Daily Report 27-04-2024 - 085232

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

DAILY REPORT

PROJECT TITLE : PKE PLANT 120 MT C/W INSTALLATION OF MACHINERY EQUIPMENT REPORT NO. : 12/PKE/DR/DOC/CSK/SDO/4/2024
LOCATION : LUBUK GAUNG, DUMAI DATE : Sabtu, 27 April 2024
CLIENT : PT. SARI DUMAI OLEO APICAL WEEKLY : 3
CONTRACTOR : PT. CEMERLANG SAMUDRA KONTRINDO

ACTIVITY TO DAY
NO MANPOWER QTY NO Volume to Erection Volume Erection Volume Erection Manpower Ket
ITEM QTY Sat
Day To Day (%) Prev Prev (%) Total Accu (%) Instalation

A MANPOWER 31 19
PKE Transfer Screw Conveyor No.1 (
1 Project Manager 1 I 2
ITEM NO. 9 )
2 Site Engineer 1 Fabrikasi Extension Cute 2 Unit 2 100% 0% 2 100% Finish
3 Quality Control 1 Install & Welding Extension Cut 1 Unit 1 100% 0% 1 100% Finish
4 Supervisior 1 Painting Equipment 5 Item 5 100% 0% 5 100% Finish
5 Surveyor 1 Stairway ( Line 9 to 13 ) 1 Unit 0,61 61% 0,01 1% 0,62 62% On Progress
6 Ass. Surveyor 1
PKE Transfer Screw Conveyor No.2 (
7 Logistik 2 II 2
ITEM NO. 10 )
8 Mekanik 1 Fabrikasi Extension Cute 2 Unit 2 100% 0% 2 100% Finish
9 Operator Crane 2 Install Extension Cut 1 Unit 1 100% 0% 1 100% Finish
10 Tim Installation 18 Install Handrail 92,8 m' 92,8 100% 0% 92,8 100% Finish
11 Tim Painting 2 Painting Equipment 7 Item 6,93 99% 0,07 1% 7 100% Finish
Stairway ( Line 10 to 11 ) 1 Unit 0,6 60% 0% 0,6 60% On Progress
Install Walkway 46,4 m' 46,4 100% 0% 46,4 100% Finish
B POWER TOOLS UNIT

PKE Transfer Screw Conveyor Line A No.1


1 Crane 50 ton 1 III
to Warehouse ( ITEM 11 )
2 Genset 50 KVA 1 Fabrikasi Extension Cute 5 Unit 5 100% 0% 5 100% Finish
3 Travo Las 2 Install & Welding Extension Cute 5 Unit 5 100% 0% 5 100% Finish
4 Grinda 4 Install & Setting DSC 5 Unit 5 100% 0% 5 100% Finish
5 Chain Block 2 Install Handrail 86 m' 86 100% 0% 86 100% Finish
6 Cutting Torch 1 Install Walkway 43 m' 43 100% 0% 43 100% Finish
7 Foco Crane 1
PKE Transfer Screw Conveyor Line A No.2
8 Pick Up 1 IV 2
to Warehouse ( ITEM 12 )
9 Waterpass 2 Fabrikasi Extension Cute 11 Unit 11 100% 0% 11 100% Finish
10 Total Station 1 Install & Welding Extension Cute 11 Unit 10,93 99% 0,001 0% 10,93 99% On Progress
Install & Setting DSC 11 Unit 11 100% 0% 11 100% Finish
Install Handrail 186 m' 186 100% 0% 186 100% Finish
C Jam Kerja (WIB) Jlh
Install Walkway 93 m' 93 100% 0% 93 100% Finish
1 07-08 1 Painting Equipment 11 Unit 10,95 100% 0% 10,95 100% Finish
2 08-09 1
PKE Transfer Screw Conveyor Line B No.1
3 09-10 1 V 3
to Warehouse ( ITEM 13 )
4 10-11 1 Fabrikasi Extension Cute 5 Unit 5 100% 0% 5 100% Finish
5 11-12 1 Install & Welding Extension Cute 5 Unit 5 100% 0% 5 100% Finish
6 12-13 Install & Setting DSC 5 Unit 5 100% 0% 5 100% Finish
7 13-14 1 Install Handrail 86 m' 84,28 98% 0,43 1% 84,71 99% On Progress
8 14-15 1 Install Walkway 43 m' 43 100% 0% 43 100% Finish
9 15-16 1 Painting Equipment 5 Unit 4,85 97% 0,025 1% 4,88 98% On Progress
10 16-17 1
PKE Transfer Screw Conveyor Line B No.2
11 17-18 1 VI 2
to Warehouse ( ITEM 14 )
TOTAL 10 Fabrikasi Extension Cute 11 Unit 11 100% 0% 11 100% Finish
Install & Welding Extension Cute 11 Unit 11 100% 0% 11 100% Finish
D WEATHER Install & Setting DSC 11 Unit 11 100% 0% 11 100% Finish
SUNNY P Install Handrail 186 m' 167,47 90% 0,025 0% 167,49 90% On Progress
CLOUDY Install Walkway 93 m' 93 100% 0% 93 100% Finish
RAINY Painting Equipment 11 Unit 10,78 98% 0,11 1% 10,89 99% On Progress
ETC
E NOTES VII Stairway
Fabrikasi 26,5 m' 26,5 100% 0% 26,5 100% Finish
Erection 26,5 m' 26,5 100% 0% 26,5 100% Finish
Install Handrail 59 m' 57,82 98% 0,295 1% 58,115 99% On progress
Install Support 6 m' 6 100% 0% 6 100% Finish
Install Plate form 8,3 m' 8,3 100% 0% 8,3 100% Finish
Painting Handrail 59 m' 55,46 94% 0,59 1% 56,05 95% On progress
Install Door 1 unit Page0,35
1 of 2 35% 0% 0,35 35% On progress
DAILY REPORT

PROJECT TITLE : PKE PLANT 120 MT C/W INSTALLATION OF MACHINERY EQUIPMENT REPORT NO. : 12/PKE/DR/DOC/CSK/SDO/4/2024
LOCATION : LUBUK GAUNG, DUMAI DATE : Sabtu, 27 April 2024
CLIENT : PT. SARI DUMAI OLEO APICAL WEEKLY : 3
CONTRACTOR : PT. CEMERLANG SAMUDRA KONTRINDO

ACTIVITY TO DAY
NO MANPOWER QTY NO Volume to Erection Volume Erection Volume Erection Manpower Ket
ITEM QTY Sat
Day To Day (%) Prev Prev (%) Total Accu (%) Instalation

VIII Dust Colecting System 8


1 Cyclon
Install Frame Cyclon 1 Unit 0,5 50% 0,5 50% 1 100% On progress
Joint Ducting Cyclon 16 pcs 9 56% 9 56% 18 113% On progress
Install Ducting Chute 2 unit 0% 0% 0 0%
Painting 16 pcs 0% 0% 0 0%
2 Fan
Install Fan 1 unit 0,6 60% 0,15 15% 0,75 75% On progress
Joint Ducting Fan 1 unit 0,5 50% 0,1 10% 0,6 60% On progress
3 Bag Filter
Install Frame Bag Filter 1 unit 0% 0,15 15% 0,15 15% On progress
Install Bag Fillter 1 unit 0% 0% 0 0%
Joint Ducting Filter 1 unit 0% 0% 0 0%