to 15 ft), since the required section modulus
increases rapidly with an increase in wall height, as the bending
moment increases with the cube of the cantilevered height of the wall.
The lateral deflection of this type of wall, because of the cantilever
action, will be relatively large. Erosion and scour in front of the wall,
i.e., lowering the dredge line, should be controlled since stability of
the wall depends primarily on the developed passive pressure in front
of the wall.
Active
Depth of E.P.
embedment, d
d
O Passive
fixity E.P.
48
CE 443 slides by T.M.Al-Hussaini
24
Assume depth of penetration of sheet pile at the beginning of
design as follows:
Conventional Method
Active
Depth of E.P.
embedment, d
d
O Passive
fixity E.P.
50
CE 443 slides by T.M.Al-Hussaini
25
Simplified Method
Active E.P.
Passive E.P.
d
R
C
51
CE 443 slides by T.M.Al-Hussaini
2=115 pcf
ka2=0.25
kp2=5.0
c2=0
26
5.0
27
CE 443 slides by T.M.Al-Hussaini 55
28
CE 443 slides by T.M.Al-Hussaini 57
29
CE 443 slides by T.M.Al-Hussaini 59
30
CE 443 slides by T.M.Al-Hussaini 61
31
CE 443 slides by T.M.Al-Hussaini 63
32
Due to
Surcharge
Water
Pressure
Backfill is cohesionless
33
Solution by Conventional Method
d & f unknown, which can be solved using
equations H=0 and Mo=0
CE 443 slides by T.M.Al-Hussaini 67
34
CE 443 slides by T.M.Al-Hussaini 69
35
CE 443 slides by T.M.Al-Hussaini 71
36
CE 443 slides by T.M.Al-Hussaini 73
37
CE 443 slides by T.M.Al-Hussaini 75
Simplified Method:
Using undrained strength parameters for cohesive soil
(short-term analysis)
38
Simplified Method:
Using final (drained) strength parameters for cohesive soil
(Long-term analysis)
Tension
Zone
39
CE 443 slides by T.M.Al-Hussaini 79
40
CE 443 slides by T.M.Al-Hussaini 81
41
Unbalanced
water
pressure
Effect of
seepage
pressure
due to
upward
flow of
water
42
NY DOT
Unbalanced water pressure
43
CE 443 slides by T.M.Al-Hussaini 87
The net earth pressure (the difference between the passive and the
active) is represented by abO'c in Fig. 20.5 (b). For design, the curve
bO'c is replaced by a straight line dc.
CE 443 slides by T.M.Al-Hussaini 88
44
Anchored Sheet Pile
Anchored bulkheads consist of a single row of relatively light sheet piles
of which the lower ends are driven into the earth and the upper ends
are anchored by tie or anchor rods. The anchor rods are held in place by
anchors which are buried in the backfill at a considerable distance from
the bulkhead.
Anchored bulkheads are widely used for dock and harbor structures.
This construction provides a vertical wall so that ships may tie up
alongside, or to serve as a pier structure, which may jet out into the
water. In these cases sheeting may be required to laterally support a fill
on which railway lines, roads or warehouses may be constructed so that
ship cargoes may be transferred to other areas. The use of anchor rod
tends to reduce the lateral deflection, the bending moment, and the
depth of the penetration of the pile.
45
Free Earth Support
46
Free Earth Support
tie rod
T da
A b
Passive E.P.
45° - /2
Active E.P.
anchor
d wall
45° + /2
no fixity
Determine the depth of embedment, d by taking
moments about A (SMA = 0, apply FP)
Find tension, T from SFH = 0 (don’t apply FP)
Constraints: failure wedges must not overlap
b > ½da
47
CE 443 slides by T.M.Al-Hussaini 95
48
CE 443 slides by T.M.Al-Hussaini 97
49
CE 443 slides by T.M.Al-Hussaini 99
50
Example (NY DOT)
51
CE 443 slides by T.M.Al-Hussaini 103
52
CE 443 slides by T.M.Al-Hussaini 105
53
CE 443 slides by T.M.Al-Hussaini 107
54
Moment reduction for anchored wall
Rowe (1952) demonstrated that the Free Earth method overestimates
the maximum bending moment in anchored walls with horizontal tie
rods. The sheet piles are relatively flexible and these deflect
considerably. Their flexibility causes a redistribution of the lateral earth
pressure. The net effect is that the maximum bending moment is
considerably reduced below the value obtained for the free earth
supports. It is used to take into consideration the flexibility of the pile
and its effect on relieving the actual bending moment the wall
experiences. The reduced bending moment for design ( Mdesign) is given
by Mdesign = MmaxRm
where,
Mmax= maximum bending moment predicted by the Free Earth method,
Rm= reduction factor depending on wall geometry, wall flexibility, and foundation soil
characteristics.
55
Use of Moment Reduction factor:
56
CE 443 slides by T.M.Al-Hussaini 113
57
CE 443 slides by T.M.Al-Hussaini 115
58
(a) Location of deadman offers no resistance
59
CE 443 slides by T.M.Al-Hussaini 119
Kp’=Kp/F.S.
60
CE 443 slides by T.M.Al-Hussaini 121
61
CE 443 slides by T.M.Al-Hussaini 123
62
II. DESIGN PREMISE
A. Lateral Earth Pressures
A flexible wall system design is required to resist the anticipated lateral pressures
without undergoing significant or excessive lateral deflections. The following list
provides an acceptable geotechnical theory for the development of the lateral earth
pressures and potential external loads and soil backfill configurations which must be
accounted for in design:
2. Surcharge Loads:
This term usually refers to traffic loading that is in proximity to the wall system. Use
the Spangler Method of analysis (area load of finite length) or Boussinesq Method of
analysis to determine the lateral pressure caused by the surcharge loading. The
uniform surcharge is usually given a value of 250 psf (12 kPa) or an equivalent height
of fill. If heavier construction equipment is in the vicinity of the wall, the surcharge
loading shall be increased accordingly.
3. Hydrostatic Pressure:
Since the locks of sheeting are more or less water tight when installed and become
more watertight as soil is drawn in, water can be trapped behind the wall causing a
head imbalance and greatly increasing the total load. Therefore, the elevation, or head
difference, shall be accounted for in design of the wall system. The hydrostatic head is
the difference between the groundwater elevation and the bottom of dewatered
excavation.
4. Inclined Backfill:
An inclined backfill will induce an additional load on the wall. If the backfill slope is
assumed to extend infinitely away from the wall at an angle β, the Rankine earth
pressure is a function of the angle β.
7. Cohesive Soil:
Due to the variability of the length of time a shoring system is in place, cohesive soils
shall be modeled in the drained condition. These soils shall be modeled as
cohesiveless soils using the drained internal angle of friction. Typically, drained internal
angles of friction for New York State clays range from 22 to 26 degree (undrained shear
strength=0).
63
B. Analysis
64
Braced Excavation
65
Typical applications of Braced Excavations:
• Laying underground pipeline
• Construction of bridge abutment.
• Construction of basement.
• Metro railway construction.
• Construction of subway tunnel.
66
Braced Excavation For narrow excavations, horizontal
struts across the excavation may be
appropriate. Struts are placed against
horizontal beams (wale) placed against
sheets or planks which support
excavation sides.
Braced
Excavation in
Sand:
Apparent
earth
pressure
diagram for
calculating
strut loads
(Peck et al., 1974)
0.65HKa
CE 443 slides by T.M.Al-Hussaini 134
67
Braced
Excavation
Soft to in Clay:
Stiff Clay Med.Stiff
Clay Apparent
H/c4 H/c>4
earth
pressure
diagram for
calculating
strut loads
(Peck et al., 1974)
0.65HK
or 0.3H a
CE 443 slides by T.M.Al-Hussaini 135
68
Experience has shown that if H/cb6, movements of the
bracing system and heave of the clay below base level are
small.
Bottom Heave
Heaving of soil will occur at the bottom of the pit due to release of
overburden pressure at that point. The pit has to be safeguarded against
this heaving.
CE 443 slides by T.M.Al-Hussaini 138
69
Factor of safety with respect
to Base Heave in clay
Clay bursting
The layer of soil below the excavation pit may not have sufficient depth
to resist the uplift force caused by water pressure in the sand layer. Then
this clay layer below the pit may burst open.
70
Clay
bursting
(contd.)
The factor of safety for clay bursting should be more than 1.3.
CE 443 slides by T.M.Al-Hussaini 141
Each strut takes the earth pressure on either halves up to half the vertical spacing (Sv).
The highest strut load is taken up for choosing the strut section which is provided
throughout.
CE 443 slides by T.M.Al-Hussaini 142
71
Typically the struts are
either pipe or I- beam
sections and are usually
preloaded to provide a
very stiff system.
Installation of the
bracing struts is done by
excavating soil locally
around the strut and
only continuing the
excavation once
preloading is complete.
A typical sequence of
excavation in braced
excavations is shown in
Figure
72
Prob:
Braced Cut in Clay
Peck et al., 1974
73
CE 443 slides by T.M.Al-Hussaini 148
Raker Bracing
For very wide excavations, raker bracing is used. The support for the
rakers (driven piles or footings) need to be installed at the bottom of the
excavation.
74
Raker Bracing Installation
75
CE 443 slides by T.M.Al-Hussaini 152
Raymond (1997)
76
Laterally Loaded Pile
77
Broms (1964) Method:
Assumption for Short piles: Ultimate lateral resistance is governed by
the passive earth pressure of the surrounding soil and the length of
pile. It is independent of bending resistance of pile section.
Assumption for Long piles: Ultimate lateral resistance for piles with
large penetration depths is governed by the ultimate or yield resistance
of the pile section and is independent of pile length.
For clay, Broms sets the soil resistance to be zero for the first 1.5 pile
diameters and 9CuD below this depth.
COHESIVE COHESIONLESS
1.5D
9cuD 9cuD
78
Long Pile in Cohesive Soil (Broms Method)
COHESIVE COHESIONLESS
79
Fixed-Head Pile in Cohesionless Soil (Broms Method)
80
Fixed Head – Restrained at top
81
Source: Gunaratne, 2006
CE 443 slides by T.M.Al-Hussaini 164
Pult/cuD2
Myield/cuD3
82
Myield/D4kp
83
Lateral Pile Load Test
84
CE 443 slides by T.M.Al-Hussaini 170
85
CE 443 slides by T.M.Al-Hussaini 172
86
Broms Method (Contd):
L=10 ft
L=20 ft L=10 ft
L=40 ft, 60 ft
Deflection (ft)
87
Laterally loaded Pile: Pressure Diagram and Bending Moment
COHESIVE SOIL
88
CE 443 slides by T.M.Al-Hussaini 178
89
Source: Gunaratne, 2006
90
Source:
Gunaratne, 2006
91
CE 443 slides by T.M.Al-Hussaini 184
Source: Gunaratne, 2006
92
CE 443 slides by T.M.Al-Hussaini 186
93
p-y Curve Method (contd.)
94
Computational p-y Curve Method (contd.)
95
CE 443 slides by T.M.Al-Hussaini 192
96
3D FEM Model of Laterally Loaded Single Pile
SAP-2000
8 noded brick
elements
PLAXIS
Laterally loaded
monopile
Note the deformations in
soil
97
CE 443 slides by T.M.Al-Hussaini 196
98
3D FINITE ELEMENT METHOD (contd.)
OTHER METHODS
99
Construction Dewatering
Construction Dewatering
100
Techniques for Dewatering
Ground freezing and electro-osmosis techniques are extremely costly and used only for particularly
difficult dewatering applications
101
Jet Grouting /Cut-Off Wall (Contd.)
By installing jet grout columns at spacings where
adjacent columns overlap continually over the
depth of treatment, a cut-off wall can be formed.
This method is ideal for areas with limited
accessibility for large equipment, or where the
zone of groundwater flow is limited in vertical
extent and is located at depth.
102
Jet Grouting /Cut-Off Wall (Contd.)
Ground Freezing
Step 4
103
Ground Freezing
to contain
contaminated
water from
nuclear reactors
after
Fukushima
Disaster
Soil Permeability
104
Choice of Technique for Dewatering
Pumping Methods
105
Open Sump
Well Points
106
Well Points (contd.)
107
Installing Well Points
108
Multiple Stage of Well Points
109
Well Point System
Source: Nemati, 2007
110
Field Tests of Well Points
Sand
111
With these pumps
which can have
high heads (up to
55 m), wellpoint
pumping may be
conducted in single
stage
112
Deep Well
- Use of deep wells with submersible pumps located at
the bottom of well.
- Deep wells are usually between 6 to 18 in. diameter
and spaced 20 to 200 ft centre to centre.
- Well depth up to 100 m.
- Well screens may be 20 to 75 ft long and surrounded
by sand-gravel mixture filter.
- Suitable for high soil permeability. Works best in
sands and gravels.
- Can dewater large areas to great depths
CE 443 slides by T.M.Al-Hussaini 229
Dewatering Submersible
Pumps is designed for
applications like:
113
Pumping Rate
114
CE 443 slides by T.M.Al-Hussaini 233
Rate of Pumping
Single
well
115
Problem: Design of Wells
116
CE 443 slides by T.M.Al-Hussaini 237
117
Slurry Trench-Wall
Construction
118
Filter Skin
119
Slurry Circulation & Cleaning
120
Advantages of Slurry Trench Wall
Loss of Slurry
121
Construction of Soil-Bentonite Cut-off Wall
122
CE 443 slides by T.M.Al-Hussaini 251
123
Tremie Concreting for Diaphragm Wall
Source: Nemati, 2007
30 ft
Diaphragm Wall
Construction for
BRAC University
Campus at
Badda
124
Construction
Site
Tremie
Concreting at
BRAC University
Campus at
Badda
CE 443 slides by T.M.Al-Hussaini 255
Diaphragm
Wall
constructed
at BRAC
University
Campus,
Badda
125
?
126
CE 443 slides by T.M.Al-Hussaini 259
127