Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Module I PLC

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

The Project Life Cycle

The project manager and project team have one shared goal: to carry out the work
of the project for the purpose of meeting the project's objectives. Every project has
beginnings, a middle period during which activities move the project toward completion,
and an ending (either successful or unsuccessful). A standard project typically has the
following four major phases (each with its own agenda of tasks and issues): initiation,
planning, implementation, and closure. Taken together, these phases represent the path a
project takes from the beginning to its end and are generally referred to as the project life
cycle .
Initiation Phase

During the first of these phases, the initiation phase, the project objective or need is
identified; this can be a business problem or opportunity. An appropriate response to the
need is documented in a business case with recommended solution options. A feasibility
study is conducted to investigate whether each option addresses the project objective and a
final recommended solution is determined. Issues of feasibility ("can we do the project?")
and justification ("should we do the project?") are addressed.

Once the recommended solution is approved, a project is initiated to deliver the


approved solution and a project manager is appointed. The major deliverables and the
participating work groups are identified and the project team begins to take shape.
Approval is then sought by the project manager to move on the detailed planning phase.
Planning Phase
The next phase, the planning phase, is where the project solution is further
developed in as much detail as possible and you plan the steps necessary to meet the
project's objective. In this step, the team identifies all of the work to be done. The project's
tasks and resource requirementsare identified, along with the strategy for producing them.
This is also referred to as scope management. A project plan is created outlining the
activities, tasks, dependencies and timeframes. The project manager coordinates the
preparation of a project budget; by providing cost estimates for the labor, equipment and
materials costs. The budget is used to monitor and control cost expenditures during project
implementation.

Once the project team has identified the work, prepared the schedule and estimated
the costs, the three fundamental components of the planning process are complete. This is
an excellent time to identify and try to deal with anything that might pose a threat to the
successful completion of the project. This is called risk management. In risk management,
"high-threat" potential problems are identified along with the action that is to be taken on
each high threat potential problem, either to reduce the probability that the problem will
occur or to reduce the impact on the project if it does occur. This is also a good time to
identify all project stakeholders, and to establish a communication plan describing the
information needed and the delivery method to be used to keep the stakeholders informed.
Finally, you will want to document a quality plan; providing quality targets,
assurance, and control measures along with an acceptance plan; listing the criteria to be
met to gain customer acceptance. At this point, the project would have been planned in
detail and is ready tobe executed.
Implementation Phase
During the third phase, the implementation phase, the project plan is put into
motion and performs the work of the project. It is important to maintain control and
communicate as needed during implementation. Progress is continuously monitored and
appropriate adjustments are made and recorded as variances from the original plan. In
any project a project manager will spend most of their time in this step. During project
implementation, people are carrying out the tasks and progress information is being
reported through regular team meetings. The project manager uses this information to
maintain control over the direction of the project by measuring the performance of the
project activities comparing the results with the project plan and takes corrective action
as needed. The first course of action should always be to bring the project back on course,
i.e., to return it to the original plan. If that cannot happen, the team should record
variations from the original plan and record and publish modifications to the plan.
Throughout this step, project sponsors and other key stakeholders should be kept
informed of project status according to the agreed upon frequency and format. The plan
should be updated and published on a regular basis.
Status reports should always emphasize the anticipated end point in terms of cost,
schedule and quality of deliverables. Each project deliverable produced should be reviewed
for quality and measured against the acceptance criteria. Once all of the deliverables have
been produced and the customer has accepted the final solution, the project is ready for
closure.
Closing phase

During the final closure, or completion phase, the emphasis is on releasing the final
deliverables to the customer, handing over project documentation to the business,
terminating supplier contracts, releasing project resources and communicating the closure
of the project to all stakeholders. The last remaining step is to conduct lessons learned
studies; to examine what went well and what didn't. Through this type of analysis the
wisdom of experience is transferred back to the project organization, which will help
future project teams.

You might also like